CN109165745A - A kind of overhaul of train-set cost information automatic management method and system - Google Patents
A kind of overhaul of train-set cost information automatic management method and system Download PDFInfo
- Publication number
- CN109165745A CN109165745A CN201810791965.5A CN201810791965A CN109165745A CN 109165745 A CN109165745 A CN 109165745A CN 201810791965 A CN201810791965 A CN 201810791965A CN 109165745 A CN109165745 A CN 109165745A
- Authority
- CN
- China
- Prior art keywords
- cost
- information
- vehicle group
- management
- vehicle
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000007726 management method Methods 0.000 title claims abstract description 237
- 230000008439 repair process Effects 0.000 claims abstract description 95
- 238000000034 method Methods 0.000 claims abstract description 67
- 239000000463 material Substances 0.000 claims description 84
- 238000012423 maintenance Methods 0.000 claims description 44
- 230000008569 process Effects 0.000 claims description 39
- 238000005553 drilling Methods 0.000 claims description 16
- 239000013070 direct material Substances 0.000 claims description 9
- 238000004590 computer program Methods 0.000 claims description 8
- 238000007689 inspection Methods 0.000 claims description 8
- 230000006854 communication Effects 0.000 claims description 6
- 238000004891 communication Methods 0.000 claims description 4
- 230000015556 catabolic process Effects 0.000 claims description 3
- 230000002123 temporal effect Effects 0.000 claims description 2
- 230000033772 system development Effects 0.000 abstract description 4
- 238000007619 statistical method Methods 0.000 description 15
- 238000004458 analytical method Methods 0.000 description 6
- 238000010586 diagram Methods 0.000 description 6
- 238000013179 statistical model Methods 0.000 description 5
- 230000001052 transient effect Effects 0.000 description 3
- 238000011161 development Methods 0.000 description 2
- 230000018109 developmental process Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 241001269238 Data Species 0.000 description 1
- 230000032683 aging Effects 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 238000012790 confirmation Methods 0.000 description 1
- 238000007728 cost analysis Methods 0.000 description 1
- 230000001419 dependent effect Effects 0.000 description 1
- 238000000151 deposition Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 230000006870 function Effects 0.000 description 1
- 230000002045 lasting effect Effects 0.000 description 1
- 238000007670 refining Methods 0.000 description 1
- 238000005070 sampling Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- 238000012795 verification Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q30/00—Commerce
- G06Q30/02—Marketing; Price estimation or determination; Fundraising
- G06Q30/0201—Market modelling; Market analysis; Collecting market data
- G06Q30/0206—Price or cost determination based on market factors
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/40—Business processes related to the transportation industry
Landscapes
- Business, Economics & Management (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Marketing (AREA)
- Human Resources & Organizations (AREA)
- Entrepreneurship & Innovation (AREA)
- Finance (AREA)
- Development Economics (AREA)
- Economics (AREA)
- Accounting & Taxation (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Tourism & Hospitality (AREA)
- Game Theory and Decision Science (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Data Mining & Analysis (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The embodiment of the present invention provides a kind of overhaul of train-set cost information automatic management method and system, this method comprises: sending inquiry request to EMU management information system, whether inquiry, which has the vehicle group of update to repair, is completed information according to preset polling cycle;The vehicle group that update is obtained if having, which is repaired, completes repairing in information and completes vehicle Groups List;By calling the outbound data query service of cost management related service system, the default cost statistic for completing each vehicle group in vehicle Groups List is repaired in acquisition;Then it is counted by preset overhaul of train-set cost statistics model, obtains the cost statistics information of each vehicle group.The embodiment of the present invention calls the data in cost management related service management system by automation, realizes the automatic accounting of the EMU bicycle cost of overhaul;Improve the automatization level and working efficiency of EMU cost information management;Meanwhile being developed based on existing operation system, reduce the cost of system development.
Description
Technical field
The present embodiments relate to automated information management technical fields, and in particular to a kind of overhaul of train-set cost information
Automatic management method and system.
Background technique
The characteristics of EMU is with its high speed, comfort, the first choice gone on a journey at most people.With the lasting fortune of EMU
Row, it may appear that aging, the damage of components;Meanwhile in order to prevent operation risk caused by components failure, also need periodically to dynamic
Vehicle group is overhauled.Therefore, after EMU puts into operation, the maintenance of EMU will be with the entire military service process of EMU.
Since the components that the car body of EMU is huge, is related to are various, maintenance business is considerably complicated;It repairs, change as pilot is advanced
Un-wheeling repair has even more aggravated the difficulty of overhaul of train-set cost information management.
EMU cost information management now is mainly by the way of manually counting, monthly from financial staff to each phase
It closes operation system and issues statistical demand, each operation system is by manually carrying out statistical correlation data, manually exporting form data, most
After be aggregated into financial staff, summarized by financial staff, calculated, generate EMU cost analysis report.
Therefore, existing EMU cost information management is mainly by the way of manually counting, information-based due to lacking
Management, is completely dependent on artificial statistics, leads to inefficiency and error rate is high.
Summary of the invention
To solve the problems, such as inefficiency caused by manually counting in the management of existing EMU cost information and error rate is high,
The embodiment of the present invention provides a kind of overhaul of train-set cost information automatic management method and system.
In a first aspect, the embodiment of the present invention provides a kind of overhaul of train-set cost information automatic management method, this method
It include: that inquiry request is sent to EMU management information system, whether inquiry has the vehicle group of update according to preset polling cycle
It repairs and completes information;If knowing that the vehicle group there are the update is repaired completes information, the vehicle group for obtaining the update, which is repaired, completes repairing in information
Complete vehicle Groups List;By calling the outbound data query service of cost management related service system, is repaired described in acquisition and complete vehicle group column
The default cost statistic of each vehicle group in table;According to the default cost statistic, examined by preset EMU
Accomplish this statistical model to be counted, obtains the cost statistics information of each vehicle group.
Second aspect, the embodiment of the present invention provide a kind of overhaul of train-set cost information automated management system, the system
Include: that vehicle group repairs and completes status inquiry module, be specifically used for: according to preset polling cycle, being sent out to EMU management information system
Inquiry request is sent, whether inquiry, which has the vehicle group of update to repair, is completed information;It repairs and completes vehicle Groups List acquisition module, be specifically used for: if knowing
It is repaired there are the vehicle group of the update and completes information, then the vehicle group for obtaining the update, which is repaired, completes repairing in information and complete vehicle Groups List;Cost
Statistical data obtains module, is specifically used for: the outbound data query service by calling cost management related service system obtains
It is described to repair the default cost statistic for completing each vehicle group in vehicle Groups List;Statistical module is specifically used for: according to described default
Cost statistic is counted by preset overhaul of train-set cost statistics model, obtains the cost of each vehicle group
Statistical information.
The third aspect, the embodiment of the present invention provide a kind of electronic equipment, including memory and processor, the processor and
The memory completes mutual communication by bus;The memory, which is stored with, to be referred to by the program that the processor executes
It enables, the processor calls described program instruction to be able to carry out following method: according to preset polling cycle, to EMU management
Information system sends inquiry request, and whether inquiry, which has the vehicle group of update to repair, is completed information;If knowing, the vehicle group there are the update is repaired
Complete information, then the vehicle group for obtaining the update, which is repaired, completes repairing in information and complete vehicle Groups List;By calling cost management related service
The outbound data query service of system repairs the default cost statistic for completing each vehicle group in vehicle Groups List described in acquisition;Root
It according to the default cost statistic, is counted, is obtained described each by preset overhaul of train-set cost statistics model
The cost statistics information of vehicle group.
Fourth aspect, the embodiment of the present invention provide a kind of computer readable storage medium, are stored thereon with computer program,
The computer program realizes following method when being executed by processor: according to preset polling cycle, to EMU agrment information system
System sends inquiry request, and whether inquiry, which has the vehicle group of update to repair, is completed information;If knowing that the vehicle group there are the update is repaired completes information,
The vehicle group for then obtaining the update, which is repaired, completes repairing in information and completes vehicle Groups List;By pair for calling cost management related service system
Outer data query service repairs the default cost statistic for completing each vehicle group in vehicle Groups List described in acquisition;According to described pre-
If cost statistic, counted by preset overhaul of train-set cost statistics model, obtain each vehicle group at
This statistical information.
The embodiment of the present invention calls the data in cost management related service management system by automation, carries out data set
At the automatic accounting of the EMU bicycle cost of overhaul may be implemented;The automatization level of EMU cost information management is improved,
It improves work efficiency;Simultaneously as data call is carried out based on existing cost management related service management system, to drop
The low cost of system development.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below
There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is the present invention
Some embodiments for those of ordinary skill in the art without creative efforts, can also basis
These attached drawings obtain other attached drawings.
Fig. 1 is overhaul of train-set cost information automatic management method flow diagram provided in an embodiment of the present invention;
Fig. 2 is overhaul of train-set cost information automated management system structural schematic diagram provided in an embodiment of the present invention;
Fig. 3 is the structural schematic diagram of electronic equipment provided in an embodiment of the present invention.
Specific embodiment
In order to make the object, technical scheme and advantages of the embodiment of the invention clearer, below in conjunction with the embodiment of the present invention
In attached drawing, the technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is
A part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, those of ordinary skill in the art
Every other embodiment obtained without creative efforts, shall fall within the protection scope of the present invention.
Fig. 1 is overhaul of train-set cost information automatic management method flow diagram provided in an embodiment of the present invention.Such as Fig. 1 institute
Show, which comprises
Step 101, according to preset polling cycle, send inquiry request to EMU management information system, inquiry is whether
There is the vehicle group of update to repair and completes information;
Overhaul of train-set cost information automated management system is according to preset polling cycle, to EMU agrment information system
System sends inquiry request, and whether inquiry, which has the vehicle group of update to repair, is completed information;Overhaul of train-set cost information automated management system
Inquiry request is sent to EMU management information system, whether inquiry, which has the vehicle group of update to repair, is completed information, can be dynamic by calling
The outbound data query service of vehicle group management information system is realized.
The polling cycle can be for per hour, such as can be in the overhaul of train-set cost information automated management system
Middle setting timer, per the outbound data query service for calling EMU management information system every other hour, to EMU management
Information system sends inquiry request, and whether inquiry, which has the vehicle group of update to repair, is completed information.
If step 102 knows that the vehicle group there are the update is repaired and completes information, the vehicle group for obtaining the update, which is repaired, completes information
In repair and complete vehicle Groups List;
The vehicle group of the update, which is repaired, completes information and refers to compared with last time query actions, and newly-increased vehicle group, which is repaired, completes information.If depositing
It is repaired in the vehicle group of the update and completes information, illustrate to have overhauled there are last time query actions and in the interval time of this query actions
At vehicle group.
If knowing that EMU management information system is repaired there are the vehicle group of the update according to query result completes information, obtain
The vehicle group of the update, which is repaired, completes repairing in information and completes vehicle Groups List;It is described repair complete vehicle Groups List can be repair complete vehicle group number column
Table.It is described repair to complete overhauled in the interval time that vehicle Groups List includes one or more last time query actions and this query actions
At vehicle group information.
Step 103, the outbound data query service by calling cost management related service system, repair described in acquisition and complete vehicle
The default cost statistic of each vehicle group in Groups List;
The cost management related service system refers to existing with cost management or the acquisition of cost information statistical data
Relevant system, depending on the division and cost information statistical method with specific reference to practical business system.For example, cost information is united
Meter necessarily includes the wage cost of maintenance worker, described if the paying out wages of the maintenance worker are recorded in financial system
Cost management related service system includes the financial system;If cost information statistics include material cost, if the material at
Originally it is stored in material Management System, then the cost management related service system includes described material Management System, etc..
The default cost statistic refers to data relevant to cost statistics.The vehicle group for obtaining the update, which is repaired, completes letter
After repairing in breath completes vehicle Groups List, by calling the outbound data query service of cost management related service system, to cost pipe
It manages related service system and sends inquiry request, can obtain respectively and described repair the default cost for completing each vehicle group in vehicle Groups List
Statistical data.It needs to dispose outbound data query service in each cost management related service system, so that EMU
The outbound data query service that cost of overhaul information automation management system passes through the corresponding cost management related service system of calling
Obtain default cost statistic accordingly.
Step 104, according to the default cost statistic, pass through preset overhaul of train-set cost statistics model and carry out
Statistics obtains the cost statistics information of each vehicle group.
For each vehicle group, according to the default cost statistic of this vehicle group, by preset overhaul of train-set at
This statistical model is counted respectively, obtains the cost statistics information of each vehicle group, and obtained cost statistics is believed
Breath is stored in the overhaul of train-set cost information automated management system.
The overhaul of train-set cost statistics model may include the cost of preset kind in overhaul of train-set, such as can wrap
Include cost of labor, material cost etc..It, can according to the default cost statistic and the overhaul of train-set cost statistics model
To obtain preset various types of cost information, and believed according to various types of available totle drilling costs of cost information
Breath.
The embodiment of the present invention calls the data in cost management related service management system by automation, carries out data set
At the automatic accounting of the EMU bicycle cost of overhaul may be implemented;The automatization level of EMU cost information management is improved,
It improves work efficiency;Simultaneously as data call is carried out based on existing cost management related service management system, to drop
The low cost of system development.
Further, based on the above embodiment, the outbound data query service includes WCF service.
The cost management related service system can be by disposing WCF (Windows Communication
Foundation) the mode serviced, disposes the outbound data query service.WCF has uniformity, interoperability, safety
And compatibility.
It should be understood that the cost management related service system can also dispose outbound data inquiry by other means
Service, such as disposes outbound data query service by way of disposing web service.
Each difference cost management related service system can be disposed to be looked into using different method deployment outbound datas
Ask service.Even if each cost management related service system disposes outbound data query service, institute by the way of different
Stating overhaul of train-set cost information automated management system can also be by calling corresponding cost management related service system to be disposed
Outbound data query service obtain the corresponding default cost statistic in each system.
On the basis of the above embodiments, the embodiment of the present invention is by using WCF service arrangement outbound data query service,
Development efficiency is improved, has ensured the safety of communication process.
Further, based on the above embodiment, the cost management related service system includes the EMU management letter
Breath system, logistic management system, material Management System, financial management system and contract management system.
According to the division of practical business system and cost information statistical method, the cost management related service system can
To include the EMU management information system, logistic management system, material Management System, financial management system and contract management
System.
Wherein, the EMU management information system can provide the relevant information of tool car group and the note of maintenance process
Information is recorded, the logistic management system can provide the material transport information in maintenance process, and the material Management System can be with
The pricing information of material is provided, the financial management system can provide wage information, and the contract management system can provide
The pricing information of the outer maintenance contract of committee.
Overhaul of train-set cost information automated management system is by calling EMU management information system, logistics management system
System, material Management System, the outbound data query service of financial management system and contract management system repair described in acquisition and complete vehicle group
The default cost statistic of each vehicle group in list;And then according to the default cost statistic, by preset dynamic
Vehicle group cost of overhaul statistical model is counted, and the cost statistics information of each vehicle group is obtained.
On the basis of the above embodiments, the embodiment of the present invention is by calling EMU management information system, logistics management
System, material Management System, the outbound data query service of financial management system and contract management system, obtain each vehicle group
Default cost statistic, ensure that the accuracy of cost statistics information.
Further, based on the above embodiment, described by calling the outbound data of cost management related service system to look into
Service is ask, the default cost statistic for completing each vehicle group in vehicle Groups List is repaired described in acquisition, specifically includes:
By calling the outbound data query service of the EMU management information system, is repaired described in acquisition and complete vehicle group
The vehicle model information of each vehicle group in list repairs journey information, worker's information, working hour information, station information, process information and interim
Committee's extreme term purpose quantity information;
When EMU feeding workshop starts maintenance, the EMU management information system generates record, and record inspection is moved
The vehicle group number of vehicle group, vehicle repair Cheng Jiqi and repair the time;Maintenance worker fingerprint login EMU management information system can open daily
Beginning operation, the daily station of each maintenance worker and process, which can be, to be pre-set, and maintenance worker's fingerprint logs in EMU
After management information system, then EMU management information system record vehicle group number, operator (maintenance worker), station, process and
The operation time started;Maintenance worker, which logs in EMU management information system, terminates operation, and EMU management information system records vehicle
Group number, station, process, operator and end-of-job time, and according to the operation time started of maintenance worker and operation at the end of
Between obtain maintenance worker in corresponding station, the working hour of process.
During overhaul of train-set, it is possible that the case where interim committee dispatches workers to do on-site repairs.When committee dispatches workers to do on-site repairs, the contract signed
It would generally indicate the project unit price that committee dispatches workers to do on-site repairs.And during actually committee dispatches workers to do on-site repairs, the quantity dispatched workers to do on-site repairs of entrusting and confirmation then usually exist
EMU management information system record.Therefore, interim committee's extreme term purpose quantity information can also be provided in EMU management information system.
Therefore, overhaul of train-set cost information automated management system is by calling the EMU management information system
The outbound data query service repairs described in acquisition and completes the vehicle model information of each vehicle group in vehicle Groups List, repairs journey information, time
Information, worker's information, working hour information, station information, process information and interim committee's extreme term purpose quantity information.Wherein, when passing through
Between described in information repair time and repairing and complete the time and can obtain the repair time.
By calling the outbound data query service of the logistic management system, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group receive the material of worker's information of material, the station information, the process information and actual consumption
Information and quantity information;
The logistic management system will record the worker's information for receiving material, accordingly when maintenance worker leads material
Station information, process information, and the material information and quantity information received;It is described when needing to return some materials after neck material
Logistic management system equally will record worker's information of store returned, corresponding station information, process information, and return
Material information and quantity information.
The logistic management system can provide each maintenance worker, each process, the practical materials information of each station,
The practical materials information refers to the material information and quantity information of institute's actual consumption.
Therefore, overhaul of train-set cost information automated management system is by calling the described right of the logistic management system
Outer data query service, it is available described to repair each vehicle group completed in vehicle Groups List and receive worker's information of material, institute
State station information, the process information and reality corresponding with worker's information, the station information, the process information
The material information and quantity information of border consumption.
By calling the outbound data query service of the material Management System, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group repair time in actual consumption material unit price;
The unit price of material Management System storage a variety of materials needed for maintenance.Therefore, overhaul of train-set cost is believed
Automated management system is ceased by the outbound data query service of the calling material Management System, is examined according to each vehicle group
The material of process institute actual consumption is repaired, available described repair actually disappears in the repair time for completing each vehicle group in vehicle Groups List
The unit price of the material of consumption.
By calling the outbound data query service of the financial management system, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group paying out wages information;
The financial management system is stored with paying out wages information, overhaul of train-set cost information automated management system root
It, can be by calling the outbound data of the financial management system to inquire clothes according to staff's situation in maintenance process
It is engaged in, repairs the paying out wages information for completing each vehicle group in vehicle Groups List described in acquisition.
By calling the outbound data query service of the contract management system, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group interim committee's extreme term purpose unit price and outer Project contract total value of entrusting in full vehicle group year;
Contract management system is stored with interim committee's extreme term purpose unit price and outer Project contract total value of entrusting in full vehicle group year.Face
When committee outer project refer to the needs according to service work, and project outside the committee of interim arrangements, the usually ability when there is maintenance requirement
It can generate;Outer project of entrusting in year refers to project outside conventional committee, and project is appointed in advance outside this committee, for example periodically carries out
The sampling observation etc. of each vehicle group, not premised on there is maintenance requirement.Outer project of entrusting in year is usually towards full vehicle group.
The external number that overhaul of train-set cost information automated management system passes through the calling contract management system
According to query service, the available interim committee's extreme term purpose unit price for repairing each vehicle group completed in vehicle Groups List and full vehicle group
The outer Project contract total value of year committee.
Overhaul of train-set cost information automated management system is according to above by EMU management information system, stream tube
The default cost statistic that reason system, material Management System, financial management system and contract management system obtain, by default
Overhaul of train-set cost statistics model counted, obtain the cost statistics information of each vehicle group.
Different from the Costing model of existing overhaul of train-set, used in the embodiment of the present invention is the side being fully automated
Method.In existing EMU cost information management, utilizable resource is limited, and it is larger to calculate result error;For example, cost structure
It can not be calculated, can only be shared equally according to the working hour of each mill count according to actual hours at maintenance worker's wage cost of item;It is examining
, can only be by the application material total value of goods and materials system as material cost in terms of repairing material, the material really claimed is not necessarily
It uses completely, the material retracted does not subtract;The direct outer cost of committee, which is subject to, entrusts what other unit provided, and whether no practical verification
The committee occurs to dispatch workers to do on-site repairs.
And the embodiment of the present invention can make full use of fining acquired in cost management related service system, comprehensive pre-
If cost statistic, realize effective management to cost information, cost can be accurate to each station, process, worker, solves
Certainly cost accounting is difficult to the problem of refining.
On the basis of the above embodiments, the embodiment of the present invention is by from EMU management information system, logistics management system
System, material Management System, financial management system and contract management system obtain default cost statistic comprehensively, fine, into
One step improves the accuracy of cost statistics information, and improves the degree of cost information fine-grained management.
Further, based on the above embodiment, the overhaul of train-set cost statistics model include direct cost and indirectly
Cost;The totle drilling cost of overhaul of train-set is the sum of the direct cost and the indirect cost.
The direct cost includes direct labor cost, direct material cost and the interim outer cost of committee;Wherein, described direct
Cost of labor refers to the wage cost of maintenance worker, and the direct material cost refers to the material cost of maintenance, outside the interim committee at
This refers to interim committee's extreme term purpose cost;
The direct labor cost refers to the wage cost of maintenance worker, can be calculated by following formula:
Wherein, CrFor the direct labor cost, ZmFor the bicycle total time to repair of worker m, SmFor the when equal work of worker m
Money, m are the label of maintenance worker, N1Represent the quantity of maintenance worker.
The direct material cost refers to the material cost of maintenance, can be calculated by following formula:
Wherein, CcFor the direct material cost, ElFor total dosage of material l, DlFor the unit price of material l, l is material
Label, N2Represent the classification total amount of material.
Cost refers to interim committee's extreme term purpose cost outside the interim committee, can be calculated by following formula:
Wherein, CwFor cost outside the interim committee, PnFor the quantity for the outer project n that temporarily entrusts, JnTemporarily to entrust outer project n's
Unit price, n are the label of material, N3Interim committee's extreme term purpose classification total amount.
The indirect cost includes indirect labour cost, entrust in year outer cost and depreciable cost;It is described for each vehicle group
Indirect labour cost, the year outer cost of committee and the depreciable cost are counted by preset algorithm of sharing equally;Wherein, described
Indirect labour cost refer to inspection and repair shop payment payroll in share wage cost, the year equally in addition to the direct labor cost
The outer cost of degree committee refers to that year committee extreme term purpose shares cost equally;What the depreciable cost referred to depreciation of fixed assets shares cost equally.
The indirect cost includes indirect labour cost, entrust in year outer cost and depreciable cost.
The indirect labour cost refer to inspection and repair shop payment payroll in share work equally in addition to the direct labor cost
Provide cost.Due to existing in maintenance process such as overhaul management person, and the service work of overhaul management person usually full vehicle group good at managing,
Therefore, cost caused by the disbursement of payrolls for overhaul management person belongs to indirect labour cost, need in each vehicle group into
Row is shared equally.
Outer cost of entrusting in the year refers to that year committee extreme term purpose shares cost equally;The outer project as previously mentioned, year entrusts
Usually for full vehicle group, therefore, by entrusting in year, the cost that outer project generates is also required to be shared equally in each vehicle group.
What the depreciable cost referred to depreciation of fixed assets shares cost equally.Since fixed assets (such as repair apparatus) are to need to examine
The vehicle group repaired be both needed to using, therefore, depreciable cost is also required to be shared equally in each vehicle group.
For each vehicle group, the indirect labour cost, the year outer cost of committee and the depreciable cost can be by pre-
If algorithm of sharing equally counted.An example for sharing algorithm equally is given below:
Firstly, according to different automobile types, repairing journey actual repair time and worker's number, the working hour for obtaining different automobile types, repairing journey
Table, as shown in table 1.
1 different automobile types of table, the working hour table for repairing journey
Again, the acquisition current year maintenance plan from EMU management information system, i.e. different automobile types, the year meter for repairing journey
Maintenance quantity table is drawn, as shown in table 2.
2 different automobile types of table, the annual plan maintenance quantity table for repairing journey
Level-one is repaired | Second level is repaired | Three-level is repaired | Level Four is repaired | Pyatyi is repaired | |
Vehicle 1 | S11 | S12 | S13 | S14 | S15 |
Vehicle 2 | S21 | S22 | S23 | S24 | S25 |
Vehicle 3 | S31 | S32 | S33 | S34 | S35 |
… |
Because it is that Pyatyi is repaired that highest, which repairs journey, on repairing journey at present, therefore, above by taking highest Pyatyi is repaired as an example.It specifically can root
Above-mentioned two table is obtained according to actual journey situation of repairing.
Then vehicle i, the ratio of sharing equally for repairing journey j can be obtained by following formula:
Wherein, Bi,jFor vehicle i, repair the ratio of sharing equally of journey j, Si,jFor vehicle i, repair journey j annual plan overhaul quantity,
Ni,jFor vehicle i, when repairing the practical check man of journey j, N4For the quantity of vehicle, N5For the quantity for repairing journey.
Therefore, share ratio equally by what is shared vehicle i that algorithm provides equally, repair journey j, by each vehicle group share equally ratio respectively with
Connect artificial totle drilling cost, the outer totle drilling cost of entrusting in year is multiplied with total depreciation, obtain the indirect labour cost of each vehicle group, the year
The degree outer cost of committee and the depreciable cost.
Wherein, the indirect labor totle drilling cost is the difference of payroll and maintenance worker's payroll, and the year committee is outer
Totle drilling cost is outer contract total value of entrusting in the year that contract management system provides, and the total depreciation is the fixed assets that goods and materials system provides
Produce the product of total value with the depreciation ratio manually set.
Since the default cost statistical data packet is included corresponding to the working hour information of worker, station and process, material information
Deng therefore, also cost statistics analysis can be carried out for specific worker, station or process.
On the basis of the above embodiments, the embodiment of the present invention is moved by direct cost with the indirect cost for sharing acquisition equally
Vehicle group single overhauls totle drilling cost, further improves the accuracy of cost statistics information.
Further, based on the above embodiment, the cost statistics information includes totle drilling cost statistical information, point vehicle cost
Statistical information, point repair journey cost statistics information, sub-station cost statistics information, operation break-down cost statistics information and divide material at
This statistical information;The method also includes: chart is analyzed according to the cost statistics acquisition of information cost statistics.
The cost statistics information includes the cost statistics information of different vehicle groups, and different vehicle group correspond to different vehicle with
Journey is repaired, and for the cost statistics information of each vehicle group, the cost statistics information including different station, different processes, and it is each
The cost statistics information of kind material.The default cost statistic may also include workshop information, as a result, the cost statistics letter
Breath may also include the cost statistics information in different workshops.
According to different requirements, can from vehicle, repair journey, workshop, station, material type and angularly realize various one-parameters
Statistical analysis and Multi-parameter Combined Tool statistical analysis, for example, can point vehicle, repair Cheng Tongji totle drilling cost, it is total that full vehicle group can be counted
In cost in the accounting and bicycle totle drilling cost of each cost structure item each cost structure item accounting etc..According to statistical analysis
As a result procurement cost statistical analysis charts.The statistical analysis charts can be the intuitive charts such as line chart, pie chart, bar chart
Form.
On the basis of the above embodiments, the embodiment of the present invention according to cost statistics acquisition of information cost statistics by analyzing
Chart, improves the intuitive of cost statistics information inspection, to be advantageously implemented the rationalization decision of cost management and control.
Fig. 2 is overhaul of train-set cost information automated management system structural schematic diagram provided in an embodiment of the present invention.Such as
Shown in Fig. 2, the system comprises Che Zuxiu to complete status inquiry module 10, repairs and completes vehicle Groups List acquisition module 20, cost statistics number
According to acquisition module 30 and statistical module 40, in which:
Che Zuxiu completes status inquiry module 10 and is specifically used for: according to preset polling cycle, to EMU agrment information system
System sends inquiry request, and whether inquiry, which has the vehicle group of update to repair, is completed information;
Che Zuxiu completes status inquiry module 10 according to preset polling cycle, sends and inquires to EMU management information system
Request, whether inquiry, which has the vehicle group of update to repair, is completed information;Che Zuxiu completes status inquiry module 10 to EMU management information system
Inquiry request is sent, whether inquiry, which has the vehicle group of update to repair, is completed information, can pass through pair of calling EMU management information system
Outer data query service is realized.
Repair complete vehicle Groups List obtain module 20 be specifically used for: if knowing that the vehicle group there are the update is repaired completes information, obtain
It takes the vehicle group of the update to repair to complete repairing in information and complete vehicle Groups List;
The vehicle group of the update, which is repaired, completes information and refers to compared with last time query actions, and newly-increased vehicle group, which is repaired, completes information.If root
Know that EMU management information system is repaired there are the vehicle group of the update according to query result and complete information, then obtains the vehicle of the update
Group, which is repaired, completes repairing in information and completes vehicle Groups List;Described repair completes vehicle Groups List and can be the vehicle group number list repaired and completed.
Cost statistic obtains module 30 and is specifically used for: the outbound data by calling cost management related service system
Query service repairs the default cost statistic for completing each vehicle group in vehicle Groups List described in acquisition;
The cost management related service system refers to existing with cost management or the acquisition of cost information statistical data
Relevant system, depending on the division and cost information statistical method with specific reference to practical business system.
The default cost statistic refers to data relevant to cost statistics.The vehicle group for obtaining the update, which is repaired, completes letter
After repairing in breath completes vehicle Groups List, cost statistic obtains module 30 by calling the external of cost management related service system
Data query service sends inquiry request to cost management related service system, can obtain described repair respectively and complete vehicle Groups List
In each vehicle group default cost statistic.It needs to dispose externally number in each cost management related service system
According to query service, so that overhaul of train-set cost information automated management system is by calling corresponding cost management related service system
The outbound data query service of system obtains default cost statistic accordingly.
Statistical module 40 is specifically used for: according to the default cost statistic, passing through preset overhaul of train-set cost
Statistical model is counted, and the cost statistics information of each vehicle group is obtained.
For each vehicle group, statistical module 40 is moved according to the default cost statistic of this vehicle group by preset
Vehicle group cost of overhaul statistical model is counted respectively, obtains the cost statistics information of each vehicle group, and will be obtained
Cost statistics information is stored in the overhaul of train-set cost information automated management system.
The embodiment of the present invention calls the data in cost management related service management system by automation, carries out data set
At the automatic accounting of the EMU bicycle cost of overhaul may be implemented;The automatization level of EMU cost information management is improved,
It improves work efficiency;Simultaneously as data call is carried out based on existing cost management related service management system, to drop
The low cost of system development.
Further, based on the above embodiment, the outbound data query service includes WCF service.
The cost management related service system can be disposed the outbound data and be looked by way of deployment WCF service
Ask service.WCF has uniformity, interoperability, safety and compatibility.Each difference cost management related service system
It can dispose using different method deployment outbound data query services.
On the basis of the above embodiments, the embodiment of the present invention is by using WCF service arrangement outbound data query service,
Development efficiency is improved, has ensured the safety of communication process.
Further, based on the above embodiment, the cost management related service system includes the EMU management letter
Breath system, logistic management system, material Management System, financial management system and contract management system.
According to the division of practical business system and cost information statistical method, the cost management related service system can
To include the EMU management information system, logistic management system, material Management System, financial management system and contract management
System.
Wherein, the EMU management information system can provide the relevant information of tool car group and the note of maintenance process
Information is recorded, the logistic management system can provide the material transport information in maintenance process, and the material Management System can be with
The pricing information of material is provided, the financial management system can provide wage information, and the contract management system can provide
The pricing information of the outer maintenance contract of committee.
On the basis of the above embodiments, the embodiment of the present invention is by calling EMU management information system, logistics management
System, material Management System, the outbound data query service of financial management system and contract management system, obtain each vehicle group
Default cost statistic, ensure that the accuracy of cost statistics information.
Further, based on the above embodiment, the cost statistic obtains module 30 and is specifically used for:
By calling the outbound data query service of the EMU management information system, is repaired described in acquisition and complete vehicle group
The vehicle model information of each vehicle group in list repairs journey information, temporal information, worker's information, working hour information, station information, process
Information and interim committee's extreme term purpose quantity information;
The EMU management information system can recorde the vehicle group number of inspection EMU, vehicle, repair journey, rise repair the time,
It repairs and completes time, operator (maintenance worker), station and process and operation time started, end-of-job time, extreme term of temporarily entrusting
Purpose quantity information etc..
