CN109296211A - 一种装配式钢结构建筑构件安装偏差控制方法 - Google Patents
一种装配式钢结构建筑构件安装偏差控制方法 Download PDFInfo
- Publication number
- CN109296211A CN109296211A CN201811154723.1A CN201811154723A CN109296211A CN 109296211 A CN109296211 A CN 109296211A CN 201811154723 A CN201811154723 A CN 201811154723A CN 109296211 A CN109296211 A CN 109296211A
- Authority
- CN
- China
- Prior art keywords
- deviation
- welding
- steel structure
- type steel
- control
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种装配式钢结构建筑构件安装偏差控制方法,包括以下步骤:步骤1,定位轴线基准控制点;步骤2,确定构件吊装位置;步骤3,吊装构件;步骤4,确定施焊顺序;步骤5,轴线复测与验收;本发明装配式钢结构建筑构件安装偏差控制方法通过运用电子全站仪、经纬仪、水准仪和激光铅垂仪实现构件安装全过程偏差控制,有效避免工程因安装构件偏差出现的质量问题,提高工程质量;本发明装配式钢结构建筑构件安装偏差控制方法,能够有效控制构件安装偏差在可控范围内,提高效率,缩短工期。
Description
技术领域
本发明属于装配式建筑安装偏差控制技术领域,具体涉及一种装配式钢结构建筑构件安装偏差控制方法。
背景技术
当前建筑工业化越发盛行,装配式钢结构建筑作为建筑工业化结构体系之一,正在得到国家政府以及企业的大力推行,但装配式钢结构建筑安装精确化的需求,使构件安装效率和准确性正成为装配式钢结构建筑施工的难点之一,迫切需要一种快速、优质的安装偏差控制方法,提高装配式钢结构项目的安装效率,节约安装成本,为企业增益。
发明内容
本发明运用电子全站仪、经纬仪、水准仪和激光铅垂仪实现安装全过程偏差控制,减少安装过程中安装误差,有效避免工程因安装偏差出现的质量问题,该方法已成功运用于装配式构件安装施工,有效提高企业安装效率和安装准确性。
为了实现上述目的,本发明采用如下技术方案:
一种装配式钢结构建筑构件安装偏差控制方法,包括以下步骤:
步骤1,定位轴线基准控制点,轴线投测,架设激光铅垂仪于首层平面控制网的基准控制点,并打开激光发生器,通过预留孔洞,将有光学成象物镜与CCD光点传感器的激光接收靶由导线引入计算机系统,移动接收靶使靶中心与基点中心相吻合,得到传递后的基准控制点即轴线基准控制点,弹正交十字墨线至楼板面上,作好标记,并保护好接收靶;
步骤2,确定构件吊装位置,依据所在楼层基准控制点,进行平面放线和投测竖向轴线,确定构件顶部位移值,对超出允许值内的偏差,进行超偏差处理,精准构件安装位置;
步骤3,吊装构件,构件到达安装位置后,进行高强度螺栓初拧和终拧,初拧前可先用长水平尺粗略控制垂直度,在形成框架后利用全站仪、水准仪和经纬仪精确校正构件垂直度和水平度,考虑偏差预留,并预留偏差范围,检验结果在偏差范围内执行步骤4;检测结果不在偏差范围内,通过执行本步骤调整构件之间的位置关系;
步骤4,确定施焊顺序,整理吊装测量记录,根据记录合理设置施焊顺序,并且跟踪测量施焊过程;
步骤5,轴线复测与验收,在焊接合格后,通过全站仪和经纬仪对构件进行轴线复测与验收,并与终拧时的测量结果进行对比,通过对比分析结果调整下节构件尺寸,以控制整个安装过程中偏差在允许范围之内。
步骤1所述的首层平面控制网的基准控制点,其中平面控制网是指在总平面布置图上设计的,网中确定的几条基本直线是施工放样的控制线,网中直线相交的点即为控制点;其中首层基准控制点产生于控制点;
步骤1所述的预留孔洞,基础工程完成后,随着结构的不断升高,逐层向上投测竖向轴线,考虑首层基准控制点能够投至最大高度,在楼板上预留孔洞使其能上、下贯通且互相通视设置。
步骤2所述的投测竖向轴线通过全站仪、经纬仪和水准仪得出。
步骤2所述的超偏差即超过现场安装可调范围内的偏差,将此偏差数值反馈给工厂,工厂根据偏差数值对下节构件尺寸进行调整,以使偏差在可控范围内。
步骤2所述的所在楼层基准控制点包括首层基准控制点和经过轴线投测后得到的基准控制点。
步骤4所述的施焊顺序为:构件与构件的焊接,由两名焊工在两相对面等温、等速对称施焊,楼层范围内焊接由四周向中心,保持焊接位置中心对称;跟踪测量则包括焊前材料机械检查、焊中质量和偏差检查以及焊后的超声波探伤检查,确保施焊合格。
本发明的有益效果:本发明装配式钢结构建筑构件安装偏差控制方法通过运用电子全站仪、经纬仪、水准仪和激光铅垂仪实现构件安装全过程偏差控制,有效避免工程因安装构件偏差出现的质量问题,提高工程质量;本发明装配式钢结构建筑构件安装偏差控制方法,能够有效控制构件安装偏差在可控范围内,提高项目构件安装效率,缩短工期,进而节约生产成本。
附图说明
图1为本发明构件安装偏差控制流程图。
具体实施方式
下面结合附图和实施例对本发明作进一步的详细说明。
如图1所示,一种装配式钢结构建筑构件安装偏差控制方法,包括以下步骤:
步骤1,定位轴线基准控制点,轴线投测,架设激光铅垂仪于首层平面控制网的基准控制点,并打开激光发生器,通过预留孔洞,将有光学成象物镜与CCD光点传感器的激光接收靶由导线引入计算机系统,移动接收靶使靶中心与基点中心相吻合,得到传递后的基准控制点即轴线基准控制点,弹正交十字墨线至楼板面上,作好标记,并保护好接收靶;
步骤2,确定构件吊装位置,依据所在楼层基准控制点,进行平面放线和投测竖向轴线,确定构件吊装位置,对超出允许值内的偏差,进行超偏差处理,精准构件安装位置;
步骤3,吊装构件,构件到达安装位置后,进行高强度螺栓初拧和终拧,初拧前可先用长水平尺粗略控制垂直度,在形成框架后利用全站仪、水准仪和经纬仪精确校正构件垂直度和水平度,考虑偏差预留,并预留偏差范围,建筑不同,偏差范围不同,偏差范围一般由工艺组根据实际工况进行设定,检验结果在偏差范围内执行步骤4;检测结果不在偏差范围内,通过执行本步骤调整构件之间的位置关系;
步骤4,确定施焊顺序,整理吊装测量记录,根据记录合理设置施焊顺序,并且跟踪测量施焊过程;
步骤5,轴线复测与验收,在焊接合格后,通过全站仪和经纬仪对构件进行轴线复测与验收,并与终拧时的测量结果进行对比,通过对比分析结果调整下节构件尺寸,以控制整个安装过程中偏差在允许范围之内。
步骤1所述的首层平面控制网的基准控制点,其中平面控制网是指在总平面布置图上设计的,网中确定的几条基本直线是施工放样的控制线,网中直线相交的点即为控制点;其中首层基准控制点产生于控制点;
步骤1所述的预留孔洞,基础工程完成后,随着结构的不断升高,逐层向上投测竖向轴线,考虑首层基准控制点能够投至最大高度,在楼板上预留孔洞使其能上、下贯通且互相通视设置。
步骤2所述的投测竖向轴线通过全站仪、经纬仪和水准仪得出。
步骤2所述的超偏差即超过现场安装可调范围内的偏差,将此偏差数值反馈给工厂,工厂根据偏差数值对下节构件尺寸进行调整,以使偏差在可控范围内。
步骤2所述的所在楼层基准控制点包括首层基准控制点和经过轴线投测后得到的基准控制点。
步骤4所述的施焊顺序为:构件与构件的焊接,由两名焊工在两相对面等温、等速对称施焊,楼层范围内焊接由四周向中心,保持焊接位置中心对称;跟踪测量则包括焊前材料机械检查、焊中质量和偏差检查以及焊后的超声波探伤检查,确保施焊合格。
Claims (7)
1.一种装配式钢结构建筑构件安装偏差控制方法,其特征在于,包括以下步骤:
步骤1,定位轴线基准控制点,轴线投测,架设激光铅垂仪于首层平面控制网的基准控制点,并打开激光发生器,通过预留孔洞,将有光学成象物镜与CCD光点传感器的激光接收靶由导线引入计算机系统,移动接收靶使靶中心与基点中心相吻合,得到传递后的基准控制点即轴线基准控制点,弹正交十字墨线至楼板面上,作好标记,并保护好接收靶;
步骤2,确定构件吊装位置,依据所在楼层基准控制点,进行平面放线和投测竖向轴线,确定构件顶部位移值,对超出允许值内的偏差,进行超偏差处理,精准构件安装位置;
步骤3,吊装构件,构件到达安装位置后,进行高强度螺栓初拧和终拧,初拧前可先用长水平尺粗略控制垂直度,在形成框架后利用全站仪、水准仪和经纬仪精确校正构件垂直度和水平度,考虑偏差预留,并预留偏差范围,检验结果在偏差范围内执行步骤4;检测结果不在偏差范围内,通过执行本步骤调整构件之间的位置关系;
步骤4,确定施焊顺序,整理吊装测量记录,根据记录合理设置施焊顺序,并且跟踪测量施焊过程;
步骤5,轴线复测与验收,在焊接合格后,通过全站仪和经纬仪对构件进行轴线复测与验收,并与终拧时的测量结果进行对比,通过对比分析结果调整下节构件尺寸,以控制整个安装过程中偏差在允许范围之内。
2.根据权利要求1所述的一种装配式钢结构建筑构件安装偏差控制方法,其特征在于:步骤1所述的首层平面控制网的基准控制点,其中平面控制网是指在总平面布置图上设计的,网中确定的几条基本直线是施工放样的控制线,网中直线相交的点即为控制点;其中首层基准控制点产生于控制点。
3.根据权利要求1所述的一种装配式钢结构建筑构件安装偏差控制方法,其特征在于:步骤1所述的预留孔洞,基础工程完成后,随着结构的不断升高,逐层向上投测竖向轴线,考虑首层基准控制点能够投至最大高度,在楼板上预留孔洞使其能上、下贯通且互相通视设置。
4.根据权利要求1所述的一种装配式钢结构建筑构件安装偏差控制方法,其特征在于:步骤2所述的投测竖向轴线通过全站仪、经纬仪和水准仪得出。
5.根据权利要求1所述的一种装配式钢结构建筑构件安装偏差控制方法,其特征在于:步骤2所述的超偏差即超过现场安装可调范围内的偏差,将此偏差数值反馈给工厂,工厂根据偏差数值对下节构件尺寸进行调整,以使偏差在可控范围内。
6.根据权利要求1所述的一种装配式钢结构建筑构件安装偏差控制方法,其特征在于:步骤2所述的所在楼层基准控制点包括首层基准控制点和经过轴线投测后得到的基准控制点。
7.根据权利要求1所述的一种装配式钢结构建筑构件安装偏差控制方法,其特征在于:步骤4所述的施焊顺序为:构件与构件的焊接,由两名焊工在两相对面等温、等速对称施焊,楼层范围内焊接由四周向中心,保持焊接位置中心对称;跟踪测量则包括焊前材料机械检查、焊中质量和偏差检查以及焊后的超声波探伤检查,确保施焊合格。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811154723.1A CN109296211B (zh) | 2018-09-30 | 2018-09-30 | 一种装配式钢结构建筑构件安装偏差控制方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811154723.1A CN109296211B (zh) | 2018-09-30 | 2018-09-30 | 一种装配式钢结构建筑构件安装偏差控制方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109296211A true CN109296211A (zh) | 2019-02-01 |
CN109296211B CN109296211B (zh) | 2021-10-22 |
Family
ID=65161246
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811154723.1A Active CN109296211B (zh) | 2018-09-30 | 2018-09-30 | 一种装配式钢结构建筑构件安装偏差控制方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109296211B (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110594536A (zh) * | 2019-09-04 | 2019-12-20 | 河南省安装集团有限责任公司 | 一种塔类设备的垂直度调整方法 |
CN111322999A (zh) * | 2020-03-27 | 2020-06-23 | 中国建筑一局(集团)有限公司 | 基于红外线传感器的可周转装配式定位装置及其使用方法 |
CN112338383A (zh) * | 2020-11-23 | 2021-02-09 | 中国建筑一局(集团)有限公司 | 一种型钢劲性柱上下节的辅助焊接装置及焊接方法 |
CN112942854A (zh) * | 2021-02-02 | 2021-06-11 | 中铁八局集团有限公司 | 一种装配式结构吊装施工方法 |
CN113374282A (zh) * | 2021-06-30 | 2021-09-10 | 中国二十二冶集团有限公司 | 采用假定坐标系控制预埋螺栓的方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101429752A (zh) * | 2007-11-05 | 2009-05-13 | 中交一航局第一工程有限公司 | 墩柱预制拼接建造技术工法 |
CN104763156A (zh) * | 2015-04-01 | 2015-07-08 | 中国核工业华兴建设有限公司 | 一种核电站钢制安全壳底封头的组装方法 |
CN106088399A (zh) * | 2016-06-07 | 2016-11-09 | 潮峰钢构集团有限公司 | 一种多腔钢柱剪力墙组合结构建筑体系的安装方法 |
CN106284787A (zh) * | 2016-08-05 | 2017-01-04 | 成都市第四建筑工程公司 | 装配式叠合板安装及定位方法 |
CN107101621A (zh) * | 2017-03-20 | 2017-08-29 | 广州珠江工程建设监理有限公司 | 一种超高层建筑工程测量的监理控制方法 |
CN107130809A (zh) * | 2017-05-23 | 2017-09-05 | 中国建筑第八工程局有限公司 | 一种超高层核心筒墙体施工测量定位方法及系统 |
-
2018
- 2018-09-30 CN CN201811154723.1A patent/CN109296211B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101429752A (zh) * | 2007-11-05 | 2009-05-13 | 中交一航局第一工程有限公司 | 墩柱预制拼接建造技术工法 |
CN104763156A (zh) * | 2015-04-01 | 2015-07-08 | 中国核工业华兴建设有限公司 | 一种核电站钢制安全壳底封头的组装方法 |
CN106088399A (zh) * | 2016-06-07 | 2016-11-09 | 潮峰钢构集团有限公司 | 一种多腔钢柱剪力墙组合结构建筑体系的安装方法 |
