CN109162444A CN201811346524.0A CN201811346524A CN109162444A CN 109162444 A CN109162444 A CN 109162444A CN 201811346524 A CN201811346524 A CN 201811346524A CN 109162444 A CN109162444 A CN 109162444A
Authority
CN
China
Prior art keywords
shaped pipes
steel pipe
shear wall
pipes card
card
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811346524.0A
Other languages
Chinese (zh)
Inventor
易忠梦
李定彬
胡成勇
蒲小吉
黄埔
由双庆
姜保勇
黄利华
欧军
朱坤
田野
刘波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201811346524.0A priority Critical patent/CN109162444A/en
Publication of CN109162444A publication Critical patent/CN109162444A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a kind of C-shaped pipes card and using the shear wall end template fixed structure of the pipe clamp, the C-shaped pipes card is plate-like, is equipped with arc bayonet in the wherein side of pipe clamp, is equipped with a through-hole in arc bayonet upper end or lower end;Shear wall end template fixed structure includes muti-piece template and multiple rows of pair of wire drawing bar, a steel pipe is equipped in up and down two sides of each row to wire drawing bar, the template is set in by one the nut on wire drawing bar is compressed steel pipe after it is fixed, a C-shaped pipes card is connected on the wherein steel pipe being affixed with each row to wire drawing bar, a reinforcing screw rod is arranged in the through-hole of C-shaped pipes card, described one end for reinforcing screw rod is clamped between two steel pipes of shear wall corner another side, and it is buckled and is fixed with a butterfly, the other end stretches out outside the through-hole of C-shaped pipes card and uses nut check.C-shaped pipes card that the present invention obtains and shear wall end template fixed structure stable connection, easy to operate using the pipe clamp.

Description

C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp
Technical field
The present invention relates to a kind of shear wall end template fixed structures, and in particular to a kind of C-shaped pipes card and uses the pipe clamp Shear wall end template fixed structure.
Background technique
Currently, shear wall be all by inside be arranged steel reinforcement cage, and with template close molding close after with concreting at Type.Before template is set, can multiple rows of pvc pipe be set in steel reinforcement cage.After closing template, in pre-set pvc pipe interpolation Enter to wire drawing bar, and a piece steel pipe is respectively set in up and down two sides of each row to wire drawing bar, then at every to drawing screw end set One butterfly buckle, the two lower both ends for buckling butterfly are stuck in steel pipe outer end, finally again with nut by butterfly snap lock, Side form is fixed together.In general, the position that side form and end mould connect needs to carry out again due to jointed presence It reinforces, to prevent shear wall corner or edge from there is the case where rising by mould and spillage.When being reinforced to long side end, due to cutting Power wall wall is longer, and the spacing on the mould of both ends between set steel pipe is larger, and then it is long in shear wall to need to be arranged more root longs The reinforcing bar is stuck in the end corresponding row of mould between two steel pipes up and down of wire drawing bar by the reinforcing bar of degree, then by butterfly buckle into Row is fixed, and this mode for reinforcing end extremely wastes material.Meanwhile lengthening to wire drawing bar stress be easy stretcher strain, and The position of card is influenced by shear wall shape, is easy to produce loosening.
Summary of the invention
In view of the above shortcomings of the prior art, the technical problems to be solved by the present invention are: how to provide a kind of operation letter It is single, it saves material and is unlikely to deform, the C-shaped pipes card of stable connection and the shear wall end template fixed structure using the pipe clamp.
In order to solve the above-mentioned technical problem, present invention employs the following technical solutions:
A kind of C-shaped pipes card, which is characterized in that the C-shaped pipes card is plate-like, is equipped with one in the wherein side of pipe clamp and is used for clamping The arc bayonet of steel pipe is equipped with one for wearing the through-hole of screw rod in arc bayonet upper end or lower end.The C-shaped pipes card is mainly used It fastening in steel pipe, and is arranged screw rod, by being stuck in C-shaped pipes card on the adjacent steel pipe of shear wall corner, and then shortening The length of required screw rod reduces the waste of screw rod, while being convenient for site operation.
Further, the C-shaped pipes card is made of the steel plate of 8-13mm thickness.In this way it can be ensured that the enough height of the intensity of pipe clamp, With stronger stretching resistance.
Further, the radian of the arc bayonet is greater than or equal to 1 π, less than 3 pi/2s.In this way, the minimum of arc bayonet Radian is formed by shape and engages enough with steel pipe for semicircle, while the maximum radian of arc bayonet is no more than circular three / bis-, in the case where that can ensure that snap openings are sufficiently wide, additionally it is possible to ensure to have between arc bayonet and steel pipe and more connect Contacting surface product, it is ensured that engage between pipe clamp and steel pipe firm.
Further, it is inclined-plane that the arc bayonet, which is formed by end face, and tilt angle is 4 ° -7 °.In this way, being set as Behind inclined-plane, under the arc bayonet of same size, the area on inclined-plane is bigger, so that the contact between arc bayonet and steel pipe Area is more, and frictional force is also just bigger, and the engaging between pipe clamp and steel pipe is also just more firm and close.Meanwhile being arranged Behind inclined-plane, under the influence of external pull, pipe clamp will appear the inclination of certain angle, this its be set as inclined-plane after, can draw Power effect is lower synchronous to direction of pull inclination, so that arc bayonet is bonded completely with steel pipe, further ensures that the steady of pipe clamp Gu preventing screw rod from deforming under the action of pulling force.
Further, the vertical range a of the one end of arc bayonet far from through-hole to C-shaped pipes card outer is 500mm ~ 800mm. In this way, the longitudinal small spacing two steel pipes between of height of pipe clamp and the adjacent one end of steel pipe, and then pipe clamp is convenient for engage with steel pipe, Keep engaging more smooth.
Further, the through-hole is vertically arranged strip-shaped hole, the upper and lower ends semicircular in shape of strip-shaped hole.In this way, by In being staggered between wire drawing bar for the identical row in the adjacent two sides of shear wall, when pipe clamp is installed and reinforces screw rod, reinforce Screw rod will be inclined, by through-hole vertically and in after bar shaped, can adjust convenient for reinforcing the angle of screw rod, provide for its adjustment Space.
A kind of shear wall end template fixed structure, template that it, which includes muti-piece, is laid with along shear wall setting position and more It arranging along the setting of shear wall's thickness direction through template to wire drawing bar, the adjacent same row in two sides shifts to install between wire drawing bar, One is equipped with for clamping the steel pipe to wire drawing bar, at the every both ends to wire drawing bar in up and down two sides of each row to wire drawing bar It is equipped with the butterfly buckle that a upper and lower ends engage with steel pipe, the template is set in by one will to the nut on wire drawing bar Steel pipe is fixed after compressing, which is characterized in that is connected with one on the wherein steel pipe being affixed with each row to wire drawing bar C-shaped pipes card as described above, the C-shaped pipes, which are stuck in, closes on shear wall corner wherein on a face steel pipe, the arc card of C-shaped pipes card Mouth one end is interlocked towards steel pipe and with steel pipe, and a reinforcing screw rod, the reinforcing screw rod are arranged in the through-hole of C-shaped pipes card One end be clamped between two steel pipes of shear wall corner another side, and with a butterfly buckle fix, the other end stretch out C-shaped The through-hole of pipe clamp is outer and uses nut check.In this way, when the end template to shear wall is reinforced, it only need to be on C-shaped pipes card One section of shorter screw rod is covered, and at the both ends for reinforcing screw rod respectively with butterfly buckle and nut check, reinforcing mode behaviour Make simplicity, meanwhile, save a large amount of screw rod.In addition, after using C-shaped pipes card, C-shaped pipes card and steel pipe clamping, to reinforce screw rod The place being arranged is provided, and provides carrier to reinforce the locking of screw rod, so that being also able to achieve end using shorter screw rod It reinforces.End face locating for the arc bayonet of C-shaped pipes card is inclined-plane, in locking screw, can be gone out during generating screw rod to pulling force Now tilting, inclined-plane is close to steel pipe when inclination, so that pipe clamp engages more closely with steel pipe, and it is set on C-shaped pipes card Strip-shaped hole provides certain activity space for screw rod, has enough spaces to generate position during fastening so that reinforcing screw rod It moves, and then deformation will not be generated because of the influence of pulling force, further ensure the stability of screw rod.
Further, the nut is cast steel nut, and a gasket is equipped between nut and C-shaped pipes card.In this way, cast steel spiral shell Female coupling mechanism force is bigger, and intensity is more preferable, and set gasket can share a part of frictional force and pretightning force.
Compared with prior art, the C-shaped pipes card that the present invention obtains and the shear wall end template fixed knot using the pipe clamp Structure has the advantages that
1, C-shaped pipes card and steel pipe clamping provide the place being arranged to reinforce screw rod, and provide load to reinforce the locking of screw rod Body, so that being also able to achieve the reinforcing of end using shorter screw rod.
2, end face locating for the arc bayonet of C-shaped pipes card is inclined-plane, in locking screw, during generating screw rod to pulling force It will appear inclination, inclined-plane is close to steel pipe when inclination, so that pipe clamp engages more closely with steel pipe.
3, strip-shaped hole set on C-shaped pipes card provides certain activity space for screw rod, so that reinforcing screw rod tight Solid process in there is enough spaces to generate displacement, due to and then deformation will not be generated because of the influence of pulling force, further ensure silk The stability of bar.
Detailed description of the invention
Fig. 1 is the positive structure schematic of C-shaped pipes card in embodiment;
Fig. 2 is the cross section view of 1-1 in Fig. 1;
Fig. 3 is the structural schematic diagram that shear wall formwork end reinforces in embodiment;
Fig. 4 is the top view of Fig. 3.
In figure: template 1, to wire drawing bar 2, steel pipe 3, butterfly buckle 4, C-shaped pipes card 5, arc bayonet 51, through-hole 52, vertical Distance a, screw rod 6, nut 7, gasket 8 are reinforced.
Specific embodiment
Present invention will be further explained below with reference to the attached drawings and examples.
Embodiment:
C-shaped pipes card provided in this embodiment and the shear wall end template fixed structure for using the pipe clamp, specifically, the C-shaped Pipe clamp 5 is plate-like, is made of the steel plate of 10mm thickness, and whole is in hooked, is equipped with a use in the wherein side of C-shaped pipes card 5 In the arc bayonet 51 of clamping steel pipe, a through-hole 52(for wearing screw rod is equipped with such as in 51 upper end of arc bayonet or lower end Shown in Fig. 1);As shown in Fig. 2, it is inclined-plane that the arc bayonet 51, which is formed by end face, tilt angle is 5 ° or so.This implementation C-shaped pipes card 5 in example is mainly used for engaging with the steel pipe 3 outside template 1, and mentions for the reinforcing screw rod 6 for reinforcing template end For installation site.As shown in Figure 3, Figure 4, shear wall end template fixed structure includes that muti-piece is set along shear wall in the present embodiment Template 1 that position is laid with and it is multiple rows of along the setting of shear wall's thickness direction through template 1 to wire drawing bar 2, adjacent two sides are same Row shifted to install between wire drawing bar 2, up and down two sides of each row to wire drawing bar 2 be equipped with one for clamp to wire drawing bar 2 Steel pipe 3, the both ends of wire drawing bar 2 are equipped with the butterfly buckle 4 that a upper and lower ends engage with steel pipe 3, the mould at every Plate 1 is set in by one will be fixed after the compression of steel pipe 3 to the nut 7 on wire drawing bar 2, what is be affixed with each row to wire drawing bar 2 A C-shaped pipes card 5 as described above is wherein connected on a steel pipe 3, the C-shaped pipes card 5 is closing on shear wall corner Wherein on a face steel pipe 3,51 one end of arc bayonet of C-shaped pipes card 5 is interlocked towards steel pipe 3 and with steel pipe 3, in C-shaped pipes card 5 A reinforcing screw rod 6 is arranged in through-hole 52, described one end for reinforcing screw rod 6 is clamped in two of shear wall corner another side Between steel pipe 3, and it is fixed with butterfly buckle 4, and the other end is stretched out outside the through-hole 52 of C-shaped pipes card 5 and is locked with nut 7.
In the specific implementation process, shear wall is integrally L-shaped or "-" type, and in general, C-shaped pipes card 5 is all mounted in On steel pipe 3 outside a longer face die plate 1, it is primarily to facilitate installation in this way.
Butterfly buckle 4 in the present embodiment is fastener conventional in building, and body shape is in the figure of three, in the middle Equipped with a tapped through hole, reinforcing screw rod 6 in the present embodiment and wire drawing bar 2 is covered in the tapped through hole.
The radian of arc bayonet 51 in the present embodiment is π.The radian size is suitable, can either very easily with steel pipe 3 Engaged, and there is enough areas to be bonded with steel pipe 3.
When C-shaped pipes card 5 to be stuck on steel pipe 3, in order to enable 5 local of C-shaped pipes card is caught in depth enough, it is ensured that C-shaped pipes Block 5 clampings, its underpart is prevented to be blocked on outside steel pipe 3, the one end of arc bayonet 51 far from through-hole to 5 outer of C-shaped pipes card is hung down Directly distance a is 500mm ~ 800mm.
In addition, due to the same row in the adjacent two sides in shear wall end to wire drawing bar 2 being staggered (in order to abutting end The steel pipe installed on face provides the space stretched out), meanwhile, the both ends for reinforcing screw rod 6 are separately fixed at the same row of not ipsilateral To on the steel pipe 3 of about 2 two sides of wire drawing bar, therefore, after installation obliquely, if the position that C-shaped pipes card 5 is installed is different, add Gu the tilt angle of screw rod 6 also just has certain variation therewith, in order to adapt to the variation, make to reinforce screw rod 6 any angle all It can cover in through-hole, the through-hole 52 is vertically arranged strip-shaped hole, and strip-shaped hole can vertically provide one to reinforce screw rod 6 A biggish mobile space.Certainly, the strip-shaped hole in order to reduce the frictional force reinforced between screw rod 6 and through-hole, in the present embodiment The upper and lower ends semicircular in shape of strip-shaped hole.
All nuts 7 are cast steel nut in the present embodiment, big with intensity, the big feature of pulling force, can satisfy and add Gu the pulling force demand of screw rod 6.As shown, being additionally provided with a gasket 8 between nut 7 and C-shaped pipes card 5.
Finally, it should be noted that technical side the above examples are only used to illustrate the technical scheme of the present invention and are not limiting Case, although applicant describes the invention in detail referring to preferred embodiment, those skilled in the art should be managed Solution, modification or equivalent replacement of the technical solution of the present invention are made for those, without departing from the objective and range of the technical program, It is intended to be within the scope of the claims of the invention.

Claims (8)

1. a kind of C-shaped pipes card, which is characterized in that the C-shaped pipes card (5) is plate-like, is equipped in the wherein side of C-shaped pipes card (5) One is used for the arc bayonet (51) of clamping steel pipe, is equipped with one for wearing screw rod in arc bayonet (51) upper end or lower end Through-hole (52).
2. C-shaped pipes card according to claim 1, which is characterized in that the C-shaped pipes card (5) uses the steel plate of 8-13mm thickness It is made.
3. C-shaped pipes card according to claim 1 or 2, which is characterized in that the radian of the arc bayonet (51) is greater than or waits In 1 π, less than 3 pi/2s.
4. C-shaped pipes card according to claim 1 or 2, which is characterized in that the arc bayonet (51) is formed by end face and is Inclined-plane, tilt angle are 4 ° -7 °.
5. C-shaped pipes card according to claim 1 or 2, which is characterized in that the one end of arc bayonet (51) far from through-hole to C The vertical range a of shape pipe clamp (5) outer is 500mm ~ 800mm.
6. C-shaped pipes card according to claim 1 or 2, which is characterized in that the through-hole (52) is vertically arranged bar shaped Hole, the upper and lower ends semicircular in shape of strip-shaped hole.
7. a kind of shear wall end template fixed structure, it include the template (1) that muti-piece is laid with along shear wall setting position and It is multiple rows of along the setting of shear wall's thickness direction through template (1) to wire drawing bar (2), the adjacent same row in two sides to wire drawing bar (2) it Between shift to install, be equipped with one for clamping steel pipe (3) to wire drawing bar (2) in up and down two sides of each row to wire drawing bar (2), The both ends of wire drawing bar (2) are equipped with the butterfly buckle (4) that a upper and lower ends engage with steel pipe (3), the template at every (1) by one be set in the nut (7) on wire drawing bar (2) will steel pipe (3) compress after it is fixed, which is characterized in that with it is each It arranges and is connected with a C-shaped pipes card (5) as claimed in claim 4 on the wherein steel pipe (3) being affixed to wire drawing bar (2), The C-shaped pipes card (5) is closing on shear wall corner wherein on a face steel pipe (3), the arc bayonet (51) one of C-shaped pipes card (5) End face is interlocked to steel pipe (3) and with steel pipe (3), is arranged with a reinforcing screw rod (6) in the through-hole (52) of C-shaped pipes card (5), Described one end for reinforcing screw rod (6) is clamped between two steel pipes (3) of shear wall corner another side, and is buckled with a butterfly (4) fixed, the other end stretches out the through-hole (52) of C-shaped pipes card (5) outside and is locked with nut (7).
8. shear wall end template fixed structure according to claim 7, which is characterized in that the nut (7) is cast steel Nut is equipped with a gasket (8) between nut (7) and C-shaped pipes card (5).
CN201811346524.0A 2018-11-13 2018-11-13 C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp Pending CN109162444A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811346524.0A CN109162444A (en) 2018-11-13 2018-11-13 C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811346524.0A CN109162444A (en) 2018-11-13 2018-11-13 C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp

Publications (1)

Publication Number Publication Date
CN109162444A true CN109162444A (en) 2019-01-08

Family

ID=64877130

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811346524.0A Pending CN109162444A (en) 2018-11-13 2018-11-13 C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp

Country Status (1)

Country Link
CN (1) CN109162444A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2480735A1 (en) * 2009-11-25 2012-08-01 Peri GmbH Formwork-stripping device
CN103114717A (en) * 2013-03-14 2013-05-22 青岛博海建设集团有限公司 Formwork system of shear walls at two sides of extensible seam
CN204492160U (en) * 2015-01-22 2015-07-22 江苏万象建工集团有限公司 Dual-shear force wall deformation slit formwork ruggedized construction
CN106013789A (en) * 2016-06-29 2016-10-12 山东三箭建设工程管理有限公司 Formwork reinforcing tool and method for reinforcing external corner formwork through the same
CN106121227A (en) * 2016-06-29 2016-11-16 山东三箭建设工程管理有限公司 A kind of moldboard reinforcing tool and utilize its method carrying out pier formwork reinforcement
CN107989370A (en) * 2017-12-08 2018-05-04 中国冶集团有限公司 A kind of C-channel stripe shape embedded part installing and fixing method of minimally invasive template
CN209163434U (en) * 2018-11-13 2019-07-26 中冶建工集团有限公司 C-shaped pipes card and the shear wall formwork fixed structure for using the pipe clamp

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2480735A1 (en) * 2009-11-25 2012-08-01 Peri GmbH Formwork-stripping device
CN103114717A (en) * 2013-03-14 2013-05-22 青岛博海建设集团有限公司 Formwork system of shear walls at two sides of extensible seam
CN204492160U (en) * 2015-01-22 2015-07-22 江苏万象建工集团有限公司 Dual-shear force wall deformation slit formwork ruggedized construction
CN106013789A (en) * 2016-06-29 2016-10-12 山东三箭建设工程管理有限公司 Formwork reinforcing tool and method for reinforcing external corner formwork through the same
CN106121227A (en) * 2016-06-29 2016-11-16 山东三箭建设工程管理有限公司 A kind of moldboard reinforcing tool and utilize its method carrying out pier formwork reinforcement
CN107989370A (en) * 2017-12-08 2018-05-04 中国冶集团有限公司 A kind of C-channel stripe shape embedded part installing and fixing method of minimally invasive template
CN209163434U (en) * 2018-11-13 2019-07-26 中冶建工集团有限公司 C-shaped pipes card and the shear wall formwork fixed structure for using the pipe clamp

Similar Documents

Publication Publication Date Title
CN209163434U (en) C-shaped pipes card and the shear wall formwork fixed structure for using the pipe clamp
CN200996205Y (en) Ultra-large area building constructral template
CN109162444A (en) C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp
CN204225229U (en) With the anti-blocking PVC sewer pipe of dredger
CN205347810U (en) Washing machine and drainage structures thereof
CN105091477A (en) Fixing part for refrigerator fin evaporator and refrigerator provided with fixing part
CN208535365U (en) A kind of bellows connection fastener
CN105155662B (en) A kind of finished product gutter of variable ditch body depth
CN212002050U (en) Decoration panel mounting structure
CN211114170U (en) Anchor bolt is moulded to special steel of insulation construction integration
CN2683703Y (en) Riveting geogrid
CN205875119U (en) Sand barrier spud pile and cylinder mould connection structure
CN106121227B (en) A kind of moldboard reinforcing tool and the method using its progress pier formwork reinforcement
CN205173169U (en) Bolt checkpost fixed structure
CN209874286U (en) Roof photovoltaic module's waterproof construction
CN210440206U (en) Connecting device for diaphragm booster pump of water purifier
CN209653378U (en) The bracing means of wall form
CN203677032U (en) Knife and fork basket and dish washer with knife and fork basket
CN108952149A (en) It is a kind of to hang form unit for settle position
CN208281789U (en) Enhanced corrugated steel
CN209603069U (en) A kind of analysis on aqueduct structure
CN209277525U (en) A kind of novel cruciform fastening for falsework
CN208243431U (en) A kind of oven sliding rail installing mechanism
CN211637757U (en) Stable sealing part of stainless steel wire drawing equipment
CN105133835A (en) Connecting element of Pi 48 single steel pipe and combined steel formwork

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination