CN109235284A - A kind of construction equipment and method of no hoist cable beam section - Google Patents

A kind of construction equipment and method of no hoist cable beam section Download PDF

Info

Publication number
CN109235284A
CN109235284A CN201811453307.1A CN201811453307A CN109235284A CN 109235284 A CN109235284 A CN 109235284A CN 201811453307 A CN201811453307 A CN 201811453307A CN 109235284 A CN109235284 A CN 109235284A
Authority
CN
China
Prior art keywords
jack
supporting platform
platform seat
steel strand
strand wires
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811453307.1A
Other languages
Chinese (zh)
Inventor
王博
朱小金
杨敏
聂宁
赵廷建
周斌斌
吕永喜
张伟
张富杰
杜海峰
白丽锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC SHB Fifth Engineering Co Ltd
Original Assignee
CCCC SHB Fifth Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC SHB Fifth Engineering Co Ltd filed Critical CCCC SHB Fifth Engineering Co Ltd
Priority to CN201811453307.1A priority Critical patent/CN109235284A/en
Publication of CN109235284A publication Critical patent/CN109235284A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/02Suspension bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides the construction equipments and method of a kind of no hoist cable beam section, construction equipment includes interim cord clip, sling cable, sling cable supporting platform seat, jack, jack supporting platform seat, steel strand wires, interim cord clip is fixed on main push-towing rope, sling cable and sling cable supporting platform seat are fixed on interim cord clip after forming a close ring by sling cable, jack supporting platform seat is set in sling cable supporting platform seat, and jack is set in jack supporting platform seat;Steel strand wires upper end is suspended on main push-towing rope, and steel strand wires lower end passes through jack, jack supporting platform seat is fixed, and steel strand wires lower end is for connecting stiff girder.The present invention is not needed using large-scale equipment, is influenced by external environment small, installs simple and fast, and good economy performance, large carrying capacity.It is simple and clear, it is easy to use, to ensuring construction safety, accelerate construction progress with remarkable result, helpful reference can be provided for similar construction.