CN106284787A (zh) * | 2016-08-05 | 2017-01-04 | 成都市第四建筑工程公司 | 装配式叠合板安装及定位方法 |
CN107101621A (zh) * | 2017-03-20 | 2017-08-29 | 广州珠江工程建设监理有限公司 | 一种超高层建筑工程测量的监理控制方法 |
CN107130809A (zh) * | 2017-05-23 | 2017-09-05 | 中国建筑第八工程局有限公司 | 一种超高层核心筒墙体施工测量定位方法及系统 |
Non-Patent Citations (1)
Title |
---|
张霞: "装配式混凝土结构质量控制及监管研究", 《施工技术》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110594536A (zh) * | 2019-09-04 | 2019-12-20 | 河南省安装集团有限责任公司 | 一种塔类设备的垂直度调整方法 |
CN110594536B (zh) * | 2019-09-04 | 2020-12-11 | 河南省安装集团有限责任公司 | 一种塔类设备的垂直度调整方法 |
CN111322999A (zh) * | 2020-03-27 | 2020-06-23 | 中国建筑一局(集团)有限公司 | 基于红外线传感器的可周转装配式定位装置及其使用方法 |
CN111322999B (zh) * | 2020-03-27 | 2023-06-30 | 中国建筑一局(集团)有限公司 | 基于红外线传感器的可周转装配式定位装置及其使用方法 |
CN112338383A (zh) * | 2020-11-23 | 2021-02-09 | 中国建筑一局(集团)有限公司 | 一种型钢劲性柱上下节的辅助焊接装置及焊接方法 |
CN112942854A (zh) * | 2021-02-02 | 2021-06-11 | 中铁八局集团有限公司 | 一种装配式结构吊装施工方法 |
CN113374282A (zh) * | 2021-06-30 | 2021-09-10 | 中国二十二冶集团有限公司 | 采用假定坐标系控制预埋螺栓的方法 |
Also Published As
Publication number | Publication date |
---|---|
CN109296211B (zh) | 2021-10-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109296211A (zh) | 一种装配式钢结构建筑构件安装偏差控制方法 | |
CN109184213B (zh) | 基于bim放样与三维扫描的钢网架施工工艺 | |
CN102251476A (zh) | 钢管格构墩现场安装测量控制方法 | |
CN108827255B (zh) | 一种基于bim的钢混组合结构索塔的索鞍测量方法 | |
CN102564393A (zh) | 隧道全断面三维激光监控量测方法 | |
CN106092059A (zh) | 一种基于多点拟合的结构物平面位移监测方法 | |
CN106638318B (zh) | 斜拉桥梁端锚固点的定位方法及索导管安装方法 | |
CN107255442B (zh) | 基于激光跟踪技术的大尺寸水轮发电机定子安装测量方法 | |
CN109959343A (zh) | 一种利用激光监测超高层建筑变形的装置和方法 | |
CN107270814A (zh) | 一种预制装配式风洞高精度安装控制方法 | |
CN105973141B (zh) | 一种盾构隧道管片错台测量装置 | |
CN102778893B (zh) | 一种桁架梁精确就位检测方法 | |
CN110470287A (zh) | 斜拉桥索导管定位方法 | |
CN106197292A (zh) | 一种建筑物位移监测方法 | |
CN113374282B (zh) | 采用假定坐标系控制预埋螺栓的方法 | |
CN109990703A (zh) | 一种预制构件的尺寸检测方法及系统 | |
CN108592877A (zh) | 一种变尺寸穹顶半径检测方法 | |
CN113865570B (zh) | 一种钢结构圆形立柱垂直度测量方法 | |
CN110318338B (zh) | 一种安装定位钢锚梁的测量控制方法 | |
CN108303072A (zh) | 一种用于闸门门槽安装过程中的测量装置以及测量方法 | |
CN108385538A (zh) | 斜拉桥的预制钢塔安装于混凝土塔柱的方法 | |
CN108507549A (zh) | 高温气冷堆堆内石墨砖和碳砖的安装测量方法 | |
CN108637037B (zh) | 一种钢材冷矫直机校验矫直辊水平度的方法 | |
CN104848829A (zh) | 组合模板检测系统及方法 | |
CN115371599A (zh) | 一种高精度地面平整度测量系统和方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |