CN109240237A - Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system - Google Patents

Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system Download PDF

Info

Publication number
CN109240237A
CN109240237A CN201811177396.1A CN201811177396A CN109240237A CN 109240237 A CN109240237 A CN 109240237A CN 201811177396 A CN201811177396 A CN 201811177396A CN 109240237 A CN109240237 A CN 109240237A
Authority
CN
China
Prior art keywords
production
dimensional
mineral processing
processing enterprises
production equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811177396.1A
Other languages
Chinese (zh)
Inventor
赵奕
王国伟
孙明俊
尤腾胜
封志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China ENFI Engineering Corp
Original Assignee
China ENFI Engineering Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China ENFI Engineering Corp filed Critical China ENFI Engineering Corp
Priority to CN201811177396.1A priority Critical patent/CN109240237A/en
Publication of CN109240237A publication Critical patent/CN109240237A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM]
    • G05B19/41885Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS], computer integrated manufacturing [CIM] characterised by modeling, simulation of the manufacturing system
    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B2219/00Program-control systems
    • G05B2219/30Nc systems
    • G05B2219/32Operator till task planning
    • G05B2219/32339Object oriented modeling, design, analysis, implementation, simulation language

Abstract

The present invention provides a kind of Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system, including data collection system, monitoring server and monitor terminal, wherein data collection system includes three dimensional data collection subsystem and production data acquisition subsystem, wherein three dimensional data collection subsystem at least is used to acquire the three-dimensional data of the production equipment of Mineral Processing Enterprises, and production data acquisition subsystem is used to acquire the production process detection parameters of production equipment;Monitoring server includes 3D modelling system, Product Data Management system and dynamic simulation system, wherein 3D modelling system is at least used to establish the threedimensional model of production equipment according to the three-dimensional data of production equipment, Product Data Management system is at least used to handle production process detection parameters, and the processing result that dynamic simulation system is at least used for threedimensional model and Product Data Management system based on production equipment is emulated to obtain the 3-D image of the production equipment of the real-time production status of Dynamically Announce;And monitor terminal 3-D image for rendering.

Description

Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system
Technical field
The present invention relates to production automation technical fields, and in particular to a kind of Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system.
Background technique
The Process supervisory system of Mineral Processing Enterprises mainly uses and computer control system (DCS at present (Distributed Control System, dcs)/PLC (Programmable Logic Controller, programmable logic controller (PLC))) the matched or host computer operation interface individually developed, realize the life in dressing plant Process control monitoring is produced, presentation mode is two-dimensional picture signal, is not enough to show mining production process entities, presentation mode is not It is enough intuitive;Although current dimensional Modeling Technology has started to be applied to Mineral Processing Enterprises, it is only limitted to the design phase, for utilizing three Dimension module realizes the monitoring and management for selecting factory's O&M stage, not yet carries out;Existing production monitoring picture and Three Dimensional Design Model, Cross-system or mobile terminal is not supported to apply, prevent information is from farthest playing effective value yet.
Therefore, designing the new Mineral Processing Enterprises three-dimension monitoring system of one kind is a technical problem to be solved urgently.
Summary of the invention
The present invention provides a kind of Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system, and then is overcome at least to a certain extent due to phase One or more problem caused by the limitation and defect of pass technology.
Other characteristics and advantages of the invention will be apparent from by the following detailed description, or partially by the present invention Practice and acquistion.
An example embodiment according to the present invention discloses a kind of Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system, the ore dressing Enterprise's Three-Dimensional Dynamic monitoring system includes data collection system, monitoring server and monitor terminal, wherein
Data collection system includes three dimensional data collection subsystem and production data acquisition subsystem, and wherein three-dimensional data is adopted Subsystem at least is used to acquire the three-dimensional data of the production equipment of Mineral Processing Enterprises, and production data acquisition subsystem is for acquiring life Produce the production process detection parameters of equipment;
Monitoring server includes 3D modelling system, Product Data Management system and dynamic simulation system, wherein three-dimensional mould The three-dimensional data for the production equipment that type system is at least used to be acquired according to three dimensional data collection subsystem establishes the three of production equipment Dimension module, Product Data Management system are at least used to carry out the production process detection parameters that production data acquisition subsystem acquires Processing, dynamic simulation system be at least used for the processing result of threedimensional model and Product Data Management system based on production equipment into Row emulation obtains the 3-D image of the production equipment of the real-time production status of Dynamically Announce;And
The monitor terminal at least 3-D image of the production equipment of the real-time production status of Dynamically Announce for rendering.
An example embodiment according to the present invention, the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system further include execution machine Structure, the operational order for being issued according to monitoring server operate production equipment.
An example embodiment according to the present invention, wherein monitoring server further includes instruction delivery system, is used for basis The processing result of Product Data Management system issues operational order to executing agency.
An example embodiment according to the present invention, wherein monitoring server further includes virtual training drilling system, is used for At least one of virtual training, the dismantling maintenance rehearsal of production equipment and fire incident rehearsal.
An example embodiment according to the present invention, the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system further include whole with monitoring Hold the VR equipment of connection.
An example embodiment according to the present invention, the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system further include whole with monitoring Hold the AR equipment of connection.
An example embodiment according to the present invention, wherein monitor terminal includes that the end PC, mobile terminal, browser end or cloud are flat Platform.
An example embodiment according to the present invention, wherein production data acquisition subsystem include DCS control system, SCADA system, sensor or man-machine interactive interface.
An example embodiment according to the present invention, wherein production process detection parameters include: process flow operation or stopping shape State, weighing, flow, frequency, speed, temperature, electric current, pressure or the level of production process.
An example embodiment according to the present invention, wherein
Three dimensional data collection subsystem is also used to acquire inside Mineral Processing Enterprises plant area and the three-dimensional data and reality of ambient enviroment Scape data;
The three-dimensional data for the production equipment that 3D modelling system is also used to be acquired according to three dimensional data collection subsystem, ore dressing Inside plant area of enterprise and the three-dimensional data and live-action data of ambient enviroment are established comprising the entire Mineral Processing Enterprises including production equipment Threedimensional model, dynamic simulation system is also used to based on the threedimensional model comprising the entire Mineral Processing Enterprises including production equipment and life Produce data management system processing result emulated to obtain the production equipment comprising the real-time production status of Dynamically Announce including The 3-D image of entire Mineral Processing Enterprises;And
Monitor terminal is also used to present the entire ore dressing enterprise including the production equipment comprising the real-time production status of Dynamically Announce The 3-D image of industry.
According to certain embodiments of the present invention, may be implemented workshop, production procedure, equipment three-dimensional visualization.
According to certain embodiments of the present invention, by threedimensional model for realizing the monitoring and management for selecting factory's O&M stage and It is applied not only to the design phase.
According to certain embodiments of the present invention, based on three-dimensional visualization, merged real time information, dynamic analog, Instruction output, training exercise function, without shut down can demonstration equipment dismantling and maintenance rehearsal, accident emergency drilling, behaviour The simulation training etc. of work, and be applied not only to be only used for visualization presentation.
According to certain embodiments of the present invention, by being combined with augmented reality AR terminal, realization employee's virtual training, The functions such as simulated operation examination, remote assistance maintenance.
According to certain embodiments of the present invention, support cross-system or mobile terminal application, enable information utmostly Ground plays effective value.
It should be understood that the above general description and the following detailed description are merely exemplary, this can not be limited Invention.
Detailed description of the invention
Its example embodiment is described in detail by referring to accompanying drawing, above and other target of the invention, feature and advantage will It becomes more fully apparent.
Fig. 1 shows the schematic diagram of the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system of an example embodiment according to the present invention.
Specific embodiment
