CN109163144A - Submarine pipeline terminates the repositioning method of submarine pipeline terminal when being laid with - Google Patents

Submarine pipeline terminates the repositioning method of submarine pipeline terminal when being laid with Download PDF

Info

Publication number
CN109163144A
CN109163144A CN201811242094.8A CN201811242094A CN109163144A CN 109163144 A CN109163144 A CN 109163144A CN 201811242094 A CN201811242094 A CN 201811242094A CN 109163144 A CN109163144 A CN 109163144A
Authority
CN
China
Prior art keywords
submarine pipeline
pipe laying
laying barge
terminal
pipeline
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811242094.8A
Other languages
Chinese (zh)
Other versions
CN109163144B (en
Inventor
梁超
王圣强
许南
曹德明
陶付文
贺辰
满新宝
杜永军
甘惠良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Offshore Oil Engineering Co Ltd
Original Assignee
Offshore Oil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Offshore Oil Engineering Co Ltd filed Critical Offshore Oil Engineering Co Ltd
Priority to CN201811242094.8A priority Critical patent/CN109163144B/en
Publication of CN109163144A publication Critical patent/CN109163144A/en
Application granted granted Critical
Publication of CN109163144B publication Critical patent/CN109163144B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/16Laying or reclaiming pipes on or under water on the bottom
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/20Accessories therefor, e.g. floats, weights
    • F16L1/202Accessories therefor, e.g. floats, weights fixed on or to vessels
    • F16L1/205Pipe-laying ships
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/20Accessories therefor, e.g. floats, weights
    • F16L1/23Pipe tensioning apparatus
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/12Laying or reclaiming pipes on or under water
    • F16L1/20Accessories therefor, e.g. floats, weights
    • F16L1/235Apparatus for controlling the pipe during laying

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Laying Of Electric Cables Or Lines Outside (AREA)
  • Electric Cable Installation (AREA)

Abstract

A kind of submarine pipeline terminates the repositioning method of submarine pipeline terminal when being laid with, using following construction procedure: one: transverse shifting pipe laying barge makes pipe laying barge deviate the design routing of submarine pipeline;Two: pipe laying barge moves forward;And submarine pipeline is made to keep the tension set;Three: continuing to move along pipe laying barge, synchronous release wirerope;Four: after pipe laying barge passes through offshore platform, stop mobile pipe laying barge, make submarine pipeline be in seabed the design of mud point route;Five: pipe laying barge is continued to move to, until the terminal of submarine pipeline is in the top of design routing;Six: the tension on release submarine pipeline is until submarine pipeline completely attaches to sea bed;Seven: removing the connection of wirerope and submarine pipeline terminal, and wirerope is recycled on pipe laying barge.The present invention not only solves the problem of pipe laying barge short distance is close to risk of collision caused by offshore platform;Moreover, solving the difficulty and risk problem of cloth anchor;Enormously simplifying makes work progress, improves construction efficiency.

Description

Submarine pipeline terminates the repositioning method of submarine pipeline terminal when being laid with
Technical field
The reset side of submarine pipeline terminal when terminating laying the present invention relates to submarine pipeline more particularly to a kind of submarine pipeline Method.Belong to ocean engineering field.
Background technique
When submarine pipeline is terminated and is laid with, need to be connect with wirerope with submarine pipeline terminal, by wirerope to seabed Pipeline applies tension, while tension on maintaining submarine pipeline, moves forward pipe laying barge, submarine pipeline is made slowly to be placed on sea In the design routing of bed.Then, the connection of wirerope and submarine pipeline terminal then in seabed is released, and recycles wirerope to pipe laying On ship.But in this operating process, if submarine pipeline terminal is too close to offshore platform or other structures object, it is Pipe laying barge is avoided to collide with offshore platform or offshore structures, pipe laying barge can deviate the design road of undersea pipe-laying Line avoids offshore platform or offshore structures with this.Therefore, lead to that submarine pipeline terminal is made finally to deviate design routing.
In order to make the submarine pipeline terminal of offset restore to design to route, pipe laying barge can be generally moved close to submarine pipeline end End, and one group of easy loop wheel machine mechanism is installed along ship side on pipe laying barge, and connect loop wheel machine with submarine pipeline by rigging Get up, then, the pipeline section at submarine pipeline terminal hung into sea bed, simultaneously, it is ensured that submarine pipeline mud point be in design road By upper, later, mobile pipe laying barge makes the pipeline section at submarine pipeline terminal be in design routing top, and by submarine pipeline terminal The pipeline section at place is placed in sea bed design routing, then, releases the connection of rigging, and recycle on rigging to pipe laying barge.But by Pipe laying barge is set to be in offshore platform or other structures object near its circumference, and pipe laying barge and offshore platform for a long time in the above method Or the safe distance wretched insufficiency between offshore structures, once there are the feelings such as instantaneous maximum wind weather or windlass failure Condition, it will there are great risk of collision, bring great security risk for offshore construction.And since pipe laying barge is anchor mooring, Frequent cloth anchor operation around platform at sea or offshore structures is needed, to smoothly complete offshore construction;In addition, due to Can there are a large amount of pipeline, optical cable and seafloor structure etc. on sea bed around offshore platform or offshore structures, for paving The anchor hawser laying of pipe ship brings greatly difficult and challenge.Meanwhile additionally increasing by one group of loop wheel machine mechanism on the ship side of pipe laying barge, The reset operation of final submarine pipeline terminal is completed with loop wheel machine mechanism, and increases cost input, also, work progress is excessively It is cumbersome.
Summary of the invention
It is a primary object of the present invention to overcome disadvantages mentioned above of the existing technology, and provide a kind of submarine pipeline termination The repositioning method of submarine pipeline terminal when laying can not only make pipe laying barge closely close to offshore platform or offshore structure The time of object greatly shortens, and solves the problems, such as to cause risk of collision due to special circumstances;Moreover, marine when reducing construction The frequency of cloth anchor solves the difficulty and risk problem of cloth anchor;Meanwhile enormously simplifying and make work progress, improve construction effect Rate.
The purpose of the present invention is implemented by the following technical solutions:
A kind of submarine pipeline terminates the repositioning method of submarine pipeline terminal when being laid with, it is characterised in that: uses following construction Step:
Step 1: making pipe laying barge deviate the design routing of submarine pipeline, to avoid using anchor hawser transverse shifting pipe laying barge Offshore platform;
Step 2: pipe laying barge is moved forward with anchor hawser after pipe laying barge avoids offshore platform, meanwhile, on pipe laying barge, use The connection of the terminal of wirerope and submarine pipeline, and so that submarine pipeline is kept the tension set by wirerope;
Step 3: continuing to move along pipe laying barge with anchor hawser, and while maintaining the tension on submarine pipeline, synchronizes and release Put wirerope;
Step 4: stopping mobile pipe laying barge, and increase seabed by wirerope after pipe laying barge passes through offshore platform completely Tension on pipeline, until make submarine pipeline mud point be in seabed design route on;
Step 5: continue to keep the tension on submarine pipeline, meanwhile, it is slowly displaced sideways pipe laying barge using anchor hawser, until The terminal pipeline section of submarine pipeline is completely in the top of design routing;
Step 6: the tension on slow release submarine pipeline, until the terminal pipeline section of submarine pipeline completely attaches to sea bed, and In design routing;
Step 7: removing the connection of wirerope and submarine pipeline terminal, and wirerope is recycled on pipe laying barge.
The submarine pipeline mud point need to be always positioned at design routing on.
Evaded distance of the pipe laying barge when avoiding offshore platform or offshore structures, need to be maintained at minimum value.
Beneficial effects of the present invention: the present invention due to the adoption of the above technical scheme, can not only make pipe laying barge closely Time close to offshore platform or offshore structures greatly shortens, and solves due to special circumstances and causes asking for risk of collision Topic;Moreover, reducing the frequency of cloth anchor in sea when construction, solve the difficulty and risk problem of cloth anchor;Meanwhile it enormously simplifying Make work progress, improves construction efficiency.
Detailed description of the invention
Fig. 1 is that submarine pipeline of the present invention terminates the schematic top plan view being laid with.
Fig. 2 is that pipe laying barge of the present invention avoids offshore platform schematic diagram.
Fig. 3 is the attached view schematic diagram of submarine pipeline terminal resets of the present invention.
Fig. 4 is the schematic side view of submarine pipeline terminal resets of the present invention.
Major Symbol explanation in figure:
1. offshore platform;2. pipe laying barge;3. submarine pipeline;4. anchor hawser;5. design routing;6. wirerope;7. mud point.
Specific embodiment
As shown in Fig. 1-Fig. 4, the present invention uses following construction procedure:
Step 1: making pipe laying barge 2 deviate the design routing 5 of submarine pipeline 3 using 4 transverse shifting pipe laying barge 2 of anchor hawser, using To avoid offshore platform 1;
Step 2: pipe laying barge 2 is moved forward with anchor hawser 4 after pipe laying barge 2 avoids offshore platform 1, meanwhile, in pipe laying barge 2 On, it is connect with wirerope 6 with the terminal of submarine pipeline 3, and so that submarine pipeline 3 is kept the tension set by wirerope 6;
Step 3: continuing to move along pipe laying barge 2 with anchor hawser 4, and while maintaining the tension on submarine pipeline 3, together Step release wirerope 6;
Step 4: stopping mobile pipe laying barge 2, and increase by wirerope 6 after pipe laying barge 2 passes through offshore platform 1 completely Tension on submarine pipeline 3, until make submarine pipeline 3 mud point 7 be in seabed design route 5 on;
Step 5: continue to keep the tension on submarine pipeline 3, meanwhile, it is slowly displaced sideways pipe laying barge 2 using anchor hawser 4, directly The top of design routing 5 is completely in the terminal pipeline section of submarine pipeline 3;
Step 6: the tension on slow release submarine pipeline 3, until the terminal pipeline section of submarine pipeline 3 completely attaches to sea bed, And it is located in design routing 5;
Step 7: removing the connection of wirerope 6 and 3 terminal of submarine pipeline, and wirerope 6 is recycled on pipe laying barge 2.
Above-mentioned submarine pipeline mud point need to be always positioned at design routing on.
Evaded distance of the above-mentioned pipe laying barge when avoiding offshore platform or offshore structures need to be maintained at minimum value.
Above-mentioned offshore platform;Pipe laying barge;Submarine pipeline;Anchor hawser;Wirerope is the prior art, and the content not being illustrated is The prior art, therefore no longer repeated.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, it is all It is any simple modification, equivalent change and modification to the above embodiments according to the technical essence of the invention, still falls within In the range of technical solution of the present invention.

Claims (3)

1. the repositioning method that a kind of submarine pipeline terminates submarine pipeline terminal when being laid with, it is characterised in that: walked using following construction It is rapid:
Step 1: making pipe laying barge deviate the design routing of submarine pipeline, to avoid sea using anchor hawser transverse shifting pipe laying barge Platform;
Step 2: pipe laying barge is moved forward with anchor hawser after pipe laying barge avoids offshore platform, meanwhile, on pipe laying barge, use steel wire Rope is connect with the terminal of submarine pipeline, and so that submarine pipeline is kept the tension set by wirerope;
Step 3: pipe laying barge is continued to move along with anchor hawser, and while maintaining the tension on submarine pipeline, synchronous release steel Cord;
Step 4: stopping mobile pipe laying barge, and increase submarine pipeline by wirerope after pipe laying barge passes through offshore platform completely On tension, until make submarine pipeline mud point be in seabed design route on;
Step 5: continue to keep the tension on submarine pipeline, meanwhile, it is slowly displaced sideways pipe laying barge using anchor hawser, until seabed The terminal pipeline section of pipeline is completely in the top of design routing;
Step 6: the tension on slow release submarine pipeline, until the terminal pipeline section of submarine pipeline completely attaches to sea bed, and is located at In design routing;
Step 7: removing the connection of wirerope and submarine pipeline terminal, and wirerope is recycled on pipe laying barge.
2. the repositioning method that submarine pipeline according to claim 1 terminates submarine pipeline terminal when being laid with, it is characterised in that: The submarine pipeline mud point need to be always positioned at design routing on.
3. submerged pipeline according to claim 1 terminates sea tube terminal repositioning method when being laid with, it is characterised in that: the paving Evaded distance of the pipe ship when avoiding offshore platform or offshore structures, need to be maintained at minimum value.
CN201811242094.8A 2018-10-24 2018-10-24 Method for resetting submarine pipeline terminal when submarine pipeline stops laying Active CN109163144B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811242094.8A CN109163144B (en) 2018-10-24 2018-10-24 Method for resetting submarine pipeline terminal when submarine pipeline stops laying

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811242094.8A CN109163144B (en) 2018-10-24 2018-10-24 Method for resetting submarine pipeline terminal when submarine pipeline stops laying

Publications (2)

Publication Number Publication Date
CN109163144A true CN109163144A (en) 2019-01-08
CN109163144B CN109163144B (en) 2020-05-22

Family

ID=64878960

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811242094.8A Active CN109163144B (en) 2018-10-24 2018-10-24 Method for resetting submarine pipeline terminal when submarine pipeline stops laying

Country Status (1)

Country Link
CN (1) CN109163144B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113700938A (en) * 2021-08-25 2021-11-26 哈尔滨工程大学 Mud contact point monitoring device and monitoring method in submarine pipeline laying process

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090118466A (en) * 2008-05-14 2009-11-18 현대중공업 주식회사 Installation method of the pipelines using laying barge with sub-sea anchor block
CN102454828A (en) * 2010-10-29 2012-05-16 中国海洋石油总公司 Pipeline recycling and discarding technology in deepwater S-shaped submarine pipeline laying process
GB2500677A (en) * 2012-03-29 2013-10-02 Technip France Pipeline and method of laying a pipeline
CN104613234A (en) * 2015-01-15 2015-05-13 中国海洋石油总公司 Recovery method of abandoned deepwater pipeline
CN105605314A (en) * 2016-02-23 2016-05-25 中国海洋石油总公司 S-shaped laying method of double-layer submarine pipelines

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090118466A (en) * 2008-05-14 2009-11-18 현대중공업 주식회사 Installation method of the pipelines using laying barge with sub-sea anchor block
CN102454828A (en) * 2010-10-29 2012-05-16 中国海洋石油总公司 Pipeline recycling and discarding technology in deepwater S-shaped submarine pipeline laying process
GB2500677A (en) * 2012-03-29 2013-10-02 Technip France Pipeline and method of laying a pipeline
CN104613234A (en) * 2015-01-15 2015-05-13 中国海洋石油总公司 Recovery method of abandoned deepwater pipeline
CN105605314A (en) * 2016-02-23 2016-05-25 中国海洋石油总公司 S-shaped laying method of double-layer submarine pipelines

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113700938A (en) * 2021-08-25 2021-11-26 哈尔滨工程大学 Mud contact point monitoring device and monitoring method in submarine pipeline laying process
CN113700938B (en) * 2021-08-25 2022-04-01 哈尔滨工程大学 Mud contact point monitoring device and monitoring method in submarine pipeline laying process

Also Published As

Publication number Publication date
CN109163144B (en) 2020-05-22

Similar Documents

Publication Publication Date Title
CN101280862B (en) Seabed PE pipe rim spreading and imbedding construction method
US3431739A (en) Method for laying underwater pipeline
CN102269296B (en) Laying process for submarine pipeline traversing floating type production oil-storing device system
CN109506044A (en) A kind of pipeline under the ocean construction technology
CN105605314B (en) The S-shaped laying method of double-layer submarine pipeline
CN101746484B (en) Operation method of anchoring type operating vessel when crossing over submarine facility during anchoring
CN106979382A (en) The starting laying process of deepwater S-shaped submarine pipeline
CN112728211B (en) Construction method for carrying sewage sea area sea drainage pipe to put water in place and carry at sea in place
Wang et al. Latest progress in deepwater installation technologies
US4051687A (en) Pipeline laying method
CN105805415B (en) The laying method of deep-water subsea pipeline starting
CN109163144A (en) Submarine pipeline terminates the repositioning method of submarine pipeline terminal when being laid with
CN209852529U (en) Offshore mobile platform crude oil export high holding power anchor and double-cable mooring system
WO2021232480A1 (en) Offshore mooring and positioning method for large-diameter hdpe pipeline
CN106704705B (en) overwater pipeline assembling operation method and system
CN106428429B (en) The method of floating production storage offloading's long pull
CN105346677B (en) A kind of folding plate anchor and its application method
US7559721B2 (en) Towing and installation method for deepwater pipelines and risers
CN109140048A (en) The method that submarine pipeline starting is laid with is carried out using jacket spud leg
CN111692427B (en) Underwater positioning method for large-diameter overlong HDPE (high-density polyethylene) pipeline
CN113879487B (en) Non-self-floating immersed tube discharging method
CN112856040B (en) Novel sea area pipeline laying floating assisting method
CN112856039A (en) L-shaped shallow sea pipeline laying process
KR20090118466A (en) Installation method of the pipelines using laying barge with sub-sea anchor block
CN112722161A (en) Low-cost launching construction process for jacket

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant