CN109242263A - A kind of assembled architecture BIM module management system - Google Patents

A kind of assembled architecture BIM module management system Download PDF

Info

Publication number
CN109242263A
CN109242263A CN201810924879.7A CN201810924879A CN109242263A CN 109242263 A CN109242263 A CN 109242263A CN 201810924879 A CN201810924879 A CN 201810924879A CN 109242263 A CN109242263 A CN 109242263A
Authority
CN
China
Prior art keywords
module
bim
information
unit
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810924879.7A
Other languages
Chinese (zh)
Inventor
张大力
殷许鹏
姬中凯
董明明
刘燕丽
郭伟
闫瑾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Urban Construction
Original Assignee
Henan University of Urban Construction
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Urban Construction filed Critical Henan University of Urban Construction
Priority to CN201810924879.7A priority Critical patent/CN109242263A/en
Publication of CN109242263A publication Critical patent/CN109242263A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisions for transferring data to distant stations, e.g. from a sensing device
    • G06K17/0029Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisions for transferring data to distant stations, e.g. from a sensing device the arrangement being specially adapted for wireless interrogation of grouped or bundled articles tagged with wireless record carriers
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/80Management or planning
    • Y02P90/82Energy audits or management systems therefor

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Primary Health Care (AREA)
  • General Health & Medical Sciences (AREA)
  • Health & Medical Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to building fields, more particularly to a kind of assembled architecture BIM module management system, processing module includes process equipment unit, machining control unit and machining information acquiring unit, the data information that control management module is used to provide according to BIM module, machining information acquiring unit is used to obtain the machining information of process equipment unit, the data information that control management module is used to provide according to BIM module, installing mobile position-fixed module includes GPS positioning device, wireless communication apparatus, camera, storage device and display, the present invention is in the construction stage, make the production installation progress of administrative staff's quick obtaining scene component by the management system, cost, quality, the engineering informations such as safety, and it is effectively managed;In the O&M stage, it is sufficiently used for facility maintenance management, realizes energy dynamic monitoring, the historical data of record can be used as the basis of energy consumption analysis comparison, be adjusted optimization to abnormal energy consumption.

Description

A kind of assembled architecture BIM module management system
Technical field
The present invention relates to building fields, and in particular to a kind of assembled architecture BIM module management system.
Background technique
Assembled architecture refers to the building built by prefabricated components by being reliably connected mode.There are two main for assembled architecture Want feature: first feature is that the main member especially structural elements of composition building is prefabricated;Second feature is prefabricated The connection type of component must be reliable.Classify by structural material, there is assembling type steel structure building, assembled steel reinforced concrete to build It builds, structure with assembled lightweight steel building, assembled composite material building.This research refers mainly to assembled steel Reinforced Concrete Buildings, and Building Information Model is a kind of multidimensional (three-dimensional space, four-dimensional time, five dimension costs, N-dimensional are more applied) integrated skill of model information Art, can make construction project each participant (including responsible departments of the government, owner, design, construction, management, cost, operation pipe Reason, project user etc.) it is generated from concept to letter can be operated in a model in the whole life cycle removed completely in project Breath and operation model in the information, thus fundamentally change practitioner by lexigraphy form drawing carry out project construction and The working method of operation management realizes construction project in Life cycle and improves working efficiency and quality and reduction fault With the targets such as risk.
And assembled architecture in building course prefabricated components it is many kinds of, how by the processing of control member until Fixing link, thus achieve the purpose that efficiently and accurately installation just seem increasingly important, in addition Building Information Model how with building Production and operation carry out further combined be also the application needs further solve the problems, such as.
Summary of the invention
To solve problem of the prior art, the present invention provides a kind of assembled architecture BIM module management systems.
In order to achieve the above object, the invention adopts the following technical scheme: a kind of assembled architecture BIM module management system System, the system include:
Processing module, processing module include process equipment unit, machining control unit and machining information acquiring unit, machining control Unit and machining information acquiring unit are connect with process equipment cell data, and machining control unit is for controlling process equipment list The processing operation of member, machining information acquiring unit are used to obtain the machining information of process equipment unit, machining information acquiring unit It is connect with BIM module, the presupposed information that the machining information of component obtains component in the information and BIM module that module obtains is carried out Compare, phase machining control unit issues signal if consistent, so that process equipment unit works normally, makes to add if inconsistent Construction equipment unit stops working;
Management module is controlled, structure is written in the information of component by the data information that control management module is used to provide according to BIM module Part RFID tag is placed in component RFID tag when mounting target member, is placed in component when mounting target member RFID tag, BIM module are responsible for receiving the label ID information of RFID reader, go to execute data base querying work by id information Make, send BIM module for the result of inquiry again later, the production that BIM module obtains component produces family, date of manufacture, size number It is believed that ceasing and showing;
Mobile position-fixed module is installed, installation mobile position-fixed module includes GPS positioning device, is asked for sending positioning to GPS system It seeks information and receives the GPS position information of GPS system return;BIM module obtains the positioning of construction personnel by GPS positioning device Information;Wireless communication apparatus passes through BIM for sending BIM module for the received GPS position information of GPS terminal module Module carries out the real-time location tracking of personnel GPS;Camera will shoot obtained picture number for shooting to construction member The size comparison of component and the Comparative result and error of component installation are carried out according to BIM module is sent to by wireless communication apparatus Correction, storage device, for storing the component data information of BIM system, component data information includes scantling information and peace Holding position information;Display, for being connect with storage device and positioning device, for showing the location information and structure of mobile terminal The BIM information of part.
The system further includes production site environment module, and production site environment module includes dust concentration detector and wind speed Wind transducer, dust concentration detector are set to construction site wall top portion all around, dust concentration detector by route with Inside server connection or construction, with real-time monitoring building yard dust concentration;
The wind speed wind direction sensor is for acquiring instantaneous wind speed, the wind speed and direction stress information caused by dust recycling and being transmitted to BIM module;
The system further includes operation control module, and operation control module includes BIM building O&M unit, building facility energy consumption data Unit and building automation unit, BIM building O&M unit are connect with building facility information data unit and building automation unit; Then BIM builds O&M unit can be led to using three-dimensional laser scanner acquisition building and pipeline solid space point cloud data It crosses data to be converted into, building facility energy consumption data module passes through the energy consumption data that arrives water level sensor, ammeter instrument to collect Incoming BIM builds O&M unit.
The building automation module can click corresponding position by video monitoring camera and play in real time, be built using BIM Build O&M module simulation adjustment monitor camera monitoring area.
Compared with prior art, advantageous effect of the invention is: in the construction stage, obtaining administrative staff quickly by the management system The engineering informations such as the production installation progress of enchashment field component, cost, quality, safety, and effectively managed;In the O&M stage, It is sufficiently used for facility maintenance management, realizes energy dynamic monitoring, the historical data of record can be used as the base of energy consumption analysis comparison Plinth is adjusted optimization to abnormal energy consumption.