Example embodiment is described more fully with reference to the drawings.However, example embodiment can be with a variety of shapes Formula is implemented, and is not understood as limited to example set forth herein;On the contrary, thesing embodiments are provided so that description of the invention Will be more full and complete, and the design of example embodiment is comprehensively communicated to those skilled in the art.Attached drawing is only Schematic illustrations of the invention are not necessarily drawn to scale.
In addition, described feature, structure or characteristic can be incorporated in one or more implementations in any suitable manner In mode.In the following description, many details are provided to provide and fully understand to embodiments of the present invention.So And it will be appreciated by persons skilled in the art that technical solution of the present invention can be practiced and omit one in the specific detail Or more, or can be using other methods, constituent element, step etc..In other cases, it is not shown in detail or describes known knot Structure, method, realization or operation are to avoid a presumptuous guest usurps the role of the host and each aspect of the present invention is made to thicken.
Some block diagrams shown in the drawings are functional entitys, not necessarily must be with physically or logically independent entity phase It is corresponding.These functional entitys can be realized in one or more hardware modules or integrated circuit, or at heterogeneous networks and/or place These functional entitys are realized in reason device device and/or microcontroller device.
It is an object of the invention to disclose a kind of Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system, the Mineral Processing Enterprises Three-Dimensional Dynamic Monitoring system includes data collection system, monitoring server and monitor terminal, and wherein data collection system includes that three-dimensional data is adopted Subsystem and production data acquisition subsystem, wherein three dimensional data collection subsystem at least is used to acquire the production of Mineral Processing Enterprises The three-dimensional data of equipment, production data acquisition subsystem are used to acquire the production process detection parameters of production equipment;Monitoring service Device includes 3D modelling system, Product Data Management system and dynamic simulation system, and wherein 3D modelling system is at least used for root The threedimensional model of production equipment, creation data pipe are established according to the three-dimensional data of the production equipment of three dimensional data collection subsystem acquisition Reason system is at least used to handle the production process detection parameters that production data acquisition subsystem acquires, dynamic simulation system Processing result at least for the threedimensional model based on production equipment and Product Data Management system is emulated to obtain dynamically aobvious Show the 3-D image of the production equipment of real-time production status;And at least Dynamically Announce produces shape to monitor terminal in real time for rendering The 3-D image of the production equipment of state.Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system of the invention may be implemented workshop, production procedure, The three-dimensional visualization of equipment, the monitoring and management that threedimensional model is selected into factory's O&M stage and be applied not only to design rank Section.Meanwhile based on three-dimensional visualization, real time information, dynamic analog, instruction output, training exercise function are merged, has been not necessarily to Shut down can demonstration equipment dismantling and maintenance rehearsal, the emergency drilling of accident, the simulation training of operation etc., and being applied not only to can It is presented depending on changing.In addition, realizing employee's virtual training, simulated operation examination, long-range association by combining with augmented reality AR terminal Help the functions such as maintenance.Further, cross-system or mobile terminal application are also supported, information is farthest played effectively Value.
The present invention proposes a kind of Three-Dimensional Dynamic monitoring system towards Mineral Processing Enterprises, based on three-dimensional visualization, access Product practice has merged the technologies such as dynamic simulation, virtual reality and augmented reality, information management.Realize that Mineral Processing Enterprises are raw Dynamic three-dimensional visualization is presented in real time for production process and device status information cross-system, is provided for Mineral Processing Enterprises more convenient intuitive Production procedure monitoring tools, for improve Mineral Processing Enterprises operational efficiency and management level play an important role.The present invention solves Following problems:
(1) workshop, life may be implemented in the upper monitoring two-dimensional picture of Mineral Processing Enterprises DCS/PLC different from the past, the present invention Produce the three-dimensional visualization of process, equipment.
(2) is only used for the design phase different from the work of existing Mineral Processing Enterprises three-dimensional modeling, and the present invention uses threedimensional model The monitoring and management in factory's O&M stage are selected in realization.
(3), which is different from the work of existing Mineral Processing Enterprises three dimensional design, only realizes presentation, and the present invention is with three-dimensional visualization Based on, merged real time information, dynamic analog, instruction output, training exercise function, without shut down can demonstration equipment tear open Solution and maintenance rehearsal, the emergency drilling of accident, the simulation training of operation etc..
(4) combines this monitoring system with augmented reality AR terminal, is showed by the quicklook to reality scene, It allows related personnel to be not necessarily to that ore dressing scene, the observation to plant area and equipment can be completed, and then understands ore-dressing technique, realization person The functions such as work virtual training, simulated operation examination, remote assistance maintenance.
(5) is different from existing production monitoring picture and design threedimensional model just for single application system, the present invention Monitoring system support cross-system or mobile terminal application, enable information farthest to play effective value.
1 pair of Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system of the invention is specifically described with reference to the accompanying drawing, wherein Fig. 1 The schematic diagram of the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system of an example embodiment according to the present invention is shown.
Fig. 1 shows the schematic diagram of the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system of an example embodiment according to the present invention.Such as Shown in Fig. 1, Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system includes data collection system 1, monitoring server 2 and monitor terminal 3, wherein Data collection system 1 includes three dimensional data collection subsystem 11 and production data acquisition subsystem 12, wherein three dimensional data collection Subsystem 11 is at least for acquiring the three-dimensional data of the production equipment of Mineral Processing Enterprises, and production data acquisition subsystem 12 is for acquiring The production process detection parameters of production equipment;Monitoring server 2 includes 3D modelling system 21,22 and of Product Data Management system Dynamic simulation system 23, wherein 3D modelling system 21 according to the production that three dimensional data collection subsystem 11 acquires at least for setting Standby three-dimensional data establishes the threedimensional model of production equipment, and Product Data Management system 22 is used for production data acquisition subsystem The production process detection parameters of 12 acquisitions are handled, and dynamic simulation system 23 is at least used for the threedimensional model based on production equipment It is emulated to obtain the three-dimensional of the production equipment of the real-time production status of Dynamically Announce with the processing result of Product Data Management system Image;And at least 3-D image of the production equipment of the real-time production status of Dynamically Announce for rendering of monitor terminal 3.The present invention The Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system of offer accesses production process real time data, fusion based on three-dimensional visualization The technologies such as dynamic simulation, virtual reality and augmented reality (being described in detail hereinafter), information management, for Mineral Processing Enterprises provide it is more convenient directly The production procedure monitoring tools of sight.
Wherein the Mineral Processing Enterprises include the main workshop of mineral processing production process and auxiliary shop, such as: coarse crushing workshop, in Fine crushing and screen house, grind grading workshop, flotation workshop, gravity treatment workshop, magnetic separation workshop, dewatering process flow, pumping plant, air blast computer room Air compressor house, medicament and lime workshop etc..
An example embodiment according to the present invention, wherein three dimensional data collection subsystem is also used to acquire Mineral Processing Enterprises factory The three-dimensional data and live-action data of environment within and around area;3D modelling system is also used to according to three dimensional data collection subsystem Inside the three-dimensional data of the production equipment of acquisition, Mineral Processing Enterprises plant area and the three-dimensional data and live-action data of ambient enviroment establish packet Threedimensional model containing the entire Mineral Processing Enterprises including production equipment, including dynamic simulation system is also used to be based on comprising production equipment The threedimensional model of entire Mineral Processing Enterprises and the processing result of Product Data Management system emulated to obtain comprising Dynamically Announce The 3-D image of entire Mineral Processing Enterprises including the production equipment of real-time production status;And monitor terminal is also used to present and includes The 3-D image of entire Mineral Processing Enterprises including the production equipment of the real-time production status of Dynamically Announce.That is, of the invention Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system both only can be monitored and present to production process, the state of production equipment, can also It to be monitored and present to comprising the entire Mineral Processing Enterprises including production equipment, can be decided according to the actual requirements, have no and appoint What is limited.
The entire Mineral Processing Enterprises three-dimension modeling is the design document based on Mineral Processing Enterprises, in conjunction with 3-D scanning, The three-dimensional data and live-action data of Mineral Processing Enterprises plant area inside and ambient enviroment that the means such as oblique photograph obtain, are Mineral Processing Enterprises Building, equipment, facility etc. establish three-dimensional scenic and model, the dimensional topography landforms including periphery.Specifically, ore dressing is established Enterprise's threedimensional model can include: the design document based on Mineral Processing Enterprises, the choosing obtained in conjunction with means such as 3-D scanning, oblique photographs The three-dimensional data and live-action data of plant area of mine enterprise inside and ambient enviroment are that building, equipment, facility of Mineral Processing Enterprises etc. are established Three-dimensional scenic and model, the dimensional topography landforms including periphery.In order to reduce the memory space of model occupancy, improve operation speed Degree, vacuates model data point, the lightweight of implementation model.The segmentation and definition that object is carried out to threedimensional model, are every A object assigns unique identification information, is classified as needed for object and is layered.Threedimensional model is uploaded to prison Control the dynamic simulation system in server.
An example embodiment according to the present invention, wherein production data acquisition subsystem include DCS control system, SCADA system (acquisition of Supervisory Control And Data Acquisition system, i.e. data and monitoring control system System), sensor or man-machine interactive interface.
An example embodiment according to the present invention, wherein production process detection parameters include: process flow operation or stopping shape State, the weighing of production process, flow, frequency, speed, temperature, electric current, pressure or level data.
The Product Data Management system, which refers to, the processing such as is converted to data, is stored, being called.
The dynamic simulation system of the production procedure be on the basis of threedimensional model, it is right according to production procedure data Production procedure carries out dynamic simulation.Such as: realizing that the transmission of belt in threedimensional model is imitative according to the run signal of ores lifting belt Very.The rotation emulation of grinding machine in threedimensional model is realized according to the run signal of grinding machine.It is realized according to the filling level signal of grinding machine The dynamic simulation of the filling level of grinding machine in threedimensional model.According to the level numerical value Dynamically Announce three-dimensional mould in storage bin or groove tank The level height of storing medium in type.The revolving speed of belt or pump in threedimensional model is converted according to the tach signal of belt or pump.
An example embodiment according to the present invention, the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system further includes executing agency 4, the operational order for being issued according to monitoring server operates production equipment.
An example embodiment according to the present invention, wherein monitoring server 2 further includes instruction delivery system 24, is used for root Operational order is issued to executing agency 4 according to the processing result of Product Data Management system.Such as: enabled instruction, halt instruction, change Frequency device signal feeding value output etc..
An example embodiment according to the present invention, wherein monitoring server 2 further includes virtual training drilling system 25, is used In at least one of the dismantling maintenance rehearsal and fire incident rehearsal of virtual training, production equipment.Specifically, the void Quasi- training exercise system 25 can be actually needed according to production, customization training demo function and man-machine interactive interface, without shutting down It can demonstrate and practice: dismantling and maintenance rehearsal, the emergency drilling of accident, the simulation training of operation of equipment etc..Such as: production Rehearsal is repaired in the dismantling of equipment.Step, service clearance place, auxiliary hoist tool, maintenance are repaired according to the dismantling of production equipment The plan such as personnel placement, is split and defines to production equipment threedimensional model object, and is disassembled, handling, personnel's operation Deng rehearsal, and human-computer interaction excuse is set, realizes the training and test of dismantling maintenance.Such as: fire incident rehearsal.Three Simulated fire accident and emergency preplan in scene, containing prediction scheme, emergency operation, physical distribution, the evacuating personnel of specification etc. are tieed up, And man-machine interactive interface is set, it can be used for safety training and test.Or for example: for new employee or new operating instruction, Production operation demonstration can be carried out by this system and human-computer interaction is tested.
An example embodiment according to the present invention, the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system further include whole with monitoring VR (virtual reality) equipment 5 for holding connection can be Virtual Reality wearing helmet equipment etc..
An example embodiment according to the present invention, the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system further include whole with monitoring AR (augmented reality) equipment 6 for holding connection, can be the augmented realities human-computer interaction device such as AR glasses.
The virtual reality and augmented reality human-computer interaction device, including Virtual Reality wearing helmet equipment and AR Mirror.It realizes and the quicklook of production scene is showed, without that can be completed to plant area and production equipment again to ore dressing scene It is existing, it allows related personnel to understand production technology, realizes the functions such as employee's virtual training, simulated operation examination, remote assistance service.
An example embodiment according to the present invention, wherein monitor terminal 3 includes the end PC 31, mobile terminal 32, browser end 33 or cloud platform 34.
Specifically, the monitor terminal may include fixed or portable operation display terminal, such as computer, flat Plate computer, mobile phone etc., the three-dimensional visualization display content that receivable monitoring server is sent, can be connected to cloud system, and Realize the functions such as browsing, display, inquiry, model modification, data update, remote service.
Illustrate the construction of the Three-Dimensional Dynamic Process supervisory system towards Mineral Processing Enterprises below with reference to specific example, Including following below scheme:
Process 1. establishes Mineral Processing Enterprises threedimensional model.Design document based on Mineral Processing Enterprises is taken the photograph in conjunction with 3-D scanning, inclination The three-dimensional data and live-action data of Mineral Processing Enterprises plant area inside and ambient enviroment that the means such as shadow obtain, for building for Mineral Processing Enterprises It builds, equipment, facility etc. establish three-dimensional scenic and model, the dimensional topography landforms including periphery.In order to reduce depositing for model occupancy It stores up space, improve the speed of service, model data point is vacuated, the lightweight of implementation model.Object is carried out to threedimensional model Segmentation and definition, assign unique identification information for each object, classified as needed for object and be layered.It will Threedimensional model is uploaded to the dynamic simulation system in monitoring server.
Process 2. establishes production data acquisition system, and production process detection parameters are transmitted to monitoring server.
Such as: production procedure data are obtained from DCS control system, SCADA system, sensor, man-machine interactive interface etc..
Such as: collecting flowchart operation or halted state, the weighing of production process, flow, frequency, speed, temperature, electric current, The processes detection data such as pressure, level.
3. monitoring server of process is converted production process detection parameters, is stored.
Process 4. plans threedimensional model object data, advises to the characteristics of objects for needing to show dynamic change It draws, extracts the parameter of characterization characteristics of objects, assign signature for parameter, and establish dynamic with collected process detection parameters Link.The real time information such as sensor detection parameters and equipment running status are presented to the user with the intuitive manner of dynamic analog. Such as: the characteristic parameter of characterization level height is the height of the medium in threedimensional model, thus height imparting signature, and with Collected real-time Level measurement parameter establishes dynamic link, so that the level in threedimensional model is according to the real-time level detected It is worth and changes.
Process 5. is to realize instruction output, develops human-computer interaction interface and interface, carries out Dynamic link library to output variable, real The publication of existing operational order, such as: equipment enabled instruction, equipment halt instruction, the output of frequency converter signal feeding value etc..
Process 6. establishes virtual training drilling system in the three-dimensional model, is actually needed according to production, customization training demonstration Function and man-machine interactive interface.
Such as: rehearsal is repaired in the dismantling of equipment.According to the dismantling maintenance flow of equipment, service clearance place, auxiliary handling The plans such as tool, maintenance personal's arrangement, are split and define to equipment threedimensional model object, and disassembled, handling, personnel The rehearsal such as operation, and human-computer interaction excuse is set, realize the training and test of dismantling maintenance.
Such as: fire incident rehearsal.Simulated fire accident and emergency preplan in three-dimensional scenic, containing prediction scheme, specification Emergency operation, physical distribution, evacuating personnel etc., and man-machine interactive interface is set, can be used for safety training and test.
Such as: for new employee or new operating instruction, production operation demonstration and human-computer interaction can be carried out by this system Test.
Process 7 carries out cross-system application and development, and the operation developed including covering the end PC, browser end, mobile terminal, which is shown, answers With may be connected to cloud system, provide the functions such as three-dimensional visible, model modification, data update, human-computer interaction, long-range monitoring.
Process 8, monitoring server show content to monitor terminal publication three-dimensional visualization, and monitor terminal receives monitoring service The three-dimensional visualization that device is sent shows content.
Process 9 is connected with Virtual Reality wearing helmet equipment or AR glasses, realizes human-computer interaction.Carry out virtual training Deng application.
By above detailed description, those skilled in the art is it can be readily appreciated that ore dressing according to an embodiment of the present invention is looked forward to Industry Three-Dimensional Dynamic monitoring system has one or more of the following advantages.
According to certain embodiments of the present invention, may be implemented workshop, production procedure, equipment three-dimensional visualization.
According to certain embodiments of the present invention, by threedimensional model for realizing the monitoring and management for selecting factory's O&M stage and It is applied not only to the design phase.
According to certain embodiments of the present invention, based on three-dimensional visualization, merged real time information, dynamic analog, Instruction output, training exercise function, without shut down can demonstration equipment dismantling and maintenance rehearsal, accident emergency drilling, behaviour The simulation training etc. of work, and be applied not only to be only used for visualization presentation.
According to certain embodiments of the present invention, by being combined with augmented reality AR terminal, realization employee's virtual training, The functions such as simulated operation examination, remote assistance maintenance.
According to certain embodiments of the present invention, support cross-system or mobile terminal application, enable information utmostly Ground plays effective value.
Those skilled in the art after considering the specification and implementing the invention disclosed here, will readily occur to of the invention its Its embodiment.This application is intended to cover any variations, uses, or adaptations of the invention, these modifications, purposes or Person's adaptive change follows general principle of the invention and including the undocumented common knowledge in the art of the present invention Or conventional techniques.The description and examples are only to be considered as illustrative, and true scope and spirit of the invention are by following Claim is pointed out.
It should be understood that the present invention is not limited to the precise structure already described above and shown in the accompanying drawings, and And various modifications and changes may be made without departing from the scope thereof.The scope of the present invention is limited only by the attached claims.

Claims (10)

1. a kind of Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system, the Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system includes data acquisition system System, monitoring server and monitor terminal, wherein
Data collection system includes three dimensional data collection subsystem and production data acquisition subsystem, and wherein three dimensional data collection is sub System at least is used to acquire the three-dimensional data of the production equipment of Mineral Processing Enterprises, and production data acquisition subsystem is set for acquiring production Standby production process detection parameters;
Monitoring server includes 3D modelling system, Product Data Management system and dynamic simulation system, wherein threedimensional model system The three-dimensional data of production equipment of the system at least for being acquired according to three dimensional data collection subsystem establishes the three-dimensional mould of production equipment Type, Product Data Management system are at least used at the production process detection parameters to the acquisition of production data acquisition subsystem Reason, the processing result that dynamic simulation system is at least used for threedimensional model and Product Data Management system based on production equipment carry out Emulation obtains the 3-D image of the production equipment of the real-time production status of Dynamically Announce;And
The monitor terminal at least 3-D image of the production equipment of the real-time production status of Dynamically Announce for rendering.
2. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that it further include executing agency, Operational order for being issued according to monitoring server operates production equipment.
3. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 2, which is characterized in that wherein monitoring server is also Including instructing delivery system, for issuing operational order to executing agency according to the processing result of Product Data Management system.
4. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that wherein monitoring server is also Including virtual training drilling system, the dismantling for virtual training, production equipment is repaired in rehearsal and fire incident rehearsal extremely Few one kind.
5. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that further include and monitor terminal The VR equipment of connection.
6. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that further include and monitor terminal The AR equipment of connection.
7. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that wherein monitor terminal includes The end PC, mobile terminal, browser end or cloud platform.
8. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that wherein production data acquisition Subsystem includes DCS control system, SCADA system, sensor or man-machine interactive interface.
9. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that wherein production process detects Parameter includes: process flow operation or halted state, weighing, flow, frequency, speed, temperature, electric current, pressure or the object of production process Position.
10. Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system according to claim 1, which is characterized in that wherein
Three dimensional data collection subsystem is also used to acquire inside Mineral Processing Enterprises plant area and the three-dimensional data and outdoor scene number of ambient enviroment According to;
The three-dimensional data for the production equipment that 3D modelling system is also used to be acquired according to three dimensional data collection subsystem, Mineral Processing Enterprises Inside plant area and the three-dimensional data and live-action data of ambient enviroment establish three comprising the entire Mineral Processing Enterprises including production equipment Dimension module, dynamic simulation system are also used to based on the threedimensional model comprising the entire Mineral Processing Enterprises including production equipment and production number It is emulated to obtain according to the processing result of management system entire including the production equipment comprising the real-time production status of Dynamically Announce The 3-D image of Mineral Processing Enterprises;And
Monitor terminal is also used to present the entire Mineral Processing Enterprises including the production equipment comprising the real-time production status of Dynamically Announce 3-D image.
CN201811177396.1A 2018-10-10 2018-10-10 Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system Pending CN109240237A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811177396.1A CN109240237A (en) 2018-10-10 2018-10-10 Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811177396.1A CN109240237A (en) 2018-10-10 2018-10-10 Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system

Publications (1)

Publication Number Publication Date
CN109240237A true CN109240237A (en) 2019-01-18

Family

ID=65055563

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811177396.1A Pending CN109240237A (en) 2018-10-10 2018-10-10 Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system

Country Status (1)

Country Link
CN (1) CN109240237A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110209089A (en) * 2019-06-13 2019-09-06 中交一航局安装工程有限公司 A kind of silo comprehensive monitoring system based on BIM
CN111522894A (en) * 2020-04-16 2020-08-11 北京龙软科技股份有限公司 Coal mine visual management and control system based on temporal GIS
CN111770450A (en) * 2020-05-22 2020-10-13 同济大学 Workshop production monitoring server, mobile terminal and application

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2009243451A1 (en) * 2009-06-12 2011-01-06 Technological Resources Pty. Limited A mine scheduling system
CN102325177A (en) * 2011-09-05 2012-01-18 太原理工大学 Coal mine production three-dimensional visualization information system based on Internet of things
CN102508989A (en) * 2011-09-27 2012-06-20 福建省电力有限公司 Dynamic power grid panorama display system on basis of virtual reality
CN106842983A (en) * 2017-01-06 2017-06-13 东华大学 A kind of method for building up of the Three-Dimensional Dynamic monitoring system towards cogeneration
CN107272634A (en) * 2017-08-23 2017-10-20 合肥中盈信息工程有限公司 A kind of virtual coal mining Exercise Control system based on three-dimensional VR and data server
CN108022052A (en) * 2017-12-14 2018-05-11 北京龙软科技股份有限公司 A kind of Safety of Coal Mine Production dynamic diagnostics system and method based on big data analysis

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
AU2009243451A1 (en) * 2009-06-12 2011-01-06 Technological Resources Pty. Limited A mine scheduling system
CN102325177A (en) * 2011-09-05 2012-01-18 太原理工大学 Coal mine production three-dimensional visualization information system based on Internet of things
CN102508989A (en) * 2011-09-27 2012-06-20 福建省电力有限公司 Dynamic power grid panorama display system on basis of virtual reality
CN106842983A (en) * 2017-01-06 2017-06-13 东华大学 A kind of method for building up of the Three-Dimensional Dynamic monitoring system towards cogeneration
CN107272634A (en) * 2017-08-23 2017-10-20 合肥中盈信息工程有限公司 A kind of virtual coal mining Exercise Control system based on three-dimensional VR and data server
CN108022052A (en) * 2017-12-14 2018-05-11 北京龙软科技股份有限公司 A kind of Safety of Coal Mine Production dynamic diagnostics system and method based on big data analysis

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110209089A (en) * 2019-06-13 2019-09-06 中交一航局安装工程有限公司 A kind of silo comprehensive monitoring system based on BIM
CN111522894A (en) * 2020-04-16 2020-08-11 北京龙软科技股份有限公司 Coal mine visual management and control system based on temporal GIS
CN111522894B (en) * 2020-04-16 2021-01-12 北京龙软科技股份有限公司 Coal mine visual management and control system based on temporal GIS
CN111770450A (en) * 2020-05-22 2020-10-13 同济大学 Workshop production monitoring server, mobile terminal and application
CN111770450B (en) * 2020-05-22 2022-02-18 同济大学 Workshop production monitoring server, mobile terminal and application

Similar Documents

Publication Publication Date Title
CN103984333B (en) A kind of power plant monitoring and control management system
CN113887016A (en) Ship digital workshop simulation method and system based on digital twinning
CN110333698A (en) Factory management system and its method based on the twin platform of number
CN110047150B (en) Complex equipment operation on-site simulation system based on augmented reality
CN109240237A (en) Mineral Processing Enterprises Three-Dimensional Dynamic monitoring system
CN103247004A (en) Information management method and system based on electromechanical integrated BIM (building information model)
CN103778566A (en) Heat-engine plant monitoring and measuring method based on three-dimensional visualization demonstration
CN110047148B (en) Simulation interaction visualization system of virtual robot workstation and implementation method
CN102930598A (en) System and method for positioning tunnel detection equipment and displaying status of tunnel detection equipment by using three-dimensional model
CN104407518A (en) Systems and methods for immersive interaction with actual and/or simulated facilities for process, environmental and industrial control
CN109976296A (en) A kind of manufacture process visualization system and construction method based on virtual-sensor
CN112130478A (en) Building integrated comprehensive management and control platform system based on BIM and management and control method thereof
CN108983729A (en) A kind of twin method and system of industrial production line number
KR101328224B1 (en) Virtual facility system for manufacturing steel and operating method thereof
KR102371336B1 (en) Smart factory monitoring system using 3 Dimention integrated monitoring and Augmented Reality and Virtual Reality
CN106408630A (en) Method for simulating optimized operation parameters of pump station based on VR interaction technology
CN211454286U (en) Building integrated comprehensive control platform system based on BIM
CN102722106A (en) Immersive virtual reality emulation interaction display method and display system
CN108038910A (en) The implementation method of substation's main equipment Virtual Reality Demonstration
CN107863049A (en) A kind of finishing outpost display system based on line holographic projections technology
US20190202059A1 (en) Dynamically representing a changing environment over a communications channel
KR20190014783A (en) Operation and maintainance virtual experience system of 3d equipment model and method thereof
CN104504175A (en) Simulation system and simulation method for spacecraft assembling
CN106444427A (en) Configuration-based physical object display method
CN101815173B (en) Method and system for remotely controlling front-end camera

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190118