CN109158877A - Hidden grilles assembling line - Google Patents
Hidden grilles assembling line Download PDFInfo
- Publication number
- CN109158877A CN109158877A CN201811203376.7A CN201811203376A CN109158877A CN 109158877 A CN109158877 A CN 109158877A CN 201811203376 A CN201811203376 A CN 201811203376A CN 109158877 A CN109158877 A CN 109158877A
- Authority
- CN
- China
- Prior art keywords
- pipeline
- steel cable
- line
- cable assembly
- main assembly
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23P—METAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
- B23P21/00—Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control
- B23P21/004—Machines for assembling a multiplicity of different parts to compose units, with or without preceding or subsequent working of such parts, e.g. with programme control the units passing two or more work-stations whilst being composed
Abstract
The application provides Hidden grilles assembling line, including girder feeding pipeline, guide rail feeding pipeline, main assembly pipeline, the first steel cable assembly line, the second steel cable assembly line and the first jacking travelling device.Girder feeding pipeline is for conveying guardrail girder, guide rail feeding pipeline is for conveying guardrail guide rail, conveying has the working plate for being assembled to form Hidden grilles of cooperation guardrail girder and guardrail guide rail on main assembly pipeline, first steel cable assembly line is set to the side of main assembly pipeline, second steel cable assembly line is set to the other side, first jacking travelling device is located at main assembly pipeline, the first steel cable assembly line and the second steel cable assembly line, for the working plate on main assembly pipeline to be moved to the first steel cable assembly line or the second steel cable assembly line.The working plate on main assembly pipeline is moved on the first steel cable assembly line or the second steel cable assembly line by the first jacking travelling device, realizes the wirerope assembling work for carrying out Hidden grilles simultaneously on two steel cable assembly lines.
Description
[technical field]
This application involves technical field of automation equipment more particularly to Hidden grilles assembling lines.
[background technique]
Consider for the factors such as anti-fall, antitheft, either bottom house or high-story house, can all there are installation Hidden grilles
Demand, therefore the production and sales of Hidden grilles have biggish market potential.General Hidden grilles mainly pass through stealth
Guardrail girder and guardrail guide rail are assembled by guardrail production line, but existing Hidden grilles production line production efficiency is lower,
The production yields of enterprise is affected to limit enterprise's competitive force in the market.
[summary of the invention]
To solve the above-mentioned problems, this application provides a kind of Hidden grilles Assembling Productions that can be improved production efficiency
Line.
Hidden grilles assembling line, comprising:
Girder feeding pipeline, is used to convey guardrail girder;
Guide rail feeding pipeline, is used to convey guardrail guide rail;
Main assembly pipeline, input terminal are conveyed close to the output end of the girder feeding pipeline and the guide rail feeding
The output end of line, conveying, which has, on the main assembly pipeline is assembled to form stealthy shield for cooperate guardrail girder and guardrail guide rail
The working plate on column;
First steel cable assembly line is set to the side of the main assembly pipeline;
Second steel cable assembly line is set to the other side of the main assembly pipeline;
First jacking travelling device is located at the input terminal and second of the main assembly pipeline, the first steel cable assembly line
On the input terminal of steel cable assembly line, for the working plate on main assembly pipeline is mobile and branch to the first steel cable assembly line or
To assemble wirerope to the Hidden grilles in working plate on second steel cable assembly line.
The Hidden grilles assembling line further include:
Automatic screw nailing device is set on the main assembly pipeline and is located at the input terminal and the of main assembly pipeline
For beating screw to the Hidden grilles in working plate between one steel cable assembly line and the second steel cable assembly line.
The Hidden grilles assembling line further include:
Second jacking travelling device is located at the output end and second of the main assembly pipeline, the first steel cable assembly line
On the output end of steel cable assembly line, for the working plate on the first steel cable assembly line and the second steel cable assembly line is mobile and collaborate
On to main assembly pipeline.
The Hidden grilles assembling line further include:
First returns plate lifting platform, is set to the output end of the main assembly pipeline;
Second returns plate lifting platform, is set to the input terminal of the main assembly pipeline;
Working plate recycles pipeline, is set to the lower section of the main assembly pipeline and is located at described first and returns plate lifting platform
It is returned between plate lifting platform with second, described first to return plate lifting platform unloaded for receive that the main assembly pipeline exported
Working plate is simultaneously carried to downwards on working plate recycling pipeline, and unloaded working plate is delivered to by the working plate recycling pipeline
Second returns at plate lifting platform, and described second returns plate lifting platform is carried to the main assembly pipeline for unloaded working plate upwards
Input terminal is input to unloaded working plate again on the main assembly pipeline.
The Hidden grilles assembling line further includes assembling set on the first steel cable assembly line side and the second steel cable
Line side is for steel conveying rope from tension wire-feed motor.
The Hidden grilles assembling line further includes being set on the girder feeding pipeline for rushing to guardrail girder
The girder hole punched device in hole.
The Hidden grilles assembling line further includes being set on the guide rail feeding pipeline for cutting to guardrail guide rail
The cutter device of long hole.
Compared with prior art, the application has the following advantages:
This Hidden grilles assembling line is moved the working plate on main assembly pipeline by the first jacking travelling device of setting
It moves and branches on the first steel cable assembly line or the second steel cable assembly line, so as to realize on two steel cable assembly lines simultaneously
The wirerope assembling work for carrying out Hidden grilles significantly improves Hidden grilles compared with traditional Hidden grilles production line
Production efficiency then enhance enterprise's competitive force in the market to effectively improve the production yields of enterprise.
[Detailed description of the invention]
In order to more clearly explain the technical solutions in the embodiments of the present application, make required in being described below to embodiment
Attached drawing is briefly described.
Fig. 1 is the schematic diagram of Hidden grilles assembling line;
Fig. 2 is the partial schematic diagram one of Hidden grilles assembling line;
Fig. 3 is the partial schematic diagram two of Hidden grilles assembling line.
[specific embodiment]
Hidden grilles assembling line as shown in Figure 1 to Figure 3, including girder feeding pipeline 1, guide rail feeding pipeline
2, main assembly pipeline 3, the first steel cable assembly line 5, the second steel cable assembly line 6 and the first jacking travelling device 7.
Girder feeding pipeline 1 is for conveying guardrail girder, and guide rail feeding pipeline 2 is for conveying guardrail guide rail, main dress
Input terminal 31 with pipeline 3 close to the girder feeding pipeline 1 output end 11 and the guide rail feeding pipeline 2 it is defeated
Outlet 21, conveying, which has, on the main assembly pipeline 3 is assembled to form Hidden grilles for cooperate guardrail girder and guardrail guide rail
Working plate 4.Frame assembly station is equipped at the input terminal 31 of main assembly pipeline 3, frame assembly station passes through manually or certainly
Guardrail girder and the corresponding assembly of guardrail guide rail are formed Hidden grilles in working plate 4 by dynamicization mechanical equipment.The assembly of first steel cable
Line 5 is set to the side of the main assembly pipeline 3, and the second steel cable assembly line 6 is set to the other side of the main assembly pipeline 3,
First jacking travelling device 7 is located at the input terminal 51 and the second steel cable dress of the main assembly pipeline 3, the first steel cable assembly line 5
On the input terminal 61 of wiring 6, for getting up mobile by the jacking of working plate 4 on main assembly pipeline 3 and branching to the first steel cable
To assemble wirerope to the Hidden grilles in working plate 4 on assembly line 5 or the second steel cable assembly line 6.First steel cable assembly line, 5 He
Second steel cable assembly line 6 needs to go out from working plate taking-up Hidden grilles and is therefore taking when assembling wirerope to Hidden grilles
Out after Hidden grilles, what is conveyed on the first steel cable assembly line 5 and the second steel cable assembly line 6 is all unloaded working plate.This is hidden
Shape guardrail assembling line is mobile by the working plate on main assembly pipeline and branch to the by the first jacking travelling device of setting
On one steel cable assembly line or the second steel cable assembly line, so as to realize on two steel cable assembly lines while carrying out Hidden grilles
Wirerope assembling work significantly improve the production efficiency of Hidden grilles compared with traditional Hidden grilles production line, from
And the production yields of enterprise is effectively improved, then enhance enterprise's competitive force in the market.
The Hidden grilles assembling line further includes defeated set on the main assembly along the main conveying direction for assembling pipeline 3
Screw station is beaten in line sending 3 and after frame assembly station, beating screw station includes automatic screw nailing device
8, the automatic screw nailing device 8 is set on the main assembly pipeline 3 and is located at the input terminal 31 and the of main assembly pipeline 3
For beating screw to the Hidden grilles in working plate 4 between one steel cable assembly line 5 and the second steel cable assembly line 6.By setting
The stability of Hidden grilles can be reinforced in assembly by setting dozen screw station.
In addition, the Hidden grilles assembling line further includes on the main assembly pipeline 3 and defeated along main assembly
The conveying direction of line sending 3 is set to the guide rail beaten after screw station and screws station, and the guide rail station that screws is used to fill
Guardrail guide rail is connected on guardrail girder by timing by screwing.
For the ease of the unloaded working plate conveyed on the first steel cable of centralized recovery assembly line 5 and the second steel cable assembly line 6
4, the Hidden grilles assembling line further includes the second jacking travelling device 9, and the second jacking travelling device 9 is located at the main assembly
On the output end 62 of pipeline 3, the output end 52 of the first steel cable assembly line 5 and the second steel cable assembly line 6, it is used for the first steel cable
The jacking of working plate 4 on assembly line 5 and the second steel cable assembly line 6 is got up mobile and is collaborated to main assembly pipeline 3.Pass through
Two jacking travelling devices 9, which concentrate the unloaded working plate 4 conveyed on the first steel cable assembly line 5 and the second steel cable assembly line 6, to converge
On to main assembly pipeline 3, concentrate on main assembly pipeline 3 recycling unloaded working plate 4 in order to subsequent.
In order to make working plate 4 on this Hidden grilles assembling line can shuttling movement to realizing the automatic of working plate
It launches and automatic recycling, the Hidden grilles assembling line further includes first returning plate lifting platform 101, second returning plate lifting platform
102 and working plate recycle pipeline (not shown).First, which returns plate lifting platform 101, is set to the defeated of the main assembly pipeline 3
Outlet 32, second returns the input terminal 31 that plate lifting platform 102 is set to the main assembly pipeline 3, and working plate recycling pipeline is set to
The lower section of the main assembly pipeline 3 and it is located at described first and returns plate lifting platform 101 and second and return between plate lifting platform 102, institute
It states first and returns plate lifting platform 101 for receiving the working plate for the zero load that the main assembly pipeline 3 is exported and being carried to downwards
Working plate recycles on pipeline, and unloaded working plate is delivered to second and returns plate lifting platform 102 by the working plate recycling pipeline
Place, described second, which returns plate lifting platform 102, makes the input terminal 31 that unloaded working plate is carried to the main assembly pipeline 3 upwards
Unloaded working plate is input on the main assembly pipeline 3 again to carry out Hidden grilles assembling work next time.
It is described hidden for the ease of the wirerope to the first steel cable assembly line 5 and the conveying of the second steel cable assembly line 6 for assembly
Shape guardrail assembling line further includes set on 5 side of the first steel cable assembly line and 6 side of the second steel cable assembly line for defeated
Send wirerope from tension wire-feed motor 103.
The Hidden grilles assembling line further includes being set on the girder feeding pipeline 1 for rushing to guardrail girder
The girder hole punched device in hole, the Hidden grilles assembling line further include be set to the guide rail feeding pipeline 2 on for pair
Guardrail guide rail cuts the cutter device of long hole.By setting girder hole punched device and cutter device in guardrail girder and guardrail guide rail
Guardrail girder and guardrail guide rail are pre-processed before being transported to main assembly pipeline 3, so that guardrail girder and guardrail be made to lead
Rail meets matching requirements.
It is a kind of embodiment provided in conjunction with particular content as described above, does not assert the specific implementation office of the application
It is limited to these explanations.It is all approximate with the present processes, structure etc., identical, if or for being made under the application concept thereof
Dry technology deduction or replace, all should be considered as the protection scope of the application.
Claims (7)
1. Hidden grilles assembling line characterized by comprising
Girder feeding pipeline (1), is used to convey guardrail girder;
Guide rail feeding pipeline (2), is used to convey guardrail guide rail;
Main assembly pipeline (3), input terminal (31) close to the girder feeding pipeline (1) output end (11) and described lead
The output end (21) of rail feeding pipeline (2), conveying on the main assembly pipeline (3) has for cooperating guardrail girder and guardrail
The working plate (4) for being assembled to form Hidden grilles of guide rail;
First steel cable assembly line (5) is set to the side of main assembly pipeline (3);
Second steel cable assembly line (6) is set to the other side of main assembly pipeline (3);
First jacking travelling device (7) is located at the input terminal of main assembly pipeline (3), the first steel cable assembly line (5)
(51) and on the input terminal (61) of the second steel cable assembly line (6), for the working plate (4) on main assembly pipeline (3) is mobile
And it branches on the first steel cable assembly line (5) or the second steel cable assembly line (6) to assemble steel to the Hidden grilles in working plate (4)
Cord.
2. Hidden grilles assembling line according to claim 1, which is characterized in that the Hidden grilles assembling line
Further include:
Automatic screw nailing device (8) is set on main assembly pipeline (3) and is located at the input of main assembly pipeline (3)
For beating the Hidden grilles in working plate (4) between end (31) and the first steel cable assembly line (5) and the second steel cable assembly line (6)
Screw.
3. Hidden grilles assembling line according to claim 1, which is characterized in that the Hidden grilles assembling line
Further include:
Second jacking travelling device (9) is located at the output end of main assembly pipeline (3), the first steel cable assembly line (5)
(52) it and on the output end (62) of the second steel cable assembly line (6), is used for the first steel cable assembly line (5) and the second steel cable assembly line
(6) working plate (4) on is mobile and collaborates to main assembly pipeline (3).
4. Hidden grilles assembling line according to claim 3, which is characterized in that the Hidden grilles assembling line
Further include:
First returns plate lifting platform (101), is set to the output end (32) of main assembly pipeline (3);
Second returns plate lifting platform (102), is set to the input terminal (31) of main assembly pipeline (3);
Working plate recycles pipeline, is set to the lower section of main assembly pipeline (3) and is located at described first and returns plate lifting platform
(101) it is returned between plate lifting platform (102) with second, described first returns plate lifting platform (101) for receiving the main assembly conveying
The working plate for the zero load that line (3) is exported simultaneously is carried to downwards on working plate recycling pipeline, and the working plate recycles pipeline
Unloaded working plate is delivered to second to return at plate lifting platform (102), described second returns plate lifting platform (102) for unloaded tooling
The input terminal (31) that plate is carried to main assembly pipeline (3) upwards makes unloaded working plate be input to the main assembly again
On pipeline (3).
5. Hidden grilles assembling line according to claim 1, which is characterized in that the Hidden grilles assembling line
It further include oneself that steel conveying rope is used for set on the first steel cable assembly line (5) side and the second steel cable assembly line (6) side
Tension wire-feed motor (103).
6. Hidden grilles assembling line according to claim 1, which is characterized in that the Hidden grilles assembling line
It further include being set on the girder feeding pipeline (1) for the girder hole punched device to guardrail girder punching.
7. Hidden grilles assembling line according to claim 1, which is characterized in that the Hidden grilles assembling line
It further include being set on the guide rail feeding pipeline (2) for cutting the cutter device of long hole to guardrail guide rail.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811203376.7A CN109158877A (en) | 2018-10-16 | 2018-10-16 | Hidden grilles assembling line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811203376.7A CN109158877A (en) | 2018-10-16 | 2018-10-16 | Hidden grilles assembling line |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109158877A true CN109158877A (en) | 2019-01-08 |
Family
ID=64878324
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811203376.7A Pending CN109158877A (en) | 2018-10-16 | 2018-10-16 | Hidden grilles assembling line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109158877A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110703704A (en) * | 2019-09-24 | 2020-01-17 | 广东鑫光智能系统有限公司 | Cutting algorithm of invisible handrail |
CN113618376A (en) * | 2021-08-23 | 2021-11-09 | 舒城恒康儿童用品有限公司 | Automatic assembling device for wooden barrier |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201287953Y (en) * | 2008-10-28 | 2009-08-12 | 荆州神电实业有限公司 | Assembly line with parallel move lifting and lowering mechanism at both ends |
CN201367244Y (en) * | 2009-02-16 | 2009-12-23 | 大连美恒电气有限公司 | Assembling line |
CN103009056A (en) * | 2012-12-05 | 2013-04-03 | 合肥天琪机电设备有限公司 | Full-automatic assembling line for electric fuel pump cores |
CN203666261U (en) * | 2014-01-21 | 2014-06-25 | 长沙伍扬工业设备科技有限公司 | Automatic production system for assembling tire assembly |
CN104476187A (en) * | 2014-12-12 | 2015-04-01 | 苏州互强工业设备有限公司 | Multi-station automatic assembly line |
CN106584103A (en) * | 2016-12-30 | 2017-04-26 | 湖南先步信息股份有限公司 | Cyclic full-automatic assembly line |
-
2018
- 2018-10-16 CN CN201811203376.7A patent/CN109158877A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201287953Y (en) * | 2008-10-28 | 2009-08-12 | 荆州神电实业有限公司 | Assembly line with parallel move lifting and lowering mechanism at both ends |
CN201367244Y (en) * | 2009-02-16 | 2009-12-23 | 大连美恒电气有限公司 | Assembling line |
CN103009056A (en) * | 2012-12-05 | 2013-04-03 | 合肥天琪机电设备有限公司 | Full-automatic assembling line for electric fuel pump cores |
CN203666261U (en) * | 2014-01-21 | 2014-06-25 | 长沙伍扬工业设备科技有限公司 | Automatic production system for assembling tire assembly |
CN104476187A (en) * | 2014-12-12 | 2015-04-01 | 苏州互强工业设备有限公司 | Multi-station automatic assembly line |
CN106584103A (en) * | 2016-12-30 | 2017-04-26 | 湖南先步信息股份有限公司 | Cyclic full-automatic assembly line |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110703704A (en) * | 2019-09-24 | 2020-01-17 | 广东鑫光智能系统有限公司 | Cutting algorithm of invisible handrail |
CN110703704B (en) * | 2019-09-24 | 2022-10-14 | 广东鑫光智能系统有限公司 | Cutting algorithm of invisible handrail |
CN113618376A (en) * | 2021-08-23 | 2021-11-09 | 舒城恒康儿童用品有限公司 | Automatic assembling device for wooden barrier |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109158877A (en) | Hidden grilles assembling line | |
WO2007031538A3 (en) | Power supply and communication system for a passenger plane | |
DE112014005267T5 (en) | Coil unit and device for contactless energy transfer | |
CN208753529U (en) | A kind of antenna PCB multimode splicing tooling | |
CN106505470A (en) | A kind of special T-shaped wire clamp of 10kV distribution line live workings | |
CN207124281U (en) | A kind of novel elevator antenna assembly | |
CN205225619U (en) | Air condition compressor support of multipurpose | |
CN208668730U (en) | A kind of novel reinforced concrete floor slab structure | |
CN202042840U (en) | Wire harness binding band with dual clamping structure | |
CN208413533U (en) | A kind of elevator electric power carrier system | |
CN211063258U (en) | PVC power protection tube with pencil classified structure | |
CN204873360U (en) | Formula sedan -chair wall cut straightly | |
CN205713013U (en) | Combined scaffold | |
CN203529658U (en) | Installation structure of guide rail for steel pylon lifting device and steel pylon | |
CN201606570U (en) | Wiring structure on main beam of single-beam crane | |
CN203660454U (en) | Extended power supply junction box used inside and outside cabin | |
CN215238132U (en) | Plate shearing machine is used in conveyer production | |
CN203728456U (en) | Rotating platform for crane and crane | |
CN216272402U (en) | Optimize stranded conductor wire winding wiring arrangement | |
CN213205222U (en) | Novel fence board | |
CN220400942U (en) | Associated wiring terminal structure | |
CN220415719U (en) | Pump body routing structure | |
CN206947878U (en) | A kind of engine wiring harness assembly bracket device | |
CN204859746U (en) | Flexible line way board and electronic equipment | |
CN219825241U (en) | Assembled soil nail wall buckle |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190108 |
|
RJ01 | Rejection of invention patent application after publication |