CN109064024A - A kind of engineering Whole Process Cost dynamic management approach and system - Google Patents
A kind of engineering Whole Process Cost dynamic management approach and system Download PDFInfo
- Publication number
- CN109064024A CN109064024A CN201810873649.2A CN201810873649A CN109064024A CN 109064024 A CN109064024 A CN 109064024A CN 201810873649 A CN201810873649 A CN 201810873649A CN 109064024 A CN109064024 A CN 109064024A
- Authority
- CN
- China
- Prior art keywords
- list
- cloud server
- cost
- item price
- stored
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 39
- 238000013459 approach Methods 0.000 title claims abstract description 20
- 238000012546 transfer Methods 0.000 claims description 5
- 230000005540 biological transmission Effects 0.000 claims description 4
- 238000000151 deposition Methods 0.000 claims 1
- 238000005516 engineering process Methods 0.000 abstract description 6
- 239000002689 soil Substances 0.000 abstract description 6
- 238000010586 diagram Methods 0.000 description 5
- 238000010276 construction Methods 0.000 description 1
- 238000011156 evaluation Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0631—Resource planning, allocation, distributing or scheduling for enterprises or organisations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Economics (AREA)
- Entrepreneurship & Innovation (AREA)
- Tourism & Hospitality (AREA)
- Theoretical Computer Science (AREA)
- Marketing (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Data Mining & Analysis (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Game Theory and Decision Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention discloses a kind of engineering Whole Process Cost dynamic management approach and systems, it is changing for solving actual soil, equipment, technology labor service and the price contracted, budget and assessment to cost teacher lead to the problem of certain influence, its key points of the technical solution are that, the described method includes: Cloud Server obtains real-time update list and reads the cost list for being stored in Cloud Server, wherein, project name and item price are stored in the update list and cost list;If judgement, which updates list and cost list, identical project name, the item price of the cost list is updated;If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server, achieve the purpose that produce new budget and assessment report according to the soil of change, equipment, technology labor service and the price contracted.
Description
Technical field
The present invention relates to project cost technical field, in particular to a kind of engineering Whole Process Cost dynamic management approach and it is
System.
Background technique
Project cost refers to engineering price, as builds up an engineering, it is contemplated that or it is practical in soil, equipment, technology labor service
And contract etc. in the market, the price and construction project total price of building installation engineering are formed by by modes of doing business such as biddings
Lattice.
But project cost needs muptiple-use budget and assessment, actual soil, equipment, technology labor service and contracts
Price be it is changing, certain influence is led to the problem of to the budget of cost teacher and assessment.
Summary of the invention
The object of the present invention is to provide a kind of engineering Whole Process Cost dynamic management approach and systems, have according to change
Soil, equipment, technology labor service and the price contracted produce the advantages of new budget and assessment report.
In a first aspect, the embodiment of the invention provides a kind of engineering Whole Process Cost dynamic management approach, the method packet
Include: Cloud Server, which obtains real-time update list and simultaneously reads, is stored in the cost list of Cloud Server, wherein the updates list with
Project name and item price are stored in cost list;If judgement, which updates list and cost list, identical entry name
Claim, then the item price of the cost list is updated;Wherein, the item price is updated as by the item of cost list
Mesh price is replaced with the item price for the corresponding project name for updating list;If the item price of the cost list carries out
After update, then the cost list updated is stored in Cloud Server.
By using above-mentioned technical proposal, i.e., go to update cost list by updating list, it can be simultaneously to multiple and different
Cost list timely updated, the secondary budget of cost teacher and the workload of assessment substantially reduce.
Preferably, after the cost list of update is stored in Cloud Server, comprising: judge whether Cloud Server connects
Receive the solicited message of user terminal;Wherein, if Cloud Server receives the solicited message of user terminal, Cloud Server will
The cost list of the update of storage is transferred and is sent in user terminal;If Cloud Server is not received by user terminal
Solicited message, then Cloud Server is not sent data in user terminal.
Preferably, real-time update list is obtained in the Cloud Server and reading is stored in the cost list of Cloud Server
Before, comprising: the Cloud Server obtains the corresponding item price of internet platform according to the project name for updating list, and will more
The item price of new list is updated;Wherein, the item price for updating list is updated as that will update list middle term
The item price of mesh title item price corresponding with the project name in internet is replaced.
Preferably, the corresponding project valence of internet platform is obtained according to the project name for updating list in the Cloud Server
Before lattice, comprising: judge whether the Cloud Server timing sends solicited message into internet platform;Wherein, if the cloud takes
Device transmission solicited message be engaged in into internet platform, then the Cloud Server obtains internet according to the project name for updating list
The corresponding item price of platform;If the Cloud Server does not send solicited message into internet platform, the cloud service
Device does not obtain the corresponding item price of internet platform according to the project name for updating list.
Preferably, before Cloud Server obtains real-time update list and reading is stored in the cost list of Cloud Server, packet
Include: the corresponding item price information of project name for updating list is manually entered.
Second aspect, the embodiment of the invention provides a kind of engineering Whole Process Cost dynamic management systems, including cloud service
Device, the Cloud Server include processor and memory, wherein the memory of the Cloud Server is for storing instruction, described
The processor of Cloud Server is for calling the instruction stored in the memory to perform the following operations: Cloud Server obtains real-time
It updates list and reads the cost list for being stored in Cloud Server, wherein be stored in the update list and cost list
Project name and item price;If judgement, which updates list and cost list, identical project name, the cost list
Item price is updated;Wherein, the item price is updated by the item price of cost list and to update list
The item price of corresponding project name is replaced;If after the item price of the cost list is updated, the institute that updates
Cost list is stated to be stored in Cloud Server.
It preferably, further include user terminal, the user terminal includes processor and memory, wherein the user is whole
For storing instruction, the processor of the user terminal is for calling the instruction stored in the memory to hold for the memory at end
The following operation of row: the cost column that the user terminal sends solicited message into Cloud Server and for receiving Cloud Server transmission
Table: the processor of the Cloud Server is also used to: after the cost list of update is stored in Cloud Server, comprising: sentence
Whether disconnected Cloud Server receives the solicited message of user terminal;Wherein, if Cloud Server receives the request letter of user terminal
Breath, then the cost list of stored update is transferred and is sent in user terminal by Cloud Server;If Cloud Server does not have
There is the solicited message for receiving user terminal, then Cloud Server is not sent data in user terminal.
Preferably, the processor of the Cloud Server is also used to: being obtained real-time update list in the Cloud Server and is read
Before taking the cost list for being stored in Cloud Server, comprising: the Cloud Server obtains interconnection according to the project name for updating list
The corresponding item price of net platform, and the item price for updating list is updated;Wherein, the project valence for updating list
Lattice are updated that the item price corresponding with the project name in internet of the item price of project name in list will be updated
It is replaced.
Preferably, the processor of the Cloud Server is also used to: in the Cloud Server according to the entry name for updating list
Claim before obtaining the corresponding item price of internet platform, comprising: judge the Cloud Server timing whether send solicited message to
In internet platform;Wherein, if the Cloud Server send solicited message into internet platform, the Cloud Server according to
The project name for updating list obtains the corresponding item price of internet platform;If the Cloud Server does not send solicited message
Into internet platform, then the Cloud Server does not obtain the corresponding project of internet platform according to the project name for updating list
Price.
Preferably, the processor for stating Cloud Server is also used to: being obtained real-time update list in Cloud Server and is read storage
Before the cost list of Cloud Server, comprising: the corresponding item price information of project name for updating list carries out manual
Input.
In conclusion the invention has the following advantages:
1, update list by network or artificial mode obtain, the acquiring way for updating list is more, be convenient for cost list
It can timely be updated;
2, multiple cost lists can store in Cloud Server, it, can be to more after Cloud Server gets and updates list
A cost list is updated simultaneously, very convenient;
3, cost list realizes in Cloud Server automatically updates, and reduces the workload of secondary evaluation or budget, while
Manage engineering Whole Process Cost dynamically.
Detailed description of the invention
Fig. 1 is a kind of flow diagram of Whole Process Cost dynamic management approach provided in an embodiment of the present invention;
Fig. 2 is the flow diagram of another Whole Process Cost dynamic management approach provided in an embodiment of the present invention;
Fig. 3 is that the process of another embodiment of another Whole Process Cost dynamic management approach provided in an embodiment of the present invention is shown
It is intended to;
Fig. 4 is a kind of structural schematic diagram of Whole Process Cost dynamic management system provided in an embodiment of the present invention.
Appended drawing reference: 1, Cloud Server;2, user terminal.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art
Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this
All by the protection of Patent Law in the scope of the claims of invention.
Embodiment: being a kind of stream of Whole Process Cost dynamic management approach provided in an embodiment of the present invention referring to Fig. 1, Fig. 1
Journey schematic diagram retouches one of embodiment of the present invention Whole Process Cost dynamic management approach from 1 side of Cloud Server in detail
It states.As shown in Figure 1, this method may comprise steps of S101- step S104.
Step S101: Cloud Server 1 obtains real-time update list and reads the cost list for being stored in Cloud Server 1.
Specifically, being stored with project name and item price in the update list and cost list.It updates in list
Data be to be adjusted according to actual soil, equipment, technology labor service and the price contracted.
Step S102: if judgement updates list and cost list and has identical project name, the item of the cost list
Mesh price is updated.
Specifically, the item price be updated for by the item price of cost list and update list corresponding project
The item price of title is replaced.
Step S103: if after the item price of the cost list is updated, the cost list updated is stored
In Cloud Server 1.
Specifically, the cost list of update is stored in Cloud Server 1 and repeatedly transfers application convenient for data.
Step S104: judge whether Cloud Server 1 receives the solicited message of user terminal 2.
Specifically, if Cloud Server 1 receives the solicited message of user terminal 2, Cloud Server 1 is by stored update
The cost list transfer and be sent in user terminal 2;If Cloud Server 1 is not received by the request letter of user terminal 2
Breath, then Cloud Server 1 is not sent data in user terminal 2.Cloud Server 1 is sent to the cost column of the update of user terminal 2
Table are as follows: period shortest cost list between the time point that the time point of update to solicited message sends.By this way, cloud
Server 1 does not need to send data to user terminal 2 in real time, reduces the computational load of Cloud Server 1.
Referring to fig. 2, Fig. 2 is a kind of process signal of Whole Process Cost dynamic management approach provided in an embodiment of the present invention
Figure, is described in detail one of embodiment of the present invention Whole Process Cost dynamic management approach from 1 side of Cloud Server.Such as figure
Shown in 2, this method may comprise steps of S201 and step S202 before step S101.
Step S201: judge whether 1 timing of Cloud Server sends solicited message into internet platform.
Specifically, thening follow the steps S202 if the Cloud Server 1 sends solicited message into internet platform;If institute
It states Cloud Server 1 and does not send solicited message into internet platform, then do not execute step S202.Internet platform includes profession
Quotation net or sales platform, convenient for getting real-time pricing information.Cloud Server 1 can be obtained from multiple internet platforms
Then data carry out operation by algorithm according to the multi-group data of acquisition and obtain reasonable data.
Step S202: the Cloud Server 1 obtains the corresponding project of internet platform according to the project name for updating list
Price, and the item price for updating list is updated.
Specifically, the item price for updating list is updated as that will update the item price of project name in list
Item price corresponding with the project name in internet is replaced.
By the process, the available pricing information to internet platform of Cloud Server 1 is obtained by way of big data
It is assessed to reasonable prices, updates Engineering Cost Management quickly.It does not need artificially to update, to reduce artificial
Error.
It is another reality of another Whole Process Cost dynamic management approach provided in an embodiment of the present invention referring to Fig. 3, Fig. 3
The flow diagram for applying example, from 1 side of Cloud Server to one of embodiment of the present invention Whole Process Cost dynamic management approach into
Row detailed description.As shown in figure 3, this method may comprise steps of S301 before step S101;
Step S301: the corresponding item price information of project name for updating list is manually entered.
Specifically, being manually entered makes the update for updating list obtain artificial control, keep the data for updating list more quasi-
Really.
Referring to fig. 4, Fig. 4 is a kind of structural representation of Whole Process Cost dynamic management system provided in an embodiment of the present invention
Figure, as shown in figure 4, including Cloud Server 1 and user terminal 2.Cloud Server 1 and user terminal 2 include processor and storage
The memory of device, Cloud Server 1 and user terminal 2 is used to store instruction, and the processor of Cloud Server 1 is for calling described deposit
The instruction that stores in reservoir performs the following operations:
Cloud Server 1 obtains real-time update list and reads the cost list for being stored in Cloud Server 1, wherein the update column
Project name and item price are stored in table and cost list.
If judgement updates list and cost list has identical project name, the item price of the cost list is carried out
It updates;Wherein, the item price be updated for by the item price of cost list and update list corresponding project name
Item price be replaced.
If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server
In 1.
Still further, further including user terminal 2, user terminal 2 includes display screen, receives data for showing.It is described
The processor of user terminal 2 is for calling the instruction stored in the memory to perform the following operations:
The user terminal 2 sends cost list of the solicited message into Cloud Server 1 and for receiving the transmission of Cloud Server 1.
Still further, the processor of the Cloud Server 1 is also used to:
After the cost list of update is stored in Cloud Server 1, comprising: judge whether Cloud Server 1 receives user
The solicited message of terminal 2;Wherein, if Cloud Server 1 receives the solicited message of user terminal 2, Cloud Server 1 will have been stored
The cost list of update transfer and be sent in user terminal 2.
If Cloud Server 1 is not received by the solicited message of user terminal 2, Cloud Server 1 does not send data to user
In terminal 2.
Still further, the processor of the Cloud Server 1 is also used to:
Before the Cloud Server 1 obtains real-time update list and reading is stored in the cost list of Cloud Server 1, comprising: institute
It states Cloud Server 1 and the corresponding item price of internet platform is obtained according to the project name for updating list, and list will be updated
Item price is updated;Wherein, the item price for updating list is updated as that will update project name in list
Item price item price corresponding with the project name in internet is replaced.
Still further, the processor of the Cloud Server 1 is also used to:
Before the Cloud Server 1 obtains the corresponding item price of internet platform according to the project name for updating list, comprising:
Judge whether 1 timing of Cloud Server sends solicited message into internet platform;Wherein, if the Cloud Server 1 is sent
Solicited message is into internet platform, then the Cloud Server 1 obtains internet platform pair according to the project name for updating list
The item price answered;If the Cloud Server 1 does not send solicited message into internet platform, the Cloud Server 1 is not
The corresponding item price of internet platform is obtained according to the project name for updating list.
Still further, the processor of the Cloud Server 1 is also used to:
Cloud Server 1 obtain real-time update list and read be stored in the cost list of Cloud Server 1 before, comprising: it is described more
The corresponding item price information of project name of new list is manually entered.
Claims (10)
1. a kind of engineering Whole Process Cost dynamic management approach, which is characterized in that the described method includes:
Cloud Server (1), which obtains real-time update list and simultaneously reads, is stored in the cost list of Cloud Server (1), wherein it is described more
Project name and item price are stored in new list and cost list;
If judgement updates list and cost list has identical project name, the item price of the cost list is carried out more
Newly;
Wherein, the item price is updated by the item price of cost list and to update the corresponding project name of list
Item price is replaced;
If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server (1)
In.
2. a kind of engineering Whole Process Cost dynamic management approach according to claim 1, which is characterized in that in the institute of update
It states after cost list is stored in Cloud Server (1), comprising: judge whether Cloud Server (1) receives asking for user terminal (2)
Seek information;Wherein,
If Cloud Server (1) receives the solicited message of user terminal (2), Cloud Server (1) is by the institute of stored update
Cost list is stated to transfer and be sent in user terminal (2);
If Cloud Server (1) is not received by the solicited message of user terminal (2), Cloud Server (1) does not send data to use
In family terminal (2).
3. a kind of engineering Whole Process Cost dynamic management approach according to claim 1, which is characterized in that taken in the cloud
Before business device (1) acquisition real-time update list and reading are stored in the cost list of Cloud Server (1), comprising: the Cloud Server
(1) the corresponding item price of internet platform, and the item price that will update list are obtained according to the project name for updating list
It is updated;Wherein, the item price for updating list is updated as that will update the item price of project name in list
Item price corresponding with the project name in internet is replaced.
4. a kind of engineering Whole Process Cost dynamic management approach according to claim 3, which is characterized in that taken in the cloud
Before device (1) is engaged according to the corresponding item price of project name acquisition internet platform for updating list, comprising: judge the cloud clothes
Whether business device (1) timing sends solicited message into internet platform;Wherein, if the Cloud Server (1) sends solicited message
Into internet platform, then the Cloud Server (1) obtains the corresponding item of internet platform according to the project name for updating list
Mesh price;If the Cloud Server (1) does not send solicited message into internet platform, the Cloud Server (1) not root
The corresponding item price of internet platform is obtained according to the project name for updating list.
5. a kind of engineering Whole Process Cost dynamic management approach according to claim 1, which is characterized in that in Cloud Server
(1) before acquisition real-time update list and reading are stored in the cost list of Cloud Server (1), comprising: the item for updating list
The corresponding item price information of mesh title is manually entered.
6. a kind of engineering Whole Process Cost dynamic management system, which is characterized in that including Cloud Server (1), the Cloud Server
(1) include processor and memory, wherein the memory of the Cloud Server (1) for storing instruction, the Cloud Server
(1) processor is for calling the instruction stored in the memory to perform the following operations:
Cloud Server (1), which obtains real-time update list and simultaneously reads, is stored in the cost list of Cloud Server (1), wherein it is described more
Project name and item price are stored in new list and cost list;
If judgement updates list and cost list has identical project name, the item price of the cost list is carried out more
Newly;
Wherein, the item price is updated by the item price of cost list and to update the corresponding project name of list
Item price is replaced;
If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server (1)
In.
7. a kind of engineering Whole Process Cost dynamic management system according to claim 6, which is characterized in that further include user
Terminal (2), the user terminal (2) includes processor and memory, wherein the memory of the user terminal (2) is for depositing
Storage instruction, the processor of the user terminal (2) is for calling the instruction stored in the memory to perform the following operations: institute
It states user terminal (2) and sends cost list of the solicited message in Cloud Server (1) and for receiving Cloud Server (1) transmission:
The processor of the Cloud Server (1) is also used to:
After the cost list of update is stored in Cloud Server (1), comprising: judge whether Cloud Server (1) receives
The solicited message of user terminal (2);Wherein,
If Cloud Server (1) receives the solicited message of user terminal (2), Cloud Server (1) is by the institute of stored update
Cost list is stated to transfer and be sent in user terminal (2);
If Cloud Server (1) is not received by the solicited message of user terminal (2), Cloud Server (1) does not send data to use
In family terminal (2).
8. a kind of engineering Whole Process Cost dynamic management system according to claim 6, which is characterized in that the cloud service
The processor of device (1) is also used to:
Before the Cloud Server (1) obtains real-time update list and reading is stored in the cost list of Cloud Server (1), packet
Include: the Cloud Server (1) obtains the corresponding item price of internet platform according to the project name for updating list, and will update
The item price of list is updated;Wherein, the item price for updating list is updated as that will update project in list
The item price of title item price corresponding with the project name in internet is replaced.
9. a kind of engineering Whole Process Cost dynamic management system according to claim 8, which is characterized in that the cloud service
The processor of device (1) is also used to:
Before the Cloud Server (1) obtains the corresponding item price of internet platform according to the project name for updating list, packet
It includes: judging whether the Cloud Server (1) timing sends solicited message into internet platform;Wherein, if the Cloud Server
(1) solicited message is sent into internet platform, then the Cloud Server (1) obtains interconnection according to the project name for updating list
The corresponding item price of net platform;If the Cloud Server (1) does not send solicited message into internet platform, the cloud
Server (1) does not obtain the corresponding item price of internet platform according to the project name for updating list.
10. a kind of engineering Whole Process Cost dynamic management system according to claim 6, which is characterized in that the cloud clothes
The processor of business device (1) is also used to:
Before Cloud Server (1) obtains real-time update list and reading is stored in the cost list of Cloud Server (1), comprising: institute
The corresponding item price information of project name for stating update list is manually entered.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810873649.2A CN109064024A (en) | 2018-08-02 | 2018-08-02 | A kind of engineering Whole Process Cost dynamic management approach and system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810873649.2A CN109064024A (en) | 2018-08-02 | 2018-08-02 | A kind of engineering Whole Process Cost dynamic management approach and system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109064024A true CN109064024A (en) | 2018-12-21 |
Family
ID=64832900
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810873649.2A Pending CN109064024A (en) | 2018-08-02 | 2018-08-02 | A kind of engineering Whole Process Cost dynamic management approach and system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109064024A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110189175A (en) * | 2019-05-29 | 2019-08-30 | 广东粤能工程管理有限公司 | A kind of project cost consulting system and method |
CN110557361A (en) * | 2019-03-14 | 2019-12-10 | 深圳市丰浩达工程项目管理有限公司 | Method and system for dynamically managing overall process cost |
CN111553633A (en) * | 2020-04-25 | 2020-08-18 | 达信建设发展有限公司 | Engineering cost management system and method |
CN113793126A (en) * | 2021-09-18 | 2021-12-14 | 河南柏诚工程管理有限公司 | Real-time dynamic monitoring method, system, terminal and storage medium for engineering cost |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100800547B1 (en) * | 2006-12-28 | 2008-02-04 | 주식회사 포스코건설 | Method of construction process management connecting cost information by element |
CN201689418U (en) * | 2010-04-14 | 2010-12-29 | 北京喻龙恒瑞科技有限公司 | Management data sheet updating device and managing system |
CN105260954A (en) * | 2015-10-09 | 2016-01-20 | 重庆工商职业学院 | Construction cost list service system based on Internet-of-things technology |
CN106530143A (en) * | 2016-11-08 | 2017-03-22 | 河南财政税务高等专科学校 | Engineering cost list service system |
CN206863742U (en) * | 2017-04-01 | 2018-01-09 | 欧群雍 | A kind of construction engineering cost specific information storage system |
CN108322341A (en) * | 2018-01-30 | 2018-07-24 | 上海康斐信息技术有限公司 | A kind of method and system in update router configuration data library |
-
2018
- 2018-08-02 CN CN201810873649.2A patent/CN109064024A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100800547B1 (en) * | 2006-12-28 | 2008-02-04 | 주식회사 포스코건설 | Method of construction process management connecting cost information by element |
CN201689418U (en) * | 2010-04-14 | 2010-12-29 | 北京喻龙恒瑞科技有限公司 | Management data sheet updating device and managing system |
CN105260954A (en) * | 2015-10-09 | 2016-01-20 | 重庆工商职业学院 | Construction cost list service system based on Internet-of-things technology |
CN106530143A (en) * | 2016-11-08 | 2017-03-22 | 河南财政税务高等专科学校 | Engineering cost list service system |
CN206863742U (en) * | 2017-04-01 | 2018-01-09 | 欧群雍 | A kind of construction engineering cost specific information storage system |
CN108322341A (en) * | 2018-01-30 | 2018-07-24 | 上海康斐信息技术有限公司 | A kind of method and system in update router configuration data library |
Non-Patent Citations (1)
Title |
---|
卢凤霞等: "基于BIM技术的电力工程造价管理研究", 《江西建材》 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110557361A (en) * | 2019-03-14 | 2019-12-10 | 深圳市丰浩达工程项目管理有限公司 | Method and system for dynamically managing overall process cost |
CN110557361B (en) * | 2019-03-14 | 2022-04-26 | 深圳市丰浩达工程项目管理有限公司 | Method and system for dynamically managing overall process cost |
CN110189175A (en) * | 2019-05-29 | 2019-08-30 | 广东粤能工程管理有限公司 | A kind of project cost consulting system and method |
CN111553633A (en) * | 2020-04-25 | 2020-08-18 | 达信建设发展有限公司 | Engineering cost management system and method |
CN113793126A (en) * | 2021-09-18 | 2021-12-14 | 河南柏诚工程管理有限公司 | Real-time dynamic monitoring method, system, terminal and storage medium for engineering cost |
CN113793126B (en) * | 2021-09-18 | 2024-01-19 | 柏诚工程管理有限公司 | Real-time dynamic monitoring method, system, terminal and storage medium for engineering cost |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109064024A (en) | A kind of engineering Whole Process Cost dynamic management approach and system | |
CN109559147B (en) | Advertisement traffic prediction method, device, server and readable storage medium | |
CN107316208B (en) | Shared automobile shared network point layout and site selection model | |
CN109508839A (en) | Order allocation method and device | |
CN113177749A (en) | Resource management method and device | |
CN109600447A (en) | For handling the methods, devices and systems of data | |
CN107241380A (en) | For the method and apparatus of the load balancing adjusted based on the time | |
US20190102746A1 (en) | Systems and method for dynamic scheduling of service appointments | |
CN109816446A (en) | A kind of cross-platform advertisement data processing method and device | |
CN111127154A (en) | Order processing method, device, server and nonvolatile storage medium | |
CN110490440A (en) | Service on buses or trains Routing Scheme and value multiply the optimization method and device of the integrated establishment of plan | |
CN113393060A (en) | Task allocation method and device, electronic equipment and storage medium | |
CN108520329B (en) | Accurate automatic allocation method and device for second-hand house clients based on broker portrait | |
CN111369025A (en) | Information display method and device, storage medium and electronic equipment | |
Ernst et al. | Dynamic scheduling of recreational rental vehicles with revenue management extensions | |
CN114298870A (en) | Path planning method and device, electronic equipment and computer readable medium | |
CN116340841A (en) | Data classification model training method based on transverse federal learning and related components thereof | |
CN104079631B (en) | A kind of method for edition management and relevant apparatus | |
CN114221960B (en) | Data pushing method based on automatic driving bus and automatic driving bus | |
CN115098290A (en) | Intelligent artificial service method and device based on automatically updated NLP model | |
CN111178823B (en) | Method and device for canceling residence related transaction | |
Barbarosoglu et al. | Mobile applications for the construction industry | |
KR101076420B1 (en) | Activity based project management apparatus and method | |
CN111325365A (en) | Method and device for pre-selling combined intermodal tickets | |
CN109474702A (en) | Information recommendation method, device, computer equipment and product |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181221 |