CN109095360B - A kind of Split mounting type building hanging device and installation method - Google Patents

A kind of Split mounting type building hanging device and installation method Download PDF

Info

Publication number
CN109095360B
CN109095360B CN201810903003.4A CN201810903003A CN109095360B CN 109095360 B CN109095360 B CN 109095360B CN 201810903003 A CN201810903003 A CN 201810903003A CN 109095360 B CN109095360 B CN 109095360B
Authority
CN
China
Prior art keywords
house
hanger
mould bases
bracket
type building
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201810903003.4A
Other languages
Chinese (zh)
Other versions
CN109095360A (en
Inventor
张建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Lu Shang Residential Industrial Technology Co Ltd
Original Assignee
Hunan Lu Shang Residential Industrial Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Lu Shang Residential Industrial Technology Co Ltd filed Critical Hunan Lu Shang Residential Industrial Technology Co Ltd
Priority to CN201810903003.4A priority Critical patent/CN109095360B/en
Publication of CN109095360A publication Critical patent/CN109095360A/en
Application granted granted Critical
Publication of CN109095360B publication Critical patent/CN109095360B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C21/00Cable cranes, i.e. comprising hoisting devices running on aerial cable-ways
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of Split mounting type building hanging device and installation methods, bracket and mould bases, bracket is set to house assembly start bit, mould bases is set to the periphery of ground, conveying device is equipped between bracket and mould bases, hanger includes vertical beam and crossbeam, and each corner cooperation of vertical beam and house compresses, multiple vertical beams are connected and fixed by crossbeam, and lifting device is connected between hanger and conveying device;Rotary joint is equipped with above hanger, rotary joint includes rotary disk one, rotary disk two and rotating shaft, and rotary disk one is connect with rotary disk two by rotating shaft, and be can be rotated;Rotary joint upper end is connect with lifting device, and lower end is connect by pull rod with hanger.The purpose of the present invention is, a kind of Split mounting type building hanging device and installation method are provided, entire Split mounting type building can be accurately delivered to from specific complicated landform by hanging device from more spacious consolidation service place, and it assists completing to install, it operates with simple, it is particularly useful for the mountain area use that landform is severe, has inconvenient traffic.

Description

A kind of Split mounting type building hanging device and installation method
Technical field
The invention belongs to building construction ancillary equipment field, specially a kind of Split mounting type building hanging device and installation side Method.
Background technique
Usually, people mostly use brick mix structure in building construction, and stability is good, durable.In recent years, because Frame structure is mostly used to the natural calamities such as antiseismic, in building, scene is dusty, with the personal expenditures of building Higher and higher, the flood tide building waste and gray haze that traditional building generates seriously affect environment, and traditional building needs to reform.
The assembled house of wooden structures is as a kind of environment-friendly type building body, more and more by big well-established.From appearance It sees, the house and indistinction in house and traditional approach construction.The difference in assembled room, only part has carried out prefabricated, to applying Work scene build or directly put up after in be transported to field-hardened installation.And wood house is for remote mountain areas, Resourceful, materials are relatively easy, especially for even more preferred for the inn Min Su, Peasants Joy.
In order to meet some actual needs in, house need to build to some special positions, such as mountain top, as going sightseeing With, however these are local, one side usual conditions are more severe, and landform is more complicated, usually not biggish working space, It cannot park using Large-scale Hoisting equipment;On the other hand in order to protect local natural environment to greatest extent, highway is not set up, Carried, built by manpower entirely, time-consuming and laborious, higher cost, especially those prefabricated wall, roofs in equal volume compared with Big component brings inconvenience to manpower transport, therefore, it is necessary to develop a kind of corresponding hanging device with regard to these problems.
Summary of the invention
The purpose of the present invention is in view of the above problems, provide a kind of Split mounting type building hanging device and installation method, lifting Entire Split mounting type building can be accurately delivered to from specific complicated landform by equipment from more spacious consolidation service place, and assisted It at installation, operates with simply, is particularly useful for the remote mountain areas use that landform is severe, has inconvenient traffic.
In order to achieve the above object, the technical solution adopted by the present invention is that: a kind of Split mounting type building hanging device, including bracket And mould bases, the bracket are set to house assembly start bit, the mould bases is set to the periphery of ground, the bracket and mould bases it Between be equipped with conveying device, the conveying device moves back and forth between bracket and mould bases for hanger, and the hanger includes vertical beam And crossbeam, each corner cooperation of the vertical beam and house compress, multiple vertical beams are connected and fixed by the crossbeam, the hanger and conveying Lifting device is connected between device;Rotary joint is equipped with above the hanger, the rotary joint includes rotary disk one, rotary disk two And rotating shaft, the rotary disk one are connect with rotary disk two by rotating shaft, and can be rotated;The rotary joint upper end and lifting fill Connection is set, lower end is connect by pull rod with hanger.
Further, the pull rod includes rod set one, rod set two and bar core, and bar core both ends are sheathed on rod set respectively One, in rod set two, and by being threadedly engaged connection, bar core both ends screw thread it is oppositely oriented.
Further, the crossbeam includes mutually matched transverse slat one and transverse slat two, is uniformly provided on the transverse slat one more A one mounting hole of transverse slat is uniformly provided with multiple two mounting holes of transverse slat on the transverse slat two.
Further, the vertical beam lower end is equipped with the vertical beam fixing bolt being detachably connected with house bottom.
Further, it is equipped on the inside of the vertical beam and is equipped with elastic cushion at the cooperation of house corner.
Further, the conveying device includes pulley blocks, hauling rope and conveyer, and the hauling rope is matched with pulley blocks It closes, and is set on bracket and mould bases, the conveyer is mobile for hauling rope, and the hauling rope is connect with hanger.
Further, the lifting device includes guide wheel, lifting rope and withdrawing rope mechanism, and the guide wheel is set to hauling rope On, the lifting rope and guide wheel cooperate, and one end is connect with hanger, and the other end and withdrawing rope mechanism are sequentially connected, the folding and unfolding Rope mechanism is set to above hanger, and the lifting moving of hanger is controlled by the folding and unfolding to lifting rope.
A kind of installation method of Split mounting type building hanging device, comprising the following steps:
Step A, house is assembled: wood house is completed according to design requirement assembly;
Step B, it builds ground: according to the size in the house installed, building corresponding ground to be installedly;
Step C, bracket and mould bases are built: according to the size of ground, house shape and installation requirement, riding upon ground for mould bases Base periphery, bracket ride upon house consolidation service end, conveying device are installed between bracket and mould bases;
Step D, hanger and house connect: hanger is guaranteed that house will not be fallen from hanger with house to be tightly connected;
Step E, lifting and conveying: after by hanger and house and being promoted to certain altitude by lifting device, conveying is opened Device is passed to above ground to be installed;
Step F, adjustment installation: adjusting the setting angle etc. in house by rotary joint, then will be hung by lifting device Frame and house are transferred to ground, and house and lot is fixedly connected;
Step G, demoulding: after house and lot fixes, mould bases and hanger etc. are removed.
Further, house can be fixedly connected on by house and lot by cast-in-place or riveting device etc. in the step F On ground.
Beneficial effects of the present invention: hanging device can be accurate from more spacious consolidation service place by entire Split mounting type building It is delivered at specific complicated landform, and assists completing to install, operate with simple, it is severe to be particularly useful for landform, has inconvenient traffic Remote mountain areas use;A large amount of generation processing cost has been saved, it is practical;In addition, be practically applicable to given area small lot at The wood house of row's setting lifts installation, and installation accuracy is high, high-efficient.
1, the length of pull rod can be adjusted by turning bar core, when house is adjusted and installed, convenient for adjusting house and lot Distance on each sideline guarantees accurate installation;
2, elongation and shortening, it can be achieved that crossbeam are coupled by selection one mounting hole of transverse slat and two mounting hole of transverse slat, The lifting for meeting different length and width house compresses;
3, vertical beam fixing bolt and house bottom are to be detachably connected, and house is prevented to be lifted, fall in transmission process The case where falling guarantees safe operation.
Detailed description of the invention
Fig. 1 is schematic view of the front view of the present invention.
Fig. 2 is hanger assembly relation structural schematic diagram of the present invention.
Fig. 3 is partial enlargement structural representation at B of the present invention.
Fig. 4 is partial enlargement structural representation at C of the present invention.
Fig. 5 is A-A the schematic diagram of the section structure of the present invention.
Fig. 6 is partial enlargement structural representation at D of the present invention.
Label character described in figure indicates are as follows: 1, bracket;2, mould bases;3, conveying device;31, pulley blocks;32, hauling rope; 33, conveyer;4, hanger;41, vertical beam;411, vertical beam fixing bolt;412, elastic cushion;42, crossbeam;421, transverse slat one;4211, One mounting hole of transverse slat;422, transverse slat two;4221, two mounting hole of transverse slat;5, lifting device;51, guide wheel;52, lifting rope;53, it receives Fang Sheng mechanism;6, rotary joint;61, rotary disk one;62, rotary disk two;63, rotating shaft;7, pull rod;71, rod set one;72, rod set Two;73, bar core;8, house.
Specific embodiment
In order to make those skilled in the art more fully understand technical solution of the present invention, with reference to the accompanying drawing to the present invention into Row detailed description, the description of this part be only it is exemplary and explanatory, should not have any limitation to protection scope of the present invention Effect.
As shown in figures 1 to 6, specific structure of the invention are as follows: a kind of Split mounting type building hanging device, including bracket 1 and mould bases 2, the bracket 1 is set to house assembly start bit, and the mould bases 2 is set to the periphery of ground, the bracket 1 and mould bases 2 it Between be equipped with conveying device 3, the conveying device 3 moves back and forth between bracket 1 and mould bases 2 for hanger 4, and the hanger 4 wraps Vertical beam 41 and crossbeam 42 are included, the vertical beam 41 is compressed with each corner cooperation in house, and the crossbeam 42 connects multiple vertical beams 41 solid It is fixed, lifting device 5 is connected between the hanger 4 and conveying device 3;Rotary joint 6, the revolution are equipped with above the hanger 4 Section 6 includes rotary disk 1, rotary disk 2 62 and rotating shaft 63, and the rotary disk 1 passes through rotating shaft 63 with rotary disk 2 62 Connection, and can be rotated;6 upper end of rotary joint is connect with lifting device 5, and lower end is connect by pull rod 7 with hanger 4.
Preferably, the pull rod 7 includes rod set 1, rod set 2 72 and bar core 73, and 73 both ends of bar core are arranged respectively In in rod set 1, rod set 2 72, and by being threadedly engaged connection, the 73 both ends screw thread of bar core it is oppositely oriented.By twisting The length of pull rod can be adjusted in lever core, when house is adjusted and installed, convenient for adjusting the distance on each sideline of house and lot, protects The accurate installation of card.
Preferably, the crossbeam 42 includes mutually matched transverse slat 1 and transverse slat 2 422, on the transverse slat 1 It is even to be equipped with multiple one mounting holes 4211 of transverse slat, multiple two mounting holes 4221 of transverse slat are uniformly provided on the transverse slat 2 422.Pass through choosing It selects one mounting hole of transverse slat and two mounting hole of transverse slat is coupled elongation and shortening, it can be achieved that crossbeam, meet different length and width The lifting for spending house compresses.
Preferably, 41 lower end of vertical beam is equipped with the vertical beam fixing bolt 411 being detachably connected with house bottom.It uses When, vertical beam fixing bolt connect with house bottom and tightens, and after house is installed, comes loose, and house is prevented to be lifted, convey The case where falling in the process guarantees safe operation.
Preferably, it is equipped on the inside of the vertical beam 41 and is equipped with elastic cushion 412 at the cooperation of house corner.Prevent vertical beam by house The destruction of outer surface.
Preferably, the conveying device 3 includes that pulley blocks 31, hauling rope 32 and conveyer 33(are such as twisted machine), it is described Hauling rope 32 and pulley blocks 31 cooperate, and are set on bracket 1 and mould bases 2, and the conveyer 33 is mobile for hauling rope 32, institute Hauling rope 32 is stated to connect with hanger 4.
Preferably, the lifting device 5 includes guide wheel 51, lifting rope 52 and withdrawing rope mechanism 53(such as bottle gouard moved by hands etc.), The guide wheel 51 is set on hauling rope 32, and the lifting rope 52 cooperates with guide wheel 51, and one end is connect with hanger 4, the other end It is sequentially connected with withdrawing rope mechanism 53, the withdrawing rope mechanism 53 is set to 4 top of hanger, passes through the folding and unfolding control to lifting rope 52 The lifting moving of hanger 4 processed.
A kind of installation method of Split mounting type building hanging device, comprising the following steps:
Step A, house is assembled: wood house is completed according to design requirement assembly;
Step B, it builds ground: according to the size in the house installed, building corresponding ground to be installedly;
Step C, bracket and mould bases are built: according to the size of ground, house shape and installation requirement, riding upon ground for mould bases Base periphery, bracket ride upon house consolidation service end, conveying device are installed between bracket and mould bases;
Step D, hanger and house connect: hanger is guaranteed that house will not be fallen from hanger with house to be tightly connected;
Step E, lifting and conveying: after by hanger and house and being promoted to certain altitude by lifting device, conveying is opened Device is passed to above ground to be installed;
Step F, adjustment installation: adjusting the setting angle etc. in house by rotary joint, then will be hung by lifting device Frame and house are transferred to ground, and house and lot is fixedly connected;
Step G, demoulding: after house and lot fixes, mould bases and hanger etc. are removed.
Preferably, house can be fixedly connected on ground by cast-in-place or riveting device etc. by house and lot in the step F On base.
When specifically used, wood house is completed according to design requirement assembly;According to the size in the house installed, to Build corresponding ground in installation ground;According to the size of ground, house shape and installation requirement, mould bases is ridden upon into ground periphery, Bracket rides upon house consolidation service end, and conveying device is installed between bracket and mould bases;Hanger is tightly connected with house, is guaranteed House will not be fallen from hanger;After by hanger and house and being promoted to certain altitude by lifting device, conveying device is opened, it will It send to ground to be installed;The setting angle etc. in house is adjusted by rotary joint, then passes through lifting device for hanger It transfers with house to ground, and house and lot is fixedly connected with (can be affixed by cast-in-place or riveting device etc.);House with After ground fixes, mould bases and hanger etc. are removed.
It should be noted that, in this document, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that the process, method, article or equipment for including a series of elements not only includes those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or equipment institute it is intrinsic Element.
Used herein a specific example illustrates the principle and implementation of the invention, the explanation of above example It is merely used to help understand method and its core concept of the invention.The above is only a preferred embodiment of the present invention, it answers When pointing out due to the finiteness of literal expression, and objectively there is unlimited specific structure, for the common skill of the art For art personnel, without departing from the principle of the present invention, several improvement, retouching or variation can also be made, can also incited somebody to action Above-mentioned technical characteristic is combined in the right way;These improve retouching, variation or combination, or the not improved structure by invention Think and technical solution directly applies to other occasions, is regarded as protection scope of the present invention.

Claims (7)

1. a kind of Split mounting type building hanging device, including bracket (1) and mould bases (2), which is characterized in that bracket (1) setting In house assembly start bit, the mould bases (2) is set to the periphery of ground, and conveying is equipped between the bracket (1) and mould bases (2) Device (3), the conveying device (3) move back and forth between bracket (1) and mould bases (2) for hanger (4), the hanger (4) Including vertical beam (41) and crossbeam (42), each corner cooperation of the vertical beam (41) and house is compressed, and the crossbeam (42) will be multiple perpendicular Beam (41) is connected and fixed, and is connected with lifting device (5) between the hanger (4) and conveying device (3);Above the hanger (4) Equipped with rotary joint (6), the rotary joint (6) includes rotary disk one (61), rotary disk two (62) and rotating shaft (63), the revolution Disk one (61) is connect with rotary disk two (62) by rotating shaft (63), and can be rotated;Rotary joint (6) upper end and lifting device (5) it connects, lower end is connect by pull rod (7) with hanger (4);
The conveying device (3) includes pulley blocks (31), hauling rope (32) and conveyer (33), the hauling rope (32) and pulley Group (31) cooperation, and be set on bracket (1) and mould bases (2), the conveyer (33) is mobile for hauling rope (32), described defeated Rope (32) is sent to connect with hanger (4);
The lifting device (5) includes guide wheel (51), lifting rope (52) and withdrawing rope mechanism (53), and the guide wheel (51) is set to On hauling rope (32), the lifting rope (52) and guide wheel (51) cooperate, and one end is connect with hanger (4), the other end and withdrawing rope Mechanism (53) transmission connection, the withdrawing rope mechanism (53) are set to above hanger (4), pass through the folding and unfolding control to lifting rope (52) The lifting moving of hanger (4) processed.
2. a kind of Split mounting type building hanging device according to claim 1, which is characterized in that the pull rod (7) includes bar One (71) of set, rod set two (72) and bar core (73), bar core (73) both ends are sheathed on rod set one (71), rod set two (72) respectively It is interior, and by being threadedly engaged connection, bar core (73) both ends screw thread it is oppositely oriented.
3. a kind of Split mounting type building hanging device according to claim 1, which is characterized in that the crossbeam (42) includes phase The transverse slat one (421) and transverse slat two (422) mutually cooperated is uniformly provided with multiple one mounting holes of transverse slat on the transverse slat one (421) (4211), multiple two mounting holes of transverse slat (4221) are uniformly provided on the transverse slat two (422).
4. a kind of Split mounting type building hanging device according to claim 1, which is characterized in that vertical beam (41) lower end is set There is the vertical beam fixing bolt (411) being detachably connected with house bottom.
5. a kind of Split mounting type building hanging device according to claim 1, which is characterized in that set on the inside of the vertical beam (41) Have and is equipped with elastic cushion (412) at the cooperation of house corner.
6. a kind of application method of Split mounting type building hanging device according to claim 1-5, which is characterized in that The following steps are included:
Step A, house is assembled: wood house is completed according to design requirement assembly;
Step B, it builds ground: according to the size in the house installed, building corresponding ground to be installedly;
Step C, bracket and mould bases are built: according to the size of ground, house shape and installation requirement, mould bases being ridden upon outside ground It encloses, bracket rides upon house consolidation service end, and conveying device is installed between bracket and mould bases;
Step D, hanger and house connect: hanger is guaranteed that house will not be fallen from hanger with house to be tightly connected;
Step E, lifting and conveying: after by hanger and house and being promoted to certain altitude by lifting device, opening conveying device, It is passed to above ground to be installed;
Step F, adjustment installation: adjusting the setting angle in house by rotary joint, then passes through lifting device for hanger and room Room is transferred to ground, and house and lot is fixedly connected;
Step G, demoulding: after house and lot fixes, mould bases and hanger are removed.
7. a kind of application method of Split mounting type building hanging device according to claim 6, which is characterized in that the step House can be fixedly connected on ground by house and lot by cast-in-place or riveting device in F.
CN201810903003.4A 2018-08-09 2018-08-09 A kind of Split mounting type building hanging device and installation method Active CN109095360B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810903003.4A CN109095360B (en) 2018-08-09 2018-08-09 A kind of Split mounting type building hanging device and installation method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810903003.4A CN109095360B (en) 2018-08-09 2018-08-09 A kind of Split mounting type building hanging device and installation method

Publications (2)

Publication Number Publication Date
CN109095360A CN109095360A (en) 2018-12-28
CN109095360B true CN109095360B (en) 2019-11-01

Family

ID=64849290

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810903003.4A Active CN109095360B (en) 2018-08-09 2018-08-09 A kind of Split mounting type building hanging device and installation method

Country Status (1)

Country Link
CN (1) CN109095360B (en)

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2055130B (en) * 1979-07-31 1983-02-09 Pynford Ltd Method of raising buildings
FR2650012B1 (en) * 1989-07-24 1994-05-13 Aragon Rene METHOD FOR CONSTRUCTING SINGLE HOUSES USING A LIFTING MEANS AND PREFABRICATED ELEMENTS FOR IMPLEMENTING SAID METHOD
CN101863427A (en) * 2010-06-10 2010-10-20 孙慧燕 Loading and unloading tool and operation method of hanging coffins
US20170067266A1 (en) * 2015-09-08 2017-03-09 Camilo Caudilla Alfarero Move up apparatus and method in multi floor construction
CN106555479B (en) * 2015-09-30 2019-12-24 李宜君 Hoisting equipment of concave floor forming device
CN206438780U (en) * 2016-12-22 2017-08-25 山东飞越钢结构工程有限公司 A kind of electromagnetic type module house suspender
CN106744170A (en) * 2017-01-26 2017-05-31 中建五局工业设备安装有限公司 A kind of vertical soft Stady On The Auxiliary Transportation Systems for skyscraper

Also Published As

Publication number Publication date
CN109095360A (en) 2018-12-28

Similar Documents

Publication Publication Date Title
CN100535361C (en) Work platform
CN212176541U (en) Light-duty high-efficient construction that can have enough to meet need makes building equipment
CN105781228B (en) A kind of movable fencing
CN111219055A (en) Light-duty recyclable efficient construction building equipment and construction method thereof
CN108996421B (en) Finished furniture hoisting machine and finished furniture hoisting method
CN103243934A (en) House system constructed by single independent foundation and erecting method of house system
CN109095360B (en) A kind of Split mounting type building hanging device and installation method
CN203112160U (en) Discharging device of high-rise storage
CN110499916B (en) Construction method of wall-penetration-free heightening, anchoring, supporting, pulling and folding type unloading platform
CN203188366U (en) House system built through single independent foundation
CN206157725U (en) Stirring adds core pile pile and lock pin integration equipment
CN202416854U (en) Table form concrete formwork device
CN209616017U (en) A kind of folding movable mixing plant
CN209145305U (en) A kind of construction device for discharging
CN102926537A (en) Method and device for fixing root of external wall formwork
CN110179295A (en) A kind of folding exhibition position device convenient for adjusting installation
CN205617771U (en) Construction operation platform and pipe -line transportation integrated device in high residential building elevartor shaft
CN205840190U (en) A kind of pin key connects the mounting structure of prefabricated bench
CN109024885B (en) Safety protection structure of conveying corridor
CN203451012U (en) Double-cage elevator safety protective door spindle device
CN209555785U (en) A kind of external quality of pier coating decoration platform suitable for high pier bridge
CN203127645U (en) Easily-disassembled type auger device
CN208088863U (en) A kind of novel municipal and environment-friendly protection network
CN208456101U (en) A kind of housing construction scaffold
CN205875410U (en) A hang module system all for tube structure room panel construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant