CN106127601A - A kind of Workshop Production Cost accounting method and system - Google Patents

A kind of Workshop Production Cost accounting method and system Download PDF

Info

Publication number
CN106127601A
CN106127601A CN201610491749.XA CN201610491749A CN106127601A CN 106127601 A CN106127601 A CN 106127601A CN 201610491749 A CN201610491749 A CN 201610491749A CN 106127601 A CN106127601 A CN 106127601A
Authority
CN
China
Prior art keywords
workshop
current
production cost
mentioned
time period
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610491749.XA
Other languages
Chinese (zh)
Inventor
周广生
李春雷
扈素红
黄亚飞
谭芹
白洪强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Software Ltd By Share Ltd
Original Assignee
Shandong Iron and Steel Group Co Ltd SISG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Iron and Steel Group Co Ltd SISG filed Critical Shandong Iron and Steel Group Co Ltd SISG
Priority to CN201610491749.XA priority Critical patent/CN106127601A/en
Publication of CN106127601A publication Critical patent/CN106127601A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/04Manufacturing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/30Computing systems specially adapted for manufacturing

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Primary Health Care (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Human Resources & Organizations (AREA)
  • Marketing (AREA)
  • Manufacturing & Machinery (AREA)
  • Health & Medical Sciences (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a kind of Workshop Production Cost accounting method and system.Described Workshop Production Cost accounting method includes: step A, gathers and stores current workshop each correlative consumption in current special time period respectively;Step B, each correlative based on above-mentioned collection consumption in above-mentioned current special time period, and the material price that each correlative of above-mentioned collection set in advance is corresponding in above-mentioned special time period, adjust current workshop production cost in above-mentioned current special time period respectively.This Workshop Production Cost accounting method also includes step C, based on the above-mentioned current workshop calculated production cost in each special time period, adds up the total cost of production of current workshop.This invention can improve accuracy and the convenience of Workshop Production cost accounting, and practicality is relatively strong, has bigger application value.

