CN109162355A - A kind of assembling type steel structure modularization campsite building construction system - Google Patents
A kind of assembling type steel structure modularization campsite building construction system Download PDFInfo
- Publication number
- CN109162355A CN109162355A CN201811101985.1A CN201811101985A CN109162355A CN 109162355 A CN109162355 A CN 109162355A CN 201811101985 A CN201811101985 A CN 201811101985A CN 109162355 A CN109162355 A CN 109162355A
- Authority
- CN
- China
- Prior art keywords
- fixed
- plate
- steel
- campsite
- support
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 64
- 239000010959 steel Substances 0.000 title claims abstract description 64
- 238000009435 building construction Methods 0.000 title claims abstract description 18
- 238000009434 installation Methods 0.000 claims description 14
- 239000012774 insulation material Substances 0.000 claims description 7
- 239000000565 sealant Substances 0.000 claims description 4
- 238000003780 insertion Methods 0.000 claims description 2
- 230000037431 insertion Effects 0.000 claims description 2
- 239000007787 solid Substances 0.000 claims 3
- 238000010276 construction Methods 0.000 abstract description 8
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 4
- 239000003651 drinking water Substances 0.000 abstract description 2
- 235000020188 drinking water Nutrition 0.000 abstract description 2
- 238000010438 heat treatment Methods 0.000 abstract description 2
- 238000012545 processing Methods 0.000 abstract description 2
- 238000009423 ventilation Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 12
- 238000004378 air conditioning Methods 0.000 description 2
- 238000013461 design Methods 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 238000009417 prefabrication Methods 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000002360 explosive Substances 0.000 description 1
- 239000003292 glue Substances 0.000 description 1
- 238000005286 illumination Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000005259 measurement Methods 0.000 description 1
- 238000000034 method Methods 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000010079 rubber tapping Methods 0.000 description 1
- 239000007921 spray Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/24—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0046—Loggias
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/61—Connections for building structures in general of slab-shaped building elements with each other
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/61—Connections for building structures in general of slab-shaped building elements with each other
- E04B1/6108—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together
- E04B1/612—Connections for building structures in general of slab-shaped building elements with each other the frontal surfaces of the slabs connected together by means between frontal surfaces
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
The present invention provides a kind of assembling type steel structure modularization campsite building construction systems, including several layers module floor, mutually splice and fix between two neighboring module floor, every layer of module floor includes the modular unit that several mutually splice, each modular unit includes bottom plate, top plate and several side plates, surrounds corridor area and the bedroom positioned at corridor area both ends.Assembling type steel structure modularization of the present invention campsite building construction system has the advantage that Prefabricated block cell height is integrated, has complete lodging function, it is integrated with independent bathroom, the functions such as drinking water, hot and cold water, fire water, heating, ventilation, TV, network system, finishing furniture has been mounted in unit module, and modular unit only needs to carry out the fixation of structure, the connection of pipeline and the processing of seam between module at the construction field (site) after lifting in place can be completed construction.
Description
Technical field
The invention belongs to modularized house fields, more particularly, to a kind of campsite building construction of assembling type steel structure modularization
System.
Background technique
Assembled architecture be by the field erected building of prefabrication, have it is high-quality, progress is fast, construction site safety,
The advantages that civilization, effect on environment is small.Assembling type steel structure building module be by prefabrication box unit at the construction field (site)
Made of quick assembling build, have many advantages, such as that prefabricated rate is higher, the site operation period is shorter, be suitable for construction site place,
The project that condition, duration are limited.However current modularization dormitory product on the market, living facilities are simpler and cruder, only provide illumination
And Independent air conditioning, it is unable to satisfy demand of the resident to independent toilet.
Summary of the invention
In view of this, the present invention is intended to provide a kind of highly integrated assembling type steel structure modularization campsite building construction body
System, suitable for solving demand of the resident to high-grade campsite house.
In order to achieve the above objectives, the technical scheme of the present invention is realized as follows:
A kind of assembling type steel structure modularization campsite building construction system, including several layers module floor, two neighboring mould
Mutually splice and fix between block floor, every layer of module floor includes the modular unit that several mutually splice, each module list
Member includes bottom plate, top plate and several side plates, surrounds corridor area and the bedroom positioned at corridor area both ends;
The corridor bracket for being used to support various pipelines is fixed at the top plate of corridor area;
Outer between two neighboring module floor is fixedly connected by I-steel with fixed plate, under upper layer module floor
Portion and the top of lower module floor are respectively fixed with I-steel and consistency from top to bottom, and fixed plate is strip board, and longitudinal section is in several
The side outwardly of shape, upper and lower two I-steel is connected and fixed by several fixed plates, and fixed plate is fixed on upper layer and lower layer mould
Between the modular unit of block floor;
The intersection of four modular units between two neighboring module floor is fixedly connected by the first locating piece, is used in combination
Button box clasps the first locating piece from outside.
Further, first locating piece includes the first connecting plate, leveling backing plate and positioning pin, the side of each modular unit
Corner fittings is fixed at angle, corner fittings is located at the intersection of I-steel and stringer, and corner fittings is to be open towards the side of positioning pin, Mei Ge
Two positioning pins are installed in the middle position of one connecting plate, and two positioning pins are corresponding to be inserted into corresponding four corner fittings up and down, and first
Connecting plate level is set between the I-steel of two module floors, in the two side positions difference of two positioning pins on the first connecting plate
If leveling backing plate is located at the upper end of the first connecting plate, and each leveling backing plate, which runs through, two there are two bolt and a leveling backing plate
A bolt, bolt sequentially pass through the I-steel of top, leveling backing plate, the first connecting plate and the I-steel of lower section from top to bottom and lead to
Cross nut fastening.
Further, the side outwardly of the angle steel is equipped with lifting eye.
Further, between upper and lower two I-steel and I-steel thermal insulation material is filled in side inwardly.
Further, the fixed plate includes integrally formed upper mounting plate, hang plate, outer casing, level board and lower installation
Plate, upper mounting plate are fixed on the I-steel of top by screw, and lower installation board is fixed on the I-steel of lower section, outer shield by screw
Plate blocks on the outside of the thermal insulation material between upper and lower two I-steel, and inwardly the one of the side inwardly of upper mounting plate and lower installation board
Side is blocked by sealant.
Further, it is equipped with protrusion in the middle part of one end of the fixed plate, is equipped with recess in the middle part of the other end.
Further, the corridor bracket include arbitrary arrangement combination several the first corridor brackets and several second walk
Corridor bracket, the first corridor bracket include first support, second support and attachment beam, and attachment beam is fixedly connected on first support and
Between two brackets, first support, second support and the second corridor bracket are in U-shape structure, and one end of attachment beam is fixed on first
The side of bracket, the other end of attachment beam are fixed on the bottom end of second support, and the upper end of first support and second support is fixed on
The top plate of corridor area.
Further, the upper end between the two neighboring modular unit of the module floor of top layer connects by the way that the second locating piece is fixed
It connects.
Further, second locating piece includes the second connecting plate and positioning bolt, and the second connecting plate passes through two positioning
The crossbeam of two neighboring modular unit is fixedly connected by bolt, is being lifted by crane on the second connecting plate for screwing in the screw hole of positioning bolt
Ear stud is screwed in when modular unit.
Compared with the existing technology, assembling type steel structure modularization of the present invention campsite building construction system has following
Advantage: Prefabricated block cell height is integrated, has complete lodging function, is integrated with independent bathroom, drinking water, disappears at hot and cold water
The functions such as waterproof, heating, ventilation, TV, network system, finishing furniture have been mounted in unit module, and modular unit is being constructed
The fixation of structure, the connection of pipeline and the processing of seam between progress module is only needed to can be completed after on-site hoisting is in place
Construction.
Detailed description of the invention
The attached drawing for constituting a part of the invention is used to provide further understanding of the present invention, schematic reality of the invention
It applies example and its explanation is used to explain the present invention, do not constitute improper limitations of the present invention.In the accompanying drawings:
Fig. 1 is main view of the invention;
Fig. 2 is the enlarged diagram of part A in Fig. 1;
Fig. 3 is the explosive view of Fig. 2;
Fig. 4 is the structural schematic diagram of fixed plate in Fig. 1;
Fig. 5 is the face the C-C cross-sectional view of Fig. 4;
Fig. 6 is the application schematic diagram of fixed plate;
Fig. 7 is the structural schematic diagram of button box in Fig. 1;
Fig. 8 is the right view of Fig. 7;
Fig. 9 is top view of the invention;
Figure 10 is the enlarged diagram of part B in Fig. 9;
Figure 11 be in Figure 10 D to schematic diagram;
Figure 12 is inside top plan view of the invention;
Figure 13 is the application schematic diagram of the first corridor bracket;
Figure 14 is the overlooking structure diagram of corridor bracket;
Figure 15 is E-E schematic diagram (i.e. the structural schematic diagram of the first corridor bracket) in Figure 14;
Figure 16 is F-F schematic diagram (i.e. the structural schematic diagram of the second corridor bracket) in Figure 14;
Figure 17 is right view of the invention;
Description of symbols:
1- fixed plate;101- upper mounting plate;102- hang plate;103- outer casing;104- level board;105- lower installation board;
2- lifting eye;3- corner fittings;4- I-steel;5- levels backing plate;The first connecting plate of 6-;7- positioning pin;8- bolt;9- stringer;10- is protected
Adiabator;11- sealant;The second connecting plate of 12-;The first corridor 13- bracket;131- first support;132- attachment beam;133-
Two brackets;The second corridor 14- bracket;The bedroom 15-;The corridor area 16-;17- button box;18- pipeline.
Specific embodiment
It should be noted that in the absence of conflict, the feature in embodiment and embodiment in the present invention can phase
Mutually combination.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", "upper", "lower",
The orientation or positional relationship of the instructions such as "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" is
It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of description of the present invention and simplification of the description, rather than instruction or dark
Show that signified device or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as pair
Limitation of the invention.In addition, term " first ", " second " etc. are used for description purposes only, it is not understood to indicate or imply phase
To importance or implicitly indicate the quantity of indicated technical characteristic.The feature for defining " first ", " second " etc. as a result, can
To explicitly or implicitly include one or more of the features.In the description of the present invention, unless otherwise indicated, " multiple "
It is meant that two or more.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " installation ", " phase
Even ", " connection " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or be integrally connected;It can
To be mechanical connection, it is also possible to be electrically connected;It can be directly connected, can also can be indirectly connected through an intermediary
Connection inside two elements.For the ordinary skill in the art, above-mentioned term can be understood by concrete condition
Concrete meaning in the present invention.
The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
As shown in Fig. 1-17, a kind of assembling type steel structure modularization campsite building construction system, including several layers module building
Layer, mutually splice and fix between two neighboring module floor, every layer of module floor includes the module list that several mutually splice
Member, whole building width direction are made of 1 modular unit.Modular unit both ends are 2 bedrooms 15, and centre is corridor area
16.The main structure of modular unit is the full steel structure frame of steel column, girder steel composition.Modular unit is equipped with top plate and bottom plate, wallboard etc.
Building enclosure.Equipped with bathroom facilities such as an independent toilets, including shower house, washbowl, toilet seat in each bedroom 15;Often
Equipped with furniture, household electrical appliances such as bed, wardrobe, desk, TV, air-conditionings in a bedroom 15.
Electrical leader cable gantry, spray main pipeline, fire chief road and hot and cold water main pipeline are mainly walked in corridor area 16, if
The fixed position integrated installation of above-mentioned Trunk Line is constituted the Trunk Line of whole building by meter production integral support.Bracket is by L50*50*
3 angle steel are welded, and according to module corridor size, design the overall dimensions of bracket, according to the specific arrangement of pipeline 18, design branch
The form of frame positions, and all fixed -piping hole locations are accurately positioned on bracket, and when pipe laying 18 is not necessarily to double measurement, directly presses
Hole location installation on bracket.The mode of this prefabricated integrated stand installation main pipeline, is greatly saved the Pipe installing time,
Improve in-site installation efficiency.The corridor bracket for being used to support various pipelines 18 is fixed at the top plate of corridor area 16.
The corridor bracket includes several the first corridor brackets 13 and several the second corridor branch of arbitrary arrangement combination
Frame 14, the first corridor bracket 13 include first support 131, second support 133 and attachment beam 132, and attachment beam 132 is fixedly connected on
Between first support 131 and second support, first support 131, second support 133 and the second corridor bracket 14 are in U-shape structure,
The side of first support 131 is fixed in one end of attachment beam 132, and the other end of attachment beam 132 is fixed on the bottom of second support 133
The top plate of corridor area 16 is fixed in the upper end of end, first support 131 and second support 133.
Outer between two neighboring module floor is fixedly connected by I-steel 4 with fixed plate 1, upper layer module floor
Lower part and the top of lower module floor are respectively fixed with I-steel 4 and consistency from top to bottom, and fixed plate 1 is strip board, longitudinal section
In several shape, the side outwardly of upper and lower two I-steel 4 is connected and fixed by several fixed plates 1, and fixed plate 1 is fixed on up and down
Between the modular unit of two layers of module floor;
The intersection of four modular units between two neighboring module floor is fixedly connected by the first locating piece, is used in combination
Button box 17 clasps the first locating piece from outside.
First locating piece includes the first connecting plate 6, leveling backing plate 5 and positioning pin 7, the edge of each modular unit
It is fixed with corner fittings 3, corner fittings 3 is located at the intersection of I-steel 4 and stringer 9, and corner fittings 3 is to be open towards the side of positioning pin 7, each
Two positioning pins 7 are installed in the middle position of first connecting plate 6, and two positioning pins 7 are corresponding to be inserted into corresponding four corner fittings 3 up and down
It is interior, between the horizontal I-steel 4 for being set to two module floors of the first connecting plate 6, in two positioning pins 7 on the first connecting plate 6
Two side positions are respectively equipped with two bolts 8 and a leveling backing plate 6, and leveling backing plate 5 is located at the upper end of the first connecting plate 6, each
It levels backing plate 5 to run through there are two bolt 8, bolt 8 sequentially passes through the I-steel 4 of top from top to bottom, leveling backing plate 5, first connects
Fishplate bar 6 and the I-steel of lower section 4 are simultaneously fastened by nut.
The side outwardly of the angle steel 3 is equipped with lifting eye 2.On the one hand convenient for lifting, observation on the other hand can be facilitated to position
The grafting situation of pin 7.
Between upper and lower two I-steel 4 and I-steel 4 thermal insulation material 10 is filled in side inwardly.
The fixed plate 1 includes integrally formed upper mounting plate 101, hang plate 102, outer casing 103,104 and of level board
Lower installation board 105, upper mounting plate 101 are fixed on the I-steel 4 of top by screw, and lower installation board 105 is fixed on by screw
The I-steel 4 of lower section, outer casing 103 block 10 outside of thermal insulation material between upper and lower two I-steel 4, upper mounting plate 101
Side inwardly and the side inwardly of lower installation board 105 pass through sealant 11 and block.
It is equipped with protrusion in the middle part of one end of the fixed plate 1, is equipped with recess in the middle part of the other end.
Upper end between the two neighboring modular unit of the module floor of top layer is fixedly connected by the second locating piece.
Second locating piece includes the second connecting plate 12 and positioning bolt, and the second connecting plate 12 passes through two positioning bolts
The crossbeam of two neighboring modular unit is fixedly connected, for screwing in the screw hole of positioning bolt in lifting mould on the second connecting plate 12
Ear stud is screwed in when module unit.
When construction, the first locating piece is first mounted between two modular units of lower section, the lower part insertion of two positioning pins 7
Into the corner fittings 3 of two modular units of lower section, after the completion of two modular units of top are lifted, alignment piles up and arrives lower section
On two modular units, the top of two positioning pins 7 is inserted into the corner fittings 3 of two modular units of top, bilevel
It is limited between modular unit by positioning pin 7, according to the position of prepared screw-bolt hole, using bolt 8 by neighbouring module
I-steel 4 vertical direction lock, four corner fittings 3 are locked, thus make modular unit connection fastening.
After the completion of the lifting of construction site, the pipeline between modular unit is by flexible connecting member, between same layer module, with
And quick-make between cross-layer module.
Seam between modular unit is completed by filling thermal insulation material 10 and with prefabricated corner fittings button box 17 and seam profile
Closing, prefabricated corner fittings button box 17 and seam profile are formed by 1.5mm thickness galvanized sheet bending, and all fasteners use hexagonal flange certainly
It attacks self-drilling screw to fix with the prefabricated board in module, self tapping self-drilling screw band waterproof pad has water-proof function.Button box 17 and perpendicular
Seam profile seam is sealed using weatherproof structure glue.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Within mind and principle, any modification, equivalent replacement, improvement and so on be should all be included in the protection scope of the present invention.
Claims (9)
1. a kind of assembling type steel structure modularization campsite building construction system, it is characterised in that: including several layers module floor, phase
Mutually splice and fix between adjacent two module floors, every layer of module floor includes the modular unit that several mutually splice, often
A modular unit includes bottom plate, top plate and several side plates, surrounds corridor area (16) and is located at corridor area (16) both ends
Bedroom (15);
The corridor bracket for being used to support various pipelines is fixed at the top plate of corridor area (16);
Outer between two neighboring module floor is fixedly connected by I-steel (4) with fixed plate (1), upper layer module floor
Lower part and the top of lower module floor are respectively fixed with I-steel (4) and consistency from top to bottom, and fixed plate (1) is strip board, indulge
Section is in several shape, and the side outwardly of upper and lower two I-steel (4) is connected and fixed by several fixed plates (1), fixed plate (1)
It is fixed between the modular unit of upper layer and lower layer module floor;
The intersection of four modular units between two neighboring module floor is fixedly connected by the first locating piece, and uses button box
(17) it is clasped from outside by the first locating piece.
2. assembling type steel structure modularization according to claim 1 campsite building construction system, it is characterised in that: described
Positioning piece includes that the first connecting plate (6), leveling backing plate (5) and positioning pin (7), the edge of each modular unit are fixed with angle
Part (3), corner fittings (3) are located at the intersection of I-steel (4) and stringer (9), and corner fittings (3) is to be open towards the side of positioning pin (7),
Two positioning pins (7) are installed in the middle position of each first connecting plate (6), and the corresponding insertion of two positioning pins (7) is corresponding up and down
In four corner fittings (3), between the horizontal I-steel (4) for being set to two module floors of the first connecting plate (6), the first connecting plate (6)
On in two side positions of two positioning pins (7) be respectively equipped with two bolts (8) and a leveling backing plate (6), level backing plate (5) position
In the upper end of the first connecting plate (6), each leveling backing plate (5) is run through there are two bolt (8), and bolt (8) successively passes through from top to bottom
I-steel (4), leveling backing plate (5), the first connecting plate (6) and the I-steel (4) of lower section of the side of putting on simultaneously are fastened by nut.
3. assembling type steel structure modularization according to claim 2 campsite building construction system, it is characterised in that: the angle
The side outwardly of steel (3) is equipped with lifting eye (2).
4. assembling type steel structure modularization according to claim 1 campsite building construction system, it is characterised in that: upper and lower two
Between a I-steel (4) and I-steel (4) thermal insulation material (10) are filled in side inwardly.
5. assembling type steel structure modularization according to claim 1 campsite building construction system, it is characterised in that: described solid
Fixed board (1) includes integrally formed upper mounting plate (101), hang plate (102), outer casing (103), level board (104) and lower peace
Loading board (105), upper mounting plate (101) are fixed on the I-steel (4) of top by screw, and lower installation board (105) is solid by screw
Due to the I-steel (4) of lower section, outer casing (103) is blocked on the outside of the thermal insulation material (10) between upper and lower two I-steel (4),
The side inwardly of upper mounting plate (101) and the side inwardly of lower installation board (105) pass through sealant (11) closure.
6. assembling type steel structure modularization according to claim 5 campsite building construction system, it is characterised in that: described solid
It is equipped with protrusion in the middle part of one end of fixed board (1), is equipped with recess in the middle part of the other end.
7. assembling type steel structure modularization according to claim 1 campsite building construction system, it is characterised in that: it is described walk
Corridor bracket includes several the first corridor brackets (13) and several the second corridor brackets (14) of arbitrary arrangement combination, and first walks
Corridor bracket (13) includes first support (131), second support (133) and attachment beam (132), and attachment beam (132) is fixedly connected on
Between first support (131) and second support, first support (131), second support (133) and the second corridor bracket (14) are in
The side of first support (131) is fixed in U-shaped structure, one end of attachment beam (132), and the other end of attachment beam (132) is fixed on
The top of corridor area (16) is fixed in the upper end of the bottom end of second support (133), first support (131) and second support (133)
Plate.
8. assembling type steel structure modularization according to claim 1 campsite building construction system, it is characterised in that: top layer
Upper end between the two neighboring modular unit of module floor is fixedly connected by the second locating piece.
9. assembling type steel structure modularization according to claim 8 campsite building construction system, it is characterised in that: described
Two locating pieces include the second connecting plate (12) and positioning bolt, and the second connecting plate (12) will be two neighboring by two positioning bolts
The crossbeam of modular unit is fixedly connected, for screwing in the screw hole of positioning bolt in lifting modular unit on the second connecting plate (12)
When screw in ear stud.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811101985.1A CN109162355A (en) | 2018-09-20 | 2018-09-20 | A kind of assembling type steel structure modularization campsite building construction system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811101985.1A CN109162355A (en) | 2018-09-20 | 2018-09-20 | A kind of assembling type steel structure modularization campsite building construction system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109162355A true CN109162355A (en) | 2019-01-08 |
Family
ID=64880026
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811101985.1A Pending CN109162355A (en) | 2018-09-20 | 2018-09-20 | A kind of assembling type steel structure modularization campsite building construction system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109162355A (en) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110258796A (en) * | 2019-06-27 | 2019-09-20 | 中冶天工集团有限公司 | A kind of attachment device in steel building centre corridor and two sides module |
CN110359732A (en) * | 2019-06-12 | 2019-10-22 | 国住人居工程顾问有限公司 | A kind of toilet and its installation method applied to existing building |
WO2020248536A1 (en) * | 2019-06-10 | 2020-12-17 | 北京秦淮数据有限公司 | Extended data center |
CN113513078A (en) * | 2021-04-30 | 2021-10-19 | 中建七局第一建筑有限公司 | Assembled building location fire prevention cooling structure |
CN113718943A (en) * | 2021-09-26 | 2021-11-30 | 中建三局集团有限公司 | Pressure-bearing space easy to combine |
CN114856000A (en) * | 2022-05-27 | 2022-08-05 | 日照大象房屋建设有限公司 | Assembled cold-formed thin-wall light steel combined building |
CN115405109A (en) * | 2022-11-01 | 2022-11-29 | 北京城建集团有限责任公司 | Construction method for synthesizing large public building through modular assembly |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2626914A1 (en) * | 2007-03-30 | 2008-09-30 | Data 4 | Structure of a building designed to store computer data |
CN201802051U (en) * | 2010-12-03 | 2011-04-20 | 中国华西企业股份有限公司 | Shared bracket for large-aperture pipelines |
CN104963408A (en) * | 2014-12-05 | 2015-10-07 | 北新集团建材股份有限公司 | Building structure and construction method thereof |
CN107386451A (en) * | 2017-07-14 | 2017-11-24 | 天水大成精工制造有限公司 | Assembled Box Modular Building |
CN107780536A (en) * | 2016-08-31 | 2018-03-09 | 中冶天工(天津)装备制造有限公司 | A kind of combined modular house of stable connection |
CN107780678A (en) * | 2016-08-31 | 2018-03-09 | 中冶天工(天津)装备制造有限公司 | A kind of exterior wall vertical connecting structure of modularized house |
CN107905380A (en) * | 2017-11-28 | 2018-04-13 | 上海建工二建集团有限公司 | The mechanical connecting structure and connection method of light steel keel gypsum board wall and steel I-beam |
CN107989172A (en) * | 2017-12-28 | 2018-05-04 | 河北卓秋实业有限公司 | Corner fittings connects light body plate structure house |
CN209145000U (en) * | 2018-09-20 | 2019-07-23 | 中冶天工(天津)装备制造有限公司 | A kind of assembling type steel structure modularization campsite building construction system |
-
2018
- 2018-09-20 CN CN201811101985.1A patent/CN109162355A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CA2626914A1 (en) * | 2007-03-30 | 2008-09-30 | Data 4 | Structure of a building designed to store computer data |
CN201802051U (en) * | 2010-12-03 | 2011-04-20 | 中国华西企业股份有限公司 | Shared bracket for large-aperture pipelines |
CN104963408A (en) * | 2014-12-05 | 2015-10-07 | 北新集团建材股份有限公司 | Building structure and construction method thereof |
CN107780536A (en) * | 2016-08-31 | 2018-03-09 | 中冶天工(天津)装备制造有限公司 | A kind of combined modular house of stable connection |
CN107780678A (en) * | 2016-08-31 | 2018-03-09 | 中冶天工(天津)装备制造有限公司 | A kind of exterior wall vertical connecting structure of modularized house |
CN107386451A (en) * | 2017-07-14 | 2017-11-24 | 天水大成精工制造有限公司 | Assembled Box Modular Building |
CN107905380A (en) * | 2017-11-28 | 2018-04-13 | 上海建工二建集团有限公司 | The mechanical connecting structure and connection method of light steel keel gypsum board wall and steel I-beam |
CN107989172A (en) * | 2017-12-28 | 2018-05-04 | 河北卓秋实业有限公司 | Corner fittings connects light body plate structure house |
CN209145000U (en) * | 2018-09-20 | 2019-07-23 | 中冶天工(天津)装备制造有限公司 | A kind of assembling type steel structure modularization campsite building construction system |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2020248536A1 (en) * | 2019-06-10 | 2020-12-17 | 北京秦淮数据有限公司 | Extended data center |
CN110359732A (en) * | 2019-06-12 | 2019-10-22 | 国住人居工程顾问有限公司 | A kind of toilet and its installation method applied to existing building |
CN110359732B (en) * | 2019-06-12 | 2024-03-01 | 国住人居工程顾问有限公司 | Toilet applied to existing building and installation method thereof |
CN110258796A (en) * | 2019-06-27 | 2019-09-20 | 中冶天工集团有限公司 | A kind of attachment device in steel building centre corridor and two sides module |
CN113513078A (en) * | 2021-04-30 | 2021-10-19 | 中建七局第一建筑有限公司 | Assembled building location fire prevention cooling structure |
CN113718943A (en) * | 2021-09-26 | 2021-11-30 | 中建三局集团有限公司 | Pressure-bearing space easy to combine |
CN114856000A (en) * | 2022-05-27 | 2022-08-05 | 日照大象房屋建设有限公司 | Assembled cold-formed thin-wall light steel combined building |
CN115405109A (en) * | 2022-11-01 | 2022-11-29 | 北京城建集团有限责任公司 | Construction method for synthesizing large public building through modular assembly |
CN115405109B (en) * | 2022-11-01 | 2023-02-28 | 北京城建集团有限责任公司 | Construction method for synthesizing large public building through modular assembly |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109162355A (en) | A kind of assembling type steel structure modularization campsite building construction system | |
US5493836A (en) | Building system based upon preformed modules | |
US20160319534A1 (en) | Reversible module co-ordination system for buildings | |
EP3186454B1 (en) | Prefabricated demising walls | |
AU2014100244A4 (en) | A prefabricated steel structural building system and construction method thereof | |
KR20100087242A (en) | A fixing device and cap of the hole pair panel | |
MX2013003931A (en) | Modular building system. | |
CN204781329U (en) | Pin -connected panel standard turnover room | |
CN103726597A (en) | Frame type unit curtain wall adopting auxiliary installing rack, tooth profile angle and tooth profile support | |
CN103485414A (en) | Prefabricated assembled type steel structure house building system and construction method thereof | |
CN108824648A (en) | Space module house | |
CN110612373A (en) | Prefabricated pre-decorated volume construction of buildings | |
IE43888B1 (en) | Improvements in or relating to prefabricated buildings | |
CN209145000U (en) | A kind of assembling type steel structure modularization campsite building construction system | |
US9453332B2 (en) | Building system, particularly a residential building | |
CZ2009545A3 (en) | Building module for demountable prefabricated constructions | |
WO2017016183A1 (en) | Basement structure connected by using fender posts | |
RU66756U1 (en) | BUTT CONNECTION OF ELEMENTS OF THE BLOCK CONTAINER (OPTIONS) | |
AU2012100822A4 (en) | Multistorey building | |
KR20200084978A (en) | Modular house and construction method thereof | |
EP1636446A1 (en) | Ready-to-use containerised house | |
WO2011077386A1 (en) | Construction system and methods therefor | |
CN106088703B (en) | A kind of assembled substation using modularization pedestal | |
KR101086060B1 (en) | Prefebrication module | |
JP5563351B2 (en) | Building unit |
Legal Events
Date | Code | Title | Description |
---|---|---|---|