Detailed description of the invention
Upon reading the detailed description of non-limiting embodiments with reference to the following drawings, other feature of the invention, Objects and advantages will become more apparent upon.
Fig. 1 is structure of the invention block diagram.
Specific embodiment
The present invention is described in further details below by embodiment, embodiment is only used to illustrate the present invention, and unlimited The scope of the present invention processed.
A kind of assembled architecture BIM module management system as shown in Figure 1, which includes that processing module includes process equipment Unit, machining control unit and machining information acquiring unit, machining control unit and machining information acquiring unit are set with processing Standby cell data connects, and machining control unit is used to control the processing operation of process equipment unit, and machining information acquiring unit is used In the machining information for obtaining process equipment unit, machining information acquiring unit connect with BIM module, the machining information of component is obtained The information that modulus block obtains is compared with the presupposed information of component in BIM module, and phase machining control unit issues if consistent Signal, so that process equipment unit works normally;Process equipment unit is made to stop working if inconsistent.Control management module Component RFID tag is written in the information of component by the data information for providing according to BIM module, and the information of component includes component Machining information and component presupposed information, when mounting target member be placed in component RFID tag, in installation targets structure It is placed in component RFID tag when part, each component of interior of building is all sticked into component RFID tag.Be conducive in this way Component tracks the development of work, and BIM module is responsible for receiving the label ID information of RFID reader, goes to execute data by id information Library inquiry work, sends BIM module for the result of inquiry again later, and the production that BIM module obtains component produces family, production date Phase, dimension data information are simultaneously shown.In the storage period of component, patrol officer to label information expansion read work when Wait, patrol officer to component carry out regularly check after, the information to database and label timely updated, will patrol The result of inspection is detailed to be recorded, and facilitates make reference next time, and after the information in database is timely updated, thus The information of the inquiry and Retrieval Component that can go deep into.Installing mobile position-fixed module includes GPS positioning device, is used for GPS system It sends positioning request information and receives the GPS position information of GPS system return;BIM module is obtained by GPS positioning device and is constructed The location information of personnel;Wireless communication apparatus, for sending BIM mould for the received GPS position information of GPS terminal module Block carries out the real-time location tracking of personnel GPS by BIM module;Camera will be shot for shooting to construction member To image data by wireless communication apparatus be sent to BIM module carry out component size comparison and component installation result pair Than the correction with error, thus the installation process of standard construction personnel in time;Storage device, for storing the component of BIM system Data information, component data information include scantling information and installation site information;Display, for storage device and calmly Position device connection, for showing that the location information of mobile terminal and the BIM information of component, mobile position-fixed module can provide in real time The operating path of each building station personnel, while personnel shoot photo by camera and BIM module carries out the size pair of component Than the correction of the Comparative result and error installed with component, the deviation in installation process is found in time, while for site operation people Member can also know the mount message of component by display.Production site environment module includes dust concentration detector and wind speed Wind transducer, dust concentration detector are set to construction site wall top portion all around, dust concentration detector by route with Inside server connection or construction, with real-time monitoring building yard dust concentration.Dust concentration detector uses ZY3400 Type, the wind speed wind direction sensor is for acquiring instantaneous wind speed, the wind speed and direction stress information caused by dust recycling and being transmitted to BIM module;Wind-force has apparent influence to dust recycling, and when wind-force increases to 6-7 grades, building dust easily expands on a large scale It dissipates, influences air quality.When this wind-force is more than preset value, warned automatically by the alarm speakers being set in place Show, for stopping construction operation and being dusted by measures such as waterings.Operation control module include BIM building O&M unit, Building facility energy consumption data unit and building automation unit, BIM build O&M unit and building facility information data unit and building The connection of space Automatic Control Unit;BIM builds O&M unit can be using three-dimensional laser scanner acquisition building and pipeline solid space Then point cloud data is converted by data, have the characteristics that high efficiency, high-precision.Building facility energy consumption data module is logical It crosses the energy consumption data for arriving water level sensor, ammeter instrument to collect and is passed to BIM building O&M unit, realize energy dynamic monitoring, The historical data of record can be used as the basis of energy consumption analysis comparison, be adjusted optimization to abnormal energy consumption.Building automation module Corresponding position can be clicked by video monitoring camera to play in real time, taken the photograph using BIM building O&M module simulation adjustment monitoring Camera monitoring area, adjustment layout prevent monitoring dead angle from generating.
The above described is only a preferred embodiment of the present invention, being not that the invention has other forms of limitations, appoint What those skilled in the art changed or be modified as possibly also with the technology contents of the disclosure above equivalent variations etc. Imitate embodiment.But without departing from the technical solutions of the present invention, according to the technical essence of the invention to above embodiments institute Any simple modification, equivalent variations and the remodeling made, still fall within the protection scope of technical solution of the present invention.

Claims (4)

1. a kind of assembled architecture BIM module management system, which is characterized in that the system includes:
Processing module, processing module include process equipment unit, machining control unit and machining information acquiring unit, machining control Unit and machining information acquiring unit are connect with process equipment cell data, and machining control unit is for controlling process equipment list The processing operation of member, machining information acquiring unit are used to obtain the machining information of process equipment unit, machining information acquiring unit It is connect with BIM module, the presupposed information that the machining information of component obtains component in the information and BIM module that module obtains is carried out Compare, phase machining control unit issues signal if consistent, so that process equipment unit works normally, makes to add if inconsistent Construction equipment unit stops working;
Management module is controlled, structure is written in the information of component by the data information that control management module is used to provide according to BIM module Part RFID tag is placed in component RFID tag when mounting target member, is placed in component when mounting target member RFID tag, BIM module are responsible for receiving the label ID information of RFID reader, go to execute data base querying work by id information Make, send BIM module for the result of inquiry again later, the production that BIM module obtains component produces family, date of manufacture, size number It is believed that ceasing and showing;
Mobile position-fixed module is installed, installation mobile position-fixed module includes GPS positioning device, is asked for sending positioning to GPS system It seeks information and receives the GPS position information of GPS system return;BIM module obtains the positioning of construction personnel by GPS positioning device Information;Wireless communication apparatus passes through BIM for sending BIM module for the received GPS position information of GPS terminal module Module carries out the real-time location tracking of personnel GPS;Camera will shoot obtained picture number for shooting to construction member The size comparison of component and the Comparative result and error of component installation are carried out according to BIM module is sent to by wireless communication apparatus Correction, storage device, for storing the component data information of BIM system, component data information includes scantling information and peace Holding position information;Display, for being connect with storage device and positioning device, for showing the location information and structure of mobile terminal The BIM information of part.
2. assembled architecture BIM module management system according to claim 1, it is characterised in that: the system further includes field Ground module, place module include dust concentration detector and wind speed wind direction sensor, and dust concentration detector is set to construction field Ground all around wall top portion, dust concentration detector by route connect with server or construction inside, built with real-time monitoring Build place dust concentration;
The wind speed wind direction sensor is for acquiring instantaneous wind speed, the wind speed and direction stress information caused by dust recycling and being transmitted to BIM module.
3. assembled architecture BIM module management system according to claim 1 or 2, it is characterised in that: the system further includes Control module is runed, operation control module includes BIM building O&M unit, building facility energy consumption data unit and building automation list Member, BIM building O&M unit are connect with building facility information data unit and building automation unit;BIM builds O&M unit can To be then converted into, be built by data using three-dimensional laser scanner acquisition building and pipeline solid space point cloud data It builds facility energy requirements data module and BIM building O&M list is passed to by the energy consumption data for arriving water level sensor, ammeter instrument to collect Member.
4. assembled architecture BIM module management system according to claim 3, it is characterised in that: the building automation mould Block can click corresponding position by video monitoring camera and play in real time, utilize BIM building O&M module simulation adjustment monitoring Camera supervised region.
CN201810924879.7A 2018-08-14 2018-08-14 A kind of assembled architecture BIM module management system Pending CN109242263A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810924879.7A CN109242263A (en) 2018-08-14 2018-08-14 A kind of assembled architecture BIM module management system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810924879.7A CN109242263A (en) 2018-08-14 2018-08-14 A kind of assembled architecture BIM module management system

Publications (1)

Publication Number Publication Date
CN109242263A true CN109242263A (en) 2019-01-18

Family

ID=65071381

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810924879.7A Pending CN109242263A (en) 2018-08-14 2018-08-14 A kind of assembled architecture BIM module management system

Country Status (1)

Country Link
CN (1) CN109242263A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110113571A (en) * 2019-05-07 2019-08-09 合肥芃明科技有限公司 A kind of approaches to IM based on virtual reality and video fusion
CN111321902A (en) * 2020-02-26 2020-06-23 浙江锐博科技工程有限公司 System and method for hoisting components on assembly building construction site
CN111563521A (en) * 2019-02-14 2020-08-21 埃森哲环球解决方案有限公司 Site-specific anomaly detection
CN112214861A (en) * 2019-07-12 2021-01-12 莱芜职业技术学院 Electromechanical system pipeline assembly system based on BIM
CN112435143A (en) * 2020-11-23 2021-03-02 温岭市第一建筑工程有限公司 Building engineering construction optimization system based on BIM
CN112634089A (en) * 2020-12-30 2021-04-09 珠海大横琴科技发展有限公司 Energy consumption processing method and device for property facility
CN112734184A (en) * 2020-12-30 2021-04-30 南通汉腾建筑科技有限公司 Acceptance method and system for assembly type building
CN113259628A (en) * 2021-05-08 2021-08-13 广西艾科普高新技术有限公司 BIM-based laboratory assembly building and method
CN114140899A (en) * 2021-12-20 2022-03-04 浙江交通职业技术学院 Engineering inspection system and method based on artificial intelligence
CN116489592A (en) * 2023-05-26 2023-07-25 安徽江澜建设工程有限公司 Assembled building construction monitored control system based on three-dimensional model

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106600239A (en) * 2016-12-28 2017-04-26 中建科技有限公司 Assembly type building construction full process data cooperation management system based on BIM
CN107967399A (en) * 2017-12-19 2018-04-27 广东建远建筑装配工业有限公司 A kind of assembled architecture Deepen Design method based on BIM softwares
CN108133430A (en) * 2017-11-15 2018-06-08 中建三局第二建设工程有限责任公司 The operation maintenance management method that personnel positioning is combined with BIM
CN108363880A (en) * 2018-02-28 2018-08-03 南通四建集团有限公司 It is a kind of to be applied to construction, operation, the D-BIM methods for safeguarding integrated management

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106600239A (en) * 2016-12-28 2017-04-26 中建科技有限公司 Assembly type building construction full process data cooperation management system based on BIM
CN108133430A (en) * 2017-11-15 2018-06-08 中建三局第二建设工程有限责任公司 The operation maintenance management method that personnel positioning is combined with BIM
CN107967399A (en) * 2017-12-19 2018-04-27 广东建远建筑装配工业有限公司 A kind of assembled architecture Deepen Design method based on BIM softwares
CN108363880A (en) * 2018-02-28 2018-08-03 南通四建集团有限公司 It is a kind of to be applied to construction, operation, the D-BIM methods for safeguarding integrated management

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
郑一梅: "BIM在装配式建筑信息化管理中的应用研究", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 *

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111563521A (en) * 2019-02-14 2020-08-21 埃森哲环球解决方案有限公司 Site-specific anomaly detection
CN111563521B (en) * 2019-02-14 2023-10-17 埃森哲环球解决方案有限公司 Site-specific anomaly detection
CN110113571A (en) * 2019-05-07 2019-08-09 合肥芃明科技有限公司 A kind of approaches to IM based on virtual reality and video fusion
CN112214861A (en) * 2019-07-12 2021-01-12 莱芜职业技术学院 Electromechanical system pipeline assembly system based on BIM
CN111321902A (en) * 2020-02-26 2020-06-23 浙江锐博科技工程有限公司 System and method for hoisting components on assembly building construction site
CN112435143A (en) * 2020-11-23 2021-03-02 温岭市第一建筑工程有限公司 Building engineering construction optimization system based on BIM
CN112734184A (en) * 2020-12-30 2021-04-30 南通汉腾建筑科技有限公司 Acceptance method and system for assembly type building
CN112734184B (en) * 2020-12-30 2022-06-03 南通汉腾建筑科技有限公司 Acceptance method and system for assembly type building
CN112634089A (en) * 2020-12-30 2021-04-09 珠海大横琴科技发展有限公司 Energy consumption processing method and device for property facility
CN113259628A (en) * 2021-05-08 2021-08-13 广西艾科普高新技术有限公司 BIM-based laboratory assembly building and method
CN114140899A (en) * 2021-12-20 2022-03-04 浙江交通职业技术学院 Engineering inspection system and method based on artificial intelligence
CN116489592A (en) * 2023-05-26 2023-07-25 安徽江澜建设工程有限公司 Assembled building construction monitored control system based on three-dimensional model
CN116489592B (en) * 2023-05-26 2024-01-26 安徽江澜建设工程有限公司 Assembled building construction monitored control system based on three-dimensional model

Similar Documents

Publication Publication Date Title
CN109242263A (en) A kind of assembled architecture BIM module management system
CN102307386B (en) Indoor positioning monitoring system and method based on Zigbee wireless network
CN111242574A (en) Intelligent site inspection management system and method based on GPS technology
CN107437153A (en) Underground pipe gallery big data visualized O&M cloud platform
CN107240166A (en) Point inspection terminal and its data processing method
CN108520342A (en) Platform of internet of things management method based on BIM and its system
CN111246083B (en) Real-time live broadcast system is patrolled and examined in 5G unmanned aerial vehicle building site
CN206775516U (en) Computer room management system based on RFID label tag
CN107239868A (en) End message processing method and processing device for security cruising inspection system
CN107240164A (en) The data processing of security cruising inspection system and device
CN116298701B (en) Power distribution network fault detection method and related device based on digital twin system
CN111260325A (en) Bridge construction progress management system based on BIM
CN104392507A (en) Intelligent line patrol monitoring system for urban gas pipe network
CN105761016A (en) Bridge disease inspection management system and method
CN112272236A (en) Routing inspection system and method based on BIM
CN103200390A (en) Method for monitoring indoor object moving track
CN109660963A (en) Shutdown system based on UWB
GB2586198A (en) A monitoring and recording system
CN212659122U (en) Intelligent water affair event scheduling management system based on three-dimensional visualization technology
CN109728540A (en) A kind of power network line inspection management method
CN114663818B (en) Airport operation core area monitoring and early warning system and method based on vision self-supervision learning
CN114926147A (en) Intelligent lightweight management platform and method
CN114493138A (en) Land-air integrated intelligent construction system and management method
CN107563529A (en) A kind of electric power geography information operating system based on GPS and inertial positioning
CN115604317B (en) Prompting system and method for industrial daily inspection

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190118

RJ01 Rejection of invention patent application after publication