CN109165837A CN201810927616.1A CN201810927616A CN109165837A CN 109165837 A CN109165837 A CN 109165837A CN 201810927616 A CN201810927616 A CN 201810927616A CN 109165837 A CN109165837 A CN 109165837A
Authority
CN
China
Prior art keywords
power supply
supply path
equipment
guarantor
risk
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810927616.1A
Other languages
Chinese (zh)
Other versions
CN109165837B (en
Inventor
周济
李晨
徐希
吴婧妤
吴奕
胡伟
杨梓俊
荆江平
张大林
马洲俊
赵肖旭
高洁
罗兴
兰岚
马海涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nari Technology Co Ltd
Nanjing NARI Group Corp
Nanjing Power Supply Co of Jiangsu Electric Power Co
Original Assignee
State Grid Corp of China SGCC
State Grid Jiangsu Electric Power Co Ltd
Nari Technology Co Ltd
Nanjing NARI Group Corp
Nanjing Power Supply Co of Jiangsu Electric Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, State Grid Jiangsu Electric Power Co Ltd, Nari Technology Co Ltd, Nanjing NARI Group Corp, Nanjing Power Supply Co of Jiangsu Electric Power Co filed Critical State Grid Corp of China SGCC
Priority to CN201810927616.1A priority Critical patent/CN109165837B/en
Publication of CN109165837A publication Critical patent/CN109165837A/en
Application granted granted Critical
Publication of CN109165837B publication Critical patent/CN109165837B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply

Abstract

Operation risk analysis method is classified based on main guarantor's power supply area with one the invention discloses a kind of, based on the main the whole network supply path search for realizing the electric user of guarantor with Integrated Model, it ties contracted areas and protects the otherness of electric user's power configuration principle and the related foundation of risk deciding grade and level, it constructs power supply and lacks risk rating experts database, the redundant configuration of electric user's different voltages grade power supply point is protected in analysis, assessment protects electricity user's power supply and lacks risk, realizes main with integral system guarantor's power supply area classification operation risk analysis.Meanwhile, it is capable to extract supply path cluster tool by Topology service dynamic based on real-time grid state, the supply path and its power supply risk of electric user are protected using tree topology mode automatic Display.The method of the present invention can assist in management and running personnel and control the electric customer power supply situation of guarantor in real time, prompt for risk, sound assurance power supply reliability.

Description

Operation risk analysis method is classified based on main guarantor's power supply area with one
Technical field
The invention belongs to dispatching automation of electric power systems field more particularly to a kind of guarantor's power supply areas based on master with one It is classified operation risk analysis method.
Background technique
Traditional responsible consumer running state monitoring only realizes the monitoring that user matches net side power supply, due to lacking major network path Information can not monitor major network power supply power supply state, cannot provide responsible consumer transmission & distribution integrally highly reliable operation risk Analysis and early warning.Based on transmission and distribution network integral system framework, it can be achieved that fortune to responsible consumer (protect electric user) transmission & distribution complete trails Row risk assessment early warning protects electric customer power supply path to 500kV by search, and electric area operation state is protected in monitoring, according to prior The evaluation criteria (different regions difference protects electric level assessment index system and evaluation criteria is different) made carries out real-time Analysis ensures the highly reliable operation of responsible consumer to the timely early warning of the electric user of the equipment of occurrence risk, path and corresponding guarantor.
Summary of the invention
Goal of the invention: in view of the above problems, the present invention proposes a kind of guarantor's power supply area classification operation based on main with one Risk analysis method.
Technical solution: to achieve the purpose of the present invention, the technical scheme adopted by the invention is that: one kind is based on main with one Guarantor's power supply area be classified operation risk analysis method, obtain main distribution Integrated Model and real time operation mode, pass through network Topological analysis searches the supply path of target device, and supply path, which is searched, flows to information according to equipment connecting relation and trend, All primary equipments on supply path are counted, the standby electricity source point of different voltages grade bus is searched, obtains on supply path The power configuration information of different voltages grade assesses the risk class of the guarantor electricity user in conjunction with power supply risk experts database.Based on confession Equipment connecting relation on power path generates supply path display diagram by the way of automatic tree layout.
Further, comprising steps of
(1) the main data information for matching Integrated Model and the method for operation is obtained, the connection relationship of equipment room is established;
(2) electric user is protected from target, obtains the device node for protecting electric user, by the connection relationship of device node, Using topology search technology, the opposite direction along trend flow direction up traces step by step, the equipment passed through during record search, until Until target voltage grade equipment;
(3) after the completion of searching for, all buses on supply path is counted, the backup power source feelings of every bus are successively analyzed Condition, and record backup power source number;
(4) power supply risk rule library is combined, judges whether the backup power source number of each voltage class meets condition, and give Corresponding risk class out;
(5) supply path connection is generated by automatic tree topology technology based on the equipment connecting relation on supply path Relational graph is simultaneously shown.
Further, the step (2) includes:
(2.1) from electric user equipment node is protected, based on the connection relationship of electric network model equipment, retrospect upwards step by step;
(2.2) equipment in search process is recorded, and forms connection relationship;
(2.3) judge whether to search target voltage grade, if having searched highest voltage level, complete this time and search Otherwise rope continues the equipment search of next voltage class.
Further, the retrospect target of supply path can be with the equipment for finding a certain voltage class by being manually specified Path tracing termination condition.
The utility model has the advantages that the present invention is based on main guarantor's power supply areas with one to be classified operation risk analysis method, matched based on master Integrated Model realizes the whole network supply path search for protecting electric user, and knot contracted areas protects the difference of electric user's power configuration principle Property and risk deciding grade and level related foundation, building power supply lacks risk rating experts database, and electric user's different voltages grade electricity is protected in analysis The redundant configuration of source point, assessment protect electricity user's power supply and lack risk, realize main with integral system guarantor's power supply area classification operation Risk analysis.Meanwhile, it is capable to supply path cluster tool be extracted by Topology service dynamic based on real-time grid state, using tree Shape layout type automatic Display protects the supply path and its power supply risk of electric user.The method of the present invention can assist in management and running people Member controls in real time protects electric customer power supply situation, prompt for risk, sound assurance power supply reliability.
Detailed description of the invention
Fig. 1 is the method for the present invention the general frame.
Specific embodiment
Further description of the technical solution of the present invention with reference to the accompanying drawings and examples.
It is of the present invention that operation risk analysis method is classified based on main guarantor's power supply area with one, master is obtained first to be matched Net Integrated Model and real time operation mode, the supply path of target device is searched by Network topology, and supply path is looked into It looks for and flows to information according to equipment connecting relation and trend, count all primary equipments on supply path, search different voltages The standby electricity source point of grade bus obtains the power configuration information of different voltages grade on the supply path, in conjunction with power supply risk Experts database assesses the risk class of the guarantor electricity user.
Supply path refers to route, the main transformer, switch, disconnecting link from designated user, passed through along the retrospect of trend opposite direction And the primary equipments such as bus.The retrospect target of supply path can find setting for a certain voltage class by being manually specified Standby is path tracing termination condition.
Meanwhile based on the equipment connecting relation on supply path, supply path is generated by the way of automatic tree layout Display diagram.Main guarantor's power supply area classification operation risk analysis method with one supports anticipation mode simultaneously, and implementation is same as above.
Specific step is as follows:
Step 1, the data information for obtaining the main electric network model with one and the method for operation, the connection for establishing equipment room are closed System, including device name, connecting node, switch state, disconnecting link state, route are active, main transformer winding is active etc.;
Step 2, electric user is protected from target, obtains the device node of the guarantor electricity user, passes through the connection of device node Relationship simultaneously combines switch, disconnecting link state, and using topology search technology, the opposite direction along trend flow direction is up traced step by step, recorded The equipment passed through in search procedure, until target voltage grade equipment;
Step 2.1, it is chased after upwards step by step from the electric user equipment node of guarantor based on the connection relationship of electric network model equipment It traces back, trace back process follows the reversed principle of trend, i.e., carries out next step search when trend is reversed, otherwise exit search;
Step 2.2, the equipment such as main transformer, route, bus, switch, the disconnecting link in search process are recorded, and forms connection and closes System;
Step 2.3, judge whether to search target voltage grade, if having searched highest voltage level, completing should Otherwise secondary search continues the equipment search of next voltage class;
Step 3, after the completion of search, all buses on the supply path is counted, the standby electricity of every bus is successively analyzed Whether source situation can search attachable stand-by heat switch, and record backup power source number;
Step 4, in conjunction with power supply risk rule library, judge whether the backup power source number of each voltage class meets condition, And provide corresponding risk class;
Step 5, the equipment such as route, main transformer, switch, disconnecting link on supply path are obtained, by automatic tree topology technology, It generates supply path annexation figure and shows.
It is of the present invention that operation risk analysis method is classified based on main guarantor's power supply area with one, it can be matched based on master The whole network supply path of electric user is protected in Integrated Model analysis, and power supply is established in the power supply redundancy configuration of analysis different voltages grade Risk experts database, assessment protect electric user's power supply and lack risk.

Claims (5)

1. a kind of be classified operation risk analysis method based on main guarantor's power supply area with one, which is characterized in that obtain main distribution Integrated Model and real time operation mode, the supply path of target device is searched by Network topology, and supply path is searched Information is flowed to according to equipment connecting relation and trend, counts all primary equipments on supply path, searches different voltages etc. The standby electricity source point of grade bus, obtains the power configuration information of different voltages grade on supply path, in conjunction with power supply risk expert The risk class of the guarantor electricity user is assessed in library.
2. according to claim 1 be classified operation risk analysis method, feature based on main guarantor's power supply area with one It is, further includes, based on the equipment connecting relation on supply path, supply path exhibition is generated by the way of automatic tree layout Diagram.
3. according to claim 2 be classified operation risk analysis method, feature based on main guarantor's power supply area with one It is, comprising steps of
(1) the main data information for matching Integrated Model and the method for operation is obtained, the connection relationship of equipment room is established;
(2) electric user is protected from target, obtains the device node for protecting electric user, by the connection relationship of device node, used Topology search technology, the opposite direction along trend flow direction up trace step by step, the equipment passed through during record search, until target Until voltage class equipment;
(3) after the completion of searching for, all buses on supply path is counted, the backup power source situation of every bus is successively analyzed, and Record backup power source number;
(4) power supply risk rule library is combined, judges whether the backup power source number of each voltage class meets condition, and provide phase The risk class answered;
(5) supply path connection relationship is generated by automatic tree topology technology based on the equipment connecting relation on supply path Scheme and shows.
4. according to claim 3 be classified operation risk analysis method, feature based on main guarantor's power supply area with one It is, the step (2) includes:
(2.1) from electric user equipment node is protected, based on the connection relationship of electric network model equipment, retrospect upwards step by step;
(2.2) equipment in search process is recorded, and forms connection relationship;
(2.3) judge whether to search target voltage grade, if having searched highest voltage level, complete the secondary search, Otherwise continue the equipment search of next voltage class.
5. according to claim 1 be classified operation risk analysis method, feature based on main guarantor's power supply area with one It is, the retrospect target of supply path can be terminated using the equipment for finding a certain voltage class as path tracing by being manually specified Condition.
CN201810927616.1A 2018-08-15 2018-08-15 Power protection and supply area grading operation risk analysis method based on main distribution integration Active CN109165837B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810927616.1A CN109165837B (en) 2018-08-15 2018-08-15 Power protection and supply area grading operation risk analysis method based on main distribution integration

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810927616.1A CN109165837B (en) 2018-08-15 2018-08-15 Power protection and supply area grading operation risk analysis method based on main distribution integration

Publications (2)

Publication Number Publication Date
CN109165837A true CN109165837A (en) 2019-01-08
CN109165837B CN109165837B (en) 2021-11-30

Family

ID=64895780

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810927616.1A Active CN109165837B (en) 2018-08-15 2018-08-15 Power protection and supply area grading operation risk analysis method based on main distribution integration

Country Status (1)

Country Link
CN (1) CN109165837B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111898925A (en) * 2020-08-13 2020-11-06 国网湖南省电力有限公司 Area protection power supply risk analysis method based on event tree
CN115347570A (en) * 2022-10-17 2022-11-15 国网浙江省电力有限公司宁波供电公司 Main-distribution cooperation-based regional power failure range analysis method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102931726A (en) * 2012-10-22 2013-02-13 深圳供电局有限公司 Main network and distribution network integrated security power supply system
CN103955789A (en) * 2014-04-18 2014-07-30 国电南瑞科技股份有限公司 Power supply path analyzing method based on integrated model for allocation
CN105305444A (en) * 2015-11-30 2016-02-03 国网浙江省电力公司绍兴供电公司 Distribution network intelligent alarm and processing method based on integrated allocation
CN107944661A (en) * 2017-10-26 2018-04-20 国电南瑞科技股份有限公司 A kind of main distribution integration regulator control system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102931726A (en) * 2012-10-22 2013-02-13 深圳供电局有限公司 Main network and distribution network integrated security power supply system
CN103955789A (en) * 2014-04-18 2014-07-30 国电南瑞科技股份有限公司 Power supply path analyzing method based on integrated model for allocation
CN105305444A (en) * 2015-11-30 2016-02-03 国网浙江省电力公司绍兴供电公司 Distribution network intelligent alarm and processing method based on integrated allocation
CN107944661A (en) * 2017-10-26 2018-04-20 国电南瑞科技股份有限公司 A kind of main distribution integration regulator control system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111898925A (en) * 2020-08-13 2020-11-06 国网湖南省电力有限公司 Area protection power supply risk analysis method based on event tree
CN111898925B (en) * 2020-08-13 2022-08-05 国网湖南省电力有限公司 Area protection power supply risk analysis method based on event tree
CN115347570A (en) * 2022-10-17 2022-11-15 国网浙江省电力有限公司宁波供电公司 Main-distribution cooperation-based regional power failure range analysis method
CN115347570B (en) * 2022-10-17 2023-01-24 国网浙江省电力有限公司宁波供电公司 Main-distribution cooperation-based regional power failure range analysis method

Also Published As

Publication number Publication date
CN109165837B (en) 2021-11-30

Similar Documents

Publication Publication Date Title
CN105894172B (en) Combined power failure research and judgment method based on marketing and distribution fusion
CN106021596B (en) A kind of analysis method of electric network fault rush of current topological diagram
CN106124935A (en) Middle and low voltage network Fault Locating Method
CN106990328A (en) The analysis of distribution repairing abnormal data, fault location system and method
CN103093276B (en) Urban power grid risk assessment method
CN104318374A (en) Method for assessing reliability of medium voltage distribution network for calculating upstream power restoration operation time
CN104914356A (en) Distribution network fault positioning method based on network structure matrix
CN107167704A (en) Fault Diagnosis of Distribution Network system and method based on CIM
CN109447284B (en) Distribution network fault information sending method and system for power supply service command platform
CN103926891B (en) Mobile Telecommunication Equipment Room environment in mobile stations equipment monitoring system and method
CN102608497B (en) Power failure diagnosis method and device
CN106097159A (en) Related information topology analyzing method and system in a kind of power distribution network
CN109165837A (en) Operation risk analysis method is classified based on main guarantor's power supply area with one
Gautam et al. Development and integration of momentary event models in active distribution system reliability assessment
CN104795897B (en) The configurable relay protecting method of intelligent substation and system
CN104123478A (en) Fast topology analysis method based on general information model
CN107067126B (en) Thermal stability key power transmission channel identification method based on power flow transfer ratio
CN110412421B (en) Method and system for intelligently analyzing and positioning faults
CN109142988A (en) A kind of distribution network fault location method and system based on electric energy quality monitoring data
CN113627766A (en) Risk identification method for topology identification power failure maintenance plan
CN105335824B (en) Distribution network failure repairing command methods and system based on data center
CN107832857A (en) A kind of low-voltage network system of smart city
CN103324795A (en) Direct current system reliability evaluation method taking station service power influence into account
CN109449930B (en) Power distribution network reliability assessment and repair time parameter modeling method, equipment and medium
CN105184657A (en) Power supply risk assessment method and system for power system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant