CN109079972A - A kind of method of entire winter prefabricated thermal insulation maintenance - Google Patents

A kind of method of entire winter prefabricated thermal insulation maintenance Download PDF

Info

Publication number
CN109079972A
CN109079972A CN201810914568.2A CN201810914568A CN109079972A CN 109079972 A CN109079972 A CN 109079972A CN 201810914568 A CN201810914568 A CN 201810914568A CN 109079972 A CN109079972 A CN 109079972A
Authority
CN
China
Prior art keywords
sleeper
workshop
maintenance
double
feed bin
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810914568.2A
Other languages
Chinese (zh)
Inventor
王艳红
贾小平
徐结明
田永涛
唐维东
张民栓
王熙
陈鹏
张山
田磊
刘志如
谭祥博
牛健龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Three Bridge And Tunnel Engineering Co Ltd Group
China Railway No 3 Engineering Group Co Ltd
China Railway No 3 Engineering Group Bridge and Tunnel Engineering Co Ltd
Original Assignee
Three Bridge And Tunnel Engineering Co Ltd Group
China Railway No 3 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Three Bridge And Tunnel Engineering Co Ltd Group, China Railway No 3 Engineering Group Co Ltd filed Critical Three Bridge And Tunnel Engineering Co Ltd Group
Priority to CN201810914568.2A priority Critical patent/CN109079972A/en
Publication of CN109079972A publication Critical patent/CN109079972A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B11/00Apparatus or processes for treating or working the shaped or preshaped articles
    • B28B11/24Apparatus or processes for treating or working the shaped or preshaped articles for curing, setting or hardening
    • B28B11/245Curing concrete articles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Drying Of Solid Materials (AREA)

Abstract

A kind of method of entire winter prefabricated thermal insulation maintenance, belong to prefabricated sleeper technical field, it is short in the reset time of the semiarid property climatic province teletostage double-block type sleeper of cool temperature zone, it is not timely completed constructing aims and the ineffective problem of conventional maintenance, the workshop includes boiler room, sandstone feed bin, mixing station, sleeper workshop and maintenance workshop, by using method of the invention, it solves under cold dry adverse weather condition, it ensure that the normal production of double-block type sleeper, it ensure that going on smoothly for construction period, while guaranteeing the construction quality of sleeper product.The automatic humidity induction having by the industrial ultrasonic wave humidifier configured and timing means, by the uniform expanding of ultrasonic wave fog of generation to sleeper surface, carry out all standing moisturizing, reduce water consumption and the artificial investment of maintenance, eliminate human factor generation leakage support and conserve it is not in place caused by mass defect, rejection rate is reduced, to improve sleeper natural curing process sleeper quality.

