CN109162293A - A kind of drainage pipeline foundation working process - Google Patents

A kind of drainage pipeline foundation working process Download PDF

Info

Publication number
CN109162293A
CN109162293A CN201811297797.0A CN201811297797A CN109162293A CN 109162293 A CN109162293 A CN 109162293A CN 201811297797 A CN201811297797 A CN 201811297797A CN 109162293 A CN109162293 A CN 109162293A
Authority
CN
China
Prior art keywords
pipeline
mould bases
foundation
rail
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811297797.0A
Other languages
Chinese (zh)
Inventor
钱野
胡石
宋小峰
施沈杰
邱林锋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201811297797.0A priority Critical patent/CN109162293A/en
Publication of CN109162293A publication Critical patent/CN109162293A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/46Foundations for supply conduits or other canals

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Sewage (AREA)

Abstract

The invention discloses a kind of drainage pipeline foundation working process, and include the following steps: (1) preliminary preparation: pipeline foundation trench is excavated to designed elevation, has managed pipeline longitudinal slope, carrying out precipitation work ensures foundation trench without ponding soaking;(2) track laying;(3) fixing of the forming frame: mould bases processes support by bar section of stainless steel, and length is 3-6 meters, consistent with draining length of tube with construction;(4) transport in pipe-line tank;(5) pipeline location;(6) concrete pouring construction;(7) maintenance and next section of construction.

Description

A kind of drainage pipeline foundation working process
Technical field
The present invention relates to a kind of pipeline construction techniques, and in particular to a kind of drainage pipeline foundation working process.
Background technique
Pipeline foundation is being poured frequently with concrete foundation form since drainage pipeline belongs to linear long apart from structures It needs a large amount of template to be installed when basic, especially when basic top surface is inclined-plane, brings very big inconvenience to concreting.
Summary of the invention
Goal of the invention: the purpose of the present invention is to solve deficiencies in the prior art, provide a kind of drainage pipeline basis Construction technology is supported using the rail for being anchored at pipeline foundation trench as mobile, and the template on track can realize longitudinal movement, both may be used With the fast transportation pipeline in foundation trench, and reusable template, construction precision and efficiency are greatly improved, is reached to casting concrete Moving die plate is facilitated to carry out next section of construction after to some strength.
Technical solution: a kind of drainage pipeline foundation working process of the present invention includes the following steps:
(1) preliminary preparation: pipeline foundation trench is excavated to designed elevation, has managed pipeline longitudinal slope, carrying out precipitation work ensures foundation trench Without ponding soaking, part is disturbed or when inundation is backfilling and compacted by rendzinas or soil cement, it is ensured that foundation bearing capacity, which meets, to be set Meter requires, and is checked and accepted by foundation trench;
(2) track laying: being respectively arranged one of rail at the outer rim of default pipeline foundation two sides, and rail foot surface is wide and in rail two sides It arranges bolt hole, screw hole is squeezed by the bolt that length is 50-120cm and fixes two sides rail;
(3) fixing of the forming frame: mould bases processes support by bar section of stainless steel, and length is 3-6 meters, consistent with draining length of tube with construction; Rubber pulley blocks are equipped on the outside of mould bases, inside is equipped with the locating wheel group connecting with rail, sets one of gusseted, mould every 80cm Frame starts to install in ducts upstream, by the way that detent wheel on the inside of mould bases to be mounted on the rail of laying;
(4) transport in pipe-line tank: pipeline is deposited in construction pipeline section upstream, and the corresponding mould bases of a length of tubing will by lifting rope Pipeline is hung on the gooseneck of top, plays fixed function with connecting at the top of the mould bases of two sides, in-orbit by pushing or pulling mould bases It is moved on road to transport tubing, pipeline transportation needed for a construction pipeline to downstream is constructed position by transporting in slot by this method It sets;
(5) pipeline location: prefabricated U-typed pipe of concrete pillow is placed at each length of tubing both ends, tube coupling on mould bases is shelved on On pipe pillow.Pipeline is connected by interface, while adjacent mould bases being fastened by bolts;
(6) it concrete pouring construction: is set by the spacing of the two pieces of aluminum alloy pattern plates in adjusting bolt adjustment inside of mould bases behind with basis Equivalent width is counted, starts casting concrete after applying one layer of release agent in template;
(7) maintenance and next section of construction: after concrete foundation maintenance to design strength 80%, first mould close to upstream is first torn open Frame twists mould bases behind bolt and template and basis is detached from, and the bolt connection released between mould bases removes all moulds with this Frame, and mould bases is moved quickly into next pipeline section and is constructed.
Further, step (2) one of rail of each setting, the rail bottom at default pipeline foundation two sides outer rim 5cm The wide 20cm in face.
Further, the bore dia 1.5cm, longitudinal pitch 100cm, horizontal spacing 80cm of step (2) described bolt hole.
Further, step (4) the top gooseneck makes width 15cm by H profile steel, together every 2-3m arrangement.
The utility model has the advantages that a kind of drainage pipeline foundation working process of the invention, is made using the rail for being anchored at pipeline foundation trench For mobile support, the template on track can realize longitudinal movement, not only can in foundation trench fast transportation pipeline, but also it is reusable Template greatly improves construction precision and efficiency, and moving die plate is facilitated to carry out next section after casting concrete reaches some strength Construction.
Detailed description of the invention
Fig. 1 is construction pipeline configuration schematic diagram of the invention;
Fig. 2 is pipeline transportation schematic diagram of the invention.
Specific embodiment
Technical solution of the present invention is described in further detail combined with specific embodiments below.
In conjunction with attached drawing 1 and attached drawing 2, wherein figure label is as follows:
1. top crossbeam;2. inside aluminum alloy pattern plate;3. drainpipe;4. outrigger;5. adjusting bolt;6. steel wheel group;7. concrete Basis;8. moving track;9. fixing bolt;10. rubber wheel group;11. handling rope.
Embodiment 1
A kind of drainage pipeline foundation working process, includes the following steps:
(1) preliminary preparation: pipeline foundation trench is excavated to designed elevation, has managed pipeline longitudinal slope, carrying out precipitation work ensures foundation trench Without ponding soaking, part is disturbed or when inundation is backfilling and compacted by rendzinas or soil cement, it is ensured that foundation bearing capacity, which meets, to be set Meter requires, and is checked and accepted by foundation trench;
(2) track laying: one of rail of each setting at default pipeline foundation two sides outer rim 5cm, the wide 20cm of rail foot surface, and Bolt hole, the bore dia 1.5cm of bolt hole, longitudinal pitch 100cm, horizontal spacing 80cm are arranged in rail two sides;It is by length 50 bolt squeezes into screw hole and fixes two sides rail;
(3) fixing of the forming frame: mould bases processes support by bar section of stainless steel, and length is 3 meters, consistent with draining length of tube with construction;Mould Rubber pulley blocks are equipped on the outside of frame, inside is equipped with the locating wheel group connecting with rail, sets one of gusseted, mould bases every 80cm Start to install in ducts upstream, by the way that detent wheel on the inside of mould bases to be mounted on the rail of laying;
(4) transport in pipe-line tank: as shown in Fig. 2, pipeline is deposited in construction pipeline section upstream, the corresponding mould bases of a length of tubing passes through Pipeline is hung on the gooseneck of top by lifting rope, and top gooseneck makes width 15cm by H profile steel, together every 2m arrangement; Fixed function is played with connecting at the top of the mould bases of two sides, tubing is transported by pushing or pulling mould bases movement in orbit, with this Mode in slot by transporting pipeline transportation needed for a construction pipeline to downstream construction location;
(5) pipeline location: prefabricated U-typed pipe of concrete pillow is placed at each length of tubing both ends, tube coupling on mould bases is shelved on On pipe pillow.Pipeline is connected by interface, while adjacent mould bases being fastened by bolts;
(6) it concrete pouring construction: is set by the spacing of the two pieces of aluminum alloy pattern plates in adjusting bolt adjustment inside of mould bases behind with basis Equivalent width is counted, starts casting concrete after applying one layer of release agent in template;
(7) maintenance and next section of construction: after concrete foundation maintenance to design strength 80%, first mould close to upstream is first torn open Frame twists mould bases behind bolt and template and basis is detached from, and the bolt connection released between mould bases removes all moulds with this Frame, and mould bases is moved quickly into next pipeline section and is constructed.
Embodiment 2
A kind of drainage pipeline foundation working process, includes the following steps:
(1) preliminary preparation: pipeline foundation trench is excavated to designed elevation, has managed pipeline longitudinal slope, carrying out precipitation work ensures foundation trench Without ponding soaking, part is disturbed or when inundation is backfilling and compacted by rendzinas or soil cement, it is ensured that foundation bearing capacity, which meets, to be set Meter requires, and is checked and accepted by foundation trench;
(2) track laying: one of rail of each setting at default pipeline foundation two sides outer rim 5cm, the wide 20cm of rail foot surface, and Bolt hole, the bore dia 1.5cm of bolt hole, longitudinal pitch 100cm, horizontal spacing 80cm are arranged in rail two sides;It is by length The bolt of 50-120cm squeezes into screw hole and fixes two sides rail;
(3) fixing of the forming frame: mould bases processes support by bar section of stainless steel, and length is 6 meters, consistent with draining length of tube with construction;Mould Rubber pulley blocks are equipped on the outside of frame, inside is equipped with the locating wheel group connecting with rail, sets one of gusseted, mould bases every 80cm Start to install in ducts upstream, by the way that detent wheel on the inside of mould bases to be mounted on the rail of laying;
(4) transport in pipe-line tank: as shown in Fig. 2, pipeline is deposited in construction pipeline section upstream, the corresponding mould bases of a length of tubing passes through Pipeline is hung on the gooseneck of top by lifting rope, and top gooseneck makes width 15cm by H profile steel, together every 3m arrangement; Fixed function is played with connecting at the top of the mould bases of two sides, tubing is transported by pushing or pulling mould bases movement in orbit, with this Mode in slot by transporting pipeline transportation needed for a construction pipeline to downstream construction location;
(5) pipeline location: prefabricated U-typed pipe of concrete pillow is placed at each length of tubing both ends, tube coupling on mould bases is shelved on On pipe pillow.Pipeline is connected by interface, while adjacent mould bases being fastened by bolts;
(6) it concrete pouring construction: is set by the spacing of the two pieces of aluminum alloy pattern plates in adjusting bolt adjustment inside of mould bases behind with basis Equivalent width is counted, starts casting concrete after applying one layer of release agent in template;
(7) maintenance and next section of construction: after concrete foundation maintenance to design strength 80%, first mould close to upstream is first torn open Frame twists mould bases behind bolt and template and basis is detached from, and the bolt connection released between mould bases removes all moulds with this Frame, and mould bases is moved quickly into next pipeline section and is constructed.
Embodiment 3
A kind of drainage pipeline foundation working process, includes the following steps:
(1) preliminary preparation: pipeline foundation trench is excavated to designed elevation, has managed pipeline longitudinal slope, carrying out precipitation work ensures foundation trench Without ponding soaking, part is disturbed or when inundation is backfilling and compacted by rendzinas or soil cement, it is ensured that foundation bearing capacity, which meets, to be set Meter requires, and is checked and accepted by foundation trench;
(2) track laying: one of rail of each setting at default pipeline foundation two sides outer rim 5cm, the wide 20cm of rail foot surface, and Bolt hole, the bore dia 1.5cm of bolt hole, longitudinal pitch 100cm, horizontal spacing 80cm are arranged in rail two sides;It is by length The bolt of 50-120cm squeezes into screw hole and fixes two sides rail;
(3) fixing of the forming frame: mould bases processes support by bar section of stainless steel, and length is 4 meters, consistent with draining length of tube with construction;Mould Rubber pulley blocks are equipped on the outside of frame, inside is equipped with the locating wheel group connecting with rail, sets one of gusseted, mould bases every 80cm Start to install in ducts upstream, by the way that detent wheel on the inside of mould bases to be mounted on the rail of laying;
(4) transport in pipe-line tank: as shown in Fig. 2, pipeline is deposited in construction pipeline section upstream, the corresponding mould bases of a length of tubing passes through Pipeline is hung on the gooseneck of top by lifting rope, and top gooseneck makes width 15cm by H profile steel, together every 2m arrangement; Fixed function is played with connecting at the top of the mould bases of two sides, tubing is transported by pushing or pulling mould bases movement in orbit, with this Mode in slot by transporting pipeline transportation needed for a construction pipeline to downstream construction location;
(5) pipeline location: prefabricated U-typed pipe of concrete pillow is placed at each length of tubing both ends, tube coupling on mould bases is shelved on On pipe pillow.Pipeline is connected by interface, while adjacent mould bases being fastened by bolts;
(6) it concrete pouring construction: is set by the spacing of the two pieces of aluminum alloy pattern plates in adjusting bolt adjustment inside of mould bases behind with basis Equivalent width is counted, starts casting concrete after applying one layer of release agent in template;
(7) maintenance and next section of construction: after concrete foundation maintenance to design strength 80%, first mould close to upstream is first torn open Frame twists mould bases behind bolt and template and basis is detached from, and the bolt connection released between mould bases removes all moulds with this Frame, and mould bases is moved quickly into next pipeline section and is constructed.
A kind of drainage pipeline foundation working process of the invention is used as mobile branch using the rail for being anchored at pipeline foundation trench Support, the template on track can realize longitudinal movement, not only can in foundation trench fast transportation pipeline, but also reusable template, greatly Width improves construction precision and efficiency, and moving die plate is facilitated to carry out next section of construction after casting concrete reaches some strength.
The above described is only a preferred embodiment of the present invention, be not intended to limit the present invention in any form, though So the present invention has been disclosed as a preferred embodiment, and however, it is not intended to limit the invention, any technology people for being familiar with this profession Member, without departing from the scope of the present invention, when the technology contents using the disclosure above make a little change or modification For the equivalent embodiment of equivalent variations, but anything that does not depart from the technical scheme of the invention content, according to the technical essence of the invention Any simple modification, equivalent change and modification to the above embodiments, all of which are still within the scope of the technical scheme of the invention.

Claims (4)

1. a kind of drainage pipeline foundation working process, characterized by the following steps:
(1) preliminary preparation: pipeline foundation trench is excavated to designed elevation, has managed pipeline longitudinal slope, carrying out precipitation work ensures foundation trench Without ponding soaking, part is disturbed or when inundation is backfilling and compacted by rendzinas or soil cement, it is ensured that foundation bearing capacity, which meets, to be set Meter requires, and is checked and accepted by foundation trench;
(2) track laying: being respectively arranged one of rail at the outer rim of default pipeline foundation two sides, and rail foot surface is wide and in rail two sides It arranges bolt hole, screw hole is squeezed by the bolt that length is 50-120cm and fixes two sides rail;
(3) fixing of the forming frame: mould bases processes support by bar section of stainless steel, and length is 3-6 meters, consistent with draining length of tube with construction; Rubber pulley blocks are equipped on the outside of mould bases, inside is equipped with the locating wheel group connecting with rail, sets one of gusseted, mould every 80cm Frame starts to install in ducts upstream, by the way that detent wheel on the inside of mould bases to be mounted on the rail of laying;
(4) transport in pipe-line tank: pipeline is deposited in construction pipeline section upstream, and the corresponding mould bases of a length of tubing will by lifting rope Pipeline is hung on the gooseneck of top, plays fixed function with connecting at the top of the mould bases of two sides, in-orbit by pushing or pulling mould bases It is moved on road to transport tubing, pipeline transportation needed for a construction pipeline to downstream is constructed position by transporting in slot by this method It sets;
(5) pipeline location: prefabricated U-typed pipe of concrete pillow is placed at each length of tubing both ends, tube coupling on mould bases is shelved on On pipe pillow.Pipeline is connected by interface, while adjacent mould bases being fastened by bolts;
(6) it concrete pouring construction: is set by the spacing of the two pieces of aluminum alloy pattern plates in adjusting bolt adjustment inside of mould bases behind with basis Equivalent width is counted, starts casting concrete after applying one layer of release agent in template;
(7) maintenance and next section of construction: after concrete foundation maintenance to design strength 80%, first mould close to upstream is first torn open Frame twists mould bases behind bolt and template and basis is detached from, and the bolt connection released between mould bases removes all moulds with this Frame, and mould bases is moved quickly into next pipeline section and is constructed.
2. a kind of drainage pipeline foundation working process according to claim 1, it is characterised in that: step (2) is described pre- If one of rail of each setting, the wide 20cm of rail foot surface at the outer rim 5cm of pipeline foundation two sides.
3. a kind of drainage pipeline foundation working process according to claim 1, it is characterised in that: step (2) described bolt The bore dia 1.5cm in hole, longitudinal pitch 100cm, horizontal spacing 80cm.
4. a kind of drainage pipeline foundation working process according to claim 1, it is characterised in that: step (4) described top Gooseneck makes width 15cm by H profile steel, together every 2-3m arrangement.
CN201811297797.0A 2018-11-02 2018-11-02 A kind of drainage pipeline foundation working process Pending CN109162293A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811297797.0A CN109162293A (en) 2018-11-02 2018-11-02 A kind of drainage pipeline foundation working process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811297797.0A CN109162293A (en) 2018-11-02 2018-11-02 A kind of drainage pipeline foundation working process

Publications (1)

Publication Number Publication Date
CN109162293A true CN109162293A (en) 2019-01-08

Family

ID=64876656

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811297797.0A Pending CN109162293A (en) 2018-11-02 2018-11-02 A kind of drainage pipeline foundation working process

Country Status (1)

Country Link
CN (1) CN109162293A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111442135A (en) * 2020-05-25 2020-07-24 郑国强 Construction method of road rainwater pipeline
CN112049218A (en) * 2020-08-26 2020-12-08 中铁十局集团有限公司 Municipal concrete drainage pipeline laying construction method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203096758U (en) * 2013-02-18 2013-07-31 江苏建筑职业技术学院 Hard concrete smooth foundation pit for installing drainage pipeline
CN204898713U (en) * 2015-06-19 2015-12-23 张家港市华正进出口贸易有限公司 Underground trench drainage mounting structure
CN107401207A (en) * 2017-09-11 2017-11-28 温州东怡园林建设有限公司 The construction method of drainage pipeline
CN207554066U (en) * 2017-09-02 2018-06-29 中铁十六局集团路桥工程有限公司 The mobile formwork of a plurality of groove in one-time-concreting tunnel

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203096758U (en) * 2013-02-18 2013-07-31 江苏建筑职业技术学院 Hard concrete smooth foundation pit for installing drainage pipeline
CN204898713U (en) * 2015-06-19 2015-12-23 张家港市华正进出口贸易有限公司 Underground trench drainage mounting structure
CN207554066U (en) * 2017-09-02 2018-06-29 中铁十六局集团路桥工程有限公司 The mobile formwork of a plurality of groove in one-time-concreting tunnel
CN107401207A (en) * 2017-09-11 2017-11-28 温州东怡园林建设有限公司 The construction method of drainage pipeline

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111442135A (en) * 2020-05-25 2020-07-24 郑国强 Construction method of road rainwater pipeline
CN111442135B (en) * 2020-05-25 2021-09-24 武汉楚耀建设工程有限公司 Construction method of road rainwater pipeline
CN112049218A (en) * 2020-08-26 2020-12-08 中铁十局集团有限公司 Municipal concrete drainage pipeline laying construction method

Similar Documents

Publication Publication Date Title
CN106089253B (en) A kind of all-hydraulic template system poured for culvert
CN104631512B (en) Hang modulus method after-pouring band beam-slab construction method
CN203022024U (en) Integrally-movable formwork for pipe gallery cast-in-situ construction
CN208294567U (en) A kind of fixation device for the soft mould pocket type mold pouring walling suitable for underground
CN206786135U (en) A kind of pipeline waterborne and π type compensator hoisting bracket
CN109162293A (en) A kind of drainage pipeline foundation working process
CN208668596U (en) A kind of reinforced concrete girder slab system and prefabricated post assembly node
CN214005605U (en) Construction device for cast-in-place concrete panel of upstream slope of dam
CN106351180A (en) Full hydraulic opening self-propelled template system for aqueduct
CN110306644A (en) The construction method of municipal rain sewage diversion pipeline
CN103074871B (en) Arc-shaped slope concrete sliding and lifting template
CN204982681U (en) Steel bow member integral translation device
CN111074950B (en) Pre-closed advanced water stop post-cast strip for basement outer wall and construction method
CN113445739A (en) Adjustable unilateral template supporting device
CN105780736B (en) A kind of chute cast-in-place construction device
CN109881592B (en) Trapezoidal drainage ditch construction method adopting single-side formwork
CN217713886U (en) Comprehensive utilization platform in ultra-long distance small-diameter tunnel
CN206538737U (en) Aqueduct is all-hydraulic to open self-propelled template system
CN205711980U (en) A kind of chute cast-in-place construction device
CN108098978A (en) A kind of assembled underground pipe gallery epimere producing device and production method
CN203096695U (en) Beam-type aqueduct rebar binding mold
CN210256628U (en) Self-adaptive outer mold system for prefabricating concrete
CN204080857U (en) Subway station Y type cast steel is in conjunction with steel pipe column interior concrete lift-up device
CN208267865U (en) A kind of backform trolley
CN201128905Y (en) Multi-degree-of-freedom toe board special-shaped slip mould

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190108