Description

A kind of construction equipment and method of no hoist cable beam section
Technical field
The invention belongs to no hoist cable beam section technical field of construction, and in particular to a kind of construction equipment of no hoist cable beam section and side Method.
Background technique
Suspension bridge is paid attention to its Great span ability by builder, and the work across rivers, straits, valley is widely used in Cheng Zhong.Due to the distinctive structure of suspension bridge, there is the beam section without hoist cable near Sarasota.In erection process, no hoist cable beam section Temporary support is needed, its absolute altitude needs to adjust to meet line type control requirement after the completion of erection.
Currently, the known common method for setting up whole segment stiff girder at the suspension bridge shoal position across rivers has trestle Method sets up the method rail rope sliding method of whole segment stiff girder in the suspension bridge gamut across valley, and deck unit erection gantry loads Walking needs the problem of homework also very big.Trestle method needs two rows of support stakes and two rows that can bear what stiff girder slided above it It is very big needed for beam, steel and equipment, if meeting the high situation of riverbed basement rock intensity, the installation of stake is supported to be difficult to handle.Rail rope is sliding Shifting method can effectively solve the installation question of both the above bridge type stiff girder, but valuableness, and girder segment of putting more energy into are handed in rail rope and anchoring When heavier, beam car dipping and heaving is bigger.
Summary of the invention
The purpose of the present invention is to provide a kind of construction equipments of no hoist cable beam section, meet the construction need without hoist cable beam section It asks.
It is another object of the present invention to provide a kind of construction methods of no hoist cable beam section.
Technical solution provided by the invention is as follows:
A kind of construction equipment of no hoist cable beam section, including it is interim cord clip, sling cable, sling cable supporting platform seat, very heavy Top, jack supporting platform seat, steel strand wires, the interim cord clip are fixed on main push-towing rope, the sling cable and sling cable Supporting platform seat is fixed on interim cord clip after forming a close ring by sling cable, and the jack supporting platform seat is set to In sling cable supporting platform seat, the jack is set in jack supporting platform seat;
The steel strand wires upper end is suspended on main push-towing rope, and the steel strand wires lower end passes through jack, jack supporting platform seat is fixed, institute Steel strand wires lower end is stated for connecting stiff girder.
The steel strand wires are fixed by anchorage one and anchorage two with jack, and the anchorage one and anchorage two are respectively arranged on thousand The top on jin top and the bottom end of jack supporting platform seat.
The interim cord clip is set on main push-towing rope, is fixed on main push-towing rope by interim cord clip fastening bolt.
The sling cable supporting platform seat is fixed on sling cable by fastening pedestal fastening bolt.
The interim cord clip includes pedestal, pressing plate and cushion block, and the pedestal is fixedly connected with pressing plate, and the cushion block is set to base Between seat and pressing plate.
A kind of construction method of no hoist cable beam section, using the construction equipment of no hoist cable beam section, including step 1) stiff girder The Pass line adjustment of temporary support and step 2 stiff girder.
Stiff girder is connect with steel strand wires lower end, and steel strand wires are anchored by anchorage one and anchorage two and jack, and realization is put more energy into The temporary support of beam.
By the load or unload of jack, steel strand wires are driven upward or downward, by the drive upward or downward of steel strand wires Stiff girder upward or downward, realizes the Pass line adjustment of stiff girder.
In the construction process, jack supporting platform seat bears the load of jack, and sling cable supporting platform seat bears thousand Load, is transferred on interim cord clip by the load that jin top support pedestal transmits by rope wirerope.
The beneficial effects of the present invention are:
The construction equipment and method of this no hoist cable beam section provided by the invention, it is simple and clear, it is easy to use, pacify to ensuring to construct Entirely, it accelerates construction progress with remarkable result, helpful reference can be provided for similar construction.
It does not need using large-scale equipment, is influenced by external environment small, simple and fast, and good economy performance, carrying are installed Ability is big.
It is described in further details below in conjunction with attached drawing.
Detailed description of the invention
Fig. 1 is optimal crosssection figure of the invention;
Fig. 2 is the facade layout drawing of Fig. 1.
In figure: 1, interim cord clip;2, main push-towing rope;3, interim cord clip fastening bolt;4, anchorage one;5, sling cable;6, thousand Jin top;7, jack supporting platform seat;8, anchorage two;9, sling cable supporting platform seat;10, steel strand wires;11, stiff girder;12, platform Seat fastening bolt.
Specific embodiment
Embodiment 1:
In order to meet the construction demand of no hoist cable beam section, a kind of construction equipment of no hoist cable beam section is present embodiments provided, including Interim cord clip 1, sling cable 5, sling cable supporting platform seat 9, jack 6, jack supporting platform seat 7, steel strand wires 10, institute It states interim cord clip 1 to be fixed on main push-towing rope 2, after the sling cable 5 and one close ring of formation of sling cable supporting platform seat 9 It is fixed on interim cord clip 1 by sling cable 5, the jack supporting platform seat 7 is set to sling cable supporting platform seat 9 On, the jack 6 is set in jack supporting platform seat 7;
10 upper end of steel strand wires is suspended on main push-towing rope 2, and 10 lower end of steel strand wires passes through jack 6, jack supporting platform seat 7 Fixed, 10 lower end of steel strand wires is for connecting stiff girder 11.
When construction, interim cord clip 1 is fixed on main push-towing rope 2, and sling cable 5 is fixed on interim cord clip 1;Sling cable 5 are combined into the ring of a closure by sling cable supporting platform seat 9, and provide support force for jack supporting platform seat 7;It is very heavy Top support pedestal 7 is supported in sling cable supporting platform seat 9, and jack 6 is supported in jack supporting platform seat 7, steel strand wires 10 pass through jack 6, jack supporting platform seat 7 is connected with stiff girder 11;Jack 6 anchors steel strand wires 10, plays temporary support The effect of stiff girder 11;When needing to carry out Pass line adjustment, 11 absolute altitude of stiff girder is carried out by the load or unload of jack 6 Adjustment is to meet line type control requirement.