Description

A kind of method of entire winter prefabricated thermal insulation maintenance
Technical field
The invention belongs to prefabricated sleeper technical fields, and in particular to a kind of method of entire winter prefabricated thermal insulation maintenance.
Background technique
In the semiarid property climatic province of cool temperature zone, winter is controlled by powerful Mongolian hyperbar, and very long cold dry, summer is more Thunderstorm, spring and autumn are windy and dusty.- 20 DEG C of winter minimum temperature, the 3 of 10 the end of month to the next year for being divided into current year of winter construction period The end of month, about 5 months or so.In the prefabricated double-block type sleeper in this area, for the realization for guaranteeing constructing aims, it is necessary to the teletostage be taken to apply Work measure carries out the prefabricated of double-block type sleeper.
For double-block type sleeper after the maintenance demoulding of channel, whether secondary natural curing link can reach concrete sleeper intensity To highest, to meet, quality requirement is particularly critical, and the later strength of sleeper depends on natural curing, and traditional approach takes watering The method of moisturizing, sleeper surface area is small, complex contour, is unfavorable for maintenance effect, and be also easy to produce water resource waste.
Summary of the invention
The present invention is short for the reset time in the semiarid property climatic province teletostage double-block type sleeper of cool temperature zone, cannot be on time complete At the ineffective problem of constructing aims and conventional maintenance, a kind of method of entire winter prefabricated thermal insulation maintenance is provided.
The present invention adopts the following technical scheme:
A kind of method of entire winter prefabricated thermal insulation maintenance, the heat preservation of heat preservation, mixing station including sandstone feed bin, sleeper produce vehicle Between heat preservation and demoulding after double-block type sleeper finished product maintenance, include the following steps:
The first step, install oil burning boiler, configuration two be respectively used to sandstone feed bin and the mixing station teletostage heat preservation steam boiler with And the steam boiler for the heat preservation of sleeper workshop teletostage;
Second step, the heat preservation of sandstone feed bin and mixing station are buried at sandstone bin bottom 5cm for the heating of sand material teletostage Jet chimney is laid for keeping jet chimney of the sandstone feed bin inner ring border temperature at 5 DEG C or more on the divider wall of sandstone feed bin;
The surrounding installation rock wool board of mixing station is closed, and steam heating pipe is installed in the position of host machine of mixing station and the position of air valve cylinder Road and radiator, the interior setting of the water tank of mixing station are used for the jet chimney of mixing water heating, and being arranged on jet chimney can control water Temperature is not less than 60 DEG C of temp.-control valve;
Third step, the heat preservation of sleeper workshop, the surrounding of sleeper workshop lay the winter for controlling sleeper workshop Jet chimney of the phase temperature at 10 DEG C or more, sleeper workshop wall and roof setting for prevent sleeper workshop and The external world generates the rock wool board with flame retarding function of thermal convection, and the window of sleeper workshop is arranged for preventing thermal loss The air-heater for extraneous cold wind to be isolated is arranged in double glazing, the feed inlet of sleeper workshop;
Double-block type sleeper after demoulding is sent into and closed is equipped with several ultrasonic waves by the 4th step, the maintenance of sleeper finished products after demoulding The double-block type sleeper for completing 10 day curing period is sent out maintenance workshop by the maintenance workshop of humidifier, and circulation completes the double of every batch of The maintenance of block type sleeper.
Steam boiler described in the first step is the steam boiler of 4t.
A steam boiler in two steam boilers passes through the jet chimney and water tank of pipeline and sandstone feed bin Interior jet chimney connection, another steam boiler are connect by pipeline with the jet chimney of sleeper workshop.
The grey trolley of overhead fortune is equipped between the discharge port of the mixing station and the entrance of sleeper workshop.
It sets on the ultrasonic humidifier in the maintenance workshop there are three mutually independent atomization conduit, atomization conduit is equipped with Several fog outlets, fog outlet setting is between every two rows of double-block type sleepers.
The maintenance workshop is closed structure, conserves and is equipped with automatically between the outlet of the entrance and sleeper workshop in workshop Go up and down rolling screen door.
Beneficial effects of the present invention are as follows:
By using method of the invention, solves under cold dry adverse weather condition, ensure that double-block type sleeper just Often production, ensure that going on smoothly for construction period, while guaranteeing the construction quality of sleeper product.
The automatic humidity induction having by the industrial ultrasonic wave humidifier configured and timing means, by the ultrasound of generation The uniform expanding of wave fog carries out all standing moisturizing, reduces water consumption and the artificial investment of maintenance, eliminate people to sleeper surface For the leakage that factor generates support and conserve it is not in place caused by mass defect, rejection rate is reduced, so that it is naturally feeding to improve sleeper Nurse's sequence sleeper quality.
Detailed description of the invention
Fig. 1 is floor map of the present invention;
Fig. 2 is maintenance workshop structural schematic diagram of the invention;
Wherein: the boiler room 1-;2- steam boiler;3- sandstone feed bin;4- jet chimney;5- host;6- water tank;7- caliduct; 8- sleeper workshop;The grey trolley of the overhead fortune of 9-;10- air-heater;11- steam curing channel;12- conserves workshop;13- ultrasonic wave Humidifier;14- automatic lifting rolling screen door;15- double-block type sleeper;16- atomization conduit.
Specific embodiment
In conjunction with attached drawing, the present invention will be further described.
In the environment of teletostage temperature is at -20 DEG C, sandstone feed bin 3, mixing station and sleeper workshop 8 need to keep the temperature extremely 5 DEG C or more, the steam boiler 2 of two 4t is configured, one keeps the temperature for the teletostage of sandstone feed bin 3 and mixing station, and another is used for The heat preservation of sleeper workshop 8.
Sandstone feed bin 3 faces when building construction, buries jet chimney 4 in subsurface, the heating of sand material when for winter construction, It prevents from freezing;Jet chimney 4 is laid on the divider wall of sandstone feed bin 3, is maintained at 5 DEG C for the environment temperature in sandstone feed bin 3 More than.The Insulation of mixing station is mainly closed mixing station surrounding using rock wool board, operates 5 position of host and air valve The position emphasis installation caliduct 7 of cylinder and radiator heat preservation, mixing water are taken jet chimney to place and are risen in water tank 6 Temperature, and install temp.-control valve, steam valve is automatically closed when water temperature is controlled to 60 DEG C, and valve is opened when being lower than this temperature.Guarantee Concrete out-of-machine temperature is not less than 10 DEG C.
Sleeper workshop 8 teletostage temperature is controlled at 10 DEG C or more, and 8 surrounding of sleeper workshop is mainly taken to lay steam Pipeline 4 is kept the temperature, and workshop wall and roof, which are all made of rock wool board with flame retarding function and the external world, can not generate thermal convection current phenomenon, Windowpane in workshop takes double glazing to prevent thermal loss.Entire workshop is at closed state.Mixing station concrete discharging mouth Take the grey trolley of overhead fortune with the transfer passage in workshop, above entrance wall the extraneous cold wind of 10 pairs of installation air-heater carry out every From.
The design in workshop 12 is conserved, designs 10 days sleeper maximum outputs first, by practical daily two classes of production 1600 The quantitative design of sleepers, 10 days 16000 sleepers stores floor space.Sleeper is stored according to 8 layers, and every layer of 4 every pile can be deposited 32 are put, occupied area 3.75m2.Area needed for 16000 sleepers are stored is 1875m2, the maintenance workshop 12 of configuration and sleeper Workshop 8 shares, span 21m, and the length for sleeper caching maintenance is 110m, can meet 10 days sleeper outputs and support Protect the requirement of time.Ground region scribing line, divides 6 region block pattern row pattern sleepers by 21m span, stays between per pass sleeper storage area The interval 50cm.
In workshop two sides, every 10m spacing lays ultrasonic humidifier 13,3.2m high above the wall of corresponding humidifier position Position weld 50cm long T-steel, the corresponding hole for boring 3 φ 10 on T-steel penetrates the wirerope of φ 8, wirerope in each hole Above the position wall of span 21m to opposite humidifier, 3 wirerope are tensed with cord holder respectively.3 on every humidifier It says mist pipeline and is individually laid along wirerope, fog outlet stays in 50cm interval location between storage sleeper, per pass fog outlet ladder Shape is laid.According to said method humidifier is corresponding two-by-two lays fog output tube.Fog output tube and wirerope are fixed by band.
After the completion of fog output tube road 16 is laid, water lines and electric line, the independent water of every equipment are laid along length of walls position Valve and circuit switch control, unwanted maintenance region can close maintenance of equipment.It is installed in 6 regions away from fog outlet highest distance position Humidity inductive is popped one's head at 6.Starting ultrasonic humidifier carries out the automatic moisture-keeping maintenance to sleeper after being all installed.
The maintenance workshop is the function and principle by concrete sample standard curing room;It is supported by the moisturizing of code requirement 10 days time of shield and this period sleeper quantity produced plan storage space area, configure certain amount and humidification Amount meets the supersonic humidifier of maintenance effect, and fog output tube road is laid in installation.By supersonic humidifier it is included be arranged automatically it is wet The function of degree and time set humidity and enter working condition.Early period is examined by 3 days, 7 days, 28 days with condition test piece intensity It surveys and determines setting humidity value.Data are obtained through test: demoulding strength 40.8Mpa;3 days intensity be averaged 48.5Mpa(47.8Mpa, 49.3Mpa, 48.5Mpa);7 days intensity is averaged 54.0Mpa(53.3Mpa, 55.8Mpa, 52.9Mpa);Intensity is average within 10 days 58.5Mpa(57.6Mpa, 59.5Mpa, 58.5Mpa).

Claims (6)

1. a kind of method of entire winter prefabricated thermal insulation maintenance, it is characterised in that: heat preservation, mixing station including sandstone feed bin (3) Heat preservation, the heat preservation of sleeper workshop (8) and the maintenance of double-block type sleeper (15) finished product after demoulding, including walk as follows It is rapid:
The first step, installs oil burning boiler, and configuration two is respectively used to the steam boiler of sandstone feed bin (3) and the heat preservation of mixing station teletostage (2) and for sleeper workshop (8) teletostage heat preservation steam boiler (2);
Second step, the heat preservation of sandstone feed bin (3) and mixing station are buried at sandstone feed bin (3) bottom 5cm for the sand material teletostage The jet chimney (4) of heating, lay on the divider wall of sandstone feed bin (3) for keep sandstone feed bin inner ring border temperature 5 DEG C with On jet chimney;
The surrounding installation rock wool board of mixing station is closed, and host (5) position of mixing station and the position installation of air valve cylinder are warm Feed channel (7) and radiator, the interior setting of the water tank (6) of mixing station are used for the jet chimney of mixing water heating, set on jet chimney Set the temp.-control valve that controlling water temperature is not less than 60 DEG C;
Third step, the heat preservation of sleeper workshop (8), the surrounding of sleeper workshop (8) are laid for controlling sleeper production vehicle Between (8) jet chimney (4) of the teletostage temperature at 10 DEG C or more, the wall and roof of sleeper workshop (8) be arranged for hindering Only sleeper workshop (8) and the extraneous rock wool board with flame retarding function for generating thermal convection, the window of sleeper workshop (8) Double glazing for preventing thermal loss is set, and the feed inlet setting of sleeper workshop (8) is for carrying out extraneous cold wind The air-heater (10) of isolation;
4th step, the maintenance of sleeper finished products after demoulding, by the double-block type sleeper (15) after demoulding be sent into it is closed be equipped with it is several super The double-block type sleeper (15) for completing 10 day curing period is sent out maintenance workshop, followed by the maintenance workshop (12) of sound wave humidifier (13) Ring completes the maintenance of the double-block type sleeper of every batch of.
2. a kind of method of entire winter prefabricated thermal insulation maintenance according to claim 1, it is characterised in that: institute in the first step State the steam boiler that steam boiler (2) are 4t.
3. a kind of method of entire winter prefabricated thermal insulation maintenance according to claim 1, it is characterised in that: two steamings The jet chimney (4) and the steaming in water tank (6) that a steam boiler (2) in boiler furnace passes through pipeline and sandstone feed bin (3) The connection of steam pipe road, another steam boiler (2) are connect by pipeline with the jet chimney (4) of sleeper workshop (8).
4. a kind of method of entire winter prefabricated thermal insulation maintenance according to claim 1, it is characterised in that: mixing station goes out The grey trolley (9) of overhead fortune is equipped between material mouth and the entrance of sleeper workshop (8).
5. a kind of method of entire winter prefabricated thermal insulation maintenance according to claim 1, it is characterised in that: described to care the car Between (12) ultrasonic humidifier (13) on set there are three mutually independent atomization conduit (16), atomization conduit (16) is if be equipped with Dry fog outlet, fog outlet setting is between every two rows of double-block type sleepers (15).
6. a kind of method of entire winter prefabricated thermal insulation maintenance according to claim 1, it is characterised in that: described to care the car Between (12) be closed structure, conserve workshop (12) entrance and sleeper workshop (8) outlet between be equipped with automatic lifting volume Curtain door (14).
CN201810914568.2A 2018-08-13 2018-08-13 A kind of method of entire winter prefabricated thermal insulation maintenance Pending CN109079972A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810914568.2A CN109079972A (en) 2018-08-13 2018-08-13 A kind of method of entire winter prefabricated thermal insulation maintenance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810914568.2A CN109079972A (en) 2018-08-13 2018-08-13 A kind of method of entire winter prefabricated thermal insulation maintenance

Publications (1)

Publication Number Publication Date
CN109079972A true CN109079972A (en) 2018-12-25

Family

ID=64834414

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810914568.2A Pending CN109079972A (en) 2018-08-13 2018-08-13 A kind of method of entire winter prefabricated thermal insulation maintenance

Country Status (1)

Country Link
CN (1) CN109079972A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000335987A (en) * 1999-05-31 2000-12-05 Tohoku Jikou Kk Steam-curing of concrete product and apparatus therefor
KR20050119483A (en) * 2004-06-16 2005-12-21 현대건설주식회사 Concrete surface heating method and device of low temperature and winter time
CN1837474A (en) * 2006-04-25 2006-09-27 中铁八局集团有限公司 Maintenance method for double-block type sleeper
CN200998886Y (en) * 2007-01-23 2008-01-02 俞加友 Humiture even concrete maintenance chamber
CN102162301A (en) * 2011-03-04 2011-08-24 葛洲坝集团第五工程有限公司 Method and device for preserving temperature and humidity and protecting during concrete construction in winter
CN202862404U (en) * 2012-10-26 2013-04-10 中铁二十二局集团第六工程有限公司 Concrete mixing plant heating system
CN107160551A (en) * 2017-06-28 2017-09-15 中国电建集团贵阳勘测设计研究院有限公司 Construction method for prefabricating box girder concrete in cold area in winter
CN206520080U (en) * 2017-02-28 2017-09-26 中国葛洲坝集团第一工程有限公司 A kind of intelligent precast construction curing means

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000335987A (en) * 1999-05-31 2000-12-05 Tohoku Jikou Kk Steam-curing of concrete product and apparatus therefor
KR20050119483A (en) * 2004-06-16 2005-12-21 현대건설주식회사 Concrete surface heating method and device of low temperature and winter time
CN1837474A (en) * 2006-04-25 2006-09-27 中铁八局集团有限公司 Maintenance method for double-block type sleeper
CN200998886Y (en) * 2007-01-23 2008-01-02 俞加友 Humiture even concrete maintenance chamber
CN102162301A (en) * 2011-03-04 2011-08-24 葛洲坝集团第五工程有限公司 Method and device for preserving temperature and humidity and protecting during concrete construction in winter
CN202862404U (en) * 2012-10-26 2013-04-10 中铁二十二局集团第六工程有限公司 Concrete mixing plant heating system
CN206520080U (en) * 2017-02-28 2017-09-26 中国葛洲坝集团第一工程有限公司 A kind of intelligent precast construction curing means
CN107160551A (en) * 2017-06-28 2017-09-15 中国电建集团贵阳勘测设计研究院有限公司 Construction method for prefabricating box girder concrete in cold area in winter

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
刘勇: "轨枕环行法生产制枕场总体设计与轨枕预制配套设备研究", 《铁道建筑技术》 *
戴会生: "《混凝土搅拌站实用技术》", 31 August 2014, 中国建材工业出版社 *
李昌宁 等: "《CRTSⅡ型双块式无砟轨道轨枕预制与铺设技术》", 31 March 2013, 中国铁道出版社 *
郑西铁路客运专线有限责任公司: "《郑西高速铁路工程总结》", 30 June 2011, 中国铁道出版社 *
钱肖萍 等: "《水利水电工程施工工厂设计实例》", 30 November 2012, 黄河水利出版社 *

Similar Documents

Publication Publication Date Title
CN104712345B (en) Tunnel lining concrete heat preserving and maintaining construction device and construction method thereof
CN105134278B (en) High aititude extremely frigid zones tunnel ventilation temperature elevation system and ventilation heating construction method
CN105737397B (en) Solar ground heat can comprehensively utilize walling system
CN209633328U (en) High speed railway prefabricating box girder intelligence steam curing system
CN107062474A (en) A kind of nearly zero energy consumption building system based on accumulation of energy
CN102972233B (en) Industrialized production straw mushroom house
CN113586120A (en) Combined hot air jet heat preservation device for cold region tunnel and control method
CN112854748A (en) Maintenance method for construction of suspension casting box girder in winter
CN108590730B (en) A kind of roadway cooling simulation test device and test method
CN109676774A (en) A kind of steam-cured cellar of efficient precast concrete shield duct piece and its application method
CN106642766B (en) Closed interior well circulating picture-changing heat pipe
CN108360523B (en) A kind of building structure with temperature control device
CN109079972A (en) A kind of method of entire winter prefabricated thermal insulation maintenance
CN104737923B (en) Severe cold and cold district scale pig house VMC (Ventilation Mechanical Control System) in winter
CN202324250U (en) Novel thermal-insulation and energy-saving wall body
CN108437181A (en) A kind of steam curing device for highway assembly concrete component
CN204894186U (en) Solar energy curing kiln
CN218669434U (en) A combined hot air jet insulation device for tunnels in cold regions
CN202350367U (en) Heating system for absorbing terrestrial heat by utilizing heat pipes
CN206669938U (en) A kind of nearly zero energy consumption building system based on accumulation of energy
CN213260125U (en) Prestressed concrete sleeper dual-mode steam curing device
CN205536362U (en) Reduce air inlet system of hot pressing effect
CN205332317U (en) Utilize energy -concerving and environment -protective heating system of millet electricity and secret cistern
CN107143056A (en) A kind of ecological energy conservation building walling system
CN207945986U (en) A kind of ceramic kiln dehumidifier exhaust gas utilization system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181225

RJ01 Rejection of invention patent application after publication