CN109137667A - A kind of construction method of backroad - Google Patents

A kind of construction method of backroad Download PDF

Info

Publication number
CN109137667A
CN109137667A CN201810908406.8A CN201810908406A CN109137667A CN 109137667 A CN109137667 A CN 109137667A CN 201810908406 A CN201810908406 A CN 201810908406A CN 109137667 A CN109137667 A CN 109137667A
Authority
CN
China
Prior art keywords
road
lime
soil
layer
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810908406.8A
Other languages
Chinese (zh)
Inventor
黄秀光
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Fu Ning Construction Engineering Co Ltd
Original Assignee
Tianjin Fu Ning Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Fu Ning Construction Engineering Co Ltd filed Critical Tianjin Fu Ning Construction Engineering Co Ltd
Priority to CN201810908406.8A priority Critical patent/CN109137667A/en
Publication of CN109137667A publication Critical patent/CN109137667A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C7/00Coherent pavings made in situ
    • E01C7/08Coherent pavings made in situ made of road-metal and binders
    • E01C7/32Coherent pavings made in situ made of road-metal and binders of courses of different kind made in situ
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)

Abstract

The present invention relates to a kind of construction methods of backroad, belong to technical field of road construction, it solves remote, the technical issues of economic poor area carries out road construction on a large scale, its work progress includes surveying setting-out, the finishing of excavated-in t4 roadbed, rendzinas mix, it lime-soil base making and rolls, lime-soil base maintenance, Portland Cement Concrete Surface Course making, Portland Cement Concrete Surface Course maintenance, by the way that lime soil layer is arranged below Portland Cement Concrete Surface Course, and simplify construction procedure, increase soil proportion in lime-soil base, not only meet the requirement of road construction, construction cost has been saved simultaneously, reduce construction period, allow to be applied on a large scale remote, the road construction in economic poor area.

Description

A kind of construction method of backroad
Technical field
The present invention relates to technical field of road construction, more specifically, it is related to a kind of construction method of backroad.
Background technique
Recently as the development of rural economy, as the important infrastructure for driving rural economic development, backroad Also more and more attention has been paid to.Backroad is to meet the roadbase that agricultural production and life of farmers traffic are needed and built to set It applies, is the important infrastructure for being related to rural economy social development.Cement concrete pavement with its stability good, endurance, Service life is high, antiskid and the advantages that good environmental adaptability, be increasingly used in urban road construction, and backroad is applied Work is generally directly laid with one layer of brick to form road, particularly with remote, economic poor rural area on ground.Therefore how will Reducing construction cost under the premise of cement concrete is applied to the making of backroad and guarantee meets road construction requirement becomes Urgent problem at present.
Summary of the invention
The purpose of the present invention is to provide a kind of construction methods of backroad, by setting below Portland Cement Concrete Surface Course Lime soil layer is set, and simplifies construction procedure, not only meets the requirement of road construction, while having saved construction cost, allows to The road construction in remote, economic poor area is applied on a large scale.
Above-mentioned technical purpose of the invention has the technical scheme that
A kind of construction method of backroad, includes the following steps:
(1) surveying setting-out: survey crew finds original point reference substance in situ face, then in situ face discharge road middle line with And roadbed sideline;
(2) excavated-in t4 roadbed is modified: cleaning road bed sundries is filled and led up roadbed lowered zones soil or stone fragment, using pressure Road machine rolls the roadbed place of filling and leading up, until roadbed wheel track depth is less than or equal to 5mm;
(3) rendzinas mix: paving one layer lime after resolution in road bed, and sprinkles water on its surface, then in stone Gray surface uniformly spreads out and spreads a layer of clay, and using mechanically or manually mix, mixes soil and lime tentatively, mixes while sprinkling water later It closes, and soil and lime is made to be sufficiently mixed bonding, obtain rendzinas mixture;
(4) it lime-soil base making and rolls: rendzinas mixture is uniformly paved in road bed, and using land leveller or scrape Plate flattens road surface, is rolled after leveling using the road roller road pavement of 12-15t, until roadbed wheel track depth is less than or equal to Until 5mm;
(5) lime-soil base conserves: road surface after the completion of rolling carries out sprinkling maintenance, conserves 7-10 days, to complete lime The making of soil matrix layer;
(6) Portland Cement Concrete Surface Course making: the installation template on road surface, and the one layer of cement concrete that pave in template pave After the completion, it immediately with plug-in type and flat-plate vibrator by the uniform jolt ramming of cement concrete, bubble and is flowed out until road surface is not emerged Until cement mortar, then road surface is flattened using plane machine or scraper plate, road pavement is plastered at least twice after leveling;
(7) Portland Cement Concrete Surface Course conserves: one layer of plastic foil of road surfacing after the completion of plastering is conserved 7-10 days, is torn open later Removing template, to complete the making of Portland Cement Concrete Surface Course.
By using above-mentioned technical proposal, the step of road construction includes: surveying setting-out, the finishing of excavated-in t4 roadbed, lime Native mix, lime-soil base making and roll, lime-soil base maintenance, Portland Cement Concrete Surface Course making, Portland Cement Concrete Surface Course Lime soil layer is arranged below Portland Cement Concrete Surface Course, and simplifies construction procedure for maintenance, not only meets the requirement of road construction, It saved construction cost simultaneously, reduced construction period, having allowed to apply the road in remote, economic poor area on a large scale Road construction.
Preferably, the proportion of lime and soil is 15:85-25:75 in step (4).
By using above-mentioned technical proposal, soil proportion in lime-soil base is increased, has not only saved and has been constructed into This, simultaneously because lime-soil base has good intensity and water stability, compression strength also with higher, load assignment energy Power can effectively disperse the bearing capacity of road, reduce the damage of road, improve the intensity of road.
Preferably, the gross dry weight of active calcium oxide and activated magnesia accounts for the 80- of lime gross dry weight in the lime 85wt%。
By using above-mentioned technical proposal, the adhesion strength between lime and soil is increased, lime-soil base is improved Strength and stability.
Preferably, the lime is cleared up using direct plus water, and the humidity after lime digestion is 20-30%.
By using above-mentioned technical proposal, the humidity after lime digestion is 20-30%, not only lime is made adequately to be disappeared Solution, makes active calcium oxide and activated magnesia in lime be fully converted to calcium hydroxide and magnesium hydroxide respectively, avoids simultaneously Amount of water is very few and makes to fly upward in lime and native mixed process;It avoids amount of water excessive and influences lime at paste or bulk The mixing of lime and soil.
Preferably, the plasticity index of the soil is 7-16.
By using above-mentioned technical proposal, native plasticity index is higher, and the draw degree of lime-soil base is bigger, reduces soil Plasticity index, not only increase lime-soil base crack resistance, while improving the strength and stability of lime-soil base.
Preferably, the lime-soil base with a thickness of 10-20cm, Portland Cement Concrete Surface Course with a thickness of 10-25cm.
By using above-mentioned technical proposal, the thickness of lime-soil base can require to be selected according to practice of construction, When the thickness of lime-soil base is excessively thin, difficulty of construction is not only increased, while the open and flat degree of lime-soil base may also be influenced, When the thickness of lime-soil base is blocked up, the maintenance difficulty of lime-soil base is not only increased, while increasing construction period;Cement The thickness of concrete topping can require to be selected according to practice of construction, when the thickness of Portland Cement Concrete Surface Course is excessively thin, no It is only difficult to ensure the intensity of road, while increasing difficulty of construction, when Portland Cement Concrete Surface Course is blocked up, increase cement concrete Construction period and construction cost.
Preferably, the lime-soil base making is multilayer, and the thickness of every layer of lime-soil base is identical.
By using above-mentioned technical proposal, the number of plies of lime-soil base can be selected according to actual needs, to full Foot difference road construction requirement, while the thickness of every layer of lime-soil base is identical, reduces difficulty of construction, accelerates construction indirectly Period.
Preferably, the strength grade of the cement concrete is one of C25, C30, C35, C40.
By using above-mentioned technical proposal, cement concrete can require to be selected according to practice of construction, meet Under the premise of the construction requirement of road, construction cost is reduced.
Preferably, the two sides of the road width that making has hardening road, and hardens road respectively is 0.5-1m, hardens road Length and road equal length, the height of the height and road of hardening road is equal.
By using above-mentioned technical proposal, hardening road is set in road both sides, not only facilitates pedestrian in both sides of the road row It walks, reduces traffic accident, the height of the height and road surface of hardening road is equal, ensure that the smooth of whole road surface, keeps away Exempt from whole road surface height injustice occur and influence whole road or cause traffic accident.
Preferably, the hardening road is prepared using following methods:
(1) surveying setting-out: survey crew finds original point reference substance in situ face, and roadbed side is then discharged in situ face Line;
(2) excavated-in t4 roadbed is modified: cleaning hardening road bed sundries fills out hardening roadbed lowered zones soil or stone fragment It is flat, the hardening roadbed place of filling and leading up is rolled using road roller, until hardening road bed wheelmark depth is less than or equal to 5mm;
(3) it rendzinas mix: sprinkles water in the lime that hardening road bed paves one layer after resolution, and on its surface, then It uniformly spreads out and spreads a layer of clay on lime surface, using mechanically or manually mix, mix soil and lime tentatively, sprinkle water one on one side later Side mix, and soil and lime is made to be sufficiently mixed bonding, obtain rendzinas mixture;
(4) it lime-soil base making and rolls: rendzinas mixture uniformly being paved in hardening road bed, and uses land leveller Or scraper plate flattens hard surface, is rolled using the road roller of 12-15t to hard surface after leveling, until hard surface wheel Until mark depth is less than or equal to 5mm;
(5) lime-soil base conserves: hard surface after the completion of rolling carries out sprinkling maintenance, conserves 7-10 days, to complete The making of lime-soil base;
(6) mix of stone fragment soil: paving one layer of stone fragment on lime-soil base surface, and sprinkles water on its surface, makes stone fragment It is all wet, it then uniformly spreads out and spreads a layer of clay on stone fragment surface, using mechanically or manually mix, keep soil and stone fragment tentatively mixed It closes, mixs on one side sprinkle water while later, and soil and stone fragment is made to be sufficiently mixed bonding, obtain stone fragment soil mixture;
(7) stone fragment layer making and roll: stone fragment soil mixture uniformly paved in lime-soil base, and using land leveller or Scraper plate flattens road surface, is rolled using the road roller of 12-15t to hard surface after leveling, until hard surface wheelmark depth Until less than or equal to 5mm, to complete the making of stone fragment layer;
(8) laying of water-permeable brick surface layer: stone fragment layer surface after the completion of rolling is laid with one layer of water-permeable brick, and water-permeable brick is uniformly spread It is located at stone fragment layer surface and forms surface layer, after the completion of laying, flattened water-permeable brick using flat-plate vibrator, to complete The laying of water-permeable brick surface layer.
By using above-mentioned technical proposal, in rural area due to lacking drainage system, encounter rainfall it is larger when, it is easy to Both sides of the road form ponding and influence the passage of road, and water-permeable brick surface layer are arranged in both sides of the road, and since water-permeable brick has The characteristics of quickly absorbing moisture and permeating water downwards, when encountering larger rainfall, rainwater flows to water-permeable brick surface layer, and permeable Make rainwater rapid osmotic to underground under the action of brick, prevents rainwater from influencing the passage of whole road in road surface formation ponding, together When water-permeable brick lower layer use stone fragment layer, saved construction cost.
In conclusion the invention has the following advantages:
The first, the construction method of backroad of the invention, by the way that lime soil layer, and letter are arranged below Portland Cement Concrete Surface Course Change construction procedure, not only meets the requirement of road construction, while having saved construction cost, allow to be applied on a large scale inclined Far, the road construction in economic poor area.
The second, it is further saved by increasing content native in lime-soil base in the case where meeting construction requirement Production cost reduces the damage of road, improves the intensity of road.
Third, the number of plies of lime-soil base can be selected according to construction requirement, and the thickness of every layer of lime-soil base It is identical, difficulty of construction is reduced, accelerates construction period indirectly.
4th, it by the way that hardening road is arranged in road both sides, not only facilitates pedestrian and walks in both sides of the road, reduce traffic The generation of accident, while hardening the water-permeable brick surface layer on road has good water permeability, prevent rainwater form ponding on road surface and Influence the passage of whole road.
Specific embodiment
Invention is further described in detail with reference to embodiments.It should be understood that described in the embodiment of the present invention Preparation method is only used for illustrating the present invention, rather than limiting the invention, to this hair under concept thereof of the invention The simple modifications of bright preparation method belong to the scope of protection of present invention.
A kind of embodiment 1, construction method of backroad, includes the following steps:
(1) surveying setting-out: according to construction requirement, survey crew finds original point reference substance in situ face, then in situ face Upper release road middle line and roadbed sideline;
(2) excavated-in t4 roadbed is modified: cleaning road bed sundries avoids sundries from influencing the construction of road, by roadbed lowered zones It is filled and led up with soil or stone fragment, it is preferably native, and the roadbed place of filling and leading up is rolled using road roller, until roadbed wheel track depth is less than or waits Until 5mm, preferably 3mm prevents road bed from out-of-flatness occur and influences subsequent construction;
(3) rendzinas mix: pave one layer lime after resolution in road bed, wherein in lime active calcium oxide and The gross dry weight of activated magnesia accounts for the 80-85wt% of lime gross dry weight, preferably 82wt%, and lime is using directly plus by the way of water It is cleared up, after clearing up, after resolution the humidity of lime be 20-30%, preferably 25%, later on the surface of lime Spray water makes lime surface wet, prevents lime fugitive dust from influencing construction environment, then uniformly spreads out and spread a layer of clay on lime surface, And the plasticity index of soil is 7-16, soil can according to need one of selection sandy soil, silty soil, and preferably plasticity index is 12 sandy soil, it is preferably mechanical using mechanically or manually mix, for mitigating the labor intensity of operator, make Tu Heshi Ash is tentatively mixed, and is mixed on one side sprinkle water while later, and soil and lime is made to be sufficiently mixed bonding, is obtained rendzinas and is mixed Material, and the proportion of lime and soil is 15:85-25:75, in order to improve the intensity of road and save production cost, lime and soil Proportion be preferably 20:80;
(4) it lime-soil base making and rolls: rendzinas mixture is uniformly paved in road bed, and using land leveller or scrape Plate flattens road surface, preferably land leveller, is rolled after leveling using the road roller road pavement of 12-15t, in order to save production And accelerate construction efficiency, the road roller road pavement of preferably 13t is rolled, until roadbed wheel track depth is less than or equal to 5mm Until, preferably 3mm guarantees the flatness on road surface;
(5) lime-soil base conserves: road surface progress sprinkling maintenance after the completion of rolling, maintenance 7-10 days, and preferably 8 days, from And complete the making of lime-soil base, lime-soil base with a thickness of 10-20cm, in order to guarantee lime-soil base intensity and Save the cost, the thickness of lime-soil base are preferably 15cm, and lime-soil base can according to need making multilayer, and every layer of lime The thickness of soil matrix layer is identical;
(6) Portland Cement Concrete Surface Course making: installation template, and the one layer of coagulating cement that pave in template are distinguished in road surface two sides Soil, cement concrete can require be selected according to practice of construction, the strength grade of cement concrete is C25, C30, C35, One of C40, preferably strength grade are the cement concrete of C25, after the completion of paving, use plug-in type and flat vibration immediately Dynamic device is by the uniform jolt ramming of cement concrete, until road surface does not emerge bubble and outflow water cement mortar, then using plane machine or Scraper plate flattens road surface, preferably scraper plate, and road pavement is plastered at least twice after leveling, wherein carrying out after leveling primary Plastering, terminates substantially in cement concrete bleeding, and in pre-hardening state but still wet surface when carries out one-coat plastering, this two It can also repeatedly be plastered as needed between secondary plastering;
(7) Portland Cement Concrete Surface Course conserves: one layer of plastic foil of road surfacing after the completion of plastering, maintenance 7-10 days, and preferably 8 It, form removal, avoids road pavement from damaging in form removal later, so that the making of Portland Cement Concrete Surface Course is completed, Portland Cement Concrete Surface Course with a thickness of 10-25cm, in order to guarantee the intensity and save the cost of Portland Cement Concrete Surface Course, cement is mixed The thickness of solidifying soil surface layer is preferably 15cm.
Quality testing is carried out to the road construction completed under priority condition, wherein the compactness of lime-soil base is more than or equal to 97%, and 7 days without lateral confinement intensity, the compression strength of Portland Cement Concrete Surface Course is 25MPa.
The step of road construction includes: surveying setting-out, the finishing of excavated-in t4 roadbed, rendzinas mix, lime-soil base making And roll, lime-soil base maintenance, the maintenance of Portland Cement Concrete Surface Course making, Portland Cement Concrete Surface Course, in Portland Cement Concrete Surface Course Lime soil layer is arranged in lower section, since lime-soil base has good intensity and water stability, while resistance to compression also with higher Intensity, load assignment ability can effectively disperse the bearing capacity of road, reduce the damage of road, improve the strong of road Degree, while simplifying construction procedure, not only meet the requirement of road construction, but also saved construction cost, reduced construction period, Also there is good compression strength simultaneously, allow to apply the road construction in remote, economic poor area on a large scale.
It is in place of embodiment 2, a kind of construction method of backroad, the present embodiment and the difference of embodiment 1, road Making has hardening road respectively for two sides, and the width for hardening road can according to need and be set as 0.5-1m, and preferably 0.8m hardens road Length and road equal length, the height of the height and road of hardening road is equal, hardening road using following methods preparation:
(1) surveying setting-out: according to construction requirement, survey crew finds original point reference substance in situ face, then in situ face Upper release road middle line and roadbed sideline;
(2) excavated-in t4 roadbed is modified: cleaning hardening road bed sundries avoids sundries from influencing the construction of hardening road, will harden Roadbed lowered zones soil or stone fragment are filled and led up, preferably native, and are rolled using road roller to the hardening roadbed place of filling and leading up, until hardening Until road bed wheelmark depth is less than or equal to 5mm, preferably 3mm, prevent hardening road bed from out-of-flatness occur and after influencing Continuous construction;
(3) rendzinas mix: in the lime that hardening road bed paves one layer after resolution, wherein active oxidation in lime The gross dry weight of calcium and activated magnesia accounts for the 80-85wt% of lime gross dry weight, preferably 82wt%, and lime uses and directly adds water Mode clears up it, after clearing up, after resolution the humidity of lime be 20-30%, preferably 25%, later in lime Surface spray water makes lime surface wet, prevents lime fugitive dust from influencing construction environment, then uniformly paves one layer on lime surface Soil, and the plasticity index of soil is 7-16, soil can according to need one of selection sandy soil, silty soil, and preferably plasticity refers to The sandy soil that number is 12, it is preferably mechanical using mechanically or manually mix, for mitigating the labor intensity of operator, make soil It is tentatively mixed with lime, is mixed on one side sprinkle water while later, and soil and lime is made to be sufficiently mixed bonding, obtained rendzinas and mix Material is closed, and the proportion of lime and soil is 15:85-25:75, in order to improve the intensity on hardening road and save production cost, lime Proportion with soil is preferably 20:80;
(4) it lime-soil base making and rolls: rendzinas mixture uniformly being paved in hardening road bed, and uses land leveller Or scraper plate flattens hard surface, preferably land leveller, is rolled using the road roller of 12-15t to hard surface after leveling, In order to save production and accelerate construction efficiency, the preferably road roller of 13t rolls hard surface, until hard surface wheel Until mark depth is less than or equal to 5mm, preferably 3mm guarantees the flatness of hard surface;
(5) lime-soil base conserves: hard surface progress sprinkling maintenance after the completion of rolling, maintenance 7-10 days, and preferably 8 It, to complete the making of lime-soil base, lime-soil base with a thickness of 10-20cm, in order to guarantee the strong of lime-soil base Degree and save the cost, the thickness of lime-soil base are preferably 15cm, and lime-soil base can according to need making multilayer, and every The thickness of layer lime-soil base is identical;
(6) mix of stone fragment soil: paving one layer of stone fragment on lime-soil base surface, and sprinkles water on its surface, makes stone fragment It is all wet, it then uniformly spreads out and spreads a layer of clay on stone fragment surface, using mechanically or manually mix, preferably machine mixing, make Soil and stone fragment tentatively mix, and mix on one side sprinkle water while later, and soil and stone fragment is made to be sufficiently mixed bonding, obtain stone fragment Native mixture, and the proportion of stone fragment and soil is 10:90-20:80, is produced into improve intensity and the saving on hardening road This, the proportion of stone fragment and soil is preferably 15:85;
(7) stone fragment layer making and roll: stone fragment soil mixture uniformly paved in lime-soil base, and using land leveller or Scraper plate flattens hard surface, preferably scraper plate, is rolled using the road roller of 12-15t to hard surface after leveling, in order to It saves production and accelerates construction efficiency, the preferably road roller of 13t rolls hard surface, until hard surface wheelmark is deep Until degree is less than or equal to 5mm, preferably 3mm guarantees the flatness of hard surface, so that the making of stone fragment layer is completed, it is broken Aggregate chips layer with a thickness of 10-20cm, in order to guarantee the intensity and save the cost of stone fragment layer, the thickness of stone fragment layer is preferably 15cm;
(8) laying of water-permeable brick surface layer: stone fragment layer surface after the completion of rolling is laid with one layer of water-permeable brick, convenient for make road surface with And the rainwater in hardening road face infiltrates through underground as early as possible, avoids the face on road surface and hardening road from forming ponding, water-permeable brick is uniform It is laid on stone fragment layer surface and forms surface layer, after the completion of laying, flattened water-permeable brick using flat-plate vibrator, thus complete At the laying of water-permeable brick surface layer.
Quality testing is carried out to the hardening road construction completed under priority condition, wherein the compactness of lime-soil base is in being equal to 97%, and 7 days without lateral confinement intensity, the compactness of stone fragment layer is more than or equal to 97%, and the compression strength of water-permeable brick surface layer is 54MPa.
By the way that hardening road is arranged in road both sides, not only facilitates pedestrian and walk in both sides of the road, reduce traffic accident Generation, rural area due to lack drainage system, encounter rainfall it is larger when, it is easy to both sides of the road formed ponding and influence The passage of whole road, and water-permeable brick surface layer is set in both sides of the road, and since water-permeable brick has quickly absorption moisture and makes water Downwards the characteristics of infiltration, when encountering larger rainfall, rainwater flows to water-permeable brick surface layer, and keeps rainwater fast under the action of water-permeable brick Speed penetrates into underground, prevents rainwater from influencing the passage of whole road in road surface formation ponding.

Claims (10)

1. a kind of construction method of backroad, characterized by the following steps:
(1) surveying setting-out: survey crew finds original point reference substance in situ face, then in situ face discharge road middle line with And roadbed sideline;
(2) excavated-in t4 roadbed is modified: cleaning road bed sundries is filled and led up roadbed lowered zones soil or stone fragment, using pressure Road machine rolls the roadbed place of filling and leading up, until roadbed wheel track depth is less than or equal to 5mm;
(3) rendzinas mix: paving one layer lime after resolution in road bed, and sprinkles water on its surface, then in stone Gray surface uniformly spreads out and spreads a layer of clay, and using mechanically or manually mix, mixes soil and lime tentatively, mixes while sprinkling water later It closes, and soil and lime is made to be sufficiently mixed bonding, obtain rendzinas mixture;
(4) it lime-soil base making and rolls: rendzinas mixture is uniformly paved in road bed, and using land leveller or scrape Plate flattens road surface, is rolled after leveling using the road roller road pavement of 12-15t, until roadbed wheel track depth is less than or equal to Until 5mm;
(5) lime-soil base conserves: road surface after the completion of rolling carries out sprinkling maintenance, conserves 7-10 days, to complete lime The making of soil matrix layer;
(6) Portland Cement Concrete Surface Course making: the installation template on road surface, and the one layer of cement concrete that pave in template pave After the completion, it immediately with plug-in type and flat-plate vibrator by the uniform jolt ramming of cement concrete, bubble and is flowed out until road surface is not emerged Until cement mortar, then road surface is flattened using plane machine or scraper plate, road pavement is plastered at least twice after leveling;
(7) Portland Cement Concrete Surface Course conserves: one layer of plastic foil of road surfacing after the completion of plastering is conserved 7-10 days, is torn open later Removing template, to complete the making of Portland Cement Concrete Surface Course.
2. a kind of construction method of backroad according to claim 1, it is characterised in that: lime and soil in step (4) Proportion be 15:85-25:75.
3. a kind of construction method of backroad according to claim 1, it is characterised in that: active oxidation in the lime The gross dry weight of calcium and activated magnesia accounts for the 80-85wt% of lime gross dry weight.
4. a kind of construction method of backroad according to claim 1, it is characterised in that: the lime, which uses, directly to be added Water is cleared up, and the humidity after lime digestion is 20-30%.
5. a kind of construction method of backroad according to claim 1, it is characterised in that: the plasticity index of the soil is 7-16。
6. a kind of construction method of backroad according to claim 1, it is characterised in that: the thickness of the lime-soil base Degree be 10-20cm, Portland Cement Concrete Surface Course with a thickness of 10-25cm.
7. a kind of construction method of backroad according to claim 1, it is characterised in that: the lime-soil base making Thickness for multilayer, every layer of lime-soil base is identical.
8. a kind of construction method of backroad according to claim 1, it is characterised in that: the cement concrete it is strong Spending grade is one of C25, C30, C35, C40.
9. a kind of construction method of backroad according to claim 1, it is characterised in that: distinguish the two sides of the road Making has hardening road, and the width for hardening road is 0.5-1m, hardens the length on road and the equal length of road, hardens the height on road It is equal with the height of road.
10. a kind of construction method of backroad according to claim 9, it is characterised in that: the hardening road use with The preparation of lower section method:
(1) surveying setting-out: survey crew finds original point reference substance in situ face, and roadbed side is then discharged in situ face Line;
(2) excavated-in t4 roadbed is modified: cleaning hardening road bed sundries fills out hardening roadbed lowered zones soil or stone fragment It is flat, the hardening roadbed place of filling and leading up is rolled using road roller, until hardening road bed wheelmark depth is less than or equal to 5mm;
(3) it rendzinas mix: sprinkles water in the lime that hardening road bed paves one layer after resolution, and on its surface, then It uniformly spreads out and spreads a layer of clay on lime surface, using mechanically or manually mix, mix soil and lime tentatively, sprinkle water one on one side later Side mix, and soil and lime is made to be sufficiently mixed bonding, obtain rendzinas mixture;
(4) it lime-soil base making and rolls: rendzinas mixture uniformly being paved in hardening road bed, and uses land leveller Or scraper plate flattens hard surface, is rolled using the road roller of 12-15t to hard surface after leveling, until hard surface wheel Until mark depth is less than or equal to 5mm;
(5) lime-soil base conserves: hard surface after the completion of rolling carries out sprinkling maintenance, conserves 7-10 days, to complete The making of lime-soil base;
(6) mix of stone fragment soil: paving one layer of stone fragment on lime-soil base surface, and sprinkles water on its surface, makes stone fragment It is all wet, it then uniformly spreads out and spreads a layer of clay on stone fragment surface, using mechanically or manually mix, keep soil and stone fragment tentatively mixed It closes, mixs on one side sprinkle water while later, and soil and stone fragment is made to be sufficiently mixed bonding, obtain stone fragment soil mixture;
(7) stone fragment layer making and roll: stone fragment soil mixture uniformly paved in lime-soil base, and using land leveller or Scraper plate flattens road surface, is rolled using the road roller of 12-15t to hard surface after leveling, until hard surface wheelmark depth Until less than or equal to 5mm, to complete the making of stone fragment layer;
(8) laying of water-permeable brick surface layer: stone fragment layer surface after the completion of rolling is laid with one layer of water-permeable brick, and water-permeable brick is uniformly spread It is located at stone fragment layer surface and forms surface layer, after the completion of laying, flattened water-permeable brick using flat-plate vibrator, to complete The laying of water-permeable brick surface layer.
CN201810908406.8A 2018-08-10 2018-08-10 A kind of construction method of backroad Pending CN109137667A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810908406.8A CN109137667A (en) 2018-08-10 2018-08-10 A kind of construction method of backroad

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810908406.8A CN109137667A (en) 2018-08-10 2018-08-10 A kind of construction method of backroad

Publications (1)

Publication Number Publication Date
CN109137667A true CN109137667A (en) 2019-01-04

Family

ID=64792720

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810908406.8A Pending CN109137667A (en) 2018-08-10 2018-08-10 A kind of construction method of backroad

Country Status (1)

Country Link
CN (1) CN109137667A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021388A (en) * 2019-12-14 2020-04-17 中冶天工集团有限公司 Construction waste house-dismantling soil treatment soft foundation structure and construction method thereof
CN112681044A (en) * 2020-12-22 2021-04-20 中建六局土木工程有限公司 Portable construction method for mucky soil layer road
CN113718579A (en) * 2021-07-30 2021-11-30 中铁十九局集团有限公司 Environment-friendly ground construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1052520A (en) * 1990-11-24 1991-06-26 李凤云 Technology for constructing highway with lime-earth bed and thin asphalt surface
CN201534947U (en) * 2009-07-04 2010-07-28 商丘市豫东公路勘察设计有限公司 Yudong plain county rural highway cement concrete pavement structure
CN102787547A (en) * 2012-08-22 2012-11-21 李凤云 Designing and constructing method for semi-rigid base asphalt pavement
CN102839580A (en) * 2012-08-22 2012-12-26 李应芝 High-dosage lime stabilized soil subbase layer construction method
KR101827960B1 (en) * 2017-03-17 2018-02-13 김균호 Brige pavement layer including latex modified concrete and construction method of the same

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1052520A (en) * 1990-11-24 1991-06-26 李凤云 Technology for constructing highway with lime-earth bed and thin asphalt surface
CN201534947U (en) * 2009-07-04 2010-07-28 商丘市豫东公路勘察设计有限公司 Yudong plain county rural highway cement concrete pavement structure
CN102787547A (en) * 2012-08-22 2012-11-21 李凤云 Designing and constructing method for semi-rigid base asphalt pavement
CN102839580A (en) * 2012-08-22 2012-12-26 李应芝 High-dosage lime stabilized soil subbase layer construction method
KR101827960B1 (en) * 2017-03-17 2018-02-13 김균호 Brige pavement layer including latex modified concrete and construction method of the same

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JI****72V: "水泥混凝土,石灰土施工工艺 水泥混凝土路面施工组织设计", 《HTTPS://WWW.JINCHUTOU.COM/P-26294871.HTML》 *
刘玉麟: "《乡村公路》", 30 November 1987, 天津科学技术出版社 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111021388A (en) * 2019-12-14 2020-04-17 中冶天工集团有限公司 Construction waste house-dismantling soil treatment soft foundation structure and construction method thereof
CN112681044A (en) * 2020-12-22 2021-04-20 中建六局土木工程有限公司 Portable construction method for mucky soil layer road
CN112681044B (en) * 2020-12-22 2024-04-23 中建六局土木工程有限公司 Portable construction method for mucky soil layer road
CN113718579A (en) * 2021-07-30 2021-11-30 中铁十九局集团有限公司 Environment-friendly ground construction method

Similar Documents

Publication Publication Date Title
CN107059573B (en) Construction method for solidifying soil body as road water stabilization layer
CN108797292A (en) A kind of cement concrete cracks breakage raggle formula patching
CN109914178B (en) Construction method for integrally paving road by using bio-enzyme curing material
CN101691736A (en) Construction method for reconstructing old concrete pavement by paving asphalt-concrete surface layer
CN207227890U (en) A kind of environment protection asphalt pavement structure
CN106759126B (en) Construction method of side slope support drainage channel
CN109137667A (en) A kind of construction method of backroad
CN103882788B (en) Based on the method for constructing roadway of the modification roller compacted concrete surface layer of enzyme soil cured substrate layer
CN105463967A (en) Water-permeable wear-resistant garden path and construction method thereof
CN105040554A (en) Garden path structure and paving construction technology thereof
CN113430887A (en) Municipal road sponge drainage noise reduction comprehensive treatment construction process
KR20190006233A (en) Construction method of water-permeable pavement with excellent properties of stability, economy and conduct ability for pavement and road
CN113123197A (en) Method and process for stabilizing macadam base with cement
CN207259961U (en) A kind of Reflection Cracking type heavy traffic drainage pavement paving structure
CN205368926U (en) Garden way supercrust structure that water permeability is strong
CN114108408A (en) Municipal road engineering pavement construction technology
CN108221533A (en) A kind of laying method in backroad face
CN106677003A (en) Pervious concrete structure and preparation method thereof
CN213772779U (en) Concrete road surface structure permeates water
CN207244376U (en) A kind of creepage concrete compression-resistance pavement structure
CN207846123U (en) Reinforced structure complex
CN108342939A (en) A kind of anti-ponding type asphalt pavement construction method
CN111549603A (en) Pavement considering water load coupling and construction method thereof
CN204780555U (en) Structure that repaired in bituminous paving hole groove
CN105155387A (en) Garden road structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104

RJ01 Rejection of invention patent application after publication