CN109162282A - A kind of deep basal pit maintenance construction - Google Patents

A kind of deep basal pit maintenance construction Download PDF

Info

Publication number
CN109162282A
CN109162282A CN201811032717.9A CN201811032717A CN109162282A CN 109162282 A CN109162282 A CN 109162282A CN 201811032717 A CN201811032717 A CN 201811032717A CN 109162282 A CN109162282 A CN 109162282A
Authority
CN
China
Prior art keywords
pile
bored concrete
stiffening
deep basal
basal pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811032717.9A
Other languages
Chinese (zh)
Inventor
赵卫政
华春忠
张勇
王长乐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical JIANGSU XINGSHA CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201811032717.9A priority Critical patent/CN109162282A/en
Publication of CN109162282A publication Critical patent/CN109162282A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/16Restraining of underground water by damming or interrupting the passage of underground water by placing or applying sealing substances
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor

Abstract

The present invention relates to Architectural Equipment technical fields, in particular a kind of deep basal pit maintenance construction, single cylindrical body peripheral pile including multiple lap connections, the inside of peripheral pile is equipped with several continuously arranged bored concrete piles, it is equipped with bored concrete pile collar tie beam and waist rail on each bored concrete pile, is mounted on stiffening pile at bored concrete pile collar tie beam and waist rail.Retaining design of the present invention includes the cylindric peripheral pile of multiple lap connections, and the cylindric peripheral pile of multiple lap connections can form closed water-stop curtain in underground, so that retaining design of the present invention be made to have good water-stagnating effect;In addition setting deposited reinforced concrete pile is used as material of putting more energy on the inside of single cylindric peripheral pile, and more anchor disk jet mixing stiffening piles together are respectively set at bored concrete pile collar tie beam and waist rail, to substantially increase the stiffness and strength of retaining design, therefore retaining design of the invention can reach the double effects of sealing and earth-retaining simultaneously;Retaining design of the present invention is structurally reasonable, reinforcement performance is good.

Description

A kind of deep basal pit maintenance construction
Technical field
The present invention relates to Architectural Equipment technical field, specially a kind of deep basal pit maintenance construction.
Background technique
In traditional Extra-Deep Foundation Pit system, it is bad or can not be same to there is unreasonable structure, reinforcement performance more in retaining design The preferable sealing of Shi Shixian and earth-retaining double effects, therefore one kind is structurally reasonable, reinforcement performance is good and it is preferable to realize simultaneously The exploitation of the Extra-Deep Foundation Pit system of sealing and earth-retaining double effects is necessary.In consideration of it, it is proposed that a kind of deep basal pit is tieed up Shield construction.
Summary of the invention
The purpose of the present invention is to provide a kind of maintenances of deep basal pit to construct, to solve mentioned above in the background art ask Topic.
To achieve the above object, the invention provides the following technical scheme:
A kind of deep basal pit maintenance construction, the single cylindrical body peripheral pile including multiple lap connections, the peripheral pile it is interior Side is equipped with several continuously arranged bored concrete piles, is equipped with bored concrete pile collar tie beam and waist rail, the bored concrete pile on each bored concrete pile It is mounted on stiffening pile at collar tie beam and waist rail, is equipped with dowel inside each stiffening pile, the bored concrete pile collar tie beam and puts more energy into The junction of stake and the junction of waist rail and stiffening pile are mounted on Two bors d's oeuveres channel steel purlin, each Two bors d's oeuveres channel steel purlin Both ends are equipped with anchor plate, and several ribbing reinforcing bars are connected between two anchor plates, are also set in the Two bors d's oeuveres channel steel purlin There is wedge, Two bors d's oeuveres channel steel purlin and wedge are run through simultaneously in the end of the stiffening pile, and extend out to outside.
Preferably, the peripheral pile is three axes agitating pile.
Preferably, the bored concrete pile is deposited reinforced concrete pile.
Preferably, the tilt angle of the stiffening pile is 45 degree, and the spacing of two neighboring stiffening pile is 1.8m.
Preferably, the dowel is made of multi beam steel strand wires, and every beam steel strand wires are twisted by seven steel wires.
Preferably, it is closely welded and fixed between the Two bors d's oeuveres channel steel purlin and anchor plate, between the anchor plate and wedge Closely it is welded and fixed.
Compared with prior art, the beneficial effects of the present invention are:
Retaining design of the present invention includes the cylindric peripheral pile of multiple lap connections, the cylindric periphery of multiple lap connections Stake can form closed water-stop curtain in underground, so that retaining design of the present invention be made to have good water-stagnating effect;In addition single Setting deposited reinforced concrete pile is as material of putting more energy on the inside of cylindric peripheral pile, and is respectively arranged at bored concrete pile collar tie beam and waist rail More anchor disk jet mixing stiffening piles together to substantially increase the stiffness and strength of retaining design, therefore of the invention are gone along with sb. to guard him System can reach the double effects of sealing and earth-retaining simultaneously;Retaining design of the present invention is structurally reasonable, reinforcement performance is good.
Detailed description of the invention
Fig. 1 is retaining design structure drawing of the present invention;
Fig. 2 is retaining design sectional view of the present invention;
Fig. 3 is Two bors d's oeuveres channel steel purlin cross-section diagram of the present invention;
Fig. 4 is the A-A sectional view of Two bors d's oeuveres channel steel purlin cross-section diagram of the present invention;
Fig. 5 is the B-B sectional view of Two bors d's oeuveres channel steel purlin cross-section diagram of the present invention.
In figure: peripheral pile 1, bored concrete pile 2, stiffening pile 3, dowel 4, bored concrete pile collar tie beam 5, waist rail 6, Two bors d's oeuveres channel steel purlin 7, anchor Backing plate 8, ribbing reinforcing bar 9, wedge 10.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside", " up time The orientation or positional relationship of the instructions such as needle ", " counterclockwise " is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of The description present invention and simplified description, rather than the equipment of indication or suggestion meaning or element must have a particular orientation, with spy Fixed orientation construction and operation, therefore be not considered as limiting the invention.
Fig. 1-5 is please referred to, the present invention provides a kind of technical solution:
A kind of deep basal pit maintenance construction, the single cylindrical body peripheral pile 1 including multiple lap connections, the inside of peripheral pile 1 Equipped with several continuously arranged bored concrete piles 2, bored concrete pile collar tie beam 5 and waist rail 6,5 He of bored concrete pile collar tie beam are equipped on each bored concrete pile 2 It is mounted on stiffening pile 3 at waist rail 6, dowel 4, the connection of bored concrete pile collar tie beam 5 and stiffening pile 3 are equipped with inside each stiffening pile 3 Place and the junction of waist rail 6 and stiffening pile 3 are mounted on Two bors d's oeuveres channel steel purlin 7, and the both ends of each Two bors d's oeuveres channel steel purlin 7 are all provided with There is anchor plate 8, several ribbing reinforcing bars 9 are connected between two anchor plates 8, wedge 10 is additionally provided in Two bors d's oeuveres channel steel purlin 7, puts more energy into Two bors d's oeuveres channel steel purlin 7 and wedge 10 are run through simultaneously in the end of stake 3, and extend out to outside.
In the present embodiment, peripheral pile 1 is three axes agitating pile.
Further, peripheral pile 1 is cylindric.
It is worth noting that peripheral pile 1 is using cement as curing agent, by three axis Mixing Machines in ground by weak soil Or the pressure of husky equal and curing agent is mixed and stirred, and is made soft base scleroma and is improved foundation strength, formed in construction multiple lap connections by justifying The cylindric condensation pile body that plate-like mixture is piled into.
In the present embodiment, bored concrete pile 2 is deposited reinforced concrete pile.
In the present embodiment, the tilt angle of stiffening pile 3 is 45 degree.
It is worth noting that the diameter of stiffening pile 3 is not less than Φ 400, stiffening pile 3 uses 52.5 grades of ordinary portland cements P.O52.5 is made, cement mixed weight 25%, the visual live soil layer situation appropriate adjustment of the ratio of mud 0.7;The pressure of jet mixing is answered For 15-25MPa.The advance and retreat number of the jet mixing of enlarged footing is more secondary than pile body increase, guarantees the straight of enlarged footing end 2m range Diameter reaches 700mm;Cement slurry answers uniform mixing, with mixing with the cement slurry once mixed and stirred should be finished before initial set.
Further, the spacing of two neighboring stiffening pile 3 is 1.8m, and is upper and lower twice fissure of displacement quincuncial arrangement.
In the present embodiment, dowel 4 is made of multi beam steel strand wires, and every beam steel strand wires are twisted by seven steel wires.
It is worth noting that steel strand manufacturing of the dowel 4 using multi beam Φ 15.2, intensity is 1860 grades;Every beam steel twists Line is twisted by 7 steel wires, stays 0.8m so as to tensioning outside stake, and dowel 4 uses QVM series anchorage.
Further, the position error that dowel 4 is inserted into stiffening pile 3 is no more than 30mm, and elevation of bottom error is not more than 20cm.Dowel 4 should be placed on the center of stiffening pile 3.
In the present embodiment, closely it is welded and fixed between Two bors d's oeuveres channel steel purlin 7 and anchor plate 8, between anchor plate 8 and wedge 10 Closely it is welded and fixed.
The working principle of the invention: when construction, peripheral pile 1 of first constructing, then the armored concrete for 1 inside of peripheral pile of constructing are filled Infuse stake 2, peripheral pile 1 is using cement as curing agent, by three axis Mixing Machines in ground by weak soil or sand etc. and curing agent Pressure is mixed and stirred, and so that soft base is hardened and is improved foundation strength, is formed being accumulated by discoid mixture for multiple lap connections in construction At cylindric condensation pile body, the cylindric condensation pile body of multiple lap connections can form closed water-stop curtain in underground, from And make retaining design of the present invention that there is good water-stagnating effect;In addition armored concrete is set on the inside of single cylindric peripheral pile 1 Bored concrete pile 2 is as material of putting more energy into, and respectively one of more anchor disk jet mixing of setting at the bored concrete pile collar tie beam 5 and waist rail 6 of bored concrete pile 2 Stiffening pile 3, to substantially increase the stiffness and strength of retaining design, therefore retaining design of the invention can reach sealing simultaneously With the double effects of earth-retaining;
3 interpolation dowel 4 of stiffening pile should enter rotary churning pile bottom.Dowel 4 is inserted into position error and is no more than 30mm, elevation of bottom Error is not more than 20cm.Dowel 4 should be placed on the center of stiffening pile 3, beam strength of bearing down on one after jet mixing pile body conserves 7 days It after reaching 70%, is locked after applying pretension on dowel 4, connects dowel 4 and bored concrete pile collar tie beam 5, waist rail 6 and stiffening pile 3 It connects securely;
Tensioning fixation is carried out using high-pressure oil pump and 1000KN punching jack.First with 20% tensile load before formal tensioning Pre- tensioning is primary, then with 50%, 100% tensile load grading tension, is kept for 5 minutes under tensile load, observation anchor head without Again by locking load locking after offset phenomena.
The basic principles, main features and advantages of the present invention have been shown and described above.The technology of the industry For personnel it should be appreciated that the present invention is not limited to the above embodiments, described in the above embodiment and specification is only the present invention Preference, be not intended to limit the invention, without departing from the spirit and scope of the present invention, the present invention also has various Changes and improvements, these changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention is by institute Attached claims and its equivalent thereof.

Claims (6)

1. a kind of deep basal pit maintenance construction, the single cylindrical body peripheral pile (1) including multiple lap connections, it is characterised in that: institute The inside for stating peripheral pile (1) is equipped with several continuously arranged bored concrete piles (2), is equipped with bored concrete pile on each bored concrete pile (2) Collar tie beam (5) and waist rail (6) are mounted on stiffening pile (3) at the bored concrete pile collar tie beam (5) and waist rail (6), each stiffening pile (3) internal to be equipped with dowel (4), the junction and waist rail (6) of the bored concrete pile collar tie beam (5) and stiffening pile (3) and stiffening pile (3) junction is mounted on Two bors d's oeuveres channel steel purlin (7), and the both ends of each Two bors d's oeuveres channel steel purlin (7) are equipped with anchor plate (8), several ribbing reinforcing bars (9) are connected between two anchor plates (8), are additionally provided on the Two bors d's oeuveres channel steel purlin (7) tiltedly Two bors d's oeuveres channel steel purlin (7) and wedge (10) are run through simultaneously in the end of iron (10), the stiffening pile (3), and extend out to outside.
2. deep basal pit maintenance construction according to claim 1, it is characterised in that: the peripheral pile (1) is three axes agitating pile.
3. deep basal pit maintenance construction according to claim 1, it is characterised in that: the bored concrete pile (2) is armored concrete Bored concrete pile.
4. deep basal pit according to claim 1 maintenance construction, it is characterised in that: the tilt angle of the stiffening pile (3) is 45 degree, and the spacing of two neighboring stiffening pile (3) is 1.8m.
5. deep basal pit maintenance construction according to claim 1, it is characterised in that: the dowel (4) is by multi beam steel strand wires structure At every beam steel strand wires are twisted by seven steel wires.
6. deep basal pit maintenance construction according to claim 1, it is characterised in that: the Two bors d's oeuveres channel steel purlin (7) and anchor pad Plate is closely welded and fixed between (8), is closely welded and fixed between the anchor plate (8) and wedge (10).
CN201811032717.9A 2018-09-05 2018-09-05 A kind of deep basal pit maintenance construction Pending CN109162282A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811032717.9A CN109162282A (en) 2018-09-05 2018-09-05 A kind of deep basal pit maintenance construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811032717.9A CN109162282A (en) 2018-09-05 2018-09-05 A kind of deep basal pit maintenance construction

Publications (1)

Publication Number Publication Date
CN109162282A true CN109162282A (en) 2019-01-08

Family

ID=64894199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811032717.9A Pending CN109162282A (en) 2018-09-05 2018-09-05 A kind of deep basal pit maintenance construction

Country Status (1)

Country Link
CN (1) CN109162282A (en)

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864773A (en) * 2010-04-14 2010-10-20 江苏江中集团有限公司 Deep foundation pit support process
KR20120013820A (en) * 2010-08-06 2012-02-15 이상헌 Method for Constructing Cap Beam Combined Wale For Retaining Wall
CN102518135A (en) * 2011-12-29 2012-06-27 标力建设集团有限公司 Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN202466594U (en) * 2011-12-29 2012-10-03 标力建设集团有限公司 Horizontal jet grouting soil anchoring and cast-in-place pile compound foundation pit supporting structure
CN203960880U (en) * 2014-07-22 2014-11-26 北京城建建设工程有限公司 Campshed and water-seal pile system of deep foundation pit support
CN204000901U (en) * 2014-08-07 2014-12-10 青岛海川建设集团有限公司 The vertical high slope prestressing anchor support of a kind of massif device
CN104790408A (en) * 2015-04-15 2015-07-22 叶长青 Irregular foundation pit construction method
CN105804117A (en) * 2016-05-17 2016-07-27 宁波交通工程建设集团有限公司 Formwork tie bar structure of soil arch mould in cover-excavation method for mountain highway tunnel, and construction method thereof
KR101691139B1 (en) * 2015-10-27 2017-01-09 하영판 Construction method using soil retaining wall
CN207582473U (en) * 2017-10-18 2018-07-06 上海宝冶集团有限公司 Foundation pit supporting construction
CN108360535A (en) * 2018-05-04 2018-08-03 广西建工集团基础建设有限公司 Foundation pit supporting construction based on campshed and inner support and its construction method
CN209162841U (en) * 2018-09-05 2019-07-26 江苏兴厦建设工程集团有限公司 A kind of deep basal pit maintenance construction

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101864773A (en) * 2010-04-14 2010-10-20 江苏江中集团有限公司 Deep foundation pit support process
KR20120013820A (en) * 2010-08-06 2012-02-15 이상헌 Method for Constructing Cap Beam Combined Wale For Retaining Wall
CN102518135A (en) * 2011-12-29 2012-06-27 标力建设集团有限公司 Foundation pit support construction method combining horizontal rotary jet-grouting soil bolting and bore concrete piles
CN202466594U (en) * 2011-12-29 2012-10-03 标力建设集团有限公司 Horizontal jet grouting soil anchoring and cast-in-place pile compound foundation pit supporting structure
CN203960880U (en) * 2014-07-22 2014-11-26 北京城建建设工程有限公司 Campshed and water-seal pile system of deep foundation pit support
CN204000901U (en) * 2014-08-07 2014-12-10 青岛海川建设集团有限公司 The vertical high slope prestressing anchor support of a kind of massif device
CN104790408A (en) * 2015-04-15 2015-07-22 叶长青 Irregular foundation pit construction method
KR101691139B1 (en) * 2015-10-27 2017-01-09 하영판 Construction method using soil retaining wall
CN105804117A (en) * 2016-05-17 2016-07-27 宁波交通工程建设集团有限公司 Formwork tie bar structure of soil arch mould in cover-excavation method for mountain highway tunnel, and construction method thereof
CN207582473U (en) * 2017-10-18 2018-07-06 上海宝冶集团有限公司 Foundation pit supporting construction
CN108360535A (en) * 2018-05-04 2018-08-03 广西建工集团基础建设有限公司 Foundation pit supporting construction based on campshed and inner support and its construction method
CN209162841U (en) * 2018-09-05 2019-07-26 江苏兴厦建设工程集团有限公司 A kind of deep basal pit maintenance construction

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
沈友法;李信江;李雨源;蒲梦江;: "SMW工法在13m深基坑支护施工中的应用", 建筑施工, no. 07 *
盛尧;程鹏;代鹏飞;: "浅谈组合加劲混凝土桩、预应力锚杆复合支护施工要点", 安徽建筑, no. 04 *

Similar Documents

Publication Publication Date Title
CN105155554B (en) A kind of deep basal pit of arching system
CN105401957B (en) A kind of duct pieces of shield tunnel two dimension prestressing bracing means and construction method
CH707671B1 (en) Supporting masonry element and retaining wall made of supporting masonry elements.
CN209162841U (en) A kind of deep basal pit maintenance construction
CN109162282A (en) A kind of deep basal pit maintenance construction
DE618328C (en) Support walls, dam walls, weir systems or similar structures
CH676015A5 (en)
CN209162840U (en) A kind of more anchor disk jet mixing stiffening piles
CN109162281A (en) A kind of more anchor disk jet mixing stiffening piles
JP3735424B2 (en) Retaining wall and its construction method
EP0109397B1 (en) Hollow foundation element and manufacturing method thereof
CN106759266A (en) Combination reinforcement diaphragm wall and its construction method
EP1707685A2 (en) Foundation for a high water barrier
CN107988896A (en) A kind of concrete-filled double skin steel tube bridge pier
DE102005013994B4 (en) Device for the concentrated introduction of force into unreinforced diaphragm walls in the ground
CN113882425A (en) Hole digging foundation structure for high and steep slope and construction method
CN102322060A (en) Composite prestressing retaining pile
CN206503171U (en) Concrete-pile
CN218437076U (en) Foundation pit supporting structure
DE1784137A1 (en) Production of walls made of concrete or reinforced concrete underground
CN211690317U (en) Double-cylinder pile type reinforced pile body
CN218667553U (en) Foundation pit supporting structure
EP4098802B1 (en) Geotechnical method and geotechnical arrangement
CN209538259U (en) A kind of connection structure on Small Diameter Pile reinforced concrete basis
CN212129124U (en) Device for fastening safety belt in manual hole digging pile plane operation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination