A kind of industrial gasses automatic charging device
Technical field
The invention belongs to the technical field of gas filling, in particular to a kind of industrial gasses automatic charging device.
Background technique
Traditional industrial gas cylinder fills, and what is used is all manually-operated gate and site pressure table, passes through observation site pressure gauge
Valve is opened and closed, is all that multiple stations that fill are filled using same gas source since industrial gas cylinder fills, in difference
It fills in the handoff procedure of station, often occurs opening not in time another after the pressure of this group of busbar connector is charged to and closes valve
When the valve of group busbar connector, it is be easy to cause hypertonia, there are very big security risk, and manual control switch's valve labor intensity
Also larger.
Summary of the invention
The object of the present invention is to provide a kind of industrial gasses automatic charging device, the labour for reducing manual control switch's valve is strong
Degree, improves work efficiency, while having very high safety.
The object of the present invention is achieved like this: a kind of industrial gasses automatic charging device, and described device includes connection work
The gas of industry gas source conveys supervisor, and the end of gas conveying supervisor, which is connected with first, to be in charge of and be in charge of with second, and first is in charge of
Connection first fills station, and second, which is in charge of connection second, fills station, and described first is in charge of and is provided with first and fills pneumatic operated valve
Door, second is in charge of and is provided with second and fills operated pneumatic valve, is provided with first pressure monitoring point on the gas conveying supervisor, the
One, which fills operated pneumatic valve and first, fills and is provided with second pressure monitoring point between station, and second fills operated pneumatic valve fills with second
Third pressure monitoring point is provided between dress station.
It is provided with the first evacuated tube on above-mentioned gas conveying supervisor, the first evacuated tube is located at after first pressure monitoring point,
The first air-discharging movable valve is provided in first evacuated tube, the first evacuated tube is connected with the external world.
Above-mentioned first is in charge of to be in charge of with second and is parallel with the second evacuated tube, and the both ends of the second evacuated tube are connected to first
It fills between operated pneumatic valve and second pressure monitoring point, second fills between operated pneumatic valve and third pressure monitoring point, second row
The second air-discharging movable valve and third emptying operated pneumatic valve are provided on blank pipe, the second air-discharging movable valve and third emptying are pneumatic
Third evacuated tube is connected between valve, third evacuated tube is connected with the external world.
Above-mentioned first is in charge of to be in charge of with second and is parallel with the first vacuum tube, and the both ends of the first vacuum tube are connected to first
Fill between operated pneumatic valve and second pressure monitoring point, second fills between operated pneumatic valve and third pressure monitoring point, first is true
The first Pneumatic vacuum valve and the second Pneumatic vacuum valve, the first Pneumatic vacuum valve and the second Pneumatic vacuum are provided on blank pipe
The second vacuum tube is connected between valve, the second vacuum tube is connected with pumped vacuum systems.
Above-mentioned each pressure monitoring point is provided with site pressure table and pressure transmitter.
Pressure signal is changed into electric signal by the pressure transmitter of above-mentioned each pressure monitoring point, and with pressure controller phase
Even, above-mentioned each operated pneumatic valve is controlled by pressure controller and PLC program timer, and is driven by pneumatic air source.Pass through
The program step that PLC program timer is set is automatically opened and is closed according to the pressure requirements of different step and is corresponding
Valve.
Above-mentioned apparatus further includes control panel, and control button, buzzer and indicator light are provided on control panel.
Compared to the prior art the present invention, has the following beneficial effects:
1, the program step that the present invention is set by PLC program timer, according to the pressure requirements of different step
Corresponding operated pneumatic valve is automatically opened and closed, the automatic filling of industrial gasses is realized, reduces the labor of manual control switch's valve
Fatigue resistance improves work efficiency.
2, the present invention opens and closes valve in strict accordance with time-program(me) and pressure instruction, therefore security performance mentions significantly
Height, meanwhile, control panel can also be further arranged in the present invention, have buzzer and indicator light to mention after each step movement in place
Wake up, be related to steel cylinder clamp and etc. when can be switched to manual operation, be then turned on next step after the completion of operation, further increase peace
Quan Xing.
3, the present invention is provided with automatic safety device, can be certainly when pressure is more than setting value or temperature is lower than setting value
The power supply of dynamic cutting compressor.
4, the operated pneumatic valve that the present invention is driven using pneumatic air source, the operation for opening and closing valve is gentle, safety
Performance is high.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention.