Therefore, overhaul of train-set cost information automated management system is by calling the EMU management information system
The outbound data query service repairs described in acquisition and completes the vehicle model information of each vehicle group in vehicle Groups List, repairs journey information, time
Information, worker's information, working hour information, station information, process information and interim committee's extreme term purpose quantity information.
By calling the outbound data query service of the logistic management system, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group receive worker's information of material, the station information, the process information and with worker's information,
The material information and quantity information of the station information, the corresponding actual consumption of the process information;
The logistic management system can provide each maintenance worker, each process, the practical materials information of each station,
The practical materials information refers to the material information and quantity information of institute's actual consumption.
Therefore, overhaul of train-set cost information automated management system is by calling the described right of the logistic management system
Outer data query service, it is available described to repair each vehicle group completed in vehicle Groups List and receive worker's information of material, institute
State station information, the process information and reality corresponding with worker's information, the station information, the process information
The material information and quantity information of border consumption.
By calling the outbound data query service of the material Management System, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group repair time in actual consumption material unit price;
The unit price of material Management System storage a variety of materials needed for maintenance.Therefore, overhaul of train-set cost is believed
Automated management system is ceased by the outbound data query service of the calling material Management System, is examined according to each vehicle group
The material of process institute actual consumption is repaired, available described repair actually disappears in the repair time for completing each vehicle group in vehicle Groups List
The unit price of the material of consumption.
By calling the outbound data query service of the financial management system, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group paying out wages information;
The financial management system is stored with paying out wages information, overhaul of train-set cost information automated management system root
It, can be by calling the outbound data of the financial management system to inquire clothes according to staff's situation in maintenance process
It is engaged in, repairs the paying out wages information for completing each vehicle group in vehicle Groups List described in acquisition.
By calling the outbound data query service of the contract management system, repairs and complete in vehicle Groups List described in acquisition
Each vehicle group interim committee's extreme term purpose unit price and outer Project contract total value of entrusting in full vehicle group year.
Contract management system is stored with interim committee's extreme term purpose unit price and outer Project contract total value of entrusting in full vehicle group year.It is dynamic
Vehicle group cost of overhaul information automation management system passes through the outbound data query service for calling the contract management system,
The available interim committee's extreme term purpose unit price for repairing each vehicle group completed in vehicle Groups List and full vehicle group year committee extreme term
Mesh contract total value.
On the basis of the above embodiments, the embodiment of the present invention is by from EMU management information system, logistics management system
System, material Management System, financial management system and contract management system obtain default cost statistic comprehensively, fine, into
One step improves the accuracy of cost statistics information, and improves the degree of cost information fine-grained management.
Further, based on the above embodiment, the overhaul of train-set cost statistics model include direct cost and indirectly
Cost;The totle drilling cost of overhaul of train-set is the sum of the direct cost and the indirect cost.
The direct cost includes direct labor cost, direct material cost and the interim outer cost of committee;Wherein, described direct
Cost of labor refers to the wage cost of maintenance worker, and the direct material cost refers to the material cost of maintenance, outside the interim committee at
This refers to interim committee's extreme term purpose cost;Cost of labor, the direct material are connect described in can calculating by preset algorithm
Cost outside cost and the interim committee.
The indirect cost includes indirect labour cost, entrust in year outer cost and depreciable cost;It is described for each vehicle group
Indirect labour cost, the year outer cost of committee and the depreciable cost are counted by preset algorithm of sharing equally;Wherein, described
Indirect labour cost refer to inspection and repair shop payment payroll in share wage cost, the year equally in addition to the direct labor cost
The outer cost of degree committee refers to that year committee extreme term purpose shares cost equally;What the depreciable cost referred to depreciation of fixed assets shares cost equally.
The indirect labour cost, the year outer cost of committee and the depreciable cost are united by preset algorithm of sharing equally
Meter.Therefore, it by sharing the corresponding vehicle and the ratio of sharing equally for repairing journey that algorithm provides equally, entrusts respectively with indirect labor totle drilling cost, year
Outer totle drilling cost is multiplied with total depreciation, obtains the indirect labour cost, entrust in the year outer cost and the depreciable cost.
On the basis of the above embodiments, the embodiment of the present invention is moved by direct cost with the indirect cost for sharing acquisition equally
Vehicle group single overhauls totle drilling cost, further improves the accuracy of cost statistics information.
Further, based on the above embodiment, the cost statistics information includes totle drilling cost statistical information, point vehicle cost
Statistical information, point repair journey cost statistics information, sub-station cost statistics information, operation break-down cost statistics information and divide material at
This statistical information;The system also includes: graphic analyses module, the graphic analyses module are specifically used for being united according to the cost
It counts acquisition of information cost statistics and analyzes chart.
The cost statistics information includes the cost statistics information of different vehicle groups, and different vehicle group correspond to different vehicle with
Journey is repaired, and for the cost statistics information of each vehicle group, the cost statistics information including different station, different processes, and it is each
The cost statistics information of kind material.
The system also includes graphic analyses module, the graphic analyses module is specifically used for being believed according to the cost statistics
Cease procurement cost statistical analysis charts.The graphic analyses module according to different requirements, can from vehicle, repair journey, workshop, work
Various one-parameter statistical analysis and Multi-parameter Combined Tool statistical analysis are angularly realized in position, material type, according to the knot of statistical analysis
Fruit procurement cost statistical analysis charts.The statistical analysis charts can be the intuitive chart shape such as line chart, pie chart, bar chart
Formula.
On the basis of the above embodiments, the embodiment of the present invention according to cost statistics acquisition of information cost statistics by analyzing
Chart, improves the intuitive of cost statistics information inspection, to be advantageously implemented the rationalization decision of cost management and control.
System provided in an embodiment of the present invention is for the above method, and concrete function can refer to above method process, this
Place repeats no more.
Fig. 3 is the structural schematic diagram of electronic equipment provided in an embodiment of the present invention.As shown in figure 3, the electronic equipment packet
Include processor 301, memory 302 and bus 303.Wherein, the processor 301 and the memory 302 pass through the bus
303 complete mutual communication;The processor 301 is used to call the program instruction in the memory 302, above-mentioned to execute
Method provided by each method embodiment, for example, according to preset polling cycle, sent to EMU management information system
Inquiry request, whether inquiry, which has the vehicle group of update to repair, is completed information;If knowing that the vehicle group there are the update is repaired completes information, obtain
The vehicle group of the update, which is repaired, completes repairing in information and completes vehicle Groups List;By the outbound data for calling cost management related service system
Query service repairs the default cost statistic for completing each vehicle group in vehicle Groups List described in acquisition;According to the default cost
Statistical data is counted by preset overhaul of train-set cost statistics model, obtains the cost statistics of each vehicle group
Information.
The embodiment of the present invention discloses a kind of computer program product, and the computer program product is non-transient including being stored in
Computer program on computer readable storage medium, the computer program include program instruction, when described program instructs quilt
When computer executes, computer is able to carry out method provided by above-mentioned each method embodiment, for example, is looked into according to preset
The period is ask, sends inquiry request to EMU management information system, whether inquiry, which has the vehicle group of update to repair, is completed information;It is deposited if knowing
It is repaired in the vehicle group of the update and completes information, then the vehicle group for obtaining the update, which is repaired, completes repairing in information and complete vehicle Groups List;Pass through tune
With the outbound data query service of cost management related service system, the pre- of each vehicle group completed in vehicle Groups List is repaired described in acquisition
If cost statistic;According to the default cost statistic, carried out by preset overhaul of train-set cost statistics model
Statistics obtains the cost statistics information of each vehicle group.
The embodiment of the present invention provides a kind of non-transient computer readable storage medium, the non-transient computer readable storage
Medium storing computer instruction, the computer instruction make the computer execute side provided by above-mentioned each method embodiment
Method, for example, according to preset polling cycle, send inquiry request to EMU management information system, whether inquiry has more
New vehicle group, which is repaired, completes information;If knowing that the vehicle group there are the update is repaired completes information, the vehicle group for obtaining the update, which is repaired, completes letter
Repairing in breath completes vehicle Groups List;By calling the outbound data query service of cost management related service system, repaired described in acquisition
Complete the default cost statistic of each vehicle group in vehicle Groups List;According to the default cost statistic, by preset
Overhaul of train-set cost statistics model is counted, and the cost statistics information of each vehicle group is obtained.
Those of ordinary skill in the art will appreciate that: realize that all or part of the steps of above method embodiment can pass through
The relevant hardware of program instruction is completed, and program above-mentioned can be stored in a computer readable storage medium, the program
When being executed, step including the steps of the foregoing method embodiments is executed;And storage medium above-mentioned includes: ROM, RAM, magnetic disk or light
The various media that can store program code such as disk.
The embodiments such as electronic equipment described above are only schematical, wherein it is described as illustrated by the separation member
Unit may or may not be physically separated, and component shown as a unit may or may not be object
Manage unit, it can it is in one place, or may be distributed over multiple network units.It can select according to the actual needs
Some or all of the modules therein is selected to achieve the purpose of the solution of this embodiment.Those of ordinary skill in the art are not paying wound
In the case where the labour for the property made, it can understand and implement.
Through the above description of the embodiments, those skilled in the art can be understood that each embodiment can
It realizes by means of software and necessary general hardware platform, naturally it is also possible to pass through hardware.Based on this understanding, on
Stating technical solution, substantially the part that contributes to existing technology can be embodied in the form of software products in other words, should
Computer software product may be stored in a computer readable storage medium, such as ROM/RAM, magnetic disk, CD, including several fingers
It enables and using so that an electronic equipment (can be personal computer, server or the network equipment etc.) executes each embodiment
Or method described in certain parts of embodiment.
Finally, it should be noted that the above embodiments are merely illustrative of the technical solutions of the present invention, rather than its limitations;Although
Present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that: it still may be used
To modify the technical solutions described in the foregoing embodiments or equivalent replacement of some of the technical features;
And these are modified or replaceed, technical solution of various embodiments of the present invention that it does not separate the essence of the corresponding technical solution spirit and
Range.
Claims (10)
1. a kind of overhaul of train-set cost information automatic management method characterized by comprising
According to preset polling cycle, inquiry request is sent to EMU management information system, whether inquiry has the vehicle group of update
It repairs and completes information;
If knowing that the vehicle group there are the update is repaired completes information, the vehicle group for obtaining the update, which is repaired, completes repairing in information and completes vehicle group
List;
Repaired by calling the outbound data query service of cost management related service system, described in acquisition complete it is each in vehicle Groups List
The default cost statistic of a vehicle group;
It according to the default cost statistic, is counted by preset overhaul of train-set cost statistics model, obtains institute
State the cost statistics information of each vehicle group.
2. the method according to claim 1, wherein the outbound data query service includes WCF service.
3. the method according to claim 1, wherein the cost management related service system includes the motor-car
Group management information system, logistic management system, material Management System, financial management system and contract management system.
4. according to the method described in claim 3, it is characterized in that, pair by calling cost management related service system
Outer data query service is repaired the default cost statistic for completing each vehicle group in vehicle Groups List described in acquisition, is specifically included:
By calling the outbound data query service of the EMU management information system, is repaired described in acquisition and complete vehicle Groups List
In each vehicle group vehicle model information, repair journey information, temporal information, worker's information, working hour information, station information, process information
With interim committee's extreme term purpose quantity information;
By calling the outbound data query service of the logistic management system, repaired described in acquisition complete it is each in vehicle Groups List
A vehicle group receive worker's information of material, the station information, the process information and with worker's information, described
The material information and quantity information of station information, the corresponding actual consumption of the process information;
By calling the outbound data query service of the material Management System, repaired described in acquisition complete it is each in vehicle Groups List
The unit price of the material of actual consumption in the repair time of a vehicle group;
By calling the outbound data query service of the financial management system, repaired described in acquisition complete it is each in vehicle Groups List
The paying out wages information of a vehicle group;
By calling the outbound data query service of the contract management system, repaired described in acquisition complete it is each in vehicle Groups List
The outer Project contract total value of interim committee's extreme term purpose unit price and full vehicle group year committee of a vehicle group.
5. according to the method described in claim 4, it is characterized in that, the overhaul of train-set cost statistics model include directly at
Sheet and indirect cost;
The direct cost includes direct labor cost, direct material cost and the interim outer cost of committee;Wherein, the direct labor
Cost refers to the wage cost of maintenance worker, and the direct material cost refers to the material cost of maintenance, and cost refers to outside the interim committee
Interim committee's extreme term purpose cost;
The indirect cost includes indirect labour cost, entrust in year outer cost and depreciable cost;It is described indirect for each vehicle group
Cost of labor, the year outer cost of committee and the depreciable cost are counted by preset algorithm of sharing equally;Wherein, described indirect
Cost of labor, which refers in the payroll of inspection and repair shop payment, shares wage cost, the year committee equally in addition to the direct labor cost
Outer cost refers to that year committee extreme term purpose shares cost equally;What the depreciable cost referred to depreciation of fixed assets shares cost equally.
6. according to the method described in claim 5, it is characterized in that, the cost statistics information include totle drilling cost statistical information,
Point vehicle cost statistics information, point repair journey cost statistics information, sub-station cost statistics information, operation break-down cost statistics information with
And divide material cost statistical information;
The method also includes: chart is analyzed according to the cost statistics acquisition of information cost statistics.
7. a kind of overhaul of train-set cost information automated management system characterized by comprising
Che Zuxiu completes status inquiry module, is specifically used for: according to preset polling cycle, sending to EMU management information system
Inquiry request, whether inquiry, which has the vehicle group of update to repair, is completed information;
It repairs and completes vehicle Groups List acquisition module, be specifically used for: if knowing that the vehicle group there are the update is repaired completes information, described in acquisition
The vehicle group of update, which is repaired, completes repairing in information and completes vehicle Groups List;
Cost statistic obtains module, is specifically used for: by calling the outbound data of cost management related service system to inquire
It services, repairs the default cost statistic for completing each vehicle group in vehicle Groups List described in acquisition;
Statistical module is specifically used for: according to the default cost statistic, passing through preset overhaul of train-set cost statistics mould
Type is counted, and the cost statistics information of each vehicle group is obtained.
8. system according to claim 7, which is characterized in that the outbound data query service includes WCF service.
9. a kind of electronic equipment, which is characterized in that including memory and processor, the processor and the memory pass through always
Line completes mutual communication;The memory is stored with the program instruction that can be executed by the processor, the processor tune
The method as described in claim 1 to 6 is any is able to carry out with described program instruction.
10. a kind of computer readable storage medium, is stored thereon with computer program, which is characterized in that the computer program quilt
The method as described in claim 1 to 6 is any is realized when processor executes.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810791965.5A CN109165745A (en) | 2018-07-18 | 2018-07-18 | A kind of overhaul of train-set cost information automatic management method and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810791965.5A CN109165745A (en) | 2018-07-18 | 2018-07-18 | A kind of overhaul of train-set cost information automatic management method and system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109165745A true CN109165745A (en) | 2019-01-08 |
Family
ID=64897742
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810791965.5A Pending CN109165745A (en) | 2018-07-18 | 2018-07-18 | A kind of overhaul of train-set cost information automatic management method and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109165745A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111798040A (en) * | 2020-06-16 | 2020-10-20 | 天津远程华瑞工业技术有限公司 | Intelligent hybrid maintenance method, device and equipment for motor train unit and storage medium |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102142112A (en) * | 2010-02-03 | 2011-08-03 | 上海市电力公司 | Data processing method for equipment overhauling cost |
CN103632251A (en) * | 2013-12-05 | 2014-03-12 | 北京奇虎科技有限公司 | Method, device and system for monitoring logistic status information |
JP2016015062A (en) * | 2014-07-03 | 2016-01-28 | 三菱電機株式会社 | Energy cost calculation device |
CN106127601A (en) * | 2016-06-29 | 2016-11-16 | 山东钢铁股份有限公司 | A kind of Workshop Production Cost accounting method and system |
-
2018
- 2018-07-18 CN CN201810791965.5A patent/CN109165745A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102142112A (en) * | 2010-02-03 | 2011-08-03 | 上海市电力公司 | Data processing method for equipment overhauling cost |
CN103632251A (en) * | 2013-12-05 | 2014-03-12 | 北京奇虎科技有限公司 | Method, device and system for monitoring logistic status information |
JP2016015062A (en) * | 2014-07-03 | 2016-01-28 | 三菱電機株式会社 | Energy cost calculation device |
CN106127601A (en) * | 2016-06-29 | 2016-11-16 | 山东钢铁股份有限公司 | A kind of Workshop Production Cost accounting method and system |
Non-Patent Citations (2)
Title |
---|
李文东: "铁路车辆段 (厂)成本管理系统解决方案", 《铁路采购与物流》 * |
袁敏: "论作业成本法在铁路机务系统的运用", 《财务监督》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111798040A (en) * | 2020-06-16 | 2020-10-20 | 天津远程华瑞工业技术有限公司 | Intelligent hybrid maintenance method, device and equipment for motor train unit and storage medium |
CN111798040B (en) * | 2020-06-16 | 2024-04-16 | 天津远程华瑞工业技术有限公司 | Intelligent hybrid maintenance method, device and equipment for motor train unit and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20030018503A1 (en) | Computer-based system and method for monitoring the profitability of a manufacturing plant | |
Borucka | Three-state Markov model of using transport means | |
CN107392422A (en) | Evaluation of employee method and system | |
Siguenza-Guzman et al. | Using Time-Driven Activity-Based Costing to support library management decisions: A case study for lending and returning processes | |
US20040243510A1 (en) | Credit management system and method | |
CN115423289B (en) | Intelligent plate processing workshop data processing method and terminal | |
CN108765071A (en) | Automobile leasing management method and device | |
CN115953038A (en) | Intelligent management system for SaaS (software as a service) sites of oil and gas station | |
KR100425910B1 (en) | Enterprise Resource Planning Method and System for performing original cost control using quality control and productivity control | |
CN110032154A (en) | A kind of production control method and system of be pilot | |
CN109165745A (en) | A kind of overhaul of train-set cost information automatic management method and system | |
CN112749911A (en) | MES production and manufacturing method and system | |
Coelho et al. | Operational improvement of an industrial equipment rental system using discrete event simulation | |
CN114971582A (en) | Material demand tracking system based on supply chain management system | |
CN107742180A (en) | A kind of ships goods goods, materials and equipments cost day reflects method and system | |
CN107122865A (en) | Method, system and the terminal device estimated are counted by flow | |
Tin | AComparative ANALYSIS OF COST-VOLUME-PROFIT (CVP) ANALYSIS AND ACTIVITY-BASED COSTING (ABC) IN IMPROVING MANAGERIAL DECISION-MAKING | |
JP3918743B2 (en) | Cost profit management system, cost profit management method, cost profit management program | |
CN205091788U (en) | Office automation system towards commercial enterprise | |
CN117557395B (en) | Research and development cost management and control method, system, electronic equipment and storage medium | |
Hang | COMPLETING COST MANAGEMENT ACCOUNTING AT PETROLIMEX BAC THAI COMPANY | |
Bakula et al. | Application of Business Intelligence System in Company Restructuring Process: The Case of Croatia. | |
Salmon | Controlling with SAP: Practical guide | |
Reider | Cost reduction analysis: A benchmarking guide for treasury managers | |
CN113570436A (en) | Rental business management method, system and computer readable storage medium |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190108 |
|
RJ01 | Rejection of invention patent application after publication |