Description

A kind of Workshop Production Cost accounting method and system
Technical field
The present invention relates to Workshop Production cost accounting field, specifically a kind of Workshop Production Cost accounting method and system.
Background technology
For a long time, the accounting of iron and steel enterprise's production cost is limited only to production line or factory level.And traditional cost Accounting mode needs substantial amounts of artificial statistical data and financial data, and the accounting cycle causing production cost is long, and data are relatively For macroscopic view, the guidance to the lacking of property of production operation of workshop teams and groups, miss the good opportunity of many cost efficiency, be unfavorable for workshop Lean manages.In place of this is the deficiencies in the prior art.
It addition, Workshop Production cost is closely bound up with the cycle of operation of workshop level equipment, for a long time, workshop level equipment Cycle of operation relies on artificial statistics, causes statistical result to there is bigger error with practical operation situation, thus to a certain degree The upper service life affecting workshop appliance, and then affect the accuracy of Workshop Production cost accounting.This is to exist in prior art Another weak point.
Summary of the invention
The technical problem to be solved is, for the deficiencies in the prior art, it is provided that a kind of Workshop Production cost core Calculate method and system, for improving accuracy and the convenience of Workshop Production cost accounting.
For solving above-mentioned technical problem, the invention provides a kind of Workshop Production Cost accounting method, including:
Step A, gather and store current workshop each correlative consumption in current special time period respectively;
Step B, each correlative based on above-mentioned collection consumption in above-mentioned current special time period, and preset The material price corresponding in above-mentioned special time period of each correlative of above-mentioned collection, adjust current workshop respectively and exist Production cost in above-mentioned current special time period.
Wherein, this Workshop Production Cost accounting method also includes:
Step C, based on the above-mentioned current workshop calculated production cost in each special time period, statistics is current to be produced The total cost of production in workshop.
Wherein, this Workshop Production Cost accounting method also includes:
Step D, Real-time Collection each operating state signal producing equipment in storing current workshop;
Step E, based on each operating state signal gathered, add up the total duration of operation that above-mentioned each production equipment is current respectively t1;
Step F, by each operation total duration t1 producing equipment of above-mentioned collection, the most corresponding prestore corresponding raw The design life cycle length of product equipment compares, and according to comparative result, it is determined whether report to the police.
Wherein, this Workshop Production Cost accounting method also includes:
Overhaul of the equipments warning step is produced in step G, current workshop.
Additionally, for each production equipment in current workshop, within its current time between overhauls(TBO), described step G includes:
Step G1, Real-time Collection also store the operating state signal of this production equipment;
Step G2, operating state signal based on this production equipment gathered, add up the operation duration that this production equipment is current t2;
Step G3, maintenance week by the operation duration t2 of this production equipment of above-mentioned collection, with this production equipment set in advance Phase length compares, and reaches the maintenance week of its correspondence at the operation duration t2 of this production equipment that comparative result is above-mentioned collection During phase length, control to report to the police, and perform step G4;
Step G4, initialize above-mentioned operation duration t2=0, in order to proceed the maintenance early warning in next time between overhauls(TBO).
As preferably, this Workshop Production Cost accounting method also includes:
Step H, for revising the step of each correlative material price corresponding in each special time period.
Present invention also offers a kind of Workshop Production Cost Accounting System, including:
Signal gathering unit, for gathering respectively and storing each correlative of current workshop in current special time period Consumption;
Control unit, the signal gathering unit described in connection, each correlative based on above-mentioned collection above-mentioned current specific time Between consumption in section, and the material that each correlative of above-mentioned collection set in advance is corresponding in above-mentioned special time period Price, adjusts current workshop production cost in above-mentioned current special time period respectively;And calculate based on above-mentioned Current workshop production cost in each special time period, adds up the total cost of production of current workshop.
Wherein, described signal gathering unit, each production equipment in being additionally operable to Real-time Collection and storing current workshop Operating state signal;Described control unit, is additionally based upon each operating state signal gathered, and adds up above-mentioned each production respectively Operation total duration t3 that equipment is current;And by each total duration of operation producing equipment of above-mentioned collection, the most corresponding is pre- The corresponding design life cycle length producing equipment first stored compares, and according to comparative result, it is determined whether report Alert.
As preferably, this Workshop Production Cost Accounting System also includes:
Overhaul of the equipments prewarning unit, is connected with described control unit, for setting each production in current workshop Back-up does not carry out overhauling early warning, maintenance early warning method particularly includes:
Step s1, Real-time Collection also store the current operating state signal producing equipment;
Step s2, based on gathered deserve before the operating state signal of production equipment, add up the operation that this production equipment is current Duration t4;
Step s3, maintenance week by the operation duration t4 of this production equipment of above-mentioned collection, with this production equipment set in advance Phase length compares, and reaches the time between overhauls(TBO) of its correspondence at the operation duration t4 that relatively fruit is this production equipment of above-mentioned collection During length, control to report to the police, and perform step s4;
Step s4, initialize above-mentioned operation duration t4=0, in order to proceed the maintenance early warning in next time between overhauls(TBO).
As preferably, this Workshop Production Cost Accounting System also includes:
Amendment unit, is connected with described control unit, for revising the thing that each correlative is corresponding in each special time period Material price.
Compared with prior art, it is an advantage of the current invention that:
The production cost in workshop can be adjusted by the present invention, has broken iron and steel producting cost accounting for a long time and has been confined to raw Produce line or the limitation of factory level, be greatly reduced iron and steel producting cost accounting unit such that it is able to improve Workshop Production cost The accuracy adjusted and convenience, it is simple to these teams and groups operator adjust its production cost in responsible workshop, and be both easy to it Carrying out longitudinal comparison, also allow for it and carry out the lateral comparison between teams and groups and teams and groups, this can promote the management of management personnel further The manipulation level of level and operator, practicality is relatively strong, has bigger application value.
As can be seen here, the present invention compared with prior art, has prominent substantive distinguishing features and significantly progress, and it is implemented Beneficial effect be also apparent from.
Accompanying drawing explanation
Fig. 1 is the structured flowchart schematic diagram of of the present invention kind of Workshop Production Cost Accounting System.
Detailed description of the invention
For making technical scheme and advantage clearer, below in conjunction with the accompanying drawing of the present invention, to the present invention's Technical scheme is clearly and completely described.
A kind of Workshop Production Cost accounting method of the present invention, including:
Step A, gather and store current workshop each correlative consumption in current special time period respectively;
Step B, each correlative based on above-mentioned collection consumption in above-mentioned current special time period, and preset The material price corresponding in above-mentioned special time period of each correlative of above-mentioned collection, adjust current workshop respectively and exist Production cost in above-mentioned current special time period;
Step C, based on the above-mentioned current workshop calculated production cost in each special time period, statistics is current to be produced The total cost of production in workshop.
The present invention is for adjusting the production cost in single workshop, and this has broken iron and steel production cost core for a long time Calculate the limitation being confined to production line or factory level, be greatly reduced the Accounting unit of iron and steel production cost, to a certain extent Improve real-time and the accuracy of iron and steel workshop producting cost accounting.
Additionally, those skilled in the art can determine the correlative described in above-mentioned steps A according to the practical situation in workshop Kind.In the present embodiment, the correlative described in above-mentioned steps A includes water, electricity, wind and steam.
Additionally, practice have shown that, Workshop Production equipment performance in use, not only can affect the normal of Workshop Production Operating, the most also can affect the accuracy of Workshop Production cost accounting.To this end, this Workshop Production Cost accounting method Also include:
Step D, Real-time Collection each operating state signal producing equipment in storing current workshop;
Step E, based on each operating state signal gathered, add up the total duration of operation that above-mentioned each production equipment is current respectively t1;
Step F, by each operation total duration t1 producing equipment of above-mentioned collection, respectively to corresponding prestore corresponding The design life cycle length of production equipment compares, and according to comparative result, it is determined whether report to the police.
And in the present embodiment, for each equipment of current inter-vehicular, gather deserve before the fortune of production equipment When the total duration of row reaches the design life cycle length of its correspondence, control to report to the police, in order to workshop relevant staff can be timely Process.
Additionally, in the present embodiment, this Workshop Production Cost accounting method also includes step G: in current workshop Produce overhaul of the equipments warning step.And for each production equipment in current workshop, within its current time between overhauls(TBO), This described step G includes:
Step G1, Real-time Collection also store the operating state signal of this production equipment;
Step G2, operating state signal based on this production equipment gathered, add up the operation duration that this production equipment is current t2;
Step G3, maintenance week by the operation duration t2 of this production equipment of above-mentioned collection, with this production equipment set in advance Phase length compares, and reaches the time between overhauls(TBO) of its correspondence at the operation duration t2 that relatively fruit is this production equipment of above-mentioned collection During length, control to report to the police, and perform step G4;
Step G4, initialize above-mentioned operation duration t2=0, in order to proceed the maintenance early warning in next time between overhauls(TBO).
Additionally, as preferably, this Workshop Production Cost accounting method also includes step H: is used for revising each correlative and exists The step of material price corresponding in each special time period.This is easy to the valency of workshop relevant staff's time update correlative Lattice, are not only convenient for improving the accuracy of workshop costing, also add the motility that the present invention uses, more practical.
To sum up, the present invention can be to the cycle of operation of workshop appliance, including design cycle and the time between overhauls(TBO) of production equipment Carrying out corresponding early warning, this can increase service life and the safety of workshop appliance to a certain extent, and then can be in certain journey Reduce Workshop Production cost on degree, and improve the accuracy of Workshop Production cost accounting to a certain extent.
In the present embodiment, present invention also offers a kind of Workshop Production Cost Accounting System, including:
Signal gathering unit, for gathering respectively and storing each correlative of current workshop in current special time period Consumption;
Control unit, the signal gathering unit described in connection, each correlative based on above-mentioned collection above-mentioned current specific time Between consumption in section, and the material that each correlative of above-mentioned collection set in advance is corresponding in above-mentioned special time period Price, adjusts current workshop production cost in above-mentioned current special time period respectively;And calculate based on above-mentioned Current workshop production cost in each special time period, adds up the total cost of production of current workshop.
Similarly, this Workshop Production Cost Accounting System also is able to adjust the production cost in workshop, and it is broken Iron and steel producting cost accounting is confined to the limitation of production line or factory level for a long time, is greatly reduced iron and steel production cost Accounting unit, improves real-time and the accuracy of iron and steel workshop producting cost accounting to a certain extent, more practical.
Wherein, described signal gathering unit is each production equipment in being additionally operable to Real-time Collection and storing current workshop Operating state signal.Described control unit is additionally based upon each operating state signal gathered, and adds up above-mentioned each production respectively and sets Standby current operation total duration t3;And by each operation total duration t3 producing equipment of above-mentioned collection, the most corresponding is pre- The corresponding design life cycle length producing equipment first stored compares, and according to comparative result, it is determined whether report Alert.
This Workshop Production Cost Accounting System also includes overhaul of the equipments prewarning unit.This overhaul of the equipments prewarning unit is with described Control unit be connected, for each production equipment in current workshop respectively carry out overhaul early warning.This is necessarily Service life and the safety of workshop appliance can be increased in degree, and then Workshop Production cost can be reduced to a certain extent, and The accuracy of Workshop Production cost accounting can be improved to a certain extent.
Each production equipment in current workshop is carried out overhauling early warning by described overhaul of the equipments prewarning unit respectively Method be:
Step s1, Real-time Collection also store the current operating state signal producing equipment;
Step s2, based on gathered deserve before the operating state signal of production equipment, add up the operation that this production equipment is current Duration t4;
Step s3, maintenance week by the operation duration t4 of this production equipment of above-mentioned collection, with this production equipment set in advance Phase length compares, and reaches the time between overhauls(TBO) of its correspondence at the operation duration t4 that relatively fruit is this production equipment of above-mentioned collection During length, control to report to the police, and perform step s4;
Step s4, initialize above-mentioned operation duration t4=0, in order to proceed the maintenance early warning in next time between overhauls(TBO).
As preferably, this Workshop Production Cost Accounting System also includes revising unit.This amendment unit and described control Unit is connected, and for revising the material price that each correlative is corresponding in each special time period, thus improves the present invention and makes Motility.
To sum up, Workshop Production Cost accounting method of the present invention and system, can not only improve Workshop Production cost The accuracy adjusted and convenience, it is simple to these teams and groups operator adjust the production cost in the workshop being responsible for, and then are easy to it Carrying out longitudinal comparison, also allow for it and carry out the lateral comparison between teams and groups and teams and groups, this can promote the management of management personnel further The manipulation level of level and operator, is also convenient for realizing, using flexibly, and practicality is relatively strong, has bigger popularization and application valency Value.
Embodiment of above only in order to technical scheme to be described, is not intended to limit;Although with reference to aforementioned enforcement The present invention has been described in detail by mode, it will be understood by those within the art that: its still can to aforementioned respectively Technical scheme described in embodiment is modified, or wherein portion of techniques feature is carried out equivalent;And these are repaiied Change or replace, not making the essence of appropriate technical solution depart from the scope of the present invention each embodiment technical scheme.

Claims (10)

1. a Workshop Production Cost accounting method, it is characterised in that including:
Step A, gather and store current workshop each correlative consumption in current special time period respectively;
Step B, each correlative based on above-mentioned collection consumption in above-mentioned current special time period, and preset The material price corresponding in above-mentioned special time period of each correlative of above-mentioned collection, adjust current workshop respectively and exist Production cost in above-mentioned current special time period.
Workshop Production Cost accounting method the most according to claim 1, it is characterised in that this Workshop Production cost accounting side Method also includes:
Step C, based on the above-mentioned current workshop calculated production cost in each special time period, statistics is current to be produced The total cost of production in workshop.
Workshop Production Cost accounting method the most according to claim 1 and 2, it is characterised in that this Workshop Production cost core Calculation method also includes:
Step D, Real-time Collection each operating state signal producing equipment in storing current workshop;
Step E, based on each operating state signal gathered, add up the total duration of operation that above-mentioned each production equipment is current respectively t1;
Step F, by each operation total duration t1 producing equipment of above-mentioned collection, respectively to corresponding prestore corresponding The design life cycle length of production equipment compares, and according to comparative result, it is determined whether report to the police.
Workshop Production Cost accounting method the most according to claim 1 and 2, it is characterised in that this Workshop Production cost core Calculation method also includes:
Overhaul of the equipments warning step is produced in step G, current workshop.
Workshop Production Cost accounting method the most according to claim 4, it is characterised in that in current workshop Each produces equipment, and within its current time between overhauls(TBO), described step G includes:
Step G1, Real-time Collection also store the operating state signal of this production equipment;
Step G2, operating state signal based on this production equipment gathered, add up the operation duration that this production equipment is current t2;
Step G3, maintenance week by the operation duration t2 of this production equipment of above-mentioned collection, with this production equipment set in advance Phase length compares, and reaches the time between overhauls(TBO) of its correspondence at the operation duration t2 that relatively fruit is this production equipment of above-mentioned collection During length, control to report to the police, and perform step G4;
Step G4, initialize above-mentioned operation duration t2=0, in order to proceed the maintenance early warning in next time between overhauls(TBO).
Workshop Production Cost accounting method the most according to claim 1 and 2, it is characterised in that this Workshop Production cost core Calculation method also includes:
Step H, for revising the step of each correlative material price corresponding in each special time period.
7. a Workshop Production Cost Accounting System, it is characterised in that including:
Signal gathering unit, for gathering respectively and storing each correlative of current workshop in current special time period Consumption;
Control unit, the signal gathering unit described in connection, each correlative based on above-mentioned collection above-mentioned current specific time Between consumption in section, and the material that each correlative of above-mentioned collection set in advance is corresponding in above-mentioned special time period Price, adjusts current workshop production cost in above-mentioned current special time period respectively;And calculate based on above-mentioned Current workshop production cost in each special time period, adds up the total cost of production of current workshop.
Workshop Production Cost Accounting System the most according to claim 7, it is characterised in that
Described signal gathering unit: each running status producing equipment in being additionally operable to Real-time Collection and storing current workshop Signal;
Described control unit: be additionally based upon each operating state signal gathered, adds up above-mentioned each production equipment current respectively Run total duration t3;And by each total duration of operation producing equipment of above-mentioned collection, the most corresponding phase prestored The design life cycle length that should produce equipment compares, and according to comparative result, it is determined whether report to the police.
9. according to the Workshop Production Cost Accounting System described in claim 7 or 8, it is characterised in that this Workshop Production cost core Calculation system also includes:
Overhaul of the equipments prewarning unit, is connected with described control unit, for setting each production in current workshop Back-up does not carry out overhauling early warning, maintenance early warning method particularly includes:
Step s1, Real-time Collection also store the current operating state signal producing equipment;
Step s2, based on gathered deserve before the operating state signal of production equipment, add up the operation that this production equipment is current Duration t4;
Step s3, maintenance week by the operation duration t4 of this production equipment of above-mentioned collection, with this production equipment set in advance Phase length compares, and reaches the maintenance week of its correspondence at the operation duration t4 of this production equipment that comparative result is above-mentioned collection During phase length, control to report to the police, and perform step s4;
Step s4, initialize above-mentioned operation duration t4=0, in order to proceed the maintenance early warning in next time between overhauls(TBO).
10. according to the Workshop Production Cost Accounting System described in claim 7 or 8, it is characterised in that this Workshop Production cost core Calculation system also includes:
Amendment unit, is connected with described control unit, for revising the thing that each correlative is corresponding in each special time period Material price.
CN201610491749.XA 2016-06-29 2016-06-29 A kind of Workshop Production Cost accounting method and system Pending CN106127601A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610491749.XA CN106127601A (en) 2016-06-29 2016-06-29 A kind of Workshop Production Cost accounting method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610491749.XA CN106127601A (en) 2016-06-29 2016-06-29 A kind of Workshop Production Cost accounting method and system

Publications (1)

Publication Number Publication Date
CN106127601A true CN106127601A (en) 2016-11-16

Family

ID=57284527

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610491749.XA Pending CN106127601A (en) 2016-06-29 2016-06-29 A kind of Workshop Production Cost accounting method and system

Country Status (1)

Country Link
CN (1) CN106127601A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109165745A (en) * 2018-07-18 2019-01-08 中国铁道科学研究院集团有限公司电子计算技术研究所 A kind of overhaul of train-set cost information automatic management method and system
CN109523299A (en) * 2018-10-17 2019-03-26 海闻科技有限公司 A kind of automatic Cost accounting method and system
CN110490530A (en) * 2019-08-31 2019-11-22 东莞市众金家具有限公司 A kind of Furniture manufacture production line operation cost intelligence accounting monitoring method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101738974A (en) * 2009-12-17 2010-06-16 四川中鼎自动控制有限公司 System for monitoring auxiliary engine state
CN103645720A (en) * 2013-12-17 2014-03-19 上海电机学院 Assembly line production cost real-time monitoring device and assembly line production cost diagnostic method
CN205091612U (en) * 2015-11-12 2016-03-16 内蒙古伊利实业集团股份有限公司 Production facility operating data's automatic collection system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101738974A (en) * 2009-12-17 2010-06-16 四川中鼎自动控制有限公司 System for monitoring auxiliary engine state
CN103645720A (en) * 2013-12-17 2014-03-19 上海电机学院 Assembly line production cost real-time monitoring device and assembly line production cost diagnostic method
CN205091612U (en) * 2015-11-12 2016-03-16 内蒙古伊利实业集团股份有限公司 Production facility operating data's automatic collection system

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109165745A (en) * 2018-07-18 2019-01-08 中国铁道科学研究院集团有限公司电子计算技术研究所 A kind of overhaul of train-set cost information automatic management method and system
CN109523299A (en) * 2018-10-17 2019-03-26 海闻科技有限公司 A kind of automatic Cost accounting method and system
CN110490530A (en) * 2019-08-31 2019-11-22 东莞市众金家具有限公司 A kind of Furniture manufacture production line operation cost intelligence accounting monitoring method

Similar Documents

Publication Publication Date Title
CN109299517B (en) Reliability-based preventive maintenance optimization method for multiple parts of metro vehicle
CN106127601A (en) A kind of Workshop Production Cost accounting method and system
CN206363377U (en) A kind of engineering progress management system
CN103500425B (en) Hydropower Unit running status Intelligent Evaluation method
EP3167528A1 (en) System and method for determining the suitability of a plurality of electrical producers and consumers which are operated in a network as a virtual power plant for providing control power
CN105932690A (en) Distribution network operation optimization method integrating reactive power optimization and network reconstruction
CN106786528A (en) It is a kind of based on the Economical Operation of Main Transformer in Substation control method of D5000 systems and application
CN107196320B (en) A kind of steel mill's load management method based on timing optimization
CN109067002A (en) A kind of distribution line monitoring system and its working method based on Cloud Server
CN206085581U (en) Injection molding machine machine oil cooling temperature regulating device
CN109636001B (en) Method, system and computer readable medium for adjusting pH value of desulfurization slurry supply system based on big data
CN104156785B (en) A kind of generation schedule optimization method for considering fired power generating unit start and stop mill
CN111049269A (en) Power dispatching remote monitering system
CN203972191U (en) A kind of spraying line without beam material hanging device
CN116005756A (en) Distributed water supply system applied to rural areas
CN104298876A (en) Partition recovery method for fault of large-scale power distribution network
CN206041460U (en) GDF 5 computer high pressure excitation control ware
CN104361401B (en) A kind of step-by-step optimization method of real-time generation schedule closed-loop control
CN107767044A (en) A kind of evaluation method for weighing power network line loss
CN209603070U (en) A kind of landscape type arcading trash rack
CN104299055B (en) It is a kind of to suppress the generation schedule optimization method that unit is reversely adjusted in power plant
CN208445951U (en) Unilateral ridger
CN105676830B (en) The tracking of process data in circulation producing line
CN109459988B (en) Desulfurization device dehydration system optimization control method and system based on big data and computer readable medium
CN204869209U (en) Gypsum board panel turnover mechanism

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20171120

Address after: 250100 Shandong city of Ji'nan province high tech Zone Shun Road No. 2000 Shun Tai Plaza No. 4

Applicant after: Software Limited by Share Ltd

Address before: Industrial Road Licheng District, Ji'nan city of Shandong Province, No. 21 250101

Applicant before: Shandong Iron & Steel Group Co., Ltd.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20161116