Appended drawing reference: 1, gas conveying supervisor;2, first is in charge of;3, second is in charge of;4, first station is filled;5, second fills
Fill station;6, first operated pneumatic valve is filled;7, second operated pneumatic valve is filled;8, first pressure monitoring point;9, second pressure monitors
Point;10, third pressure monitoring point;11, the first evacuated tube;12, the first air-discharging movable valve;13, the second evacuated tube;14, second
Empty operated pneumatic valve;15, third empties operated pneumatic valve;16, third evacuated tube;17, the first vacuum tube;18, the first Pneumatic vacuum
Valve;19, the second Pneumatic vacuum valve;20, the second vacuum tube.
Specific embodiment
With specific embodiment, the invention will be further described with reference to the accompanying drawing, referring to Fig. 1:
A kind of industrial gasses automatic charging device, described device include connecting the gas conveying supervisor 1 of industrial gasses gas source,
The end of gas conveying supervisor 1, which is connected with first, to be in charge of 2 and second and is in charge of 3, and first, which is in charge of 2 connections first, fills station 4, and second
It is in charge of 3 connections second and fills station 5, described first is in charge of on 2 and is provided with first and fills operated pneumatic valve 6, and second is in charge of on 3 and is arranged
There is second to fill operated pneumatic valve 7, is provided with first pressure monitoring point 8 on the gas conveying supervisor 1, first fills operated pneumatic valve
6 and first fill and are provided with second pressure monitoring point 9 between station 4, second fill operated pneumatic valve 7 and second fill station 5 it
Between be provided with third pressure monitoring point 10.
It is provided with the first evacuated tube 11 on above-mentioned gas conveying supervisor 1, the first evacuated tube 11 is located at first pressure monitoring point 8
Later, the first air-discharging movable valve 12 is provided in the first evacuated tube 11, the first evacuated tube 11 is connected with the external world.
Above-mentioned first, which is in charge of 2 and second, is in charge of 3 and is parallel with the second evacuated tube 13, and the both ends of the second evacuated tube 13 are separately connected
It fills between operated pneumatic valve 6 and second pressure monitoring point 9 first, second fills operated pneumatic valve 7 and third pressure monitoring point 10
Between, the second air-discharging movable valve 14 and third emptying operated pneumatic valve 15 are provided in the second evacuated tube 13, the second air-discharging is dynamic
It is connected with third evacuated tube 16 between valve 14 and third emptying operated pneumatic valve 15, third evacuated tube 16 is connected with the external world.
Above-mentioned first, which is in charge of 2 and second, is in charge of 3 and is parallel with the first vacuum tube 17, and the both ends of the first vacuum tube 17 are separately connected
It fills between operated pneumatic valve 6 and second pressure monitoring point 9 first, second fills operated pneumatic valve 7 and third pressure monitoring point 10
Between, the first Pneumatic vacuum valve 18 and the second Pneumatic vacuum valve 19, the first Pneumatic vacuum are provided on the first vacuum tube 17
The second vacuum tube 20, the second vacuum tube 20 and pumped vacuum systems phase are connected between valve 18 and the second Pneumatic vacuum valve 19
Even.
Above-mentioned each pressure monitoring point is provided with site pressure table and pressure transmitter.
Pressure signal is changed into electric signal by the pressure transmitter of above-mentioned each pressure monitoring point, and with pressure controller phase
Even, above-mentioned each operated pneumatic valve is controlled by pressure controller and PLC program timer, and is driven by pneumatic air source.Pass through
The program step that PLC program timer is set is automatically opened and is closed according to the pressure requirements of different step and is corresponding
Valve.
Automatic filling process of the invention is as follows: the program step set according to PLC program timer successively into
Row operation controls first first and fills operated pneumatic valve 6, and other operated pneumatic valves are closed, and the steel cylinder for filling station 4 to first fills
Dress, after the pressure of second pressure monitoring point 9 reaches setting value, stops filling, and closes first and fills operated pneumatic valve 6, opens the
Two fill operated pneumatic valve 7, and the steel cylinder for filling station 5 to second fills, and set when the pressure of third pressure monitoring point 10 reaches
After definite value, stop filling.
When needing to empty pipeline, corresponding emptying operated pneumatic valve is opened, other operated pneumatic valves is closed, is arranged
Do-nothing operation.
When needing to carry out steel cylinder exclusion residual gas before filling, when extracting vacuum, opens and vacuumize accordingly pneumatically
Valve closes other operated pneumatic valves, carries out vacuum pumping.
Above-mentioned apparatus further includes control panel, and control button, buzzer and indicator light are provided on control panel.Buzzer
It is used to indicate step with indicator light to complete or sound an alarm, control button is used to carry out the operation needed for other, such as switches artificial
Operation etc..
Above-described embodiment is only presently preferred embodiments of the present invention, is not limited the scope of the invention according to this, therefore: it is all according to
The equivalence changes that structure of the invention, shape, principle are done, should all be covered by within protection scope of the present invention.