CN109179157A - Shallow pit formula modularization installs elevator additional - Google Patents

Shallow pit formula modularization installs elevator additional Download PDF

Info

Publication number
CN109179157A
CN109179157A CN201811122799.6A CN201811122799A CN109179157A CN 109179157 A CN109179157 A CN 109179157A CN 201811122799 A CN201811122799 A CN 201811122799A CN 109179157 A CN109179157 A CN 109179157A
Authority
CN
China
Prior art keywords
additional
installs
pit
elevator
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811122799.6A
Other languages
Chinese (zh)
Inventor
沈益祥
虞丹萍
孙聪聪
薄建林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Days Austrian Elevator (china) Co Ltd
Original Assignee
Days Austrian Elevator (china) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Days Austrian Elevator (china) Co Ltd filed Critical Days Austrian Elevator (china) Co Ltd
Priority to CN201811122799.6A priority Critical patent/CN109179157A/en
Publication of CN109179157A publication Critical patent/CN109179157A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B11/00Main component parts of lifts in, or associated with, buildings or other structures
    • B66B11/02Cages, i.e. cars
    • B66B11/0226Constructional features, e.g. walls assembly, decorative panels, comfort equipment, thermal or sound insulation
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B13/00Doors, gates, or other apparatus controlling access to, or exit from, cages or lift well landings
    • B66B13/30Constructional features of doors or gates
    • B66B13/301Details of door sills

Abstract

The present invention relates to Car frame structure field, specially shallow pit formula modularization installs elevator additional.It includes that the preceding pre-assembled pit of factory installs section additional, floor installs section additional and computer room installs section additional that shallow pit formula modularization, which installs elevator additional,;It includes pit that the pit, which installs section additional, and the pit includes the pit straight beam of four-part form, and pit straight beam upper end is provided with the lower layer's interconnecting piece for installing the minimum floor portion bottom riveting of section additional with the floor;It includes multiple floor portions that the floor, which installs section additional, and the multiple floor portion includes that structure and/or multiple nonstandardized techniques installation mechanism are installed in multiple standardization additional;It includes top layer machine room framework that the computer room, which installs section additional, running gear is provided on the upper beam of the top layer machine room framework, the running gear includes the crosshead sheave being arranged on the upper beam, and the bottom plate of the top layer machine room framework is connect with the top floor portion top that the floor installs section additional.Modularized design of the present invention, facilitates cell to construct, and greatly shortens the set-up time.

Description

Shallow pit formula modularization installs elevator additional
Technical field
The present invention relates to Car frame structure field, specially shallow pit formula modularization installs elevator additional.
Background technique
There are two types of implementations for existing installation elevator: the first, make pit, steelframe, decoration, this scheme construction week Phase is up to 3 months, and construction period causes tremendous influence to resident's daily life.Second, pit is made, steelframe is in factory Interior completion, on-site hoisting combination, then normal procedure installs elevator, this scheme construction period has larger shadow at 1 month, to resident It rings.There is site operation period length in above two mode, need short construction period, influence on resident's daily life small Design scheme.
Summary of the invention
Above-mentioned technical purpose of the invention has the technical scheme that
Shallow pit formula modularization installs elevator additional, including the preceding pre-assembled pit of factory installs section additional, floor installs section additional and computer room installs additional Section;
It includes pit that the pit, which installs section additional, and the pit includes the pit straight beam of four-part form, the setting of pit straight beam upper end There is the lower layer's interconnecting piece for the minimum floor portion bottom riveting for installing section additional with the floor;
It includes multiple floor portions that the floor, which installs section additional, and the multiple floor portion includes multiple standardization installation structures and/or multiple Structure is installed in nonstandardized technique additional, and the standardization installs riveting and/or the nonstandardized technique between structure additional and installs riveting between structure additional It connects in succession and/or structure is installed in the standardization additional, riveting between structure is installed in the nonstandardized technique additional;
It includes top layer machine room framework that the computer room, which installs section additional, is provided with running gear on the upper beam of the top layer machine room framework, institute Stating running gear includes the crosshead sheave being arranged on the upper beam, and the bottom plate and the floor of the top layer machine room framework install section additional Top floor portion at the top of connection.
As the preferred of the technical program, it includes straight beam before two sections, straight beam after two sections that structure is installed in the standardization, which additional,;Two sections Pairs of elevator lobby bottom attachment device and elevator lobby top attachment device are provided between the preceding straight beam;
Spaced rear straight beam attachment device is set between straight beam after described two sections.
As the preferred of the technical program, at least a pair of elevator lobby bottom attachment device and the elevator lobby top The distance between attachment device is with other between elevator lobby bottom attachment device and elevator lobby top attachment device Distance it is different.
As the preferred of the technical program, the distance between adjacent described rear straight beam attachment device is identical.
As the preferred of the technical program, elevator lobby bottom attachment device, elevator lobby top attachment device and The preceding straight beam surrounds elevator lobby area, and the hoistway door of removable switch is provided in the elevator lobby area.
As the preferred of the technical program, the hoistway door is arranged with the collapsible gate toeguard that can be stretched.
As the preferred of the technical program, pit has downlink holdout device holding part, the downlink holdout device accommodating Portion can accommodate downlink holdout device insertion.
As the preferred of the technical program, the pit straight beam can be directly connected to car floor.
As the preferred of the technical program, damping rubber block is provided between the crosshead sheave and the upper beam.
As the preferred of the technical program, it further includes the ventilation shutter for being set to top that the computer room, which installs section additional,.
The beneficial effect of the technical program is:
1, pre-assembled pit installs section additional before design factory from top to bottom, floor installs section additional and computer room installs section additional, logical between each other Lifting riveting is crossed, construction requirement is substantially reduced, shortens the construction time.
2, the multiple floor portion includes that structure and/or multiple nonstandardized techniques installation knot are installed in multiple standardization additional,
Structure not pre-assembly is installed in the nonstandardized technique additional, accomplishes fluently adjustment hole in the channel steel junction of preceding straight beam, prevents from answering floor Height is not allowed to bring error, causes lading door dill and shelter bridge uneven.
3, top is designed equipped with ventilation shutter, prevents computer room temperature excessively high, influences elevator operation.
Detailed description of the invention
Fig. 1 is the facing structure figure that shallow pit formula modularization of the invention installs elevator additional;
Fig. 2 is the backsight structure chart that shallow pit formula modularization of the invention installs elevator additional;
Fig. 3 is that shallow pit formula modularization of the invention installs the structure chart that elevator(lift) machine room installs section additional additional;
Fig. 4 is the structure chart of pit straight beam of the present invention;
Fig. 5 is the structure chart of downlink holdout device of the present invention.
Wherein, 1- pit installs section, 11- pit, 111- pit straight beam, 112- downlink holdout device holding part, 12- downlink additional Device, 113- lower layer interconnecting piece are prevented, 2- floor installs section additional, and 21-, which is standardized, installs structure additional, straight beam before 211-, straight beam after 212-, 213- elevator lobby bottom attachment device, 214- elevator lobby top attachment device, straight beam attachment device after 215-, 22- nonstandardized technique Install structure, 23- hoistway door additional, 3- computer room installs section, 31- upper beam, 32- running gear, 321- crosshead sheave, 322- rubber shock-absorbing additional Block, 33- ventilation shutter.
Specific embodiment
Following specific embodiments are only explanation of the invention, are not limitation of the present invention, art technology Personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as All by the protection of Patent Law in scope of the presently claimed invention.
Embodiment 1
As shown in Figure 1-3, installing elevator additional for shallow pit formula modularization.
Shallow pit formula modularization installs elevator additional, including the preceding pre-assembled pit of factory installs section 1 additional, floor installs section 2 and machine additional Room installs section 3 additional.
Pre-assembled pit installs section 1 additional before design factory from top to bottom, floor installs section 2 additional and computer room installs section 3 additional, mutually it Between by lifting riveting, substantially reduce construction requirement, shorten the construction time.
It includes pit 11 that the pit, which installs section 1 additional, and the pit 11 includes the pit straight beam 111 of four-part form, the pit 111 upper end of straight beam is provided with the lower layer's interconnecting piece 113 for installing the minimum floor portion bottom riveting of section 2 additional with the floor.
Further, installation is guaranteed that varying environment steel construction main body is stronger, is not shaken using insertion pit design. Using no lower beam structure, car floor is directly connected to the pit straight beam 111, is substantially reduced lower space, is designed using shallow pit, As long as the minimum 800MM of pit.
It includes multiple floor portions that the floor, which installs section 2 additional, and the multiple floor portion includes that structure 21 is installed in multiple standardization additional And/or structure 22 is installed in multiple nonstandardized techniques additional, the standardization is installed riveting and/or the nonstandardized technique between structure 21 additional and is added Structure 21 is installed in riveting and/or the standardization additional between assembling structure 22, the company of riveting between structure 22 is installed in the nonstandardized technique additional It connects.
It includes top layer machine room framework that the computer room, which installs section 3 additional, is provided with operation on the upper beam 31 of the top layer machine room framework Device 32, the running gear 32 include the crosshead sheave 321 being arranged on the upper beam 31, the bottom plate of the top layer machine room framework The 33 top floor portion tops for installing section 2 additional with the floor are connect.The upper beam 31 uses two 321 cloth of crosshead sheave It sets, the crosshead sheave 321 is arranged among the upper beam 31 using multiple damping rubber blocks, and the stabilization of carriage operation had both been improved Property, and the comfort of carriage operation is improved, reduce noise and vibration.
Further, it is steel construction which, which installs the hoistway structure of elevator additional, and main structure selects H profile steel knot Structure, intensity is big, has a safety feature.External decoration structure selects stainless steel and the double-deck tempering heat insulation clamps glue tempered glass to combine, and has Segmented and split blade type exterior decoration assemble factory with steel construction, are sent by special tooling to scene.
Further, external decoration structure selects stainless steel and the double-deck tempering heat insulation clamps glue tempered glass to combine.
Further, segmented and split blade type installation are not necessarily to scaffolding, and lifting, and guide rail, guide rail can be completed within one day Bracket is preceding pre-assembled with steel construction factory, greatly shortens the set-up time.
Structure of the invention installs elevator research and development manufacture additional mainly for aging blocks, by the different several installation sides of cell execution conditions Formula combines Uniting, and versatility is stronger, segmented and split blade type etc. by with the pre-assembled forms such as guide rail, compared to tradition Steel construction accelerates installation speed, accomplishes not disturb residents really.The characteristics of installing additional also directed to Lao Lou, hoistway is small, and pit should descend facial canal Road reason than it is shallower the features such as, shallow pit design structure has been carried out to elevator, and guarantee that elevator safety is unaffected.
Embodiment 2
As shown in Figs. 1-5, it is based on embodiment 1, difference from Example 1 is:
The standardization installs structure 21 additional and includes straight beam 212 after 211, two sections of straight beam before two sections;Between two sections of preceding straight beams 211 It is provided with pairs of elevator lobby bottom attachment device 213 and elevator lobby top attachment device 214;
Spaced rear straight beam attachment device 215 is set between straight beam 212 after described two sections.
Further, which installs the straight beam of elevator additional using four-part form structure (i.e. two institutes in front Before stating two of straight beam 211 and rear it is described after straight beams 212), middle position is substantially reduced guide rail away from keeping hoistway wide without straight beam Spend small as far as possible, saving installation elevator the space occupied.
Between at least a pair of elevator lobby bottom attachment device 213 and elevator lobby top attachment device 214 Distance with other to the distance between elevator lobby bottom attachment device 213 and elevator lobby top attachment device 214 no Together.At practice of construction scene, it is possible to deposit that height between floors is different to establish a capital the same situation, answer story height in order to prevent Degree is not allowed to bring error, and it is uneven to cause lading door dill and shelter bridge, so in the preceding 211 top pre-assembly of straight beam, root on the spot According to story height, adjustable to elevator lobby bottom attachment device 213 and institute with the channel steel junction of the preceding straight beam 211 Elevator lobby top attachment device 214 is stated to be installed.
The distance between the adjacent rear straight beam attachment device 215 is identical.
Elevator lobby bottom attachment device 213, elevator lobby top attachment device 214 and the preceding straight beam 211 enclose At elevator lobby area, the hoistway door 23 of removable switch is provided in the elevator lobby area.
The hoistway door 23 is arranged with the collapsible gate toeguard that can be stretched.
Further, the gate toeguard uses collapsible, with switch at hall door lockhole, toeguard when usually running It shrinks, when the hoistway door 23 is unlocked, the gate toeguard is elongated to normal length (in addition to the first floor), has both guaranteed shallow bottom The gate toeguard does not hit pit when the operation of hole, and guarantees that the gate toeguard reaches safe length in rescue.
Pit 11 has downlink holdout device holding part 112, and the downlink holdout device holding part 112 can accommodate downlink Device 12 is prevented to be inserted into.
The downlink holdout device 12 is bolt form, and the downlink can be inserted into maintenance staff's pit overhaul and is prevented Device holding part 112.
Further, pit is equipped with the downlink holdout device 12, and when maintenance staff's pit overhaul, the downlink prevented dress 12 are set, elevator can only overhaul uplink and downlink after triggering by inductive switch.
The pit straight beam 111 can be directly connected to car floor.Using no lower beam structure, car floor and the pit straight beam 111 are directly connected to, and are substantially reduced lower space, are designed using shallow pit, as long as the minimum 800MM of pit.
Damping rubber block 322 is provided between the crosshead sheave 321 and the upper beam 31.The upper beam 31 uses two institutes The arrangement of crosshead sheave 321 is stated, the crosshead sheave 321 is arranged among the upper beam 3 using multiple damping rubber blocks 322, both The stability of carriage operation is improved, and improves the comfort of carriage operation, reduces noise and vibration.
It further includes the ventilation shutter 33 for being set to top that the computer room, which installs section 3 additional,.Top is equipped with the ventilation shutter 33, it prevents computer room temperature excessively high, influences elevator operation.

Claims (10)

1. shallow pit formula modularization installs elevator additional, which is characterized in that install section (1), floor additional including pre-assembled pit before dispatching from the factory It installs section (2) additional and computer room installs section (3) additional;
It includes pit (11) that the pit, which installs section (1) additional, and the pit (11) includes the pit straight beam (111) of four-part form, described Pit straight beam (111) upper end is provided with the lower layer's interconnecting piece for installing the minimum floor portion bottom riveting of section (2) additional with the floor (113);
It includes multiple floor portions that the floor, which installs section (2) additional, and the multiple floor portion includes that structure (21) are installed in multiple standardization additional And/or structure (22) are installed in multiple nonstandardized techniques additional, riveting and/or described non-standard between standardization installation structure (21) Change and installs riveting and/or standardization installation structure (21), nonstandardized technique installation structure (22) between structure (22) additional Between riveting;
It includes top layer machine room framework that the computer room, which installs section (3) additional, is provided with operation on the upper beam (31) of the top layer machine room framework Device (32), the running gear (32) include the crosshead sheave (321) being arranged on the upper beam (31), the top layer computer room frame The bottom plate (33) of frame is connect with the top floor portion top that the floor installs section (2) additional.
2. shallow pit formula modularization according to claim 1 installs elevator additional, which is characterized in that structure is installed in the standardization additional It (21) include straight beam (211), straight beam (212) after two sections before two sections;Pairs of electricity is provided between two sections of preceding straight beams (211) Terraced entrance hall bottom attachment device (213) and elevator lobby top attachment device (214);
Spaced rear straight beam attachment device (215) is set between straight beam (212) after described two sections.
3. shallow pit formula modularization according to claim 2 installs elevator additional, which is characterized in that at least a pair of elevator The distance between entrance hall bottom attachment device (213) and elevator lobby top attachment device (214) are with other to the elevator door The distance between Room bottom attachment device (213) and elevator lobby top attachment device (214) difference.
4. shallow pit formula modularization according to claim 2 installs elevator additional, which is characterized in that the adjacent rear straight beam connection The distance between device (215) is identical.
5. shallow pit formula modularization according to claim 2 installs elevator additional, which is characterized in that the elevator lobby bottom connection Device (213), elevator lobby top attachment device (214) and the preceding straight beam (211) surround elevator lobby area, the elevator The hoistway door (23) of removable switch is provided in the area of entrance hall.
6. shallow pit formula modularization according to claim 5 installs elevator additional, which is characterized in that under the hoistway door (23) It is provided with the collapsible gate toeguard that can be stretched.
7. shallow pit formula modularization according to claim 1 installs elevator additional, which is characterized in that pit (11) is hindered with downlink Locking apparatus holding part (112), the downlink holdout device holding part (112) can accommodate downlink holdout device (12) insertion.
8. shallow pit formula modularization according to claim 1 installs elevator additional, which is characterized in that the pit straight beam (111) It can be directly connected to car floor.
9. shallow pit formula modularization according to claim 1 installs elevator additional, which is characterized in that the crosshead sheave (321) with Damping rubber block is provided between the upper beam (31).
10. shallow pit formula modularization according to claim 1 installs elevator additional, which is characterized in that the computer room installs section (3) additional It further include the ventilation shutter (33) for being set to top.
CN201811122799.6A 2018-09-26 2018-09-26 Shallow pit formula modularization installs elevator additional Pending CN109179157A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811122799.6A CN109179157A (en) 2018-09-26 2018-09-26 Shallow pit formula modularization installs elevator additional

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811122799.6A CN109179157A (en) 2018-09-26 2018-09-26 Shallow pit formula modularization installs elevator additional

Publications (1)

Publication Number Publication Date
CN109179157A true CN109179157A (en) 2019-01-11

Family

ID=64906402

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811122799.6A Pending CN109179157A (en) 2018-09-26 2018-09-26 Shallow pit formula modularization installs elevator additional

Country Status (1)

Country Link
CN (1) CN109179157A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110316637A (en) * 2019-08-08 2019-10-11 中科鼎盛电梯科技江苏有限公司浙江分公司 A kind of no foundation pit installation earthquake resistance of elevator attachment device

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101066735A (en) * 2007-05-09 2007-11-07 西子奥的斯电梯有限公司 Foot protecting plate for telescopic cage
CN102120542A (en) * 2010-12-30 2011-07-13 沈阳博林特电梯股份有限公司 Telescopic foot protection plate
CN102180394A (en) * 2011-05-30 2011-09-14 张凡 Integrated building-block-type lift of strip steel structure
CN203715021U (en) * 2014-03-06 2014-07-16 苏州德奥电梯有限公司 Car roof wheel assembly of machine roomless elevator
CN104291179A (en) * 2014-10-24 2015-01-21 森赫电梯股份有限公司 Mechanical stop device for elevator
CN104326320A (en) * 2014-10-29 2015-02-04 康力电梯股份有限公司 Telescopic lift car toe guard
CN105775949A (en) * 2016-05-06 2016-07-20 南京市莱茵帝得电梯有限公司 Detachable and telescopic lift car kickplate and high-reliability bottomless pit elevator
CN209009921U (en) * 2018-09-26 2019-06-21 天奥电梯(中国)有限公司 Shallow pit formula modularization installs elevator additional

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101066735A (en) * 2007-05-09 2007-11-07 西子奥的斯电梯有限公司 Foot protecting plate for telescopic cage
CN102120542A (en) * 2010-12-30 2011-07-13 沈阳博林特电梯股份有限公司 Telescopic foot protection plate
CN102180394A (en) * 2011-05-30 2011-09-14 张凡 Integrated building-block-type lift of strip steel structure
CN203715021U (en) * 2014-03-06 2014-07-16 苏州德奥电梯有限公司 Car roof wheel assembly of machine roomless elevator
CN104291179A (en) * 2014-10-24 2015-01-21 森赫电梯股份有限公司 Mechanical stop device for elevator
CN104326320A (en) * 2014-10-29 2015-02-04 康力电梯股份有限公司 Telescopic lift car toe guard
CN105775949A (en) * 2016-05-06 2016-07-20 南京市莱茵帝得电梯有限公司 Detachable and telescopic lift car kickplate and high-reliability bottomless pit elevator
CN209009921U (en) * 2018-09-26 2019-06-21 天奥电梯(中国)有限公司 Shallow pit formula modularization installs elevator additional

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110316637A (en) * 2019-08-08 2019-10-11 中科鼎盛电梯科技江苏有限公司浙江分公司 A kind of no foundation pit installation earthquake resistance of elevator attachment device

Similar Documents

Publication Publication Date Title
CN102180395B (en) Integrated sightseeing lift with steel-structured hoistway
CN102180394B (en) Integrated building-block-type lift of strip steel structure
CN202072375U (en) Installation-free type steel structure framework integral elevator
CN204588379U (en) For the Dokdo type elevator of outdoor
CN209009921U (en) Shallow pit formula modularization installs elevator additional
CN109179157A (en) Shallow pit formula modularization installs elevator additional
CN104016212B (en) Panoramic observation elevator without machine room four sides door opening method and four sides door-opened sightseeing elevator
CN107108168B (en) Elevator system
CN105645223A (en) Integrated lift of steel structure
CN208329500U (en) Steel structure lift shaft and the elevator for using the hoistway
CN106044489A (en) Household car frame with overhang safety tongs
JP2002087741A (en) Elevator
CN107902523B (en) Sheet-shaped old building additional elevator
CN114127002B (en) Method and auxiliary device for installing elevator
CN207526051U (en) A kind of hoistway structure for installing elevator additional
CN208856755U (en) A kind of machine room structure of subsidiary inspection platform
CN210619950U (en) Three-side-opening elevator without machine room
JPS63202579A (en) Method of renewal construction of elevator
CN208413580U (en) A kind of shallow pit elevator carriage
CN207536962U (en) A kind of car external passenger elevators
JP5832676B2 (en) Elevator door apparatus and elevator door installation method
CN110436301B (en) Emergency rescue channel structure of elevator
CN209536752U (en) A kind of band steel structure modularization elevator
CN216471868U (en) Tower crane-free building assembled component hoisting platform
KR20200000741A (en) Method for installing elevator and structure therefor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination