CN109356429A - A kind of double loop 110kV, which is bored, gets over tower - Google Patents

A kind of double loop 110kV, which is bored, gets over tower Download PDF

Info

Publication number
CN109356429A
CN109356429A CN201811419228.9A CN201811419228A CN109356429A CN 109356429 A CN109356429 A CN 109356429A CN 201811419228 A CN201811419228 A CN 201811419228A CN 109356429 A CN109356429 A CN 109356429A
Authority
CN
China
Prior art keywords
tower
arm
tower body
gets over
bored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811419228.9A
Other languages
Chinese (zh)
Inventor
马钦国
袁斌
杨大渭
寇峰
朱晓鹏
霍仪
张皓维
谭蓉
贺育明
李波
吴亮
宁昭晔
张军强
张功望
高永亮
董卓元
姚新宇
李晓婷
盛飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shangluo Power Supply Company State Grid Shaanxi Electric Power Co Ltd
China Energy Engineering Group Shaanxi Electric Ppower Design Institute Co Ltd
State Grid Shaanxi Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Shaanxi Electric Power Co Ltd
Original Assignee
Shangluo Power Supply Company State Grid Shaanxi Electric Power Co Ltd
China Energy Engineering Group Shaanxi Electric Ppower Design Institute Co Ltd
State Grid Shaanxi Electric Power Co Ltd
Economic and Technological Research Institute of State Grid Shaanxi Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shangluo Power Supply Company State Grid Shaanxi Electric Power Co Ltd, China Energy Engineering Group Shaanxi Electric Ppower Design Institute Co Ltd, State Grid Shaanxi Electric Power Co Ltd, Economic and Technological Research Institute of State Grid Shaanxi Electric Power Co Ltd filed Critical Shangluo Power Supply Company State Grid Shaanxi Electric Power Co Ltd
Priority to CN201811419228.9A priority Critical patent/CN109356429A/en
Publication of CN109356429A publication Critical patent/CN109356429A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/08Structures made of specified materials of metal
    • E04H12/10Truss-like structures

Abstract

A kind of double loop 110kV, which is bored, gets over tower, is related to electric force pole tower field.It include: tower body, tower body includes tower body main material, tower body X-braced panels, tower leg and the oblique material in leg for connecting tower leg;Tower body is equipped with cross-arm structure, is from top to bottom followed successively by ground wire cross-arm, conducting wire cross-arm;Ground wire cross-arm, conducting wire cross-arm are symmetricly set on tower body two sides;It bores and gets over the full tower of tower using angle steel production.The double loop 110kV provided by the present application, which is bored, gets over tower, including two layers of cross-arm structure, respectively ground wire cross-arm and conducting wire cross-arm, can be effectively reduced total height of shaft tower.It bores the more full tower of tower and is all made of angle steel production, structure is simple, convenient processing and manufacture, and can guarantee shaft tower rigidity, guarantees safety.The double loop 110kV provided by the present application, which is bored, gets over the very big height of head for reducing steel tower of tower, reduces total height of steel tower.It is bored using the double loop 110kV provided by the present application and gets over tower, width of corridor can be saved, reduce cost, improve the environment friendly of engineering.

Description

A kind of double loop 110kV, which is bored, gets over tower
Technical field
It is bored this application involves electric force pole tower technical field more particularly to a kind of double loop 110kV and gets over tower.
Background technique
As power grid construction is more and more intensive, often exists in 110kV work transmission line and bores the case where getting over other shaft towers, And bore and get over enough clear distances and distance to the ground that tower needs to keep scissors crossing, therefore, boring more tower need to reasonably be designed, to protect Demonstrate,prove the safety of power transmission electric network.
Currently, more tower is bored on many 110kV common-tower double-returns road is typically provided with three floor cross-arm, it is followed successively by ground wire cross from top to bottom Load, upper conducting wire cross-arm, middle lower wire cross-arm.Three layers of cross-arm are vertically arranged, and the tower head of shaft tower is higher, and difficulty of construction is big, work of constructing Journey amount is big, and bore get over All other routes when increase difficulty, sometimes for meet bore get over demand, need to original transmission line of electricity into Row transformation, not only improvement cost is high, but also increases construction period.
Summary of the invention
It is bored this application provides a kind of double loop 110kV and gets over tower, to solve 110kV brill, more tower tower head is high, difficulty of construction is big, The problem of taking up a large area.
A kind of double loop 110kV, which is bored, gets over tower, comprising: tower body, the tower body include tower body main material, tower body X-braced panels, tower The oblique material in leg of leg and the connection tower leg;The tower body is equipped with cross-arm structure, is from top to bottom followed successively by ground wire cross-arm, leads Line cross-arm;
The ground wire cross-arm, the conducting wire cross-arm are symmetricly set on the tower body two sides;
Described bore gets over the full tower of tower using angle steel production.
Optionally, the central axes section along the tower body of the ground wire cross-arm is irregular quadrilateral, described irregular The top of quadrangle is parallel to horizontal plane, below shorter than top, and is obliquely installed;The total length of the ground wire cross-arm is 25.4m.
Optionally, ground wire cross-arm two sides are respectively provided with two hanging wire holes;Tower body central axes described in first hanging wire pitch-row 6.45m, tower body central axes 12.7m described in second hanging wire pitch-row.
Optionally, the conducting wire cross-arm along the central axes section of the tower body be irregular quadrilateral, described irregular four Side of the side shape far from the tower body central axes and the axis parallel are described trapeziform flat with horizontal plane below Row;The total length of the conducting wire cross-arm is 27m.
Optionally, conducting wire cross-arm two sides are respectively provided with three hanging wire holes;Tower body central axes described in first hanging wire pitch-row 4.1m, tower body central axes 8.8m described in second hanging wire pitch-row, tower body central axes 13.5m described in third hanging wire pitch-row.
Optionally, become at slope with the vertical range of the conducting wire cross-arm as 3m.
Optionally, the cross section for becoming the above tower body at slope is square, and the tower body become at slope is wide Degree is 2.6m.
Optionally, described bore gets over tower overall height as 14m~20m.
The technical scheme provided by the application includes following advantageous effects:
Compared with prior art, a kind of double loop 110kV, which is bored, gets over tower, comprising: tower body, tower body include tower body main material, tower body X-braced panels, tower leg and the oblique material in leg for connecting tower leg;Tower body is equipped with cross-arm structure, is from top to bottom followed successively by ground wire cross Load, conducting wire cross-arm;Ground wire cross-arm, conducting wire cross-arm are symmetricly set on tower body two sides;It bores and gets over the full tower of tower using angle steel production.This Shen The double loop 110kV that please be provided, which is bored, gets over tower, including two layers of cross-arm structure, respectively ground wire cross-arm and conducting wire cross-arm, tower head are a height of 5m.Every side of ground wire cross-arm is equipped with two hanging wire points, and every side of conducting wire cross-arm is equipped with three hanging wire points.It is complete to bore more tower Tower is all made of angle steel production, and plate efficiency is high, and structure is simple, convenient processing and manufacture, and can guarantee shaft tower rigidity, guarantees peace Quan Xing.It bores more tower and there was only one layer of ground wire cross-arm and a layer conductor cross-arm, conducting wire cross-arm side in the double loop 110kV provided by the present application Three-phase conducting wire is hung, the very big height of head for reducing steel tower reduces total height of steel tower.Use 110kV provided by the present application Double loop, which is bored, gets over tower, can save width of corridor, reduce cost, improve the environment friendly of engineering.
Detailed description of the invention
In order to illustrate more clearly of the technical solution of the application, letter will be made to attached drawing needed in the embodiment below Singly introduce, it should be apparent that, for those of ordinary skills, without any creative labor, It is also possible to obtain other drawings based on these drawings.
Fig. 1 is that the structure diagram for getting over tower is bored in a kind of double loop 110kV provided by the embodiments of the present application.
Description of symbols:
1, tower body main material;2, tower body X-braced panels;3, tower leg;4, the oblique material in leg;5, ground wire cross-arm;6, conducting wire cross-arm;7, Become at slope.
Specific embodiment
Attached drawing 1 is please referred to, the structure for getting over tower is bored the figure shows a kind of double loop 110kV provided by the embodiments of the present application.
A kind of double loop 110kV, which is bored, gets over tower characterized by comprising tower body, tower body include that tower body main material 1, tower body intersect Oblique material 2, tower leg 3 and the oblique material 4 in leg for connecting tower leg 3;Tower body is equipped with cross-arm structure, is from top to bottom followed successively by ground wire cross-arm 5, conducting wire cross-arm 6;Ground wire cross-arm 5, conducting wire cross-arm 6 are symmetricly set on tower body two sides;It bores and gets over the full tower of tower using angle steel production.
The double loop 110kV provided by the embodiments of the present application, which is bored, gets over tower, including two layers of cross-arm structure, is followed successively by ground from top to bottom Line cross-arm and conducting wire cross-arm bore and get over the full tower of tower and be all made of angle steel production, steel grade used in shaft tower component be Q235B, Q345B and Q420B, and all components of shaft tower, including bolt, foot nail, washer etc. are all made of galvanizing by dipping anti-corrosion, are being used with improving shaft tower Durability in period, improves service life, and guarantees shaft tower safety.
As shown in Figure 1, tower body includes three parts, upper section is trapezoidal column, and the horizontal cross-section of this section is square, and is located at upper The area in portion is slightly less than the area positioned at lower part;Interrupting is trapezoidal column, is interrupted with upper section by becoming 7 at slope Connection, the horizontal cross-section of this section are square, and superposed area is less than the area positioned at lower part;Lower end For splayed tower leg 3.
The double loop 110kV provided by the embodiments of the present application, which is bored, gets over tower, and tower body main material 1 is connected by tower body X-braced panels 2, ground The tower body X-braced panels 2 of two intersections are equipped between two tower body main materials 1 where line cross-arm 5, every;Where conducting wire cross-arm 6, It is equipped with the tower body X-braced panels 2 more than two between every two tower body main materials 1 and forms multiple triangular elements, to reinforce shaft tower Rigidity.Between cross-arm structure tower body main material 1 below, between tower leg 3, it is equipped with more tower body X-braced panels 2, the oblique material 4 in leg Form multiple triangular elements.
As shown in Figure 1, ground wire cross-arm 5 and conducting wire cross-arm 6 are using tower body central axes as the symmetrical structure of symmetry axis, the two There is points of common connection on tower body, a nodal-connection components are set at this tie point, can reduce cost input and Difficulty of construction improves construction efficiency.
For the connection of shaft tower component mainly based on being bolted, the connection with column foot plate uses welding connecting mode.
The double loop 110kV provided by the embodiments of the present application, which is bored, gets over tower, including two layers of cross-arm structure, can be effectively reduced, tower Grease head highness guarantees that transmission line of electricity bores normal, the safety more constructed and carries out to reduce the height of shaft tower.Also, the full tower of shaft tower is equal It is made of angle steel, column plate effect, structure is simple, convenient processing and manufacture.All components of shaft tower are all made of galvanizing by dipping anti-corrosion, energy The durability for enough improving shaft tower, guarantees the safety of shaft tower.It bores more tower and there was only one layer of ground wire in the double loop 110kV provided by the present application Cross-arm and a layer conductor cross-arm, one side hanging three-phase conducting wire of conducting wire cross-arm are bored using the double loop 110kV provided by the present application and get over tower, Width of corridor can be saved, reduce cost, improve the environment friendly of engineering.
Optionally, the central axes section along tower body of ground wire cross-arm 5 is irregular quadrilateral, trapeziform top It is parallel to horizontal plane, below shorter than top, and is obliquely installed;The total length of ground wire cross-arm 5 is 25.4m.
As shown in Figure 1, ground wire cross-arm 5 is irregular quadrilateral along the central axes section of tower body, wherein top is parallel to water Plane;First side close to tower body side is a part of tower body main material 1;Opposite with top is following, is obliquely installed, and short Length in top;It is second side connection top far from tower body side, following.
Bolted angle connection bottom and upper segment in first unit of ground wire cross-arm 5, i.e., close to the part of tower body setting intersection; Single inclined Bolted angle connection bottom and upper segment is only arranged in other units, i.e. another part far from tower body.Herein, unit is to set Setting vertical angle steel is boundary.
Always up to 2m, overall length reach 25.4m to ground wire cross-arm 5.
Optionally, 5 two sides of ground wire cross-arm are respectively provided with two hanging wire holes;First hanging wire pitch-row tower body central axes 6.45m, the Two hanging wire pitch-row tower body central axes 12.7m.
The two sides of ground wire cross-arm 5 are all provided with there are two hanging wire hole, the distance of hanging wire pitch-row tower body central axes be respectively 6.45m and 12.7m, to meet lightning protection requirement, electric clearance requirement, electromagnetic environment requirements, insulation distance requirement.
Optionally, conducting wire cross-arm 6 is irregular quadrilateral along the central axes section of tower body, and irregular quadrilateral is far from tower body The side of central axes and axis parallel, it is trapeziform to be parallel to the horizontal plane below;The total length of conducting wire cross-arm 6 is 27m。
As shown in Figure 1, conducting wire cross-arm 6 is irregular quadrilateral along the central axes section of tower body, wherein be parallel to water below Plane;First side close to tower body side is a part of tower body main material 1;With following opposite top, it is obliquely installed, is longer than Following length, also, one end of top and ground wire cross-arm 5 have points of common connection;Far from tower body side second side with Axis parallel, connects bottom and upper segment, and the height of second side is 1m.
First unit of conducting wire cross-arm 6, i.e., the angle steel that setting intersects close to the part of tower body form multiple triangle lists Member is to reinforce the rigidity of shaft tower;Other units, i.e., the Bolted angle connection bottom and upper segment that another part setting far from tower body intersects.
Always up to 3m, overall length reach 27m to conducting wire cross-arm 6.
Optionally, 6 two sides of conducting wire cross-arm are respectively provided with three hanging wire holes;First hanging wire pitch-row tower body central axes 4.1m, the Two hanging wire pitch-row tower body central axes 8.8m, third hanging wire pitch-row tower body central axes 13.5m.
Different from the prior art, the double loop 110kV provided by the embodiments of the present application, which is bored, gets over tower, on the conducting wire cross-arm 6 of two sides Respectively three hanging wire holes of setting, the distance of hanging wire pitch-row tower body central axes is respectively 4.1m, 8.8m and 12.7m, is wanted with meeting lightning protection It asks, electric clearance requirement, electromagnetic environment requirements, insulation distance requirement.
Optionally, become at slope 7 with the vertical range of conducting wire cross-arm 6 as 3m.
To meet lightning protection requirement, electric clearance requirement, electromagnetic environment requirements, insulation distance requirement, it is horizontal with conducting wire to become at slope 7 Load 6 is 3m in the distance of vertical direction.
Optionally, the cross section for becoming 7 or more tower bodies at slope is square, and 7 tower body width is 2.6m at change slope.
As shown in Figure 1, the double loop 110kV provided by the embodiments of the present application, which is bored, gets over tower, upper section is trapezoidal column, to become at slope 7 be boundary, and the tower body width on upper section top is 2.0m, becomes at slope 7 tower body width as 2.6 meters.
Optionally, boring and getting over tower overall height is 14m~20m.
The double loop 110kV provided by the embodiments of the present application, which is bored, gets over tower, and shaft tower overall height range is 14m~20m.According to construction feelings Condition, when exhaling the minimum 9m of height, shaft tower root is opened as 4.28m, and shaft tower overall height is 14m;When exhaling high up to 15m, shaft tower root is opened For 5.96m, shaft tower overall height is 20m.
The double loop 110kV provided by the embodiments of the present application, which is bored, gets over tower, and the two sides of ground wire cross-arm 5 are respectively provided with two hanging wire points, The two sides of conducting wire cross-arm 6 are respectively provided with three hanging wire points, and two layers of cross-arm is only arranged, can effectively reduce tower head height, thus control-rod Tower overall height ensure that transmission line of electricity is boring safety when getting in control range.Simultaneously as full tower is all made of angle steel material Production, column plate effect, structure is simple, convenient processing and manufacture.All components of shaft tower are all made of galvanizing by dipping anti-corrosion, can be improved bar The durability of tower guarantees the safety of shaft tower.It bores more tower and there was only one layer of ground wire cross-arm and one in the double loop 110kV provided by the present application Layer conductor cross-arm, one side hanging three-phase conducting wire of conducting wire cross-arm are bored using the double loop 110kV provided by the present application and get over tower, can saved Width of corridor alleviates land used anxiety, reduces cost, improve the environment friendly of engineering.
It should be noted that the terms "include", "comprise" or its any other variant are intended to the packet of nonexcludability Contain, so that article or equipment including a series of elements not only include those elements, but also including not arranging clearly Other element out, or further include for elements inherent to such a process, method, article, or device.Not more In the case where limitation, the element that is limited by sentence "including a ...", it is not excluded that including process, the side of the element There is also other identical elements in method, article or equipment.
The above is only the specific embodiment of the application, is made skilled artisans appreciate that or realizing this Shen Please.Various modifications to these embodiments will be apparent to one skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the application.Therefore, the application It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.
It should be understood that the application is not limited to the content being described above, and its model can not departed from It encloses and carry out various modifications and change.Scope of the present application is only limited by the accompanying claims.

Claims (8)

1. a kind of double loop 110kV, which is bored, gets over tower characterized by comprising tower body, the tower body include tower body main material (1), tower body The oblique material in leg (4) of X-braced panels (2), tower leg (3) and the connection tower leg (3);The tower body is equipped with cross-arm structure, by Ground wire cross-arm (5), conducting wire cross-arm (6) are followed successively by under;
The ground wire cross-arm (5), the conducting wire cross-arm (6) are symmetricly set on the tower body two sides;
Described bore gets over the full tower of tower using angle steel production.
2. double loop according to claim 1, which is bored, gets over tower, which is characterized in that the ground wire cross-arm (5) along the tower body Central axes section be irregular quadrilateral, the trapeziform top is parallel to horizontal plane, below shorter than top, and It is obliquely installed;The total length of the ground wire cross-arm (5) is 25.4m.
3. double loop according to claim 2, which is bored, gets over tower, which is characterized in that ground wire cross-arm (5) two sides are respectively provided with two A hanging wire hole;Tower body central axes 6.45m described in first hanging wire pitch-row, tower body central axes 12.7m described in second hanging wire pitch-row.
4. double loop according to claim 1, which is bored, gets over tower, which is characterized in that the conducting wire cross-arm (6) is along the tower body Central axes section is irregular quadrilateral, side of the irregular quadrilateral far from the tower body central axes and the central axes In parallel, described trapeziform to be parallel to the horizontal plane below;The total length of the conducting wire cross-arm (6) is 27m.
5. double loop according to claim 4, which is bored, gets over tower, which is characterized in that conducting wire cross-arm (6) two sides are respectively provided with three A hanging wire hole;Tower body central axes 4.1m described in first hanging wire pitch-row, tower body central axes 8.8m described in second hanging wire pitch-row, Tower body central axes 13.5m described in three hanging wire pitch-rows.
6. double loop according to claim 1, which is bored, gets over tower, which is characterized in that become (7) and the conducting wire cross-arm (6) at slope Vertical range is 3m.
7. double loop according to claim 6, which is bored, gets over tower, which is characterized in that described to become (7) the above tower body at slope Cross section is square, and the tower body width for becoming (7) at slope is 2.6m.
8. double loop according to claim 1, which is bored, gets over tower, which is characterized in that described bore gets over tower overall height as 14m~20m.
CN201811419228.9A 2018-11-26 2018-11-26 A kind of double loop 110kV, which is bored, gets over tower Pending CN109356429A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811419228.9A CN109356429A (en) 2018-11-26 2018-11-26 A kind of double loop 110kV, which is bored, gets over tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811419228.9A CN109356429A (en) 2018-11-26 2018-11-26 A kind of double loop 110kV, which is bored, gets over tower

Publications (1)

Publication Number Publication Date
CN109356429A true CN109356429A (en) 2019-02-19

Family

ID=65342831

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811419228.9A Pending CN109356429A (en) 2018-11-26 2018-11-26 A kind of double loop 110kV, which is bored, gets over tower

Country Status (1)

Country Link
CN (1) CN109356429A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924732A (en) * 2019-12-09 2020-03-27 广州增立钢管结构股份有限公司 Main material and cross connecting plate assembling method of multi-main material iron tower

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101510679A (en) * 2009-03-20 2009-08-19 江苏科能电力工程咨询有限公司 110KV double-loop T connection steel pipe pole
CN102817491A (en) * 2012-08-08 2012-12-12 邯郸供电公司 110kV dual-loop line drilling iron tower
CN204691370U (en) * 2015-04-09 2015-10-07 国家电网公司 The novel butterfly in 110kV double loop, high altitude localities bores more tower
CN105155911A (en) * 2015-09-07 2015-12-16 安徽华电工程咨询设计有限公司 Double-loop double-side on-off steel tube role tower adopting triangular cross beam arrangement
CN205243135U (en) * 2015-12-16 2016-05-18 龙源(北京)风电工程设计咨询有限公司 Two times overhead transmission line alternately bores tower more
RU170640U1 (en) * 2017-01-20 2017-05-03 Евгений Вячеславович Хорошкеев TWO-CHAIN INTERMEDIATE MULTI-DIMENSIONAL SUPPORT OF ELECTRIC TRANSMISSION LINES
WO2018059190A1 (en) * 2016-09-29 2018-04-05 江苏神马电力股份有限公司 Tower head of power transmission tower, and power transmission tower
CN209976137U (en) * 2018-11-26 2020-01-21 中国能源建设集团陕西省电力设计院有限公司 110kV double-loop drilling and crossing tower

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101510679A (en) * 2009-03-20 2009-08-19 江苏科能电力工程咨询有限公司 110KV double-loop T connection steel pipe pole
CN102817491A (en) * 2012-08-08 2012-12-12 邯郸供电公司 110kV dual-loop line drilling iron tower
CN204691370U (en) * 2015-04-09 2015-10-07 国家电网公司 The novel butterfly in 110kV double loop, high altitude localities bores more tower
CN105155911A (en) * 2015-09-07 2015-12-16 安徽华电工程咨询设计有限公司 Double-loop double-side on-off steel tube role tower adopting triangular cross beam arrangement
CN205243135U (en) * 2015-12-16 2016-05-18 龙源(北京)风电工程设计咨询有限公司 Two times overhead transmission line alternately bores tower more
WO2018059190A1 (en) * 2016-09-29 2018-04-05 江苏神马电力股份有限公司 Tower head of power transmission tower, and power transmission tower
RU170640U1 (en) * 2017-01-20 2017-05-03 Евгений Вячеславович Хорошкеев TWO-CHAIN INTERMEDIATE MULTI-DIMENSIONAL SUPPORT OF ELECTRIC TRANSMISSION LINES
CN209976137U (en) * 2018-11-26 2020-01-21 中国能源建设集团陕西省电力设计院有限公司 110kV double-loop drilling and crossing tower

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110924732A (en) * 2019-12-09 2020-03-27 广州增立钢管结构股份有限公司 Main material and cross connecting plate assembling method of multi-main material iron tower

Similar Documents

Publication Publication Date Title
CN203334759U (en) Novel double-loop terminal tower with one side hanging wires
CN203583974U (en) 750KV outdoor A-shaped column, lattice type column and power distribution device
CN109356429A (en) A kind of double loop 110kV, which is bored, gets over tower
CN201953131U (en) 220kV one-tower double-loop straight corner penetrating tower
CN203905588U (en) Extra high voltage AC wineglass type tangent tower in heavy ice zone
CN207260730U (en) A kind of double loop cable termination tower
CN204691370U (en) The novel butterfly in 110kV double loop, high altitude localities bores more tower
CN201406865Y (en) 66KV overhead transmission line double-circuit horizontal crossing tower
CN207538321U (en) A kind of 500kV long cantilevers lattice triangular-section outlet structure crossbeam
CN209976137U (en) 110kV double-loop drilling and crossing tower
CN207847235U (en) No ground pole DC transmission line line pole tower
CN203205717U (en) Compact 220kV outdoor GIS power distribution equipment
CN108005458A (en) Singly cut-off π sections towers in double loop
CN112160642B (en) Double-return pi-shaped connecting tower
CN204668884U (en) A kind of preformed damping conductor spacer
CN103354319A (en) 220kV outdoor GIS double-dragonfly-type outlet wire arrangement structure
CN102979348B (en) Tower is forced down in a kind of high-tension line four loops
CN206071191U (en) Bore and get over tower in 110kV common-tower double-returns road
CN215331824U (en) Corner tower
CN216699321U (en) Transformer substation framework adopting cantilever beam structure
CN203867258U (en) 110kV lattice composite material pole tower
CN216197038U (en) Double-loop pi connects strain insulator steel pipe pole
CN207568301U (en) F sections towers
CN215168584U (en) Strain tower and power transmission system
CN203334761U (en) Abnormal-shaped double-loop iron tower

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination