CN109098187A - A kind of method of basement room heart backfilling material - Google Patents

A kind of method of basement room heart backfilling material Download PDF

Info

Publication number
CN109098187A
CN109098187A CN201810972263.7A CN201810972263A CN109098187A CN 109098187 A CN109098187 A CN 109098187A CN 201810972263 A CN201810972263 A CN 201810972263A CN 109098187 A CN109098187 A CN 109098187A
Authority
CN
China
Prior art keywords
layer
room
basement
foam concrete
backfilling material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810972263.7A
Other languages
Chinese (zh)
Inventor
黄平干
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China IPPR International Engineering Co Ltd
Original Assignee
China IPPR International Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China IPPR International Engineering Co Ltd filed Critical China IPPR International Engineering Co Ltd
Priority to CN201810972263.7A priority Critical patent/CN109098187A/en
Publication of CN109098187A publication Critical patent/CN109098187A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/12Back-filling of foundation trenches or ditches

Abstract

The present invention provides a kind of method of basement room heart backfilling material, is backfilled using foam concrete, includes the following steps: step 1, and partition wall basis is directly built from sole plate or float Structure plate face, keeps the higher partition wall basis in each room clear and definite;Step 2, after the completion of pipeline is pre-buried in surface structures layer height and after the completion of each room partition wall is all built from sole plate, foam concrete is sent in each room with adjustable pipe using concrete pump and is tamped, the step 2 can be with are as follows: is sent to foam concrete after tamping in each room, pipe built-in is completed in surface structures layer height and builds each room partition wall from sole plate, the drainage layer living alternatively descended between room floor and sole plate in architectural construction layer using foam concrete of the drainage layer between room floor and sole plate in architectural construction layer is alternatively descended using foam concrete, filled layer and rigid layer become new filled layer, selectivity adds waterproof layer and protective layer above new filled layer.

Description

A kind of method of basement room heart backfilling material
Technical field
The present invention relates to industrial building and public building technical fields, the especially method of basement backfilling material.
Background technique
In urban land today in short supply, basement is no longer simple garage parking or equipment room, it usually may be used The miscellaneous function room for being designed to the first floor function room with general hospital or also serving as other layers, for example, design is on ground at present Lower room has: outpatient service, image dept. of radiology, hyperbaric oxygen chamber, radiotherapy center, simulating chamber, information centre, pharmacy, Administrative Area etc., this A little rooms all seem critically important, and ground requires also high.Referring to Fig. 1, the prior art is due to structure basis form and electromechanical tube sewer pipe Line must must have an architectural construction layer total height on the ground that subsurface set aside pre-embedded, basement are finally completed to sole plate, This architectural construction layer generally comprises surface layer, rigid layer, filled layer, drainage layer, and rigid layer is also known as rigid waterproof layer, usually 150 is thick, and C25/P6 water-proof concrete production, the interior diameter with reinforcing bar is 4, and the spacing between reinforcing bar is 200, is set as two-way Single layer, and with pouring with troweling, wherein filled layer and the material of drainage layer require to backfill and meet compacting factor requirement, usually Compacting factor is not less than 0.94, therefore each room floors correspond to this highly and just have a room heart backfilling material way, usually Layer material is filled using plain earthen backfill, drainage layer material is using 300 thick medium coarse sand backfills.Using former basement room heart element earthen backfill When scheme, existing a large amount of holes on live upper floor plate (each stairs port, elevator shaft mouth, daylighting garden, escalator mouth, Post-cast strip whole audience openings, first and second phase interface, vestibule interface, pipe well mouth etc.) and outer wall of basement set aside pre-embedded hole, it is impossible to Close these holes one by one to backfill and halt other processes and stop doing business, these holes will lead to certainly rainwater and construction water into Enter basement, the result is that water, which will impregnate plain soil, becomes mud or spring soil, compacting factor is unable to reach former design requirement and is greater than etc. In 0.94, reprocess dry again or again soil removal and replacement and transport it is all extremely difficult, hidden danger is more.Summarize the plain earthen backfill of the prior art Scheme has the following technical defects:
If 1) the soft or hard unevenness of ground element earthen backfill, compaction in layers and draining hydrofuge cannot be ensured, later building coats Will strain cracking, wall the foot of a wall humidity rise it is mould decortication possibly even there is crack, tile surface and seam crossing also easily play wet spot Block has greater environmental impacts and influences to use function.
2) because compacting tool at basement sole plate reversed beam periphery and dead angle and can not wear beam duct bottom hardly possible in place To tamp plain earthen backfill.
3) plain earthen backfill cannot first build partition wall on sole plate, secondary excavation again after waiting plain earthen backfill complete Partition wall foundation pit, otherwise, wall side and corner are all difficult to tamp, time-consuming;
4) plain earthen backfill, not can guarantee and be not immersed in water, because upper floor plate and underground external wall have greatly in work progress The reserved opening of amount, it is impossible to stop other operations of top to close, rainwater and construction water can enter from reserved opening Basement makes the plain soil of backfill become mud and spring soil, leads to that acceptance requirement is not achieved and there are more hidden danger, here it is existing Deformed in real using the ground of plain earthen backfill scheme the basic reason of hollowing of cracking often, so this element earthen backfill side Case needs to improve.
Summary of the invention
In order to overcome the problems, such as the design present invention of the existing technology, the purpose of the present invention is to provide a kind of basement rooms The method of heart backfilling material, is backfilled using foam concrete, is included the following steps:
Step 1 directly builds partition wall basis from sole plate or float Structure plate face, makes the higher partition wall in each room Basis is clear and definite;
Step 2, after the completion of pipeline is pre-buried in surface structures layer height and each room partition wall is all built from sole plate After the completion, foam concrete is sent in each room and is tamped.
Preferably, the step 2 can be with are as follows: is sent to foam concrete after tamping in each room, in surface structures layer Pipe built-in is completed in height and builds each room partition wall from sole plate.
Preferably, the foam concrete is sent in each room using concrete pump with adjustable pipe and is tamped by the step 2.
It preferably, further include the equipment for lag bid without installing in advance, using the cutting foam concrete Mode change basis size positions and room wall.
Preferably, the drainage between room floor and sole plate in architectural construction layer is alternatively descended using foam concrete Layer.
Preferably, the drainage between room floor and sole plate in architectural construction layer is alternatively descended using foam concrete Layer, filled layer and rigid layer become new filled layer, and the rigid layer has water-proof function.
Preferably, foam concrete dry density Ji other≤B08 of the new filled layer, Qiang degree Ji other≤A3.5, and use Surface press polish.
Preferably, waterproof layer and protective layer are added above the new filled layer, the waterproof layer and protective layer are in the bubble It is completed after the troweling of foam concrete face, prevention and treatment moisture influences the drying of the above room floors of basement upwards.
Preferably, between for there is boiled water room, waterproof layer and protective layer are not added above the new filled layer.
Preferably, the waterproof layer uses 1.5 thick polymer cement waterproof paints, meets wall and turns over 300, meets door and puts up door 300, the protective layer uses 20 thickness 1:3 cement mortar.
Beneficial effect by adopting the above technical scheme is: the present invention is replaced normal using improved foam concrete backfill scheme The plain earthen backfill scheme of rule: solve the room heart backfill when, basement structure basis reversed beam periphery, dead angle and wear beam duct bottom and Partition wall periphery, dead angle are all difficult to the problem of tamping and leading to ground local subsidence hollowing, solve plain soil collapse by water logging maceration and The problem of causing ground deformation to crack;It solves the mould decortication of room the foot of a wall humidity and crack and floor tile table possibly even occurs The problem of face seam crossing easily plays wet patch and influences environment and use function;The difficulty of partition wall cannot be first built before solving backfill Topic, keep its precedence adjustable, especially control partition wall basis confirm on sole plate and wall two sides buried depth backfill quality It is secure, it ensure that wall stability conscientiously;Backfill compacting factor has reached design and job specfication requirement, has prevented construction Hidden danger of quality exists;Former drainage layer, filled layer and rigid lamination three are a new filled layer of composition, and material uses foam concrete generation It replaces, simple process and globality is strong also keeps and improves former water filtering function, is now three because monolithic entity drainage is originally Unify body drainage, obtains good economic and social benefit;Waterproof layer is added together with protective layer on new filled layer, prevents moist water Divide up to walk, guarantees that each room floors are dry conscientiously;Transport and construction are extremely convenient;Duration shortens 2/3;Use manpower and material resources sparingly wealth Power.
According to the following detailed description of specific embodiments of the present invention in conjunction with the accompanying drawings, those skilled in the art will be brighter The above and other objects, advantages and features of the present invention.
The brief description of accompanying drawing
Some specific embodiments of the present invention is described in detail by way of example and not limitation with reference to the accompanying drawings hereinafter. Identical appended drawing reference denotes same or similar part or part in attached drawing.It should be appreciated by those skilled in the art that these What attached drawing was not necessarily drawn to scale.Target and feature of the invention will be apparent from view of following description taken together with the accompanying drawings, In attached drawing:
Attached drawing 1 is the plain earthen backfill method schematic diagram of the basement flooring of the prior art;
Attached drawing 2 is the method schematic diagram according to the basement room heart backfilling material of the embodiment of the present invention.
Specific embodiment
Detailed description of the preferred embodiments with reference to the accompanying drawing, but be not intended to limit the invention Protection scope.
The declaratives of attached drawing 1 are referring to background technology part.
Referring to attached drawing 2, the background of the embodiment is the Outpatient Building basement one of hospital, designs having in basement at present: Outpatient service, image dept. of radiology, hyperbaric oxygen chamber, radiotherapy center, simulating chamber, information centre, pharmacy, Administrative Area etc., these rooms are all Seem critically important, ground requires also high.Conventional plain earthen backfill scheme is improved to foam concrete backfill New Scheme, logical first Cross analysis comparison and ascertain the reason to formulate new solution it is quite important, this programme is innovated in conjunction with practical concrete engineering 's.
If the soft or hard unevenness of ground element earthen backfill, compaction in layers and draining hydrofuge cannot ensure that later building coats is just Meeting strain cracking, wall the foot of a wall humidity play mould decortication and crack possibly even occur, and tile surface and seam crossing also easily play wet patch, It has greater environmental impacts and influences to use function.At basement sole plate reversed beam periphery and dead angle and wears beam duct bottom and be difficult to Plain earthen backfill is tamped, because compacting tool can not be in place.Plain earthen backfill cannot first build partition wall on sole plate, wait Secondary excavation partition wall foundation pit again after plain earthen backfill is complete, otherwise, wall side and corner are all difficult to tamp, time-consuming.Meanwhile element soil returns Filling out, which can not guarantee, is not immersed in water, because in work progress, upper floor plate and underground external wall have a large amount of reserved opening, it is impossible to Stop other operations of top to close, rainwater and construction water can enter basement from reserved opening, make the element soil of backfill Become mud and spring soil, leads to that acceptance requirement is not achieved and there are more hidden danger, here it is use plain earthen backfill in reality The ground of scheme deforms the basic reason of hollowing of cracking often, so this element earthen backfill scheme needs to improve, this implementation Example proposes new departure way using new material foam concrete feature, includes the following steps:
Step 1 first should directly build partition wall basis because basement floor is high from sole plate or float Structure plate face, Keep the basis of the higher partition wall in each room clear and definite, stablizes its reasonable benefit/risk indeformable;Scheme energy is backfilled using foam concrete Reach this requirement;
Step 2, after the completion of pipeline is pre-buried in surface structures layer height and each room partition wall is all built from sole plate After the completion of building, reusing concrete pump and foam concrete is sent in each room tamps with adjustable pipe, convenient and quick construction, solidification is fast, Curing period, is short, not afraid of water, and quality is secure, and solves sole plate reversed beam periphery and dead angle and wear beam duct bottom and be difficult to fill out Real quality problems, it is not in that pixel earthen backfill needs like that partition wall basis and piping laying can construct before backfill Secondary heavy excavation wall base slot and tube seat.Certainly, according to engineering reality, first foam concrete can also be sent in each room and tamped Afterwards, pipe built-in is then completed in surface structures layer height and build each room partition wall from sole plate.Foam coagulation There are one features for earthen backfill scheme, change to the Equipment Foundations size positions of lag bid or room wall has change, It easily cuts foam concrete and can be effectively ensured in conjunction with old concrete secret.
The Construction of Basement duration applied in the present embodiment shortens, and general larger basement is super with overlength Width, area are big, and sole plate, often with reversed beam, essence earthen backfill transport difficult on reversed beam, structure security risk is also big, construction Slowly, normal need 3 months.And the present embodiment is simple and fast using foam concrete placings, completes within 1 month, shortens the backfill time 2 Month, be conducive to integrated engineering progress.Using the use scope of two ways extension foam concrete, one is mixed using foam Solidifying soil alternatively descends the drainage layer between room floor and sole plate in architectural construction layer, this is to be based on facts have proved foam coagulation Native air entrapment not necessarily all completely encloses, and has certain infiltration function;Another is to substitute basement using foam concrete Drainage layer, filled layer and rigid layer between ground and sole plate in architectural construction layer become new filled layer, and rigid layer has Water-proof function.For the second way, foam concrete dry density Ji other≤B08 of new filled layer, Qiang degree Ji other≤A3.5, and Using surface press polish.In addition, adding waterproof layer and protective layer above new filled layer, waterproof layer and protective layer are in the foam coagulation It is completed after native face troweling, prevention and treatment moisture influences the drying of the above room floors of basement upwards.It should be noted that for Between having boiled water room, do not add waterproof layer and protective layer above new filled layer because this two layers inside architectural construction surface layer way Through having.In this way, waterproof layer uses 1.5 thick polymer cement waterproof paints, meets wall and turns over 300, meets door and puts up door 300, protective layer uses 20 thickness 1:3 cement mortar.
Beneficial effect by adopting the above technical scheme is: the present invention is replaced normal using improved foam concrete backfill scheme The plain earthen backfill scheme of rule: solve the room heart backfill when, basement structure basis reversed beam periphery, dead angle and wear beam duct bottom and Partition wall periphery, dead angle are all difficult to the problem of tamping and leading to ground local subsidence hollowing, solve plain soil collapse by water logging maceration and The problem of causing ground deformation to crack;It solves the mould decortication of room the foot of a wall humidity and crack and floor tile table possibly even occurs The problem of face seam crossing easily plays wet patch and influences environment and use function;The difficulty of partition wall cannot be first built before solving backfill Topic, keep its precedence adjustable, especially control partition wall basis confirm on sole plate and wall two sides buried depth backfill quality It is secure, it ensure that wall stability conscientiously;Backfill compacting factor has reached design and job specfication requirement, has prevented construction Hidden danger of quality exists;Former drainage layer, filled layer and rigid lamination three are a new filled layer of composition, and material uses foam concrete generation It replaces, simple process and globality is strong also keeps and improves former water filtering function, is now three because monolithic entity drainage is originally Unify body drainage, obtains good economic and social benefit;Waterproof layer is added together with protective layer on new filled layer, prevents moist water Divide up to walk, guarantees that each room floors are dry conscientiously;Transport and construction are extremely convenient;Duration shortens 2/3;Use manpower and material resources sparingly wealth Power.
It is provided for the embodiments of the invention technical solution above to be described in detail, specific case used herein The principle and embodiment of the embodiment of the present invention are expounded, the explanation of above embodiments is only applicable to help to understand this The principle of inventive embodiments;Simultaneously those of ordinary skill in the art, according to an embodiment of the invention, specific embodiment with And there will be changes in application range, in conclusion the contents of this specification are not to be construed as limiting the invention.

Claims (10)

1. a kind of method of basement room heart backfilling material, it is characterised in that: backfilled using foam concrete, including walked as follows It is rapid:
Step 1 directly builds partition wall basis from sole plate or float Structure plate face, makes the higher partition wall basis in each room It is clear and definite;
Step 2, after the completion of pipeline is pre-buried in surface structures layer height and each room partition wall all builds from sole plate and completes Afterwards, foam concrete is sent in each room and is tamped.
2. a kind of method of basement room heart backfilling material according to claim 1, it is characterised in that: the step 2 is also It can be with are as follows: foam concrete is sent to after being tamped in each room, pipe built-in is completed in surface structures layer height and from base Plinth bottom plate builds each room partition wall.
3. a kind of method of basement room heart backfilling material according to claim 1 or 2, it is characterised in that: the step Two, which use concrete pump that the foam concrete is sent in each room with adjustable pipe, tamps.
4. a kind of method of basement room heart backfilling material according to claim 1, it is characterised in that: further include, for Equipment of the lag bid without installing in advance, use the mode for cut foam concrete change basic size positions with And the wall in room.
5. a kind of method of basement room heart backfilling material according to claim 1, it is characterised in that: use foam coagulation Soil alternatively descends the drainage layer between room floor and sole plate in architectural construction layer.
6. a kind of method of basement room heart backfilling material according to claim 1, it is characterised in that: use foam coagulation Soil alternatively descends drainage layer, filled layer and rigid layer between room floor and sole plate in architectural construction layer to become new filling Layer, the rigid layer have water-proof function.
7. a kind of method of basement room heart backfilling material according to claim 6, it is characterised in that: the new filled layer Foam concrete dry density Ji Bie≤B08, Qiang degree Ji Bie≤A3.5, and use surface press polish.
8. a kind of method of basement room heart backfilling material according to claim 6 or 7, it is characterised in that: described newly to fill out It fills above layer and adds waterproof layer and protective layer, the waterproof layer and protective layer are completed after the troweling of the foam concrete face, are prevented Controlling moisture upwards influences the drying of the above room floors of basement.
9. a kind of method of basement room heart backfilling material according to claim 6 or 7, it is characterised in that: for there is water Waterproof layer and protective layer are not added in room, the new filled layer top.
10. a kind of method of basement room heart backfilling material according to claim 8, it is characterised in that: the waterproof layer It using 1.5 thick polymer cement waterproof paints, meets wall and turns over 300, meet door and put up door 300, the protective layer uses 20 thickness 1:3 water Cement mortar.
CN201810972263.7A 2018-08-24 2018-08-24 A kind of method of basement room heart backfilling material Pending CN109098187A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810972263.7A CN109098187A (en) 2018-08-24 2018-08-24 A kind of method of basement room heart backfilling material

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810972263.7A CN109098187A (en) 2018-08-24 2018-08-24 A kind of method of basement room heart backfilling material

Publications (1)

Publication Number Publication Date
CN109098187A true CN109098187A (en) 2018-12-28

Family

ID=64851332

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810972263.7A Pending CN109098187A (en) 2018-08-24 2018-08-24 A kind of method of basement room heart backfilling material

Country Status (1)

Country Link
CN (1) CN109098187A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778341A (en) * 2019-11-01 2020-02-11 中建八局轨道交通建设有限公司 Backfill construction method for construction vertical shaft and construction transverse passage
CN110847247A (en) * 2019-11-14 2020-02-28 中国二十冶集团有限公司 Waterproof operation construction method on multi-anti-floating anchor rod node basement bottom plate

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2861285Y (en) * 2005-11-10 2007-01-24 德胜(苏州)洋楼有限公司 Indoor moisture proof foundation for timber structure house
CN203213533U (en) * 2013-04-24 2013-09-25 国家电网公司 Substation indoor floor structure
CN107304625A (en) * 2016-04-22 2017-10-31 中国二十冶集团有限公司 Foam concrete is combined terrace and its construction method with concrete

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2861285Y (en) * 2005-11-10 2007-01-24 德胜(苏州)洋楼有限公司 Indoor moisture proof foundation for timber structure house
CN203213533U (en) * 2013-04-24 2013-09-25 国家电网公司 Substation indoor floor structure
CN107304625A (en) * 2016-04-22 2017-10-31 中国二十冶集团有限公司 Foam concrete is combined terrace and its construction method with concrete

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110778341A (en) * 2019-11-01 2020-02-11 中建八局轨道交通建设有限公司 Backfill construction method for construction vertical shaft and construction transverse passage
CN110847247A (en) * 2019-11-14 2020-02-28 中国二十冶集团有限公司 Waterproof operation construction method on multi-anti-floating anchor rod node basement bottom plate

Similar Documents

Publication Publication Date Title
CN100473790C (en) Tower crane foundation for construction and manufacturing method thereof
CN107447770A (en) A kind of big open caisson of superelevation and construction method
CN102430277B (en) Coarse grid sunk well for physically processing waste water and construction method thereof
CN106894431B (en) Hypogee pit body waterproof construction precipitation processing method under a kind of water resource enriched environment
CN109706952A (en) Large-scale well-sinking construction method
CN109098187A (en) A kind of method of basement room heart backfilling material
CN107675704A (en) A kind of artificial digging pile assembled retaining wall and its construction technology
CN107326928A (en) A kind of part is related to the construction method in the deeper subsurface garage of basement
CN103469828A (en) Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN110055845B (en) Construction method for soft soil roadbed on two sides of highway bridge and culvert
CN111042310A (en) Basement bottom plate structure and construction method thereof
CN207211176U (en) A kind of big open caisson of superelevation
CN106836182A (en) A kind of compacted technique of vibroflotation water conservancy diversion
CN206204969U (en) Reservoir submerges area's brick mixed building terrace lift structure
CN107460949B (en) Chassis system of light steel structure assembly and decoration integrated building
CN207160074U (en) A kind of non-settling structure of stable public way well body
KR100981061B1 (en) Method for backfill gap of structure
CN111501959A (en) Combined cast-in-situ drainage ditch and construction method
CN109667278A (en) Tower crane anti-cracking and seepage control construction method is set under underground garage isolated footing
CN103711146B (en) Supporting pillar reinforcement underground reverse layer addition construction method
CN106498958B (en) Reservoir submerges area's brick mixed building terrace lift structure and technique
JPH09250144A (en) Outside waterproof method of basement
CN114688347B (en) Method for embedding flexible pipeline by using controllable low-strength material prefabricated block
CN202263468U (en) Coarse screen open caisson for physical wastewater treatment
CN106948356A (en) A kind of land-based area reinforced concrete open caisson coxopodite connects high method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181228

RJ01 Rejection of invention patent application after publication