CN109132844B - Anchor rod hanging bracket and anchor rod combined installation method - Google Patents

Anchor rod hanging bracket and anchor rod combined installation method Download PDF

Info

Publication number
CN109132844B
CN109132844B CN201811157238.XA CN201811157238A CN109132844B CN 109132844 B CN109132844 B CN 109132844B CN 201811157238 A CN201811157238 A CN 201811157238A CN 109132844 B CN109132844 B CN 109132844B
Authority
CN
China
Prior art keywords
anchor rod
anchor
hanger
hanging frame
rods
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201811157238.XA
Other languages
Chinese (zh)
Other versions
CN109132844A (en
Inventor
夏江南
王海伟
刁先觉
陈杨
刘怀刚
高世强
肖向荣
檀兴华
赵升辉
吴曼
葛纪平
陈振宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge South China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge South China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN202210023686.0A priority Critical patent/CN114408727A/en
Priority to CN201811157238.XA priority patent/CN109132844B/en
Publication of CN109132844A publication Critical patent/CN109132844A/en
Application granted granted Critical
Publication of CN109132844B publication Critical patent/CN109132844B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/22Rigid members, e.g. L-shaped members, with parts engaging the under surface of the loads; Crane hooks
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/14Towers; Anchors ; Connection of cables to bridge parts; Saddle supports
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention provides an anchor rod hanging bracket and an anchor rod combined installation method. The anchor rod hanging frame comprises a hanging frame and a plurality of transverse arrangement and bearing flat linkages which are fixedly connected with the hanging frame and used for bearing anchor rods, wherein the hanging frame comprises a plurality of hanging frame upright posts, the bearing flat linkages are fixedly connected with the hanging frame upright posts, limiting pieces used for limiting the positions of the anchor rods are arranged on the bearing flat linkages in pairs, and clamping openings used for clamping the anchor rods are formed between the same pair of limiting pieces in a limiting mode. The anchor rod combination installation method applies the anchor rod hanging bracket and comprises the following steps: assembling the anchor rod hanging frame; sequentially hoisting anchor rods on the anchor rod hanging frame; and integrally lifting the anchor rod hanging frame with the anchor rod mounted to a preset position. Therefore, the anchor rod hanging bracket and the anchor rod combined installation method can carry or hang groups of anchor rods to preset positions in batches, avoid mechanical labor of independent lifting, improve construction efficiency, and also can keep the shape of the anchor rods in the lifting process and avoid deformation affecting performance.

Description

Anchor rod hanging bracket and anchor rod combined installation method
Technical Field
The invention relates to the technical field of building construction, in particular to a method for installing an anchor rod hanging bracket and an anchor rod combination.
Background
In the construction of large buildings such as bridges, it is necessary to install a plurality of anchor rods for some building components, and there are many components for installing the anchor rods.
At present, constructors need to carry and lift each independent anchor rod, the repeated mechanical labor is more, the construction time is prolonged, and the completion date is prolonged. The anchor rods which are lifted independently are also required to be lifted to the corresponding building structure, and then are installed in the independent alignment positions.
In addition, when a single anchor rod is lifted, the anchor rod is easy to bend due to the fact that the dead weight is large, irreversible deformation occurs, and the service life of the anchor rod is influenced.
Disclosure of Invention
The invention aims to provide an anchor rod hanging frame capable of hanging or carrying in batches and keeping the shape of an anchor rod and an anchor rod combination installation method matched with the anchor rod hanging frame.
In order to achieve the purpose, the invention adopts the following technical scheme:
the invention provides an anchor rod hanging frame which comprises a hanging frame and a plurality of bearing parallel joints which are fixedly connected with the hanging frame and used for bearing anchor rods, wherein the hanging frame comprises a plurality of hanging frame upright posts, the bearing parallel joints are fixedly connected with the hanging frame upright posts, limiting pieces used for limiting the positions of the anchor rods are arranged on the bearing parallel joints, the limiting pieces are arranged in pairs, and clamping openings used for clamping the anchor rods are defined between the same pair of limiting pieces.
Preferably, diagonal braces are arranged between the two hanger upright posts of the hanger frame, and the diagonal braces are arranged on two opposite side surfaces of the hanger frame.
Preferably, the bearing parallel connection comprises a plurality of first flat beams and second flat beams which are intersected with the hanging bracket upright post at the same time, and stiffening beams for reinforcing bearing capacity are further vertically arranged between the plurality of second flat beams.
Preferably, the bearing parallel connection is provided with multiple layers along the height direction of the hanger upright post.
Preferably, the limiting piece adopts at least one limiting structure of a reinforcing steel bar, a frame and a hard pipe.
The invention also provides a method for installing the anchor rod combination, which comprises the following steps:
assembling the anchor rod hanging bracket of any one of the above;
sequentially hoisting anchor rods on the anchor rod hanging frame;
and integrally lifting the anchor rod hanging frame with the anchor rod mounted to a preset position.
Preferably, the anchor rod hanging bracket is assembled; the anchor rod hanging bracket sequentially hangs an anchor rod, and comprises the following steps:
assembling the hanger frame;
Assembling a single layer of the bearing parallel connection on the hanger frame;
and hoisting the anchor rod to the bearing parallel joint before assembling the next layer of bearing parallel joint.
Preferably, the method further comprises the step of:
after the anchor rod hanging frame is lifted to a preset position, inserting an anchor rod into the preset position;
And after the inserted anchor rod is initially fixed, the stress tensioning is applied in a grading manner.
More preferably, the staged stretching loads at least three stages, each stage holding a load for a period of 1 to 10 minutes.
Further preferably, the staged tension load applies the tension load according to a level of 10%, 50%, 70%, 100%, 120% of the preset load.
It is further preferred that the load is unloaded after 3 minutes of holding of each stage.
Compared with the prior art, the invention has the following advantages:
(1) According to the anchor rod hanging bracket, the anchor rods are placed on the bearing parallel connection, so that the anchor rods can be carried and lifted in groups, single anchor rods are prevented from being carried or lifted independently, the efficiency of carrying and lifting the anchor rods is improved, meanwhile, bending of the anchor rods caused by dead weight can be avoided, and the service life and performance of the anchor rods are improved;
(2) According to the anchor rod hanging bracket, the inclined struts are arranged on the side faces of the anchor rod hanging bracket, so that the structural strength of the anchor rod hanging bracket is enhanced, a certain amount of anchor rods with larger dead weights can be lifted, and the deformation of the anchor rod hanging bracket is avoided;
(3) According to the anchor rod hanger provided by the invention, the stiffening beam is arranged on the bearing parallel connection, so that the capability of bearing anchor rods is improved, the anchor rods with different lengths can be borne by setting the positions of the stiffening beam according to the lengths of the anchor rods, and the bending degree of the anchor rods can be further reduced;
(4) According to the anchor rod hanging bracket, the limiting pieces corresponding to the anchor rod positions are further arranged on the first flat beam or the stiffening beam of the bearing flat joint, and are arranged on two sides of the anchor rod, so that the anchor rod can be clamped, and the positions of the anchor rod are kept relatively fixed;
(5) According to the anchor rod hanging bracket, the positions of the bearing parallel connection and the limiting piece are determined according to the positions of the anchor rods to be installed subsequently, after the anchor rod hanging bracket is lifted, the anchor rods can be installed directly according to the positions of the anchor rods only by aligning the anchor rod hanging bracket, and the process of aligning a plurality of anchor rods independently can be omitted;
(6) According to the anchor rod combined installation method provided by the invention, the anchor rod hanging frame is correspondingly adopted, and the anchor rods can be lifted or carried in a group mode by integrally placing batches of anchor rods;
(7) According to the method for installing the anchor rod combination, the anchor rods are sequentially placed in layers in a single-layer installation bearing parallel connection mode, so that the interference of other bearing parallel connections to the placement of the anchor rods is avoided, the need of independent alignment of anchor rods is avoided, and the construction difficulty is reduced;
(8) According to the method for installing the anchor rod combination, provided by the invention, the hierarchical load is applied to the anchor rod in a hierarchical tensioning mode, so that the tensioning effect of the anchor rod is better.
Drawings
FIG. 1 is a schematic overall construction of an exemplary embodiment of a bolt hanger according to the present invention;
FIG. 2 is a schematic view of a top view of a layer of load-bearing flat linkages of the anchor hanger of the present invention;
FIG. 3 is a schematic view of the structure of the anchor hanger in the direction C-C of FIG. 2;
FIG. 4 is a schematic view of the anchor hanger in the B-B direction of FIG. 3;
FIG. 5 is an enlarged view of a portion F shown in FIG. 3;
FIG. 6 is a schematic view of the structure of the anchor hanger in the D-D direction of FIG. 2;
FIG. 7 is a schematic view of the anchor hanger E-E of FIG. 2;
FIG. 8 is a schematic view of another embodiment of the anchor hanger E-E of FIG. 2;
FIG. 9 is a schematic view of another embodiment of the anchor hanger C-C of FIG. 2 in a direction opposite to that of the anchor hanger C-C;
FIG. 10 is a flow chart of a method of installing a bolt assembly according to the present invention;
FIG. 11 is a flow chart of a method of assembling the anchor hanger of the present invention;
fig. 12 is a schematic flow chart of a method subsequent to the method of installing the anchor assembly shown in fig. 10.
Detailed Description
The invention is further described below with reference to the drawings and exemplary embodiments, wherein like reference numerals refer to like parts throughout. Further, if detailed description of the known art is not necessary to illustrate the features of the present invention, it will be omitted.
In one embodiment, please refer to fig. 1 to 7, fig. 1 is a schematic overall structure of an exemplary embodiment of the anchor rod hanger 1 according to the present invention, fig. 2 is a schematic a-a schematic structure of a layer of the bearing parallel 12 of the anchor rod hanger 1 according to the present invention, fig. 3 is a schematic C-C structure of the anchor rod hanger 1 according to fig. 2, fig. 4 is a schematic B-B structure of the anchor rod hanger 1 according to fig. 3, fig. 5 is a partial enlarged view of a portion F shown in fig. 3, fig. 5 is a schematic C-C structure of fig. 2, fig. 6 is a schematic D-D structure of the anchor rod hanger 1 according to fig. 2, and fig. 7 is a schematic E-E structure of the anchor rod hanger 1 according to fig. 2.
Fig. 2 is a view showing one layer of the load-bearing parallel units 12 of the anchor hanger 1 in a plan view, and defines the plan direction as a-a direction. It should be noted that, in the anchor rod hanger 1 in fig. 1, a round steel pipe assembly display manner is adopted, in the following schematic diagrams, for convenience of display and display of additional materials, the practicality of the anchor rod hanger 1 may also be assembled, in the following schematic diagrams, materials such as angle steel and the like are adopted to form the anchor rod hanger 1, but the constituent materials of the anchor rod hanger 1 of the present invention are not limited to the round steel pipe and the angle steel. In addition to the combination of the anchor rod 2 and the anchor rod hanger 1 shown in fig. 5, the anchor rod 2 is omitted from the other schematic drawings for simplicity of illustration and clarity of structural illustration.
In this embodiment, an anchor hanger 1 is shown. The anchor hanger 1 comprises a hanger frame 11 and a load bearing parallel 12. The hanger frame 11 is in this embodiment enclosed by a number of hanger uprights 111. The bearing parallel connection 12 is fixedly connected with the hanger frame 11 and is transversely arranged. For example, the load-bearing flat-bed 12 is connected to the hanger column 111 by welding or fasteners, and the load-bearing flat-bed 12 is connected to the hanger column 111 vertically for superior connection strength. Referring to fig. 5, the bearing parallel 12 is used for supporting a plurality of anchor rods 2, so the bearing parallel 12 is provided with a plurality of limiting members 13 for limiting the positions of the anchor rods 2, the limiting members 13 arranged in pairs are used for limiting the positions of two ends of the anchor rods 2, a clamping opening for clamping the anchor rods 2 is defined between the same pair of limiting members 13, and the anchor rods 2 are positioned at the clamping opening so as to avoid the anchor rods 2 from sliding along the axial direction of the bearing parallel 12, so that the anchor rods 2 limited to move can be conveyed to a designated position along with the anchor rod hanging frame 1.
Referring to fig. 6, fig. 6 is a schematic view of the anchor hanger 1 in fig. 2 in the direction D-D, which is understood as a side view of the anchor hanger 1, and the direction orthogonal to the direction D-D is a forward direction of the anchor 2 (in fig. 5). On the basis of the above embodiment, diagonal braces 112 are provided between every two hanger columns 111 of the hanger frame 11, and the diagonal braces 112 are used for keeping the shape of the hanger columns 111 stable and strengthening the strength of the hanger frame 11. The diagonal braces 112 may be provided on opposite sides of the hanger frame 11, or may be provided on other sides, such as upper and lower sides, that do not affect the direction in which the anchor rod 2 extends in fig. 5. In addition, the hanger frame 11, the bearing parallel connection 12 and the diagonal brace 112 can be formed by welding angle steel, reinforcing steel bars or hard pipe fittings. In order to enhance the strength of the side surfaces, a separation beam 113 belonging to the hanger frame 11 is further arranged between the two diagonal braces 112 along the height direction of the frame, and the separation beam 113 is used for separating the two diagonal braces 112 and assisting in strengthening the strength of the hanger frame 11 and avoiding deformation of the hanger frame 11. In other possible embodiments, several basic anchor-and-hanger units, which perform the function of the anchor-and-hanger 1, may be formed, bounded by the dividing beams 113. The basic anchor rod hanging frame unit can also adapt to the arrangement requirements of anchor rods 2 with different sizes by connecting the separation cross beams 113 and the anchor rod hanging frames 1 extending in the length direction or the width direction.
Please refer to fig. 2, 3 and 4. Fig. 3 is a C-C angular view of the anchor hanger 1, which can be understood as a front view of the anchor hanger 1. The direction a-a of fig. 2 shows the specific structure of the bearing parallel 12 of the bottom layer of the anchor hanger 1. The direction B-B of fig. 4 shows the specific structure of the bearing parallel 12 in the middle of the anchor hanger 1. Based on the above embodiment, the load-bearing parallel connection 12 includes a plurality of first flat beams 121 and second flat beams 122 intersecting the hanger upright 111 at the same time, the first flat beams 121 and part of the second flat beams 122 are connected to the outer side of the hanger frame 11, part of the second flat beams 122 are disposed inside the hanger frame 11, and the second flat beams 122 are arranged parallel to each other. Stiffening girders 123 are further vertically arranged between the second flat girders 122, and the stiffening girders 123 are used for enhancing bearing capacity and maintaining integral structural integrity. The stiffening girder 123 is set on the bearing parallel connection 12, the capacity of bearing the anchor rod 2 is improved, the position of the stiffening girder 123 is set according to the length of the anchor rod 2, and the bearing parallel connection 12 can bear the stiffening girders 123 with unequal lengths. The bearing parallel connection 12 is provided with multiple layers along the height direction of the hanger upright 111 of the hanger frame 11, and the layer number of the bearing parallel connection 12 is set according to engineering requirements. The stiffening girder 123 can also support part of the short anchor rods 2. In contrast to fig. 4, a dividing beam 113 is also connected between the first flat beams 121 on both sides of the load-bearing flat link 12 shown in fig. 2.
With further reference to fig. 7 on the basis of the above schematic diagram, in order to enhance the ability of the stiffening beam 123 to support the anchor rod 2 due to the weight of the anchor rod 2, an auxiliary column 111 belonging to the hanger column 11 is further provided, and the stiffening beam 123 is disposed at the intersection of the auxiliary column 111 and the second flat beam 122. Fig. 7 fails to show the stiffener 123 due to perspective. The second flat beam 122 in fig. 7 reflects the position of the load bearing flat tie 12 (in fig. 1), and in this embodiment, the second flat beam 122 is configured with three load bearing flat ties 12 to accommodate three layers of anchors 2. In another embodiment, referring to fig. 8, the observation direction of fig. 8 is the same as that of fig. 7, the anchor rod hanger 1 may be provided with a plurality of second flat beams 122 along the height direction of the hanger column, reflecting that the bearing parallel units 12 may be fully distributed with the anchor rod hanger 1, and the intervals between the bearing parallel units 12 are arranged according to specific construction requirements, but the intervals between the two bearing parallel units 12 should be kept larger than the radial length of one anchor rod 2. In this embodiment, the distance of the load-bearing parallel 12 is kept between 120% and 200% of the diameter length of the anchor rod 2.
With further reference to fig. 9 based on the above schematic drawings, fig. 9 is a schematic structural view of another embodiment of the anchor hanger 1 of fig. 2 in the opposite direction C-C, which can be understood as the rear view direction of the anchor hanger 1. The number of first flat beams 121 between the hanger columns 111 can be reduced as needed. For example, referring to fig. 9, the first flat beams 121 except for the two outer regions are reduced, and the first flat beams 121 of the two outer regions remain. By reducing a portion of the first planar beam 121, while maintaining the overall strength unchanged or within an acceptable range, the overall weight of the anchor hanger 1 can be reduced, reducing the pressure of the crane lifting.
With further reference to fig. 5, the limiting members 13 are used for clamping on two sides of the radial single anchor rod 2, and in order to clearly show the structure in fig. 5, a large gap is left between the limiting members 13 and the anchor rod 2. The limiting piece 13 adopts at least one limiting structure of a reinforcing steel bar, a frame and a hard pipe as the limiting piece 13, and angle steel can be further applied. In this embodiment, short steel bars are disposed at both sides of the single anchor rod 2, and are welded to the first flat beam 121 at preset intervals as the limiting members 13. In order to better limit the position of the anchor rod 2, limiting pieces 13 are arranged on two sides of the same anchor rod 2. Accordingly, the stop 13 may be provided on the stiffener 123 according to the specific position of the anchor rod 2.
The arrangement of the anchor rods 2 on the anchor rod hanging frame 1 can be pre-installed according to the arrangement condition of the required installation, and the bearing parallel connection 12 and the corresponding limiting piece 13 are arranged. After the anchor rod hanging frame 1 is integrally lifted, the anchor rods 2 can be directly installed to building components according to the combined arrangement of the anchor rods 2 on the anchor rod hanging frame 1.
With continued reference to fig. 10 to 12 on the basis of the above schematic diagrams, fig. 10 is a schematic flow chart of a method for assembling and installing an anchor rod 2 according to the present invention; fig. 11 is a schematic flow chart of a method for assembling the anchor hanger 1 according to the present invention; fig. 12 is a schematic flow chart of a method subsequent to the method of installing the anchor rod 2 shown in fig. 10.
Referring to fig. 10, the method for assembling and installing the anchor rod 2 is correspondingly provided in the present embodiment in cooperation with the anchor rod hanger 1, and in the process of applying the anchor rod hanger 1, the method includes the following steps:
in step S1, the anchor hanger 1 is assembled.
In the above steps, tools and corresponding parts are prepared according to the structure of the anchor hanger 1. In this embodiment, the load-bearing parallel 12 may be installed after the hanger frame 11 is built. After the hanger frame 11 is installed, the stopper 13 is further welded to facilitate the alignment. The distance between the limiting parts 13 can be determined by the diameter length of the anchor rod 2 to be clamped, and a certain allowance is reserved. The remaining margin allows for subsequent ease of installation of the anchor rod 2.
In step S2, the anchor rods 2 are sequentially hoisted on the anchor rod hanger 1.
In the above steps, the anchor rod 2 is transferred to the position of the limiting piece 13 corresponding to the anchor rod hanger 1 by using the lifting tool, and the positions of the limiting pieces 13 are different according to the different lengths. In order to protect the anchor rod 2 from being worn by the limiting piece 13, a protective sleeve or a rubber ring made of plastic can be sleeved at the limiting piece 13. The length of the limiting piece 13 is controlled to be 60-120% of the diameter length of the anchor rod 2 and is smaller than the distance between the two layers of bearing parallel units 12.
In step S3, the entire anchor hanger 1 after the anchor rod 2 is installed is lifted to a predetermined position.
In the above process, after the anchor rod 2 is installed on the whole anchor rod hanger 1 according to the preset position, the whole anchor rod hanger 1 is lifted to the specified position at one time. In addition, the anchor rod hanging frame 1 can be used as a tool for providing temporary placement besides one-time transportation, and the anchor rod 2 is installed to a designated position by using a lifting tool, so that the positioning prompt function is realized, and the condition that the anchor rod 2 which is not corresponding to the lifting tool or the installation position is deviated is avoided.
In this embodiment, the anchor rod 2 may be lifted at one time after the anchor rod hanger 1 is assembled, or the anchor rod 2 may be lifted alternately during the process of assembling the anchor rod hanger 1. Taking the process of assembling the anchor rod hanger 1 as an example, alternatively hoisting the anchor rods 2, please refer to fig. 11, the step S1 of assembling the anchor rod hanger 1 specifically includes the steps of:
In step S11, the hanger frame 11 is assembled. Referring to fig. 6, after the hanger columns 111 are fixed, diagonal braces 112 and dividing beams 113 may be welded. In other possible embodiments, when the anchor hanger 1 is designed as an anchor hanger unit as described above, the anchor hanger unit may be assembled directly according to the preset position of the anchor 2 or engineering needs.
In step S12, on the hanger frame 11, a single layer of the load-bearing parallel 12 is assembled.
In the above process, the anchor rods 2 are then installed between the stoppers 13 during the assembly of the hanger frame 11. The hanger frame 11 includes multiple layers of load-bearing ties 12, the multiple layers of load-bearing ties 12 being assembled sequentially from bottom to top.
In step S13, the anchor rods 2 are hoisted to the load-bearing flat combination 12 before the next layer of load-bearing flat combination 12 is assembled.
In this step, taking the example of installing a layer of load-bearing parallel bars 12, a first flat beam 121 and a second flat beam 122 are sequentially installed, and a stopper 13, such as a short steel bar, is welded on the first flat beam 121. In other possible embodiments, the connection between the stop 13 and the first flat beam 121 may also be by means of a screw connection. After the limiting pieces 13 are welded, the anchor rods 2 are assembled in sequence, and after the anchor rods 2 of the layer are assembled, the assembly of the bearing parallel connection 12 of the next layer is continued. By means of the sequential assembly mode, the anchor rod 2 can be prevented from being blocked by the bearing parallel connection 12 during installation, and operation time and misoperation rate are reduced.
Referring to fig. 12, on the basis of the above embodiment, the method further includes step S4 and step S5:
In step S4, after the anchor hanger 1 is lifted to a preset position, the anchor 2 is inserted into a hole at the preset position.
The preset position refers to the position of the main tower or the steel beam, and specifically refers to a reserved hole site of the steel beam corresponding to the anchor rod 2. The anchor rod hanging frame 1 is lifted to a position where concrete is to be poured, and is placed opposite to the side main beam which is accurately positioned. The constructor inserts single stock 2 or batch with stock 2 to reserve the hole site, and in this in-process, stock gallows 1 can also play the effect of bearing stock 2, the cartridge of stock 2 of being convenient for. This arrangement can prevent the anchor rod 2 from bending in the longitudinal direction due to its own weight.
In step S5, after the inserted anchor rod 2 is preliminarily fixed, a stress tension is applied in stages.
Taking the example of installing the anchor rod 2 on the steel beam, the anchor rod 2 is primarily fixed with the steel beam through a fastener, and the anchor rod hanging frame 1 continuously supports the corresponding anchor rod 2. And after the steel bars of the main tower section are bound, pouring concrete into the main tower section after the template of the main tower section is installed, and applying prestress to the anchor rods 2.
On the basis of the embodiment, the grading tensioning loads at least three stages, and the holding time of each stage is 1-10 min. In this process, the loading load is graded from small to large. The hold time for each load remains uniform to achieve a staged load before the load level. And after the tension load is loaded for the maintenance time, the load is unloaded.
Further improved in the above step, the staged tension load is applied with tension loads according to five levels of 10%, 50%, 70%, 100%, 120% of the preset load. Still further, the load is unloaded after 3 minutes of each stage of tensile load. The graded loading load tensioning can enable the stress distribution of the anchor rod 2 to be more uniform, and the prestress loss of the anchor rod 2 can be reduced.
According to the anchor rod hanging bracket 1 disclosed by the invention, through arranging the multi-layer bearing parallel connection 12, a plurality of anchor rods 2 can be placed on each layer of bearing parallel connection 12, so that the anchor rods 2 can be carried and lifted in groups, single anchor rods 2 can be prevented from being carried or lifted independently, the efficiency of carrying and lifting the anchor rods 2 is improved, the repeated mechanical labor is reduced, meanwhile, the bending of the anchor rods 2 caused by dead weight can be avoided, and the service life and performance of the anchor rods 2 are improved.
According to the invention, the inclined struts 112 are arranged on the side surfaces of the anchor rod hanging frame 1, so that the structural strength of the anchor rod hanging frame 1 is enhanced, a certain amount of anchor rods 2 with larger dead weights can be lifted, and the deformation of the anchor rod hanging frame 1 is avoided.
The invention also sets the stiffening girder 123 on the bearing parallel connection 12, thereby improving the capacity of bearing the anchor rod 2, setting the position of the stiffening girder 123 according to the length of the anchor rod 2, bearing the anchor rod 2 with unequal lengths, and further reducing the bending degree of the anchor rod 2.
The invention also provides a limiting piece 13 corresponding to the position of the anchor rod 2 is arranged on the first flat beam 121 or the stiffening beam 123 of the bearing parallel connection 12, and the limiting piece 13 is arranged at two ends of the anchor rod 2, so that the anchor rod 2 can be clamped, and the position of the anchor rod 2 is kept relatively fixed. The anchor rod hanging frame 1 can also confirm the position of the bearing parallel connection 12 and the limiting piece 13 through the position of the anchor rod 2 which is required to be installed subsequently, after the anchor rod hanging frame 1 is lifted, only the anchor rod hanging frame 1 is required to be aligned, the anchor rod can be installed directly according to the position of the anchor rod 2, and the procedure of aligning a plurality of anchor rods 2 independently can be omitted.
The invention also provides a method for installing the anchor rod combination, which correspondingly adopts the anchor rod hanging frame 1, and the anchor rods 2 can be lifted or carried in a group mode by integrally placing batches of the anchor rods 2. The anchor rod combined installation method is characterized in that the anchor rods 2 are sequentially placed in layers in a single-layer installation bearing parallel connection 12 mode, interference of other bearing parallel connection 12 to the anchor rod placement is avoided, independent alignment of anchor rods 2 is avoided, and construction difficulty is reduced. According to the method for installing the anchor rod combination, the hierarchical load is applied to the anchor rod 2 in a hierarchical tensioning mode, so that the tensioning effect of the anchor rod 2 is better.
Although a few exemplary embodiments of the present invention have been shown above, it will be appreciated by those skilled in the art that changes may be made in these exemplary embodiments without departing from the principles or spirit of the invention, the scope of which is defined in the claims and their equivalents.

Claims (8)

1. A method of installing a bolt assembly comprising the steps of:
Preparing an assembling tool of an anchor rod hanging bracket and corresponding parts according to a preset installation position of an anchor rod; the anchor rod hanging frame comprises a hanging frame and a plurality of bearing parallel joints which are fixedly connected with the hanging frame and used for bearing anchor rods, the hanging frame comprises a plurality of hanging frame upright posts, the bearing parallel joints are fixedly connected with the hanging frame upright posts, limiting pieces used for limiting the positions of the anchor rods are arranged on the bearing parallel joints, the limiting pieces are arranged in pairs, a clamping opening used for clamping the anchor rods is defined between the same pair of limiting pieces, and the bearing parallel joints are provided with a plurality of layers along the height direction of the hanging frame upright posts;
In the process of assembling the anchor rod hanging frame, alternately hanging the anchor rods, comprising: assembling the hanger frame; assembling a single layer of the bearing parallel connection on the hanger frame; before the next layer of bearing parallel connection is assembled, hoisting the anchor rod to the current bearing parallel connection according to the preset installation position of the anchor rod;
lifting the whole anchor rod hanging frame after anchor rod installation to a preset installation position;
And inserting a single or batch of anchor rods into the hole sites at preset positions, wherein in the process, the anchor rod hanging bracket supports the part of the anchor rods which are not inserted into the hole sites and is used for preventing the anchor rods from bending in the length direction due to dead weight.
2. The method according to claim 1, characterized in that the method further comprises the step of:
And after the inserted anchor rod is initially fixed, the stress tensioning is applied in a grading manner.
3. The method of claim 2, wherein the staged stretching loads at least three stages, each stage holding a load for a period of 1 to 10 minutes.
4. A method according to claim 3, wherein the staged tension load applies the tension load according to a level of 10%, 50%, 70%, 100%, 120% of the preset load.
5. The method of claim 2, wherein the load is unloaded after 3 minutes of holding at each stage.
6. The method of claim 1, wherein diagonal braces are disposed between the hanger posts of the hanger frame, the diagonal braces being disposed on opposite sides of the hanger frame.
7. The method of claim 1, wherein the load-bearing parallel comprises a plurality of first flat beams and second flat beams intersecting the hanger columns at the same time, and stiffening beams for reinforcing bearing capacity are vertically arranged between the plurality of second flat beams.
8. The method of claim 1, wherein the limiting member is at least one of a steel bar, a frame, and a rigid pipe.
CN201811157238.XA 2018-09-30 2018-09-30 Anchor rod hanging bracket and anchor rod combined installation method Active CN109132844B (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202210023686.0A CN114408727A (en) 2018-09-30 2018-09-30 Anchor rod hanger
CN201811157238.XA CN109132844B (en) 2018-09-30 2018-09-30 Anchor rod hanging bracket and anchor rod combined installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811157238.XA CN109132844B (en) 2018-09-30 2018-09-30 Anchor rod hanging bracket and anchor rod combined installation method

Related Child Applications (1)

Application Number Title Priority Date Filing Date
CN202210023686.0A Division CN114408727A (en) 2018-09-30 2018-09-30 Anchor rod hanger

Publications (2)

Publication Number Publication Date
CN109132844A CN109132844A (en) 2019-01-04
CN109132844B true CN109132844B (en) 2024-07-02

Family

ID=64814141

Family Applications (2)

Application Number Title Priority Date Filing Date
CN201811157238.XA Active CN109132844B (en) 2018-09-30 2018-09-30 Anchor rod hanging bracket and anchor rod combined installation method
CN202210023686.0A Pending CN114408727A (en) 2018-09-30 2018-09-30 Anchor rod hanger

Family Applications After (1)

Application Number Title Priority Date Filing Date
CN202210023686.0A Pending CN114408727A (en) 2018-09-30 2018-09-30 Anchor rod hanger

Country Status (1)

Country Link
CN (2) CN109132844B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110510504B (en) * 2019-07-29 2021-08-13 沪东中华造船(集团)有限公司 Hoisting method of deck pipe system unit module

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938877A (en) * 2014-03-12 2014-07-23 中建钢构有限公司北京分公司 Assembly method for anchor bolt sleeve frame
CN106241165A (en) * 2016-08-30 2016-12-21 中建八局第二建设有限公司 A kind of mechanical steel bar storage rack and mechanical steel bar deposit method
CN207891746U (en) * 2017-12-29 2018-09-21 中交路桥华南工程有限公司 The decentralization platform and hanger of the component of steel wall root key combination stake
CN208906994U (en) * 2018-09-30 2019-05-28 中交路桥华南工程有限公司 Anchor pole hanger

Family Cites Families (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0570090A (en) * 1991-09-05 1993-03-23 Haseko Corp Conveying method for reinforcing bar
JP2001081969A (en) * 1999-09-14 2001-03-27 Takeshi Awakuni Device for arrangement of reinforcing bars
JP2003128377A (en) * 2001-10-24 2003-05-08 Hmy Ltd Load-carrying platform for lengthy material, lengthy material handling method using it, and lengthy material conveying system
US9546830B2 (en) * 2014-01-28 2017-01-17 Brentwood Industries, Inc. Composite hanger grid and components, splash bar, assembly thereof and method of assembly
CN104480860B (en) * 2014-11-11 2016-05-04 中交路桥华南工程有限公司 The method and apparatus of lifting reinforcing bar in batches
CN204751886U (en) * 2015-07-01 2015-11-11 中铁十局集团第二工程有限公司 Batch reinforcing bar lifting device frame
CN105800450B (en) * 2016-05-17 2017-07-11 上海锅炉厂有限公司 A kind of scattered pipe hoisting device
CN206503075U (en) * 2016-11-05 2017-09-19 中交一航局第四工程有限公司 A kind of hollow thin-walled high pier reinforcing bar lifts mould bases

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103938877A (en) * 2014-03-12 2014-07-23 中建钢构有限公司北京分公司 Assembly method for anchor bolt sleeve frame
CN106241165A (en) * 2016-08-30 2016-12-21 中建八局第二建设有限公司 A kind of mechanical steel bar storage rack and mechanical steel bar deposit method
CN207891746U (en) * 2017-12-29 2018-09-21 中交路桥华南工程有限公司 The decentralization platform and hanger of the component of steel wall root key combination stake
CN208906994U (en) * 2018-09-30 2019-05-28 中交路桥华南工程有限公司 Anchor pole hanger

Also Published As

Publication number Publication date
CN114408727A (en) 2022-04-29
CN109132844A (en) 2019-01-04

Similar Documents

Publication Publication Date Title
CN109056548B (en) Steel arch construction method
CN108316479B (en) Truss arch system and construction method thereof
CN113882712A (en) Temporary support reinforcing method for large-scale suspension type steel structure construction
CN113718955A (en) Construction method of giant asymmetric suspension pure steel structure tower
CN110318344B (en) Novel steel box girder No. 0 block support and No. 0 block erection construction method
CN109132844B (en) Anchor rod hanging bracket and anchor rod combined installation method
CN111779274A (en) Construction method for integrally lifting temporary hoisting point of large-span unequal-height steel structure net rack
CN116856544A (en) Annular inclined truss structure and installation method thereof
CN109184199B (en) Torsion and shear resisting reinforcing method for ring beam in cast-in-place construction of 3m prestressed arch bar
CN214737303U (en) Truss type steel pipe concrete cable tower structure
CN214531431U (en) Truss combination roof truss of opening string roof beam and encorbelmenting
CN110805308B (en) Method for installing and dismantling temporary support at top center of silo
CN212611918U (en) Connecting structure of steel plate beam
CN108797350B (en) Tower column inner and outer stiff skeleton device and construction method thereof
CN109235943B (en) Reinforced concrete prefabricated assembly type cinema stand structure
CN112575948A (en) Truss string beam and cantilever truss combined roof truss and construction method
CN111560846B (en) Method for mounting bridge deck system steel longitudinal and transverse beams
CN112411753B (en) Construction method of large-span suspended steel truss girder structure
CN217438905U (en) Arch bridge oblique pile reinforcement cage segment structure
CN113845030B (en) Lifting method of stepped steel truss
CN113293710A (en) Sheet type truss support tool and bridge construction method
CN118166654A (en) Prefabricated bridge assembling construction process
CN208440995U (en) A kind of bracket of steel truss concrete composite beam bridge
CN115324355A (en) Construction process of roof prestressed cable arch structure
JP2691261B2 (en) Facility method of arch form support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Xia Jiangnan

Inventor after: Wu Man

Inventor after: Ge Jiping

Inventor after: Chen Zhenyu

Inventor after: Wang Haiwei

Inventor after: Diao Xianjue

Inventor after: Chen Yang

Inventor after: Liu Huaigang

Inventor after: Gao Shiqiang

Inventor after: Xiao Xiangrong

Inventor after: Tan Xinghua

Inventor after: Zhao Shenghui

Inventor before: Liu Huaigang

Inventor before: Wu Man

Inventor before: Ge Jiping

Inventor before: Chen Zhenyu

Inventor before: Wang Haiwei

Inventor before: Gao Shiqiang

Inventor before: Diao Xianjue

Inventor before: Xiao Xiangrong

Inventor before: Xia Jiangnan

Inventor before: Tan Xinghua

Inventor before: Chen Yang

Inventor before: Zhao Shenghui

CB03 Change of inventor or designer information
GR01 Patent grant