CN109145376A - A kind of reservoir flood area based on CAD topographic map determines method - Google Patents

A kind of reservoir flood area based on CAD topographic map determines method Download PDF

Info

Publication number
CN109145376A
CN109145376A CN201810796100.8A CN201810796100A CN109145376A CN 109145376 A CN109145376 A CN 109145376A CN 201810796100 A CN201810796100 A CN 201810796100A CN 109145376 A CN109145376 A CN 109145376A
Authority
CN
China
Prior art keywords
flood
cad
data
file
tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810796100.8A
Other languages
Chinese (zh)
Inventor
李继清
李建昌
姚凯文
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Electric Power University
Original Assignee
North China Electric Power University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Electric Power University filed Critical North China Electric Power University
Priority to CN201810796100.8A priority Critical patent/CN109145376A/en
Publication of CN109145376A publication Critical patent/CN109145376A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F30/00Computer-aided design [CAD]
    • G06F30/20Design optimisation, verification or simulation
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/40Controlling or monitoring, e.g. of flood or hurricane; Forecasting, e.g. risk assessment or mapping

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Computer Hardware Design (AREA)
  • Evolutionary Computation (AREA)
  • Geometry (AREA)
  • General Engineering & Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of reservoir flood areas based on CAD topographic map of the analysis for belonging to flood control water disaster and prevention technique field to determine method.Elevation point data can be extracted by GIS by the pretreatment to CAD data file using existing CAD terrain data resource;Recycle GIS that elevational point is converted to dem data, finally method for flood submerged area, depth of immersion and inundated area is carried out using the dem data being converted to analyze, this method is based on the common CAD formatted data of current exploration results, be conducive to maximally utilize currently existing landform exploration results, flood risk analysis cost is reduced, human and material resources, financial resources investment are reduced;This method is flooded analysis method and flood analysis to flood using passive, method and step simplicity, and visual results are convenient for promoting as it can be seen that of less demanding to operator's technical level.

Description

A kind of reservoir flood area based on CAD topographic map determines method
Technical field
It is the invention belongs to the analysis for water disaster of controlling flood and prevention technique field, in particular to a kind of based on CAD topographic map Reservoir flood area determines method.
Background technique
China is the very frequent country of a natural calamity, and flood seriously threatens always people's lives and properties peace Complete and society stabilization and development.In recent decades, the development and utilization of water resource constantly expand, and urban and rural economies construction is rapidly sent out Exhibition, frequency that flood occurs and its caused by lose also continuous increase.Therefore, quickly, accurate, scientific simulation, prediction and It shows method for flood submerged area, to play flood control project benefit, and flood harm is mitigated with non-engineering measure, to flood control and disaster reduction It is of great significance.At present analysis of flood inundation method mainly include the following types:
(1) hydraulic model.It is divided into a peacekeeping two dimensional model.One-dimensional hydraulic model is primarily used to simulating riverway and pipe The water flow movement rule in road.Famous foreign software such as Gary storm water man- agement model (Storm Water Management Model, SWMM) and urban drainage pipe network model (Modeling of Urban Sewer, MOUSE) be all made of one-dimensional hydrodynamic force It learns principle and constructs model.This method biggest advantage is that stability is good, precision is high, computational efficiency is high.But be not suitable for solving anxious The defects of stream, the flowing such as critical flow, processing Gan Tan and relatively difficult small depth of water.Two-dimentional hydraulic model can more fully hereinafter consider The characteristic distributions of landform and building, physical motion process of the preferable simulation flood in two-dimensional space, are mainly used to simulate Square, flood storage areas etc. do not have the region of one-dimensional characteristic, can provide more detailed flowing information, and can provide flood in detail The situation of change of each hydraulic elements value in water evolution process.Currently, establishing, such model difficulty is larger, and solution is also cumbersome, It is required that data is detailed, but its simulation accuracy is relatively high.Although hydrodynamic model can accurately simulate advance of freshet Process, but since hydraulic model modeling process is complicated, modeling is costly, and versatility is bad, and a regional model cannot answer Use another area.
(2) GIS-Geographic Information System (Geographic Information System, GIS).Utilize the spatial analysis of GIS Ability can analyze submergence ratio, depth of immersion, inundated area of flood etc..Such as to plain beautiful (1995) according to Mathematical Morphology It learns and geodesic circle concept, researching and designing " expansion " simulation algorithm and submergence ratio searching algorithm of flood range of scatter, and general Model is applied to the analysis of flood inundation in city;Yang Yi etc. (2009) is based on flow path algorithm, and in conjunction with hydrologic method Establish urban storm ponding model;Liu Renyi etc. (2001) will drown out based on digital complex demodulation and be divided into active flood It is not flooded with passive, carries out flooding analytical calculation using seed spread algorithm.Flood-inundated simulation based on GIS be unable to do without number The support of elevation model (Digital Elevation Model, DEM), but survey and design department still uses calculating substantially at present Machine Computer Aided Design (Computer Aided Design, CAD) carries out exploration and design drawing, and phasic results are still CAD format Electronic data and its paper drawing the output form of expression, high-precision dem data is not widely present.
(3) analysis of flood inundation is carried out using satellite remote sensing date.Freshwater monitoring is carried out using satellite remote-sensing image data Techniqueflow mainly include solution formulation, data acquisition, data prediction, information extraction, thematic mapping and assessment report The related links such as generation.Radiant correction, geometric correction, atmospheric correction, shadow are carried out to the satellite remote-sensing image data of acquisition first As cutting and inlaying, the processing such as colored synthesis and enhancing, produce the professional remote sensing image number that can preferably reflect Flood Information According to;Relevant information is extracted by man-machine interaction method based on the satellite remote-sensing image again;Finally make thematic map, statistics phase Data are closed, and generate corresponding assessment report.However satellite remote sensing date acquisition is limited to the factors such as weather environment, revisiting period, The missing that information results in part remotely-sensed data cannot be received all the period of time, flood can not be recorded within the period for receiving information and is flooded Do not have the evolution process of range and historical information, is unable to complete the prediction of information yet.
Summary of the invention
The purpose of the present invention is to propose to a kind of reservoir flood areas based on CAD topographic map to determine method, which is characterized in that Elevation points can be extracted by GIS by the pretreatment to CAD data file using existing CAD terrain data resource According to;Recycle GIS that elevational point is converted to dem data, finally using the dem data being converted to carry out method for flood submerged area, Depth of immersion and inundated area analysis, its step are as follows:
(1) CAD topographic map elevational point segment decomposes, and the elevational point of CAD topographic map is segment, has a height in segment Journey point and its height value mark;GIS is unable to segment in Direct Recognition CAD, and segment can only be identified as polygon, is importing GIS Before need to carry out " fried block " processing using " Hunan source regulatory control " software, segment is divided into elevational point and height value and is marked;
(2) CAD elevation point data is extracted and is corrected, and the segment in CAD topographic map is by a variety of map overlays, in commercialization In software Arc GIS, the affiliated figure layer of CAD elevation point data is entitled " mark ", and " mark " is in English edition Arc GIS software For " Annotation ";It is " shapes file " by " analysis tool case-extracting tool collection-select tools " separation and Extraction, it is described " shapes file " is in one of Arc GIS file format, i.e. " Shape-file " file;
(3) CAD elevational point is converted to DEM file;The aforementioned obtained CAD elevational point that extracts is vector file, vector Dotted altitude data be converted to the DEM altitude data model of continuous planar and need to carry out interpolation, which can not be direct It is raster data by vector interpolation, therefore first interpolation is needed to generate irregular triangle network (Triangulated Irregular Network, TIN) format vectored digital triangle mesh model, then be translated into grid digital complex demodulation file;
(4) DEM subregion is divided according to flood return water line.It is each calculating cross section place and corresponding water that flood, which returns line data, Position floods analysis to carry out return water, needs to establish profile data.According to each section at a distance from dam site, by along main stem Heart line measures the mode of distance by hand, cross section place is demarcated in Arc GIS, and record the return water water level of each section part;Later, According to the cross section place of calibration, DEM is divided into several child partitions.
(5) use passive method of flooding by subregion calculating method for flood submerged area, depth, area according to average water surface curve.It is right Obtained all subregion is divided, be averaged water surface curve according to corresponding return water, using " raster symbol-base device " tool extraction flood Return water water level region below subtracts elevation and obtains depth of immersion as return water flooding area, flood return water water level;To flooded area The statistics for carrying out depth of immersion and area calculates, and it is corresponding that the available different depth of immersion of " reclassification " tool statistics can be used Inundated area.
The TIN file that the mode that the step (1), (2) extract data will lead to generation in the abnormal meeting of height value goes out Existing mistake, it is therefore desirable to use " field calculator " tool according to the data of " text " field to altitude data in " attribute list " It corrects.
The concrete mode that step (3) the CAD elevational point is converted to DEM file is in Arc GIS using " three dimensional analysis Tool box-data organizing tool collection-TIN tool set-creation TIN tool " generates TIN file, then uses " three dimensional analysis tool Case-crossover tool collection-is turnstiled lattice tool by TIN turning out device collection-TIN " TIN file is converted into DEM file.
Present invention has the advantages that this method is based on the common CAD formatted data of current exploration results, be conducive to maximize Using current existing landform exploration results, flood risk analysis cost is reduced, reduces human and material resources, financial resources investment;This method uses nothing Source floods analysis method and carries out flooding analysis to flood, and method and step is easy, and visual results are as it can be seen that operator's technical level It is of less demanding, it is convenient for promoting.
Detailed description of the invention
Fig. 1 is the flow chart for determining reservoir flood area.
Fig. 2 is the elevational point segment schematic diagram in CAD topographic map.
Fig. 3 is " shapes file " schematic diagram that CAD elevation point data is extracted.
Fig. 4 is to make amendment schematic diagram to altitude data according to the data of Text field.
Fig. 5 is the DEM schematic diagram for being converted to TIN file.
Fig. 6 is the return water hydrograph for recording each section part.
Fig. 7, Fig. 8 are the small towns range that may relate to be submerged.
Fig. 9 is 100 years one chance flood inundation on tracks depth.
Figure 10 is 50 years one chance flood inundation on tracks depth.
Specific embodiment
The present invention proposes that a kind of reservoir flood area based on CAD topographic map determines method, using existing CAD figurate number Elevation point data can be extracted by GIS by the pretreatment to CAD data file according to resource;Recycle GIS by elevational point Dem data is converted to, finally carries out method for flood submerged area, depth of immersion and inundated area point using the dem data being converted to Analysis, step are as shown in Figure 1.Include:
(1) CAD topographic map elevational point segment.CAD topographic map is subjected to " fried block " processing using " Hunan source regulatory control " software, point Solution is the segment with an elevational point and its height value mark.
(2) CAD elevation point data is extracted and is corrected, and the segment in CAD topographic map is by a variety of map overlays, in Arc In GIS, the affiliated figure layer of CAD elevation point data entitled " mark " (being in English edition Arc GIS software " Annotation ") can By " analysis tool case-extracting tool collection-select tools " from being extracted as " shapes file " (one of Arc GIS tray Formula, i.e. " Shape-file " file);
Usually there is the abnormal TIN that will lead to generation of some problems, especially height value in the data that aforesaid way extracts There is mistake in file, it is therefore desirable to use " field calculator " tool according to the data of " text " field to height in " attribute list " Number of passes evidence is corrected.
(3) CAD elevational point is converted to DEM file.The aforementioned obtained CAD elevational point that extracts is vector file, vector Dotted altitude data be converted to the DEM altitude data model of continuous planar and need to carry out interpolation, which can not be direct It is raster data by vector interpolation, therefore needs first interpolation to generate the vectored digital triangle mesh model of TIN format, then be translated into Grid digital complex demodulation file." three dimensional analysis tool box-data organizing tool collection-TIN work can be used in Arc GIS Have collection-creation TIN tool " TIN file is generated, then using " three dimensional analysis tool box-crossover tool collection-is by TIN turning out device Collection-TIN turnstilees lattice tool " TIN file is converted into DEM.
(4) DEM subregion is divided according to flood return water line.It is each calculating cross section place and equivalent water level that flood, which returns line data, Establish profile data.According to each section at a distance from dam site, by way of measuring distance by hand along main stem center line, Cross section place is demarcated in Arc GIS, and records the return water water level of each section part.Later, according to the cross section place of calibration, by DEM It is divided into several child partitions.
(5) use passive method of flooding by subregion calculating method for flood submerged area, depth, area according to average water surface curve.It is right Flooded area carries out depth of immersion and the statistics of area calculates, and is explained with reference to the accompanying drawing with embodiment.
Embodiment
Based on the overall flow of the above-mentioned analysis of flood inundation method based on CAD topographic map and DEM, the present invention is with Guangdong Province For the key water control project of the pond Han Jiang high, the pond Han Jiang high key water control project is located at that Guangdong Province Dapu County is domestic, is that the Chaozhou in the mainstream Han Jiang supplies One comprehensive key water control project of water hinge upstream takes into account power generation and shipping etc. based on controlling flood, supply water.It is transported in reservoir flood storage Used time since reservoir water conservation causes flood return water line to be lifted, and then causes to flood, flood so as to cause flood to reservoir bank Do not lose.Loss is flooded for this to be analyzed.
According to the above process, when reservoir, which meets with 50 years one, meets with 100 years one chance floods, reservoir flood retention causes after adjusting flood The more natural same frequency flood level of flood backed-up water level increases, increased retention, temporary inundation range will be caused to expand, to library It causes on periphery centainly to flood loss in area, it is necessary to study it.
When meeting with 50 years one chances and 100 years one chance floods to reservoir, flood return water caused by reservoir water conservation floods model Enclose, area, the depth of water are calculated, and calculate flood loss.According to submergence ratio on map, according to flood level and local elevation Depth of the water submerging can be obtained.It can be according to the index in terms of material products number of different frequency flood inundation on tracks further according to the inundated area ratio of different water depth Meter calculates the different water depth index in terms of material products quantity that is included, further according to the depth of the water submerging of different frequency flood in submergence ratio, It extrapolates and floods duration, can determine the loss rate of inundation of different indexs in terms of material products, and then calculate loss caused by flood.
Through counting, 50 years one chance flood temporary inundations influence main index in terms of material products and are related to 25023 people of household registration population, permanent people 14138 people of mouth, house 861619m2, 8832 mu of arable land etc..100 years one chance flood temporary inundations influence main index in terms of material products and are related to 36489 people of household registration population, 20332 people of permanent resident population, house 1256429m2, 11553 mu of arable land etc..It is public for special facility Road, transformer, transmission line of electricity, communication line, historical relic and school etc., which will receive, floods influence, wherein relating generally to second level public affairs Road, Class III highway and township road, 35kV and 10kV low-voltage distributing line, movement, connection, telecommunications and Meizhou local network route, reservoir area The transformer of range about 1~2% will receive influence when meeting extraodinary flood.According to the loss meter to family's property and special facility Calculate result known to occur 50 years one 39232.47 ten thousand yuan of flood losses of chance, 100 years one 61002.14 ten thousand yuan of flood losses of chances.According to The submergence ratio of flood and the distribution situation of the depth of water can formulate phase in conjunction with the corresponding loss caused by flood that assessment obtains in advance Measure is answered, is had for flood risk mapping production, flood control command scheduling, redemption people's lives and properties and reduction losses due to flood and waterlogging Highly important value.
Each frequency flood inundation on tracks index in terms of material products of table 1 and economic loss
Concrete operation step are as follows:
(1) basic data
(1) flood return water line.When reservoir area occurs to meet for 50 years one, 100 years one meet design flood, 50 years after Flood Routing through Reservoir One to meet flood and 100 years one chance upstream water levels be respectively 44.67m and 47.44m, flood backwater effect range are as follows: Mei Jiang is to fluffy peppery Beach power station, apart from plum rivers mouth 9.15km, apart from dam site 38.62km;Spit of fland Jiang Zhicha positive electricity station, apart from spit of fland rivers mouth 25.65km, Apart from dam site 55.13km.
(2) CAD topographic map.CAD topographic map range includes the mainstream Han Jiang from dam site to the section in the town San He, Mei Jiang from three rivers Town is to the section in fluffy peppery beach power station and the spit of fland river Jiang Congsan town to the section at tea positive electricity station and the terrain data of section two sides, base Originally the geographic range of flood temporary inundation influence is covered.
(2) flood return water floods analysis
(1) CAD topographic map elevational point segment decomposes.Using " Hunan source regulatory control " software to CAD topographic map elevational point segment (such as Shown in Fig. 2) " fried block " processing is carried out, segment is divided into elevational point and height value marks.
(2) CAD elevation point data is extracted and is corrected." fried block " treated cad file is imported into Arc GIS, by " point Analysis tool box-extracting tool collection-select tools " separation and Extraction " mark " figure layer is " shapes file " (one of Arc GIS text Part format, i.e. " Shape-file " file), as the point in Fig. 3 as extracts obtained elevational point.Later, in " attribute list " Using " field calculator " tool, altitude data is corrected according to the data of " text " field, as shown in Figure 4.
(3) CAD elevational point is converted to DEM file." three dimensional analysis tool box-data organizing tool is used in Arc GIS Collection-TIN tool set-creation TIN tool " generates TIN file, then using " three dimensional analysis tool box-crossover tool collection-is turned by TIN Tool set-TIN turnstilees lattice tool out " TIN file is converted into DEM, as shown in Figure 5.
(5) DEM subregion is divided according to flood return water line.According to each section at a distance from dam site, by along main stem center Line measures the mode of distance by hand, cross section place is demarcated in Arc GIS, and record the return water water level of each section part, in Fig. 6 A part of cross section place shown.Figure orbicular spot is the cross section place demarcated.Later, according to the cross section place of calibration, by DEM It is divided into several child partitions.
(6) use passive method of flooding by subregion calculating method for flood submerged area, depth, area according to average water surface curve.It is right Obtained all subregion is divided, be averaged water surface curve according to corresponding return water, using " raster symbol-base device " tool water intaking upper thread Water level region below is as return water flooding area.In conjunction with DEM and investigation submergence ratio is modified, obtain 100 years one meet and 50 years one chance flood temporary inundation range lines, are conducted into Google Earth, it is available flood be related to small towns range (such as Fig. 7, Shown in Fig. 8).It can be seen that, key water control project influence in the pond Han Jiang high relates generally to Dapu County Gao Po, Yin Jiang, big on Google Earth Fiber crops, three rivers and the town tea Yang Wuge, wherein the town Gao Po, hemp town are affected maximum, the silver-colored town Jiang Zhen, San He takes second place, the town Cha Yang only Being related to part soil influences minimum.
To the obtained all subregion of division, it is averaged water surface curve according to corresponding return water, using " raster symbol-base device " work Tool calculates all subregion depth of immersion.Calculated result is modified in conjunction with DEM and investigation, obtains 100 years and 50 years one chance floods Water temporary inundation depth, and expression is classified to different depth of immersion, obtain depth of immersion schematic diagram (as shown in Figure 9, Figure 10).River Stream two sides area depth of immersion is substantially between 0-14m, and depth of immersion tapers off trend along river updrift side.For water Reservoir backwater, the height difference along updrift side water level and Natural Floods become smaller, i.e., reservoir harmony height reduces, so that depth of immersion reduces, It is consistent with analysis result.
The statistics for carrying out depth of immersion and area to remaining flooded area calculates." reclassification " tool of utilization counts to obtain pair The inundated area for answering depth of immersion 0-0.5m, 0.5-1m, 1-2m, 2-4m and 4m or more, such as table 2.
Frequency flood does not correspond to depth of the water submerging and inundated area to table 2

Claims (3)

1. a kind of reservoir flood area based on CAD topographic map determines method, which is characterized in that using existing CAD figurate number Elevation point data can be extracted by GIS by the pretreatment to CAD data file according to resource;Recycle GIS by elevational point Dem data is converted to, finally carries out method for flood submerged area, depth of immersion and inundated area point using the dem data being converted to Analysis, its step are as follows:
(1) CAD topographic map elevational point segment decomposes, and the elevational point of CAD topographic map is segment, has an elevational point in segment And its height value mark;GIS is unable to segment in Direct Recognition CAD, and segment can only be identified as polygon, needs before importing GIS " fried block " processing is carried out using " Hunan source regulatory control " software, and segment is divided into elevational point and height value marks;
(2) CAD elevation point data is extracted and is corrected, and the segment in CAD topographic map is by a variety of map overlays, in business software In Arc GIS, the affiliated figure layer of CAD elevation point data is entitled " mark ", and " mark " is in English edition Arc GIS software "Annotation";It is " shapes file ", " shape by " analysis tool case-extracting tool collection-select tools " separation and Extraction Shape file " is in one of Arc GIS file format, i.e. " Shape-file " file;
(3) CAD elevational point is converted to DEM file;The aforementioned obtained CAD elevational point that extracts is vector file, the point of vector The DEM altitude data model that shape altitude data is converted to continuous planar needs to carry out interpolation, which can not be directly by arrow Amount interpolation is raster data, therefore needs first interpolation to generate the vectored digital triangle mesh model of TIN format, then be translated into grid Digital complex demodulation file;
(4) DEM subregion is divided according to flood return water line, it is each calculating cross section place and equivalent water level that flood, which returns line data, is It carries out return water and floods analysis, need to establish profile data, according to each section at a distance from dam site, by along main stem center line hand Work measures the mode of distance, cross section place is demarcated in Arc GIS, and record the return water water level of each section part;Later, according to mark DEM is divided into several child partitions by fixed cross section place;
(5) use passive method of flooding by subregion calculating method for flood submerged area, depth, area according to average water surface curve, to division Obtained all subregion is averaged water surface curve according to corresponding return water, extracts flood return water using " raster symbol-base device " tool Water level region below subtracts elevation and obtains depth of immersion as return water flooding area, flood return water water level;Flooded area is carried out The statistics of depth of immersion and area calculates, and " reclassification " tool statistics can be used, and available different depth of immersion is corresponding floods Area.
2. a kind of reservoir flood area based on CAD topographic map determines method according to claim 1, which is characterized in that institute State step (1), (2) extract data mode height value it is abnormal can when will lead to generation TIN file there is mistake, therefore It needs to correct altitude data according to the data of " text " field using " field calculator " tool in " attribute list ".
3. a kind of reservoir flood area based on CAD topographic map determines method according to claim 1, which is characterized in that institute Stating step (3) CAD elevational point and being converted to the concrete mode of DEM file is in Arc GIS using " three dimensional analysis tool box-number According to management tool collection-TIN tool set-creation TIN tool " TIN file is generated, then use " three dimensional analysis tool box-crossover tool Collection-is turnstiled lattice tool by TIN turning out device collection-TIN " TIN file is converted into DEM file.
CN201810796100.8A 2018-07-19 2018-07-19 A kind of reservoir flood area based on CAD topographic map determines method Pending CN109145376A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810796100.8A CN109145376A (en) 2018-07-19 2018-07-19 A kind of reservoir flood area based on CAD topographic map determines method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810796100.8A CN109145376A (en) 2018-07-19 2018-07-19 A kind of reservoir flood area based on CAD topographic map determines method

Publications (1)

Publication Number Publication Date
CN109145376A true CN109145376A (en) 2019-01-04

Family

ID=64800998

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810796100.8A Pending CN109145376A (en) 2018-07-19 2018-07-19 A kind of reservoir flood area based on CAD topographic map determines method

Country Status (1)

Country Link
CN (1) CN109145376A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110348324A (en) * 2019-06-20 2019-10-18 武汉大学 A kind of flood based on remote sensing big data floods analysis method and system in real time
CN110414041A (en) * 2019-06-13 2019-11-05 中国地质大学深圳研究院 It is a kind of that storm tidal mashland is established based on GIS technology and floods the method and system of analysis
CN110598302A (en) * 2019-09-06 2019-12-20 佛山世寰智能科技有限公司 Inundation analysis method, module and system based on three-dimensional real scene
CN111260714A (en) * 2020-01-17 2020-06-09 成都理工大学 Flood disaster assessment method, device, equipment and computer storage medium
CN111652777A (en) * 2020-05-15 2020-09-11 长江勘测规划设计研究有限责任公司 Flood emergency risk avoiding method
CN111949752A (en) * 2020-08-05 2020-11-17 江西省寄生虫病防治研究所 Specific biological population elevation acquisition method based on digital elevation model
CN112070849A (en) * 2020-11-11 2020-12-11 江西武大扬帆科技有限公司 Flood inundation range dynamic display method based on BIM and GIS
CN112097851A (en) * 2019-06-17 2020-12-18 深圳市振瀚信息技术有限公司 Detection method for waterlogging situation of waterlogging-prone point and waterlogging prediction method
CN112732390A (en) * 2021-01-19 2021-04-30 广东省水文局韶关水文分局 Man-machine cooperative interaction method for flood process line forecast
CN114547869A (en) * 2022-01-27 2022-05-27 中国水利水电科学研究院 Method for processing flow boundary under two-dimensional non-structural dry beach condition
CN115186040A (en) * 2022-07-27 2022-10-14 湖南省水利水电科学研究院 Method for efficiently, simply and conveniently defining flood submerging range of small river in hilly area
CN116778332A (en) * 2023-06-25 2023-09-19 重庆市地理信息和遥感应用中心(重庆市测绘产品质量检验测试中心) DEM-based river coastal easy-inundation range identification method and system

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103256914A (en) * 2012-12-27 2013-08-21 北京地拓科技发展有限公司 Method and system for calculating inundated areas of warp land dam based on DEM
CN103955565A (en) * 2014-04-08 2014-07-30 天津大学城市规划设计研究院 GIS (Geographic Information System) platform-based urban water system construction planning method
CN104460343A (en) * 2014-11-13 2015-03-25 长江水利委员会长江科学院 Riverway flood inundation simulation method based on water level monitoring data
CN104851360A (en) * 2014-02-14 2015-08-19 杭州贵仁科技有限公司 Method and system for generating flood risk map
CN104898183A (en) * 2015-05-29 2015-09-09 杭州辰青和业科技有限公司 Modeling evaluation method for urban heavy rain inundation
US20160047099A1 (en) * 2014-08-13 2016-02-18 Intermap Technologies, Inc. Systems and methods for flood zone modeling
CN105631168A (en) * 2016-03-25 2016-06-01 中国水利水电科学研究院 Real-time and efficient drainage basin flood routing visual simulation method
US20180165616A1 (en) * 2016-12-13 2018-06-14 John Sun System and Method for Producing and Distributing Information Relevant to Water Events

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103256914A (en) * 2012-12-27 2013-08-21 北京地拓科技发展有限公司 Method and system for calculating inundated areas of warp land dam based on DEM
CN104851360A (en) * 2014-02-14 2015-08-19 杭州贵仁科技有限公司 Method and system for generating flood risk map
CN103955565A (en) * 2014-04-08 2014-07-30 天津大学城市规划设计研究院 GIS (Geographic Information System) platform-based urban water system construction planning method
US20160047099A1 (en) * 2014-08-13 2016-02-18 Intermap Technologies, Inc. Systems and methods for flood zone modeling
CN104460343A (en) * 2014-11-13 2015-03-25 长江水利委员会长江科学院 Riverway flood inundation simulation method based on water level monitoring data
CN104898183A (en) * 2015-05-29 2015-09-09 杭州辰青和业科技有限公司 Modeling evaluation method for urban heavy rain inundation
CN105631168A (en) * 2016-03-25 2016-06-01 中国水利水电科学研究院 Real-time and efficient drainage basin flood routing visual simulation method
US20180165616A1 (en) * 2016-12-13 2018-06-14 John Sun System and Method for Producing and Distributing Information Relevant to Water Events

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110414041A (en) * 2019-06-13 2019-11-05 中国地质大学深圳研究院 It is a kind of that storm tidal mashland is established based on GIS technology and floods the method and system of analysis
CN110414041B (en) * 2019-06-13 2023-04-21 中国地质大学深圳研究院 Method and system for establishing storm surge and flood analysis based on GIS technology
CN112097851B (en) * 2019-06-17 2024-06-04 深圳市振瀚信息技术有限公司 Waterlogging condition detection method and waterlogging prediction method for easy waterlogging point
CN112097851A (en) * 2019-06-17 2020-12-18 深圳市振瀚信息技术有限公司 Detection method for waterlogging situation of waterlogging-prone point and waterlogging prediction method
CN110348324B (en) * 2019-06-20 2022-06-14 武汉大学 Flood real-time flooding analysis method and system based on remote sensing big data
CN110348324A (en) * 2019-06-20 2019-10-18 武汉大学 A kind of flood based on remote sensing big data floods analysis method and system in real time
CN110598302A (en) * 2019-09-06 2019-12-20 佛山世寰智能科技有限公司 Inundation analysis method, module and system based on three-dimensional real scene
CN110598302B (en) * 2019-09-06 2023-05-12 广东世寰智能科技有限公司 Inundation analysis method, module and system based on three-dimensional live-action
CN111260714A (en) * 2020-01-17 2020-06-09 成都理工大学 Flood disaster assessment method, device, equipment and computer storage medium
CN111260714B (en) * 2020-01-17 2023-07-04 成都理工大学 Flood disaster recovery assessment method, device and equipment and computer storage medium
CN111652777A (en) * 2020-05-15 2020-09-11 长江勘测规划设计研究有限责任公司 Flood emergency risk avoiding method
CN111949752A (en) * 2020-08-05 2020-11-17 江西省寄生虫病防治研究所 Specific biological population elevation acquisition method based on digital elevation model
CN111949752B (en) * 2020-08-05 2024-05-31 江西省寄生虫病防治研究所 Specific biological population elevation acquisition method based on digital elevation model
CN112070849B (en) * 2020-11-11 2021-07-09 江西武大扬帆科技有限公司 Flood inundation range dynamic display method based on BIM and GIS
CN112070849A (en) * 2020-11-11 2020-12-11 江西武大扬帆科技有限公司 Flood inundation range dynamic display method based on BIM and GIS
CN112732390A (en) * 2021-01-19 2021-04-30 广东省水文局韶关水文分局 Man-machine cooperative interaction method for flood process line forecast
CN114547869A (en) * 2022-01-27 2022-05-27 中国水利水电科学研究院 Method for processing flow boundary under two-dimensional non-structural dry beach condition
CN115186040A (en) * 2022-07-27 2022-10-14 湖南省水利水电科学研究院 Method for efficiently, simply and conveniently defining flood submerging range of small river in hilly area
CN116778332A (en) * 2023-06-25 2023-09-19 重庆市地理信息和遥感应用中心(重庆市测绘产品质量检验测试中心) DEM-based river coastal easy-inundation range identification method and system
CN116778332B (en) * 2023-06-25 2024-03-26 重庆市地理信息和遥感应用中心(重庆市测绘产品质量检验测试中心) DEM-based river coastal easy-inundation range identification method and system

Similar Documents

Publication Publication Date Title
CN109145376A (en) A kind of reservoir flood area based on CAD topographic map determines method
CN107704592A (en) A kind of flood forecasting service construction method based on WebGIS
CN108643116B (en) A kind of evaluation method of mountain area property Reservoir region river water surface width
CN107832931A (en) A kind of Modularity analysis method of plain river network region waterlogging risk
Saksena et al. Flood inundation modeling and mapping by integrating surface and subsurface hydrology with river hydrodynamics
CN106650618A (en) Random forest model-based population data spatialization method
CN108984771B (en) River channel width extraction method based on Mann-Kendall mutation test of river channel section gradient value
CN110400014A (en) A kind of coastal cities multi-source flood method for numerical simulation based on GIS grid operation
CN105893770A (en) Method for quantifying influence on basin water resources by climate change and human activities
CN110175370A (en) A kind of REGION OF WATER INJECTION OILFIELD recognition methods of city charge for remittance
Amatya et al. Application of LiDAR data for hydrologic assessments of low-gradient coastal watershed drainage characteristics
CN105261067A (en) Overground and underground integrated modeling method based on true 3D volumetric display technique and system
CN115115262A (en) Flood risk disaster assessment method
CN108681639A (en) A kind of dynamic precipitation NO emissions reduction method considering local variable and global variable
CN116401327A (en) Storm flood calculation auxiliary system for small and medium-sized watershed design in non-data area
CN106096129A (en) A kind of foot of the hill water surface scale analysis method calculated based on mountain region charge for remittance
Yonehara et al. Assessment of the tidal effect on flood inundation in a low‐lying river basin under composite future scenarios
CN110109194A (en) River grid based on grid land-surface model and vectorization flow path enters flow calculation methodologies
Susilowati et al. Micro hydropower plant potential study based on Landsat 8 operational land imager satellite data
CN112507635B (en) Method for quantitatively evaluating flood regulation and storage functions of watershed wetland
Tang et al. Review of digital elevation model (DEM) based research on China Loess Plateau
Gautam Flow routing with Semi-distributed hydrological model HEC-HMS in case of Narayani River Basin.
Qi et al. Topographical mapping of a bare tidal flat outside a mangrove area based on the waterline method and an iterative hydrodynamic model: a case study of Yingluo Bay, South China
Kang et al. Study on two-dimensional numerical simulation of rainstorm and torrent in small watershed based on lidar data
Prakasam et al. Evaluation of geomorphic resources using GIS technology: a case study of selected villages in Ausgram Block, Burdwam District, West Bengal, India

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104

RJ01 Rejection of invention patent application after publication