CN103114717A - Formwork system of shear walls at two sides of extensible seam - Google Patents

Formwork system of shear walls at two sides of extensible seam Download PDF

Info

Publication number
CN103114717A
CN103114717A CN2013100811505A CN201310081150A CN103114717A CN 103114717 A CN103114717 A CN 103114717A CN 2013100811505 A CN2013100811505 A CN 2013100811505A CN 201310081150 A CN201310081150 A CN 201310081150A CN 103114717 A CN103114717 A CN 103114717A
Authority
CN
China
Prior art keywords
template
shrinkage joint
sides
formwork
shear wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100811505A
Other languages
Chinese (zh)
Other versions
CN103114717B (en
Inventor
王贤茂
李宗强
陶官思
张明平
李文涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao Bohai Construction Group Co Ltd
Original Assignee
Qingdao Bohai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao Bohai Construction Group Co Ltd filed Critical Qingdao Bohai Construction Group Co Ltd
Priority to CN201310081150.5A priority Critical patent/CN103114717B/en
Publication of CN103114717A publication Critical patent/CN103114717A/en
Application granted granted Critical
Publication of CN103114717B publication Critical patent/CN103114717B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a formwork system of shear walls at two sides of an extensible seam. The formwork system of the shear walls at the two sides of the extensible seam comprises two sets of wall body pouring formworks arranged symmetrically with the extensible seam as a symmetric axis, side face fastening steel tubes and end portion fastening steel tubes, wherein, the side face fastening steel tubes and the end portion fastening steel tubes are used for fixing the wall body pouring formworks. Each set of the wall body pouring formwork is respectively enclosed by an outer side formwork, an inner side formwork and an end portion formwork. A support block is respectively arranged between the outer side formwork and the inner side formwork in each set of the wall body pouring formwork and each outer side formwork and each inner side formwork are fastened through each transverse fastening steel tube, each side face fastening steel tube and a split bolt. Each end portion formwork is pressed on each outer side formwork and each inner side formwork through the end portion fastening steel tubes, bolt rods and match of end portion movable nuts on the bolt rods. According to the formwork system of the shear walls at the two sides of the extensible seam, the formworks at the two sides of the extensible seam can be erected by once in a narrow space, construction period is greatly shortened, engineering cost is reduced, and the formwork system is not limited by the size of the extensible seam and particularly applicable to the condition that the extensible seam is small.

Description

Both sides, a kind of shrinkage joint shear wall formwork system
Technical field
The present invention relates to the civil engineering construction technical field, relate in particular to the template system of both sides, a kind of shrinkage joint shear wall.
Background technology
The building shrinkage joint is also referred to as the shrinkage joint, refers in order to prevent building member because climate temperature changes (heat rises, shrinkage), makes fabric structure produce crack or destruction and a build joint vertically arranging along the suitable position of house length direction.
The both sides at shrinkage joint respectively have shear wall one, when constructing at the scene, because the inner space at shrinkage joint is narrow and small, wall form is not easy to reinforce, at present general employing is first completed the concreting of shrinkage joint one side and is carried out the construction of opposite side structure afterwards again, and its constructure scheme mainly contains following several:
Scheme one: according to traditional mold method, complete the construction of the concrete shear wall structure of shrinkage joint one side, then polyphenyl plate 04 is set and lays bakelite plate as disposable packing material on its surface in the shrinkage joint of the shear wall 01 of completing a construction side, perhaps adopt old wood glue plate to add rough ground 044 as disposable packing material, then carry out the casting of shrinkage joint opposite side concrete shear force wall by the single surface formwork system that is consisted of by template 02 and falsework 03, as shown in Fig. 1 and Fig. 2;
Scheme two: complete the concrete shear wall structure construction of shrinkage joint one side according to traditional mold method, the shear wall of opposite side adopts square steel 003 or other shaped steel as the vertical and horizontal keel, wood glue plate 001 is as template, adopt unidirectional fastening screw 002, form the split bolt reinforcement system but tighten from operation one side penetrates into the nut of no operatton face one side firm welding, as shown in Figure 3.
can find out in the constructure scheme of the shear wall of the both sides, shrinkage joint that provide in scheme one and scheme two, the shear wall of the both sides at shrinkage joint be all by first to the shear wall of shrinkage joint one side complete build after, by the mode of single surface formwork, the shear wall of the other side in shrinkage joint is built again, the reinforcing difficulty of single surface formwork system is larger, and what this kind mode also needed to grow builds the time, can't guarantee the duration in the situation that the construction period requirement is tighter, included disposable packing material in shrinkage joint in scheme one, the benzene plate is combustible material, can't satisfy fire protection requirement, be the rigidity packing material and old wood glue plate adds rough ground, with it during as the packing material at shrinkage joint, can affect the structure function of deformation joint.
Therefore, how can provide a kind of speed of application faster both sides, shrinkage joint shear wall formwork system be the technical problem that present those skilled in the art need solution badly.
Summary of the invention
One of purpose of the present invention is to provide both sides, a kind of shrinkage joint shear wall formwork system, to improve the casting rate of both sides, shrinkage joint shear wall.
For solving above-mentioned prior art problem, both sides, shrinkage joint provided by the invention shear wall formwork system, comprise the two cover body of wall cast moulds that are arranged symmetrically with about the shrinkage joint, and the fastening steel pipe of side fastening steel pipe and end of building mould for fixing described body of wall, the described body of wall of every cover is built mould and is surrounded by outboard template, inner side template, end template, wherein
laterally be provided with on described outboard template and ranked first bolt hole more, and the side of described outboard template towards the shrinkage joint is fixedly installed many horizontal anchorage bars from the bottom to top, on described horizontal anchorage bar, the position relative with described the first bolt hole is fixedly installed the axis clamp nut vertical with described outboard template, described horizontal anchorage bar is fixedly installed the axis mounting nuts parallel with described outboard template near the position of end template, be provided with second bolt hole corresponding with described the first bolt hole on described inner side template, be equipped with sleeve pipe in the first corresponding bolt hole and the second bolt hole, be provided with back-up block between described outboard template and inner side template, be equipped with split bolt in described sleeve pipe, and described split bolt one end is threaded with described clamp nut, the other end is pressed in the side fastening steel pipe of horizontally set on described inner side template by the side traveling nut that is set on split bolt, the shank of bolt that has been threaded on described mounting nuts is arranged with the end traveling nut on described shank of bolt, described end traveling nut is pressed in the fastening steel pipe in end and realizes the fixing of end template on the leading section template.
Preferably, the side of described outboard template towards the shrinkage joint also is fixedly installed the many longitudinal reinforcement lumps of wood vertical with described horizontal anchorage bar, and described horizontal anchorage bar is fixedly installed on the described longitudinal reinforcement lumps of wood.
Preferably, described horizontal anchorage bar is parallel to each other by two and the reinforcing bar that all is welded on described clamp nut cylindrical consists of, and the side end of described clamp nut towards the shrinkage joint is provided be used to the tension sheet of straining described reinforcing bar.
Preferably, the described horizontal anchorage bar position corresponding with the described longitudinal reinforcement lumps of wood is welded with wire nail, and described horizontal anchorage bar clenches on the described longitudinal reinforcement lumps of wood by described wire nail.
Preferably, described mounting nuts is welded between two described reinforcing bars.
Preferably, also be provided with the many longitudinal reinforcement lumps of wood on described inner side template, described side fastening steel pipe compresses described inner side template by the longitudinal reinforcement lumps of wood on described inner side template.
Preferably, the described split bolt end of stretching out described inner side template one end also is welded with hold-down nut.
Preferably, described outboard template is the bamboo offset plate.
Preferably, described outboard template is the segmented template, and between each section template, the junction is that tongue and groove connects.
Preferably, described sleeve pipe is the PVC sleeve pipe, and described back-up block is the concrete support piece, and described concrete support piece is quincuncial arrangement.
as can be seen from the above technical solutions, both sides, shrinkage joint provided by the present invention shear wall formwork system comprise about the shrinkage joint be arranged symmetrically with two the cover bodies of wall build mould, and the fastening steel pipe of side fastening steel pipe and end of building mould for fixing described body of wall, and every cover body of wall cast mould all has outboard template, inner side template, end template surrounds, every cover body of wall is built between outboard template in mould and inner side template and is provided with back-up block, and outboard template and inner side template are all by horizontal anchorage bar, side fastening steel pipe and split bolt are fastening, end template is by the fastening steel pipe in end, the cooperation of the end traveling nut on shank of bolt and shank of bolt is pressed on outboard template and inner side template.
Because having comprised two cover bodies of wall, this template system builds mould, thereby the shear wall of both sides, shrinkage joint can be realized building simultaneously, build with respect to first completing at present shrinkage joint one side shear wall, carry out again the template system that the opposite side shear wall is built, both sides, shrinkage joint provided by the present invention shear wall formwork system can shorten the construction period of both sides, shrinkage joint shear wall greatly, thereby assurance construction speed, and adopting two covers to build mould, all to adopt separate split bolt to carry out fastening, required construction space is less, restraining factors are less, and the scope of application is wider.
Description of drawings
Fig. 1 is that polyphenyl plate of the prior art is filled the shrinkage joint and watered the injection molding schematic diagram;
Fig. 2 is that in prior art, the injection molding schematic diagram is watered at old lumps of wood filling shrinkage joint;
Fig. 3 is that the one-sided body of wall in shrinkage joint of prior art Shaped Steel combination is built the mould schematic diagram;
Both sides, the shrinkage joint shear wall formwork system schematic that Fig. 4 provides for the embodiment of the present invention;
Fig. 5 is the assembling schematic diagram of horizontal anchorage bar and clamp nut;
Fig. 6 is that the A-A of Fig. 5 is to sectional view;
Fig. 7 is the assembling schematic diagram of screw rod and side traveling nut and hold-down nut;
Fig. 8 is the assembling schematic diagram of mounting nuts and horizontal anchorage bar.
The specific embodiment
The purpose of this invention is to provide both sides, a kind of shrinkage joint shear wall formwork system, this both sides, shrinkage joint shear wall formwork system is by arranging two covers about the wall pouring mould of shrinkage joint symmetry in the both sides, shrinkage joint, and realize watering the fastening of injection molding by the fastening steel pipe of side fastening steel pipe and end, this both sides, shrinkage joint shear wall formwork system can disposablely water injection molding with both sides, shrinkage joint shear wall and install complete, thereby build when realizing both sides, shrinkage joint shear wall, this is the reduction of erection time greatly, guarantees construction speed.
In order to make those skilled in the art person understand better the solution of the present invention, the present invention is described in further detail below in conjunction with the drawings and specific embodiments.
Both sides, the shrinkage joint shear wall formwork system that provides in the present invention mainly comprise about the shrinkage joint be arranged symmetrically with two the cover bodies of wall build mould, and be used for the fastening steel pipe of side fastening steel pipe 3 and end that fixing body of wall is built mould, above-mentioned body of wall is the shear wall of both sides, shrinkage joint, and every cover body of wall is built mould and surrounded by outboard template 1, inner side template 2 and end template;
wherein laterally be provided with on outboard template 1 and ranked first bolt hole more, the side of outboard template towards the shrinkage joint is provided with many horizontal anchorage bars 13 from top to bottom, certainly, laterally the length of anchorage bar 13 should be not less than the length of outboard template 1, so that laterally anchorage bar 13 can be with the whole compression of outboard template 1, laterally on anchorage bar 13, the position corresponding with the first bolt hole is fixedly installed clamp nut 14, and the axis of clamp nut 14 is vertical with outboard template 1, laterally anchorage bar 13 is fixedly installed the axis mounting nuts parallel with outboard template 1 15 near the position of end template,
be provided with on inner side template 2 and the first bolt hole the second bolt hole one to one, mutually be equipped with sleeve pipe in the first corresponding bolt hole and the second bolt hole, this sleeve pipe is passed wall pouring mould inside and is worn in the first bolt hole of outboard template 1 by the second bolt hole of inner side template 2, be provided with back-up block 11 between inner side template 2 and outboard template 1, be equipped with split bolt 5 in sleeve pipe, and an end of split bolt 5 is threaded with fastening bolt 14, the other end is pressed in the side fastening steel pipe 3 of lateral arrangement on inner side template 2 by the side movable bolt 7 that is set on split bolt 5, shank of bolt has been threaded on mounting nuts 15, and be arranged with the end traveling nut on shank of bolt, the end traveling nut is pressed in the fastening steel pipe in end on end template, thereby realize the fixing of end template.
The outboard template 1 of mentioning in the embodiment of the present invention refers to the wall pouring mould near shrinkage joint one side, and inner side template 2 refers to a side relative with outboard template 1, and end template refers to embody the template at the two ends of thickness of wall body; What is called laterally refers to along continuous straight runs in embodiments of the present invention, vertically refers to vertically.
by finding out in above embodiment, both sides, shrinkage joint provided by the present invention shear wall formwork system is disposable namely completed both sides, shrinkage joint shear walls water installing of mold, casting when having realized both sides, shrinkage joint shear wall the saving formwork erection time, this has just effectively shortened the construction period of both sides, shrinkage joint shear walls, thereby in the situation that the tighter reduction of erection time of construction period, effectively guarantee programming, and the both sides shear wall water mold be two about the shrinkage joint the symmetrical and separate mold that waters, every cover waters mold by outboard template 1, inner side template 2 and end template consist of, outboard template 1 and inner side template 2 are undertaken fastening by split bolt 5, split bolt 5 only needs when fastening pass successively the second bolt hole and the first bolt hole from inner side template 2 carrying out, and be tightened against on the horizontal anchorage bar of outboard template 1 on 13 clamp nut 14 and can realize the fastening of outboard template 1, screw the side traveling nut 7 that is sheathed on split bolt 5 other ends, can realize inner side template 2 fastening, this shows, the needed space of work progress is less, thereby be particularly suitable for the situation that the narrower employing conventional method in shrinkage joint can't be constructed, simultaneously because split bolt 5 is sheathed in sleeve pipe, therefore when form removal, sleeve pipe will be stayed shear wall inside, split bolt 5, outboard template 1, inner side template 2 and end template will be removed and carry out recycling.
This shows, shrinkage joint provided by the present invention shear wall formwork system has the formwork erection time of saving, shorten the construction period of both sides, shrinkage joint shear wall, and effectively overcome at present narrow due to the shrinkage joint and can't carry out the problem of formwork erection, both sides, shrinkage joint provided by the present invention shear wall formwork system also has advantages of reusable edible simultaneously, thereby it can effectively reduce engineering cost.
For further prioritization scheme, guarantee that body of wall builds the rigidity of mould, avoid deforming in the body of wall casting process, also be provided with the many longitudinal reinforcement lumps of wood 4 that are parallel to each other in the side of outboard template 1 towards the shrinkage joint in the present embodiment, laterally anchorage bar 13 is fixedly installed on the longitudinal reinforcement lumps of wood 4.
Laterally anchorage bar 13 can have multiple way of realization, can be common steel tube, horizontal anchorage bar 13 in the present embodiment preferably is made of the reinforcing bar that is parallel to each other and all be welded on clamp nut 14 cylindricals, and the side end of clamp nut 14 towards the shrinkage joint is provided with for can strain the tension sheet 12 of reinforcing bar when split bolt 5 is tightened, as shown in Fig. 4, Fig. 5 and Fig. 6.
Laterally anchorage bar 13 can be taked to bundle or other fixed forms realize fixing with the longitudinal reinforcement lumps of wood 4, in the present embodiment on horizontal anchorage bar 13 position corresponding with the longitudinal reinforcement lumps of wood 4 be welded with wire nail, laterally anchorage bar 13 clenches on the longitudinal reinforcement lumps of wood 4 by wire nail.
Because the reinforcing bar that is welded on the nut cylindrical of serving as reasons of the horizontal anchorage bar 13 in above-described embodiment consists of, therefore the mounting nuts 15 in the present embodiment also is welded between two reinforcing bars, please refer to Fig. 8, certainly, the diameter of mounting nuts 15 should be identical with clamp nut 14 sizes.
In order further to improve the stability that body of wall is built mould, also be provided with the many longitudinal reinforcement lumps of wood 4 on the inner side template 2 in the present embodiment, side fastening steel pipe 3 compresses inner side template 2 by the longitudinal reinforcement lumps of wood 4, as shown in Figure 4.
Build in the process that mould installs at body of wall, rotation split bolt 5 can be realized the fastening of outboard template 1, for handled easily, be welded with hold-down nut 8 in the end end that split bolt 5 stretches out inner side template 2 in the present embodiment, with convenient by instrument with split bolt 5 clampings and rotation.
In order to alleviate formwork integral weight, reduce simultaneously the cost of manufacture of template, the outboard template 1 in the present embodiment adopts the bamboo offset plate to make, and in order to guarantee the mechanical strength of template, generally should adopt thickness to make at 10mm and above bamboo offset plate thereof.
For the larger shrinkage joint of length, if outboard template 1 is made of one, very inconvenient when being positioned over outboard template 1 on backing plate, therefore in order to facilitate installing of outboard template 1, the preferred segmented template that adopts of outboard template 1 in the present embodiment, the outboard template 1 that the multistage template group is synthetic whole, and the junction of each section template makes the tongue and groove shape, and the length of preferred every section template is 5.0m.
In order further to reduce engineering cost, sleeve pipe in the present embodiment adopts the PVC(polyvinylchloride polyvinyl chloride) sleeve pipe, back-up block 11 for can with the concrete support piece of building body of wall and combining together, and the concrete support piece is quincuncial arrangement in body of wall is built mould.
The embodiment of the present invention also discloses the preparation method of outboard template in the both sides shear wall formwork system of a kind of above-mentioned shrinkage joint simultaneously:
Concrete, comprise step:
1) according to drawing requirement, the bamboo offset plate cutting that 10mm is thick becomes outboard template 1, and guarantees the smooth Founder of outboard template 1;
2) jewel hole forms the first bolt hole on outboard template 1;
3) the longitudinal reinforcement lumps of wood 4 and outboard template 1 are nailed together, the longitudinal reinforcement lumps of wood 4 should be dodged out the first bolt hole in the process that clenches;
4) parallel reinforced steel bar with two 25mm is welded on the periphery of nut, consist of horizontal anchorage bar 13, the axis of nut is vertical with reinforcing bar, thereby form clamp nut 14, at an end welding Upper gasket of nut, make pad form tension sheet 12, at two end reinforced and nut formation mounting nuts 15 axis of a weld and parallel reinforced steel bar between two reinforcing bars, weld wire nail on two reinforcing bars, wire nail is corresponding with the longitudinal reinforcement lumps of wood 4;
5) at an end of split bolt 5 two nuts of screwing on, and will form set bolts 8 near spiral shell order and split bolt 5 welding of end, another bolt is side traveling nut 7, as shown in Figure 7;
6) horizontal anchorage bar 13 is clenched with the longitudinal reinforcement lumps of wood 4.
The making of inner side template comprises the following steps:
11) jewel hole forms the second bolt hole on the bamboo offset plate, and the second bolt hole is corresponding one by one with the first bolt hole.
Both sides, shrinkage joint shear wall formwork system installs:
111) outboard template 1 of being made by the tower crane lifting is placed on outboard template 1 on the backing plate 10 that has been placed in advance on bearing bar 9;
222) inner side template 2 is installed, and guarantees on the second bolt hole and outboard template on inner side template 2 that the first bolt hole of 1 is corresponding good;
333) wear the PVC sleeve pipe in the first bolt hole of correspondence and the second bolt hole, and lay the concrete support piece between inner side template 2 and outboard template 1, and be quincuncial arrangement;
444) penetrate into PVC sleeve pipe in by inner side template 2 split bolt 5 and split bolt 5 ends and fastening bolt 14 are tightened, thereby realize the fastening of outboard template 1, cooperation by side fastening steel pipe 3 and cruciform fastening for falsework 6 and side traveling nut 7 is fastening with inner side template 2, as shown in Figure 4;
555) at the interior screw-in shank of bolt of mounting nuts 15, and be arranged with the end traveling nut on shank of bolt, realize the fastening of end template by end traveling nut and the fastening steel pipe of cruciform fastening for falsework 6 and end, the fastening means of end template please refer to the fastening means of inner side template.
so far completed installing of whole shrinkage joint both sides shear wall formwork system, this shows, having utilized simple material commonly used to complete both sides, shrinkage joint bodies of wall in the embodiment of the present invention builds mould and installs reliably, engineering cost is lower, and whole operating process is not subjected to the restriction of shrinkage joint size, applicable equally for the situation that the shrinkage joint is less, for the long situation in shrinkage joint, the outboard template design can be become segmented, thereby further reduced the impact of shrinkage joint length on outboard template, do not affect surrounding structure construction and stressed when shrinkage joint length is longer, and can satisfy the requirement of construction quality and safety, and reduction of erection time greatly, reduce engineering cost.
Used specific case herein principle of the present invention and embodiment are set forth, the explanation of above embodiment just is used for helping to understand method of the present invention and core concept thereof.Should be pointed out that for those skilled in the art, under the prerequisite that does not break away from the principle of the invention, can also carry out some improvement and modification to the present invention, these improvement and modification also fall into the protection domain of claim of the present invention.

Claims (10)

1. both sides, shrinkage joint shear wall formwork system, it is characterized in that, comprise the two cover body of wall cast moulds that are arranged symmetrically with about the shrinkage joint, and the fastening steel pipe of side fastening steel pipe (3) and end of building mould for fixing described body of wall, the described body of wall of every cover is built mould and is surrounded by outboard template (1), inner side template (2) and end template, wherein
laterally be provided with on described outboard template (1) and ranked first bolt hole more, and the side of described outboard template (1) towards the shrinkage joint is fixedly installed many horizontal anchorage bars (13), the upper position relative with described the first bolt hole of described horizontal anchorage bar (13) is fixedly installed the axis clamp nut (14) vertical with described outboard template (1), described horizontal anchorage bar (13) is fixedly installed the axis mounting nuts (15) parallel with described outboard template (1) near the position of end template, be provided with second bolt hole corresponding with described the first bolt hole on described inner side template (2), be equipped with sleeve pipe in the first corresponding bolt hole and the second bolt hole, be provided with back-up block (11) between described outboard template (1) and inner side template (2), be equipped with split bolt (5) in described sleeve pipe, and described split bolt (5) one ends are threaded with described clamp nut (14), the other end is pressed in the side fastening steel pipe (3) of horizontally set on described inner side template (2) by the side traveling nut (7) that is set on split bolt (5), the shank of bolt that has been threaded on described mounting nuts (15) is arranged with the end traveling nut on described shank of bolt, described end traveling nut is pressed in the fastening steel pipe in end on end template.
2. both sides, shrinkage joint according to claim 1 shear wall formwork system, it is characterized in that, the side of described outboard template towards the shrinkage joint also is fixedly installed the many longitudinal reinforcement lumps of wood (4), and described horizontal anchorage bar (13) is fixedly installed on the described longitudinal reinforcement lumps of wood (4).
3. both sides, shrinkage joint according to claim 3 shear wall formwork system, it is characterized in that, described horizontal anchorage bar (13) is parallel to each other by two and the reinforcing bar that all is welded on described clamp nut (14) cylindrical consists of, and the side end of described clamp nut (14) towards the shrinkage joint is provided be used to the tension sheet (12) of straining described reinforcing bar.
4. both sides, shrinkage joint according to claim 3 shear wall formwork system, it is characterized in that, described horizontal anchorage bar (13) position corresponding with the described longitudinal reinforcement lumps of wood (4) is welded with wire nail, and described horizontal anchorage bar (13) clenches on the described longitudinal reinforcement lumps of wood (4) by described wire nail.
5. both sides, shrinkage joint according to claim 3 shear wall formwork system, is characterized in that, described mounting nuts is welded between two described reinforcing bars.
6. both sides, shrinkage joint according to claim 2 shear wall formwork system, it is characterized in that, also be provided with the many longitudinal reinforcement lumps of wood (4) on described inner side template (2), described side fastening steel pipe (3) compresses described inner side template (2) by the longitudinal reinforcement lumps of wood (4) on described inner side template.
7. both sides, shrinkage joint according to claim 1 shear wall formwork system, is characterized in that, the end that described split bolt (5) stretches out described inner side template (2) one ends also is welded with hold-down nut (8).
8. both sides, shrinkage joint according to claim 1 shear wall formwork system, is characterized in that, described outboard template (1) is the bamboo offset plate.
9. both sides, shrinkage joint according to claim 1 shear wall formwork system, is characterized in that, described outboard template (1) is the segmented template, connects for tongue and groove between each section.
10. both sides, shrinkage joint according to claim 1 shear wall formwork system, is characterized in that, described sleeve pipe is the PVC sleeve pipe, and described back-up block (11) is the concrete support piece, and described concrete support piece is quincuncial arrangement.
CN201310081150.5A 2013-03-14 2013-03-14 A kind of both sides, shrinkage joint shear wall formwork system Expired - Fee Related CN103114717B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310081150.5A CN103114717B (en) 2013-03-14 2013-03-14 A kind of both sides, shrinkage joint shear wall formwork system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310081150.5A CN103114717B (en) 2013-03-14 2013-03-14 A kind of both sides, shrinkage joint shear wall formwork system

Publications (2)

Publication Number Publication Date
CN103114717A true CN103114717A (en) 2013-05-22
CN103114717B CN103114717B (en) 2015-12-02

Family

ID=48413145

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310081150.5A Expired - Fee Related CN103114717B (en) 2013-03-14 2013-03-14 A kind of both sides, shrinkage joint shear wall formwork system

Country Status (1)

Country Link
CN (1) CN103114717B (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005556A (en) * 2013-10-23 2014-08-27 闫相明 Shaped and fabricated formwork construction process used for shear wall at expansion and contraction joint
CN104295088A (en) * 2014-09-29 2015-01-21 中国建筑第八工程局有限公司 Steel-wood combined formwork structure of shear walls on two sides of deformation joint and construction method of steel-wood combined formwork structure
CN104727446A (en) * 2013-12-21 2015-06-24 中建四局第三建筑工程有限公司 Construction method of large aluminum alloy formwork at settlement joint
CN104912320A (en) * 2015-05-28 2015-09-16 中国十七冶集团有限公司 Synchronous construction method of shear walls on the two sides of settlement joint
CN105201082A (en) * 2015-10-10 2015-12-30 中建二局第二建筑工程有限公司 Construction method of expansion joint shape setting formwork
CN105804398A (en) * 2014-12-31 2016-07-27 山东三箭建设工程股份有限公司 Deformation joint formwork erecting device and using method thereof
CN106284981A (en) * 2015-06-05 2017-01-04 中国建筑第四工程局有限公司 The mold method of two side templates in a kind of shear force wall deformation slit
CN106284978A (en) * 2016-08-10 2017-01-04 中建新疆建工集团第建筑工程有限公司 A kind of movement joint both sides shear wall synchronous construction technique and canalization template
CN106437140A (en) * 2016-07-06 2017-02-22 江苏江中集团有限公司 Vault shear wall anti-explosion and drilling-resistant formwork erecting construction method
CN108625589A (en) * 2017-03-24 2018-10-09 中国二十冶集团有限公司 The mutual support shaped steel mould method for supporting of shear force wall deformation slit
CN109162444A (en) * 2018-11-13 2019-01-08 中冶建工集团有限公司 C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp
CN109763642A (en) * 2019-03-15 2019-05-17 中国五冶集团有限公司 Skyscraper expansion joint wall construction structure and construction method
CN109779249A (en) * 2018-12-28 2019-05-21 中国二十冶集团有限公司 A kind of mold method at narrow expansion joint
CN110043032A (en) * 2019-05-04 2019-07-23 唐世飞 A kind of auxiliary system of the nonstandard structure formwork of building
CN110080518A (en) * 2019-04-19 2019-08-02 中国二十二冶集团有限公司 Face the cast-in-place position template of side precast wall body and its installation method
CN110984562A (en) * 2019-12-18 2020-04-10 核工业西南建设集团有限公司 Double-shear wall long and narrow deformation joint and construction method
CN111042523A (en) * 2019-12-31 2020-04-21 中国建筑第二工程局有限公司 Reinforcing structure and method for simultaneously constructing wall column templates on two sides of expansion joint
CN113216610A (en) * 2021-06-22 2021-08-06 中国建筑第七工程局有限公司 Aluminum alloy template for narrow building construction joint

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0274758A (en) * 1988-09-08 1990-03-14 Tokyu Constr Co Ltd Expansion joint form and process therefor
CN101349106A (en) * 2008-08-26 2009-01-21 江苏南通二建集团有限公司 Dual-shear force wall deformation slit formwork
CN201486133U (en) * 2009-07-17 2010-05-26 中达建设集团股份有限公司 Reinforced concrete double-shear wall template
CN101949213A (en) * 2010-10-25 2011-01-19 中国建筑第六工程局有限公司 Special support system of building structure deformed seam template
CN202131770U (en) * 2011-06-13 2012-02-01 常州市戴溪建筑工程有限公司 Deformation joint molding plate supporting structure
CN102587665A (en) * 2012-03-21 2012-07-18 苏州第五建筑集团有限公司 Pouring method of coupled shear wall structure
CN102953546A (en) * 2012-08-28 2013-03-06 中联世纪建设集团有限公司 Construction method for mounting deformation joint template at double walls

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0274758A (en) * 1988-09-08 1990-03-14 Tokyu Constr Co Ltd Expansion joint form and process therefor
CN101349106A (en) * 2008-08-26 2009-01-21 江苏南通二建集团有限公司 Dual-shear force wall deformation slit formwork
CN201486133U (en) * 2009-07-17 2010-05-26 中达建设集团股份有限公司 Reinforced concrete double-shear wall template
CN101949213A (en) * 2010-10-25 2011-01-19 中国建筑第六工程局有限公司 Special support system of building structure deformed seam template
CN202131770U (en) * 2011-06-13 2012-02-01 常州市戴溪建筑工程有限公司 Deformation joint molding plate supporting structure
CN102587665A (en) * 2012-03-21 2012-07-18 苏州第五建筑集团有限公司 Pouring method of coupled shear wall structure
CN102953546A (en) * 2012-08-28 2013-03-06 中联世纪建设集团有限公司 Construction method for mounting deformation joint template at double walls

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陆汉时等: ""变形缝处双剪力墙模板施工"", 《工程质量》, vol. 29, no. 12, 10 December 2011 (2011-12-10) *

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104005556A (en) * 2013-10-23 2014-08-27 闫相明 Shaped and fabricated formwork construction process used for shear wall at expansion and contraction joint
CN104005556B (en) * 2013-10-23 2016-05-11 闫相明 For the fixed form combination shuttering construction technology of expansion joint place shear wall
CN104727446A (en) * 2013-12-21 2015-06-24 中建四局第三建筑工程有限公司 Construction method of large aluminum alloy formwork at settlement joint
CN104295088A (en) * 2014-09-29 2015-01-21 中国建筑第八工程局有限公司 Steel-wood combined formwork structure of shear walls on two sides of deformation joint and construction method of steel-wood combined formwork structure
CN105804398A (en) * 2014-12-31 2016-07-27 山东三箭建设工程股份有限公司 Deformation joint formwork erecting device and using method thereof
CN104912320A (en) * 2015-05-28 2015-09-16 中国十七冶集团有限公司 Synchronous construction method of shear walls on the two sides of settlement joint
CN106284981B (en) * 2015-06-05 2019-08-13 中国建筑第四工程局有限公司 The mold method of two side templates in a kind of shear force wall deformation slit
CN106284981A (en) * 2015-06-05 2017-01-04 中国建筑第四工程局有限公司 The mold method of two side templates in a kind of shear force wall deformation slit
CN105201082A (en) * 2015-10-10 2015-12-30 中建二局第二建筑工程有限公司 Construction method of expansion joint shape setting formwork
CN106437140A (en) * 2016-07-06 2017-02-22 江苏江中集团有限公司 Vault shear wall anti-explosion and drilling-resistant formwork erecting construction method
CN106284978A (en) * 2016-08-10 2017-01-04 中建新疆建工集团第建筑工程有限公司 A kind of movement joint both sides shear wall synchronous construction technique and canalization template
CN108625589A (en) * 2017-03-24 2018-10-09 中国二十冶集团有限公司 The mutual support shaped steel mould method for supporting of shear force wall deformation slit
CN108625589B (en) * 2017-03-24 2021-01-19 中国二十冶集团有限公司 Mutual supporting type steel mould supporting method for shear wall deformation joint
CN109162444A (en) * 2018-11-13 2019-01-08 中冶建工集团有限公司 C-shaped pipes card and the shear wall end template fixed structure for using the pipe clamp
CN109162444B (en) * 2018-11-13 2024-06-11 中冶建工集团有限公司 C-shaped pipe clamp and shear wall end template fixing structure adopting same
CN109779249A (en) * 2018-12-28 2019-05-21 中国二十冶集团有限公司 A kind of mold method at narrow expansion joint
CN109763642A (en) * 2019-03-15 2019-05-17 中国五冶集团有限公司 Skyscraper expansion joint wall construction structure and construction method
CN109763642B (en) * 2019-03-15 2023-10-13 中国五冶集团有限公司 Construction structure and construction method for expansion joint wall of high-rise building
CN110080518A (en) * 2019-04-19 2019-08-02 中国二十二冶集团有限公司 Face the cast-in-place position template of side precast wall body and its installation method
CN110043032A (en) * 2019-05-04 2019-07-23 唐世飞 A kind of auxiliary system of the nonstandard structure formwork of building
CN110984562A (en) * 2019-12-18 2020-04-10 核工业西南建设集团有限公司 Double-shear wall long and narrow deformation joint and construction method
CN110984562B (en) * 2019-12-18 2022-05-13 核工业西南建设集团有限公司 Double-shear wall long and narrow deformation joint and construction method
CN111042523A (en) * 2019-12-31 2020-04-21 中国建筑第二工程局有限公司 Reinforcing structure and method for simultaneously constructing wall column templates on two sides of expansion joint
CN113216610A (en) * 2021-06-22 2021-08-06 中国建筑第七工程局有限公司 Aluminum alloy template for narrow building construction joint

Also Published As

Publication number Publication date
CN103114717B (en) 2015-12-02

Similar Documents

Publication Publication Date Title
CN103114717A (en) Formwork system of shear walls at two sides of extensible seam
CN102828510B (en) H type soldier pile and preparation method thereof
CN204703498U (en) Wall of High-building deformation joint template construction structure
CN104295088A (en) Steel-wood combined formwork structure of shear walls on two sides of deformation joint and construction method of steel-wood combined formwork structure
JP2010174474A (en) Prestressed concrete pile, method of manufacturing the same, and connection structure between pile and footing
JP6263873B2 (en) Pile head reinforcement structure
CN109208790A (en) Circular arc shear wall single side formwork construction method
CN108660910A (en) Precast pier, track support component and its manufacture installation method
KR102069419B1 (en) Composite pile internally reinforced by steel tube
CN109208393A (en) A kind of track girder steel reinforcement cage bolt embedment structure
KR101598339B1 (en) Fastener for deck plate combine
CN202572610U (en) Die for foam mandrel precasting hollow plate girder
CN110499914A (en) Anti- bank formwork reinforcement built-in fitting, anti-bank formwork reinforcement structure and its construction method
JP5349263B2 (en) SC pile, its manufacturing method and its pile head joining method
CN204703499U (en) Wall of High-building deformation joint template
CN105648932B (en) Fixing device and its application method for highway reinforced concrete box culvert end template
CN204531386U (en) Shrinkage joint shear wall Simple lock catch formwork structure
CN109208756B (en) Fabricated shear wall and manufacturing method thereof
KR101372899B1 (en) Deck plate spacer
CN203346917U (en) Brick for mold sealing of basement exterior wall post-cast strip and formwork structure of basement exterior wall post-cast strip
CN201597115U (en) Pipe pile prestressed tension device
CN205033367U (en) Drawing of patterns component
CN110629933A (en) Structure of structural column without supporting form
CN203878757U (en) Shear wall rebar and horizontal structural beam longitudinal bar connecting structure
CN204983162U (en) Soft all alone connecting piece, prefab and wallboard

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20151202

Termination date: 20190314