Embodiment 2:
On the basis of embodiment 1, a kind of construction equipment of no hoist cable beam section is present embodiments provided, the steel strand wires 10 pass through Anchorage 1 and anchorage 28 and jack 6 are fixed, and the anchorage 1 and anchorage 28 are respectively arranged on the top of jack 6 and very heavy The bottom end of top support pedestal 7.
The interim cord clip 1 is set on main push-towing rope 2, is fixed on main push-towing rope 2 by interim cord clip fastening bolt 3.
The sling cable supporting platform seat 9 is fixed on sling cable 5 by fastening pedestal fastening bolt 12.
The interim cord clip 1 includes pedestal, pressing plate and cushion block, and the pedestal is fixedly connected with pressing plate, and the cushion block is set to Between pedestal and pressing plate.In the construction process, cushion block can prevent interim cord clip 1 from sliding on main push-towing rope 2.
The construction equipment of this no hoist cable beam section provided in this embodiment, structure is simple, easy to use, pacifies to ensuring to construct Entirely, it accelerates construction progress with remarkable result, helpful reference can be provided for similar construction.
Embodiment 3:
On the basis of embodiment 2, a kind of construction equipment of hoist cable beam section as shown in Figure 1 and Figure 2 is present embodiments provided, is wrapped Include interim cord clip 1, main push-towing rope 2, interim cord clip fastening bolt 3, anchorage 1, sling cable 5, jack 6, jack supporting table Seat 7, anchorage 28, sling cable supporting platform seat 9, steel strand wires 10, stiff girder 11, pedestal fastening bolt 12.
Stiff girder 11 is suspended on main push-towing rope 2 by steel strand wires 10.Steel strand wires 10 are fixed on by anchorage 1 and anchorage 28 On jack 6, by the load or unload of jack 6, drive steel strand wires 10 upward or downward, from the upward of steel strand wires 10 or to Upward or downward, the adjustment of the absolute altitude of stiff girder 11 may be implemented in lower drive stiff girder 11.
Jack 6 is supported in jack supporting platform seat 7, bears the load of jack 6, and jack supporting platform seat 7 supports In sling cable supporting platform seat 9, sling cable supporting platform seat 9 bears the load that jack supporting platform seat 7 transmits.Hoist cable Wirerope supporting platform seat 9 is fixed on sling cable 5 by fastening pedestal fastening bolt 12, and the ring for forming a closure is solid It is scheduled on interim cord clip 1, the load that the jack supporting platform seat 7 in sling cable supporting platform seat 9 is transmitted passes through hoist cable steel Cord 5 is transferred on interim cord clip 1.Interim cord clip 1 is fixed on main push-towing rope 2 by interim cord clip fastening bolt 3, work progress In, interim cord clip fastening bolt 3 is fastened in time, prevent interim cord clip 1 from sliding on main push-towing rope 2.
As shown in Figure 1, two sets of construction equipments is needed to be fixed on main push-towing rope 2, temporary support and absolute altitude are carried out to stiff girder 11 Adjustment.
Embodiment 4:
On the basis of embodiment 2, a kind of construction method of no hoist cable beam section is present embodiments provided, no hoist cable beam section is used Construction equipment, the Pass line adjustment of temporary support and step 2 stiff girder 11 including step 1) stiff girder 11.
Interim cord clip 1 is fixed on main push-towing rope 2 by interim cord clip fastening bolt 3, and sling cable 5 is fixed on interim cord clip On 1;Sling cable 5 is combined into the ring of a closure by sling cable supporting platform seat 9 and pedestal anchor bolt, and is thousand Jin top support pedestal 7 provides support force;Jack supporting platform seat 7 is supported in sling cable supporting platform seat 9, and 6, jack Support is in jack supporting platform seat 7;Steel strand wires 10 pass through anchorage 1, jack 6, anchorage 28 and are connected with stiff girder 11;It is very heavy Top 6 anchors steel strand wires 10 by anchorage 1 and anchorage 28, plays the role of temporary support stiff girder 11;It needs to carry out absolute altitude tune When whole, the adjustment of 11 absolute altitude of stiff girder is carried out by the load or unload of jack 6.This method simple structure, it is easy to operate, it can Helpful reference is provided for the construction of similar bridge.
Embodiment 5:
On the basis of embodiment 4, a kind of construction method of no hoist cable beam section, stiff girder 11 and steel strand wires are present embodiments provided The connection of 10 lower ends, steel strand wires 10 are anchored by anchorage 1 and anchorage 28 and jack 6, realize the temporary support of stiff girder 11.
By the load or unload of jack 6, steel strand wires 10 are driven upward or downward, upward or downward by steel strand wires 10 It drives stiff girder 11 upward or downward, realizes the Pass line adjustment of stiff girder 11 to meet line type control requirement.
Before construction, interim cord clip 1 is fixed on main push-towing rope 2 by interim cord clip fastening bolt 3, in work progress, and When fasten interim cord clip fastening bolt 3, prevent interim cord clip 1 from sliding on main push-towing rope 2.
Wherein, the interim cord clip 1 includes pedestal, pressing plate and cushion block, and the pedestal is fixedly connected with pressing plate, the cushion block Between pedestal and pressing plate.In the construction process, cushion block can further prevent interim cord clip 1 to slide on main push-towing rope 2.Cushion block Longitudinal cross-section be wedge shape, one large one small, transversal cross-section is in a ring.Cushion block is relatively moved and the extruding force that generates, The crush resistance prevents to continue to slide between interim cord clip 1 and main push-towing rope 2.
In the construction process, jack supporting platform seat 7 bears the load of jack 6, and sling cable supporting platform seat 9 is born Load is transferred on interim cord clip 1 by the load that jack supporting platform seat 7 transmits by rope wirerope.
The construction method of this no hoist cable beam section provided by the invention, support and Pass line adjustment including no hoist cable beam section, It does not need to be influenced small, simple and fast, easy to operate, the construction safety of installation by external environment using large-scale equipment.
The foregoing examples are only illustrative of the present invention, does not constitute the limitation to protection scope of the present invention, all It is within being all belonged to the scope of protection of the present invention with the same or similar design of the present invention.The component that embodiment does not describe in detail With the well-known components and common structure or conventional means of the structure category industry, do not describe one by one here.

Claims (9)

1. a kind of construction equipment of no hoist cable beam section, it is characterised in that: including interim cord clip (1), sling cable (5), hoist cable Wirerope supporting platform seat (9), jack (6), jack supporting platform seat (7), steel strand wires (10), the interim cord clip (1) are fixed On main push-towing rope (2), pass through hoist cable after the sling cable (5) and sling cable supporting platform seat (9) one close ring of formation Wirerope (5) is fixed on interim cord clip (1), and the jack supporting platform seat (7) is set to sling cable supporting platform seat (9) On, the jack (6) is set on jack supporting platform seat (7);
Steel strand wires (10) upper end is suspended on main push-towing rope (2), and steel strand wires (10) lower end passes through jack (6), jack Supporting platform seat (7) is fixed, and steel strand wires (10) lower end is for connecting stiff girder (11).
2. a kind of construction equipment of no hoist cable beam section according to claim 1, it is characterised in that: the steel strand wires (10) are logical It crosses anchorage one (4) and anchorage two (8) and jack (6) is fixed, the anchorage one (4) and anchorage two (8) are respectively arranged on jack (6) bottom end on top and jack supporting platform seat (7).
3. a kind of construction equipment of no hoist cable beam section according to claim 1, it is characterised in that: the interim cord clip (1) It is set on main push-towing rope (2), is fixed on main push-towing rope (2) by interim cord clip fastening bolt (3).
4. a kind of construction equipment of no hoist cable beam section according to claim 1, it is characterised in that: the sling cable branch Support pedestal (9) is fixed on sling cable (5) by fastening pedestal fastening bolt (12).
5. a kind of construction equipment of no hoist cable beam section according to claim 1, it is characterised in that: the interim cord clip (1) Including pedestal, pressing plate and cushion block, the pedestal is fixedly connected with pressing plate, and the cushion block is set between pedestal and pressing plate.
6. a kind of construction method of no hoist cable beam section, uses the construction equipment of no hoist cable beam section as claimed in claim 2, feature It is: the Pass line adjustment of temporary support and step 2 stiff girder (11) including step 1) stiff girder (11).
7. a kind of construction method of no hoist cable beam section according to claim 6, it is characterised in that: stiff girder in step 1) (11) it is connect with steel strand wires (10) lower end, steel strand wires (10) are anchored by anchorage one (4) and anchorage two (8) and jack (6), real The temporary support of existing stiff girder (11).
8. a kind of construction method of no hoist cable beam section according to claim 6, it is characterised in that: by very heavy in step 2 The load or unload of (6) is pushed up, steel strand wires (10) are driven upward or downward, by the drive stiff girder upward or downward of steel strand wires (10) (11) upward or downward, the Pass line adjustment of stiff girder (11) is realized.
9. a kind of construction method of no hoist cable beam section according to claim 6, it is characterised in that: in the construction process, thousand Jin top support pedestal (7) bears the load of jack (6), and sling cable supporting platform seat (9) bears jack supporting platform seat (7) Load is transferred on interim cord clip (1) by the load transmitted by rope wirerope.
CN201811453307.1A 2018-11-30 2018-11-30 A kind of construction equipment and method of no hoist cable beam section Pending CN109235284A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811453307.1A CN109235284A (en) 2018-11-30 2018-11-30 A kind of construction equipment and method of no hoist cable beam section

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811453307.1A CN109235284A (en) 2018-11-30 2018-11-30 A kind of construction equipment and method of no hoist cable beam section

Publications (1)

Publication Number Publication Date
CN109235284A true CN109235284A (en) 2019-01-18

Family

ID=65074368

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811453307.1A Pending CN109235284A (en) 2018-11-30 2018-11-30 A kind of construction equipment and method of no hoist cable beam section

Country Status (1)

Country Link
CN (1) CN109235284A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109975110A (en) * 2019-04-29 2019-07-05 中交二公局第五工程有限公司 A kind of socket bearing capacity test method and device
CN110593112A (en) * 2019-09-25 2019-12-20 中交二公局第五工程有限公司 Suspension bridge hanging beam system and hanging beam process

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446068A (en) * 2008-12-25 2009-06-03 湖南路桥建设集团公司 Method for erecting suspension bridge main girder by segmenting and jacking and adopted device for rolling and moving heavy objects
CN102071651A (en) * 2010-12-15 2011-05-25 江苏法尔胜新日制铁缆索有限公司 Sling replacement method for suspension bridge
US20130174361A1 (en) * 2010-09-06 2013-07-11 Shunquan Qin Three-truss continuous steel truss girder-pushing device and arrangement method thereof
CN203174516U (en) * 2013-04-16 2013-09-04 中交二公局第五工程有限公司 Suspension bridge closure segment construction beam segment traction pre-deflection device
CN108625289A (en) * 2018-04-24 2018-10-09 中铁大桥勘测设计院集团有限公司 A kind of stringer and erection method suitable for stiffening girder of suspension bridge
CN209292900U (en) * 2018-11-30 2019-08-23 中交二公局第五工程有限公司 A kind of construction equipment of no hoist cable beam section

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446068A (en) * 2008-12-25 2009-06-03 湖南路桥建设集团公司 Method for erecting suspension bridge main girder by segmenting and jacking and adopted device for rolling and moving heavy objects
US20130174361A1 (en) * 2010-09-06 2013-07-11 Shunquan Qin Three-truss continuous steel truss girder-pushing device and arrangement method thereof
CN102071651A (en) * 2010-12-15 2011-05-25 江苏法尔胜新日制铁缆索有限公司 Sling replacement method for suspension bridge
CN203174516U (en) * 2013-04-16 2013-09-04 中交二公局第五工程有限公司 Suspension bridge closure segment construction beam segment traction pre-deflection device
CN108625289A (en) * 2018-04-24 2018-10-09 中铁大桥勘测设计院集团有限公司 A kind of stringer and erection method suitable for stiffening girder of suspension bridge
CN209292900U (en) * 2018-11-30 2019-08-23 中交二公局第五工程有限公司 A kind of construction equipment of no hoist cable beam section

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109975110A (en) * 2019-04-29 2019-07-05 中交二公局第五工程有限公司 A kind of socket bearing capacity test method and device
CN109975110B (en) * 2019-04-29 2024-05-03 中交二公局第五工程有限公司 Method and device for detecting bearing capacity of cable joint
CN110593112A (en) * 2019-09-25 2019-12-20 中交二公局第五工程有限公司 Suspension bridge hanging beam system and hanging beam process

Similar Documents

Publication Publication Date Title
CN202090286U (en) Traction system suitable for self-anchored type double cable plane suspension bridge
CN102713071A (en) Method for constructing a suspension bridge using temporary cables under tensionless stay cable conditions, and temporary cable for same
CN101139821A (en) Method and system for erecting steel trusses by stay cable auxiliary complete cantilever
CN205387439U (en) Mast hoisting accessory
CN201106155Y (en) Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
CN109235284A (en) A kind of construction equipment and method of no hoist cable beam section
CN210858062U (en) Self-lifting unloading platform system attached to floor
CN110468743B (en) Movable hanging bracket for transformation of old bridge pier cap and construction method
CN209292900U (en) A kind of construction equipment of no hoist cable beam section
CN109853393A (en) A kind of the hanging cable construction system and its construction method of king-tower vertical transfer cable-stayed bridge
CN207987749U (en) Ride cable-styled erection crane
CN101314937B (en) Construction method and apparatus of vertically rotating arch case downside
CN203653080U (en) Mooring rope hanging mechanism capable of meeting motion of portal crane
CN109374396A (en) The hydraulic vertical transfer experiment porch of anchor tie plate fatigue test
CN108625289A (en) A kind of stringer and erection method suitable for stiffening girder of suspension bridge
CN104085832B (en) A kind of method for improving of flexible member lifting device
CN211691355U (en) A construction platform for high slope construction usefulness
CN210002233U (en) Hoisting system suitable for suspension bridge steel structure bridge deck system
CN211257921U (en) Steel bar truss building carrier plate draws device and system to one side
CN211645924U (en) Self-balancing suspension bridge structure system
CN114541283A (en) Structure and method for solving continuous downwarping problem of large-span PC beam bridge
CN203065046U (en) Self-stabilizing double-rocker-arm lifting device for installation of high-rise tower
CN105735155A (en) Bridge mid-span droop reinforcing device and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination