CN109064024A - A kind of engineering Whole Process Cost dynamic management approach and system - Google Patents

A kind of engineering Whole Process Cost dynamic management approach and system Download PDF

Info

Publication number
CN109064024A
CN109064024A CN201810873649.2A CN201810873649A CN109064024A CN 109064024 A CN109064024 A CN 109064024A CN 201810873649 A CN201810873649 A CN 201810873649A CN 109064024 A CN109064024 A CN 109064024A
Authority
CN
China
Prior art keywords
list
cloud server
cost
item price
stored
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810873649.2A
Other languages
Chinese (zh)
Inventor
刘寰湘
邓永维
卢亮华
谭超华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Zhencheng Engineering Consulting Co Ltd
Original Assignee
Guangdong Zhencheng Engineering Consulting Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Zhencheng Engineering Consulting Co Ltd filed Critical Guangdong Zhencheng Engineering Consulting Co Ltd
Priority to CN201810873649.2A priority Critical patent/CN109064024A/en
Publication of CN109064024A publication Critical patent/CN109064024A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Data Mining & Analysis (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of engineering Whole Process Cost dynamic management approach and systems, it is changing for solving actual soil, equipment, technology labor service and the price contracted, budget and assessment to cost teacher lead to the problem of certain influence, its key points of the technical solution are that, the described method includes: Cloud Server obtains real-time update list and reads the cost list for being stored in Cloud Server, wherein, project name and item price are stored in the update list and cost list;If judgement, which updates list and cost list, identical project name, the item price of the cost list is updated;If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server, achieve the purpose that produce new budget and assessment report according to the soil of change, equipment, technology labor service and the price contracted.

Description

A kind of engineering Whole Process Cost dynamic management approach and system
Technical field
The present invention relates to project cost technical field, in particular to a kind of engineering Whole Process Cost dynamic management approach and it is System.
Background technique
Project cost refers to engineering price, as builds up an engineering, it is contemplated that or it is practical in soil, equipment, technology labor service And contract etc. in the market, the price and construction project total price of building installation engineering are formed by by modes of doing business such as biddings Lattice.
But project cost needs muptiple-use budget and assessment, actual soil, equipment, technology labor service and contracts Price be it is changing, certain influence is led to the problem of to the budget of cost teacher and assessment.
Summary of the invention
The object of the present invention is to provide a kind of engineering Whole Process Cost dynamic management approach and systems, have according to change Soil, equipment, technology labor service and the price contracted produce the advantages of new budget and assessment report.
In a first aspect, the embodiment of the invention provides a kind of engineering Whole Process Cost dynamic management approach, the method packet Include: Cloud Server, which obtains real-time update list and simultaneously reads, is stored in the cost list of Cloud Server, wherein the updates list with Project name and item price are stored in cost list;If judgement, which updates list and cost list, identical entry name Claim, then the item price of the cost list is updated;Wherein, the item price is updated as by the item of cost list Mesh price is replaced with the item price for the corresponding project name for updating list;If the item price of the cost list carries out After update, then the cost list updated is stored in Cloud Server.
By using above-mentioned technical proposal, i.e., go to update cost list by updating list, it can be simultaneously to multiple and different Cost list timely updated, the secondary budget of cost teacher and the workload of assessment substantially reduce.
Preferably, after the cost list of update is stored in Cloud Server, comprising: judge whether Cloud Server connects Receive the solicited message of user terminal;Wherein, if Cloud Server receives the solicited message of user terminal, Cloud Server will The cost list of the update of storage is transferred and is sent in user terminal;If Cloud Server is not received by user terminal Solicited message, then Cloud Server is not sent data in user terminal.
Preferably, real-time update list is obtained in the Cloud Server and reading is stored in the cost list of Cloud Server Before, comprising: the Cloud Server obtains the corresponding item price of internet platform according to the project name for updating list, and will more The item price of new list is updated;Wherein, the item price for updating list is updated as that will update list middle term The item price of mesh title item price corresponding with the project name in internet is replaced.
Preferably, the corresponding project valence of internet platform is obtained according to the project name for updating list in the Cloud Server Before lattice, comprising: judge whether the Cloud Server timing sends solicited message into internet platform;Wherein, if the cloud takes Device transmission solicited message be engaged in into internet platform, then the Cloud Server obtains internet according to the project name for updating list The corresponding item price of platform;If the Cloud Server does not send solicited message into internet platform, the cloud service Device does not obtain the corresponding item price of internet platform according to the project name for updating list.
Preferably, before Cloud Server obtains real-time update list and reading is stored in the cost list of Cloud Server, packet Include: the corresponding item price information of project name for updating list is manually entered.
Second aspect, the embodiment of the invention provides a kind of engineering Whole Process Cost dynamic management systems, including cloud service Device, the Cloud Server include processor and memory, wherein the memory of the Cloud Server is for storing instruction, described The processor of Cloud Server is for calling the instruction stored in the memory to perform the following operations: Cloud Server obtains real-time It updates list and reads the cost list for being stored in Cloud Server, wherein be stored in the update list and cost list Project name and item price;If judgement, which updates list and cost list, identical project name, the cost list Item price is updated;Wherein, the item price is updated by the item price of cost list and to update list The item price of corresponding project name is replaced;If after the item price of the cost list is updated, the institute that updates Cost list is stated to be stored in Cloud Server.
It preferably, further include user terminal, the user terminal includes processor and memory, wherein the user is whole For storing instruction, the processor of the user terminal is for calling the instruction stored in the memory to hold for the memory at end The following operation of row: the cost column that the user terminal sends solicited message into Cloud Server and for receiving Cloud Server transmission Table: the processor of the Cloud Server is also used to: after the cost list of update is stored in Cloud Server, comprising: sentence Whether disconnected Cloud Server receives the solicited message of user terminal;Wherein, if Cloud Server receives the request letter of user terminal Breath, then the cost list of stored update is transferred and is sent in user terminal by Cloud Server;If Cloud Server does not have There is the solicited message for receiving user terminal, then Cloud Server is not sent data in user terminal.
Preferably, the processor of the Cloud Server is also used to: being obtained real-time update list in the Cloud Server and is read Before taking the cost list for being stored in Cloud Server, comprising: the Cloud Server obtains interconnection according to the project name for updating list The corresponding item price of net platform, and the item price for updating list is updated;Wherein, the project valence for updating list Lattice are updated that the item price corresponding with the project name in internet of the item price of project name in list will be updated It is replaced.
Preferably, the processor of the Cloud Server is also used to: in the Cloud Server according to the entry name for updating list Claim before obtaining the corresponding item price of internet platform, comprising: judge the Cloud Server timing whether send solicited message to In internet platform;Wherein, if the Cloud Server send solicited message into internet platform, the Cloud Server according to The project name for updating list obtains the corresponding item price of internet platform;If the Cloud Server does not send solicited message Into internet platform, then the Cloud Server does not obtain the corresponding project of internet platform according to the project name for updating list Price.
Preferably, the processor for stating Cloud Server is also used to: being obtained real-time update list in Cloud Server and is read storage Before the cost list of Cloud Server, comprising: the corresponding item price information of project name for updating list carries out manual Input.
In conclusion the invention has the following advantages:
1, update list by network or artificial mode obtain, the acquiring way for updating list is more, be convenient for cost list It can timely be updated;
2, multiple cost lists can store in Cloud Server, it, can be to more after Cloud Server gets and updates list A cost list is updated simultaneously, very convenient;
3, cost list realizes in Cloud Server automatically updates, and reduces the workload of secondary evaluation or budget, while Manage engineering Whole Process Cost dynamically.
Detailed description of the invention
Fig. 1 is a kind of flow diagram of Whole Process Cost dynamic management approach provided in an embodiment of the present invention;
Fig. 2 is the flow diagram of another Whole Process Cost dynamic management approach provided in an embodiment of the present invention;
Fig. 3 is that the process of another embodiment of another Whole Process Cost dynamic management approach provided in an embodiment of the present invention is shown It is intended to;
Fig. 4 is a kind of structural schematic diagram of Whole Process Cost dynamic management system provided in an embodiment of the present invention.
Appended drawing reference: 1, Cloud Server;2, user terminal.
Specific embodiment
Below in conjunction with attached drawing, invention is further described in detail.
This specific embodiment is only explanation of the invention, is not limitation of the present invention, those skilled in the art Member can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but as long as at this All by the protection of Patent Law in the scope of the claims of invention.
Embodiment: being a kind of stream of Whole Process Cost dynamic management approach provided in an embodiment of the present invention referring to Fig. 1, Fig. 1 Journey schematic diagram retouches one of embodiment of the present invention Whole Process Cost dynamic management approach from 1 side of Cloud Server in detail It states.As shown in Figure 1, this method may comprise steps of S101- step S104.
Step S101: Cloud Server 1 obtains real-time update list and reads the cost list for being stored in Cloud Server 1.
Specifically, being stored with project name and item price in the update list and cost list.It updates in list Data be to be adjusted according to actual soil, equipment, technology labor service and the price contracted.
Step S102: if judgement updates list and cost list and has identical project name, the item of the cost list Mesh price is updated.
Specifically, the item price be updated for by the item price of cost list and update list corresponding project The item price of title is replaced.
Step S103: if after the item price of the cost list is updated, the cost list updated is stored In Cloud Server 1.
Specifically, the cost list of update is stored in Cloud Server 1 and repeatedly transfers application convenient for data.
Step S104: judge whether Cloud Server 1 receives the solicited message of user terminal 2.
Specifically, if Cloud Server 1 receives the solicited message of user terminal 2, Cloud Server 1 is by stored update The cost list transfer and be sent in user terminal 2;If Cloud Server 1 is not received by the request letter of user terminal 2 Breath, then Cloud Server 1 is not sent data in user terminal 2.Cloud Server 1 is sent to the cost column of the update of user terminal 2 Table are as follows: period shortest cost list between the time point that the time point of update to solicited message sends.By this way, cloud Server 1 does not need to send data to user terminal 2 in real time, reduces the computational load of Cloud Server 1.
Referring to fig. 2, Fig. 2 is a kind of process signal of Whole Process Cost dynamic management approach provided in an embodiment of the present invention Figure, is described in detail one of embodiment of the present invention Whole Process Cost dynamic management approach from 1 side of Cloud Server.Such as figure Shown in 2, this method may comprise steps of S201 and step S202 before step S101.
Step S201: judge whether 1 timing of Cloud Server sends solicited message into internet platform.
Specifically, thening follow the steps S202 if the Cloud Server 1 sends solicited message into internet platform;If institute It states Cloud Server 1 and does not send solicited message into internet platform, then do not execute step S202.Internet platform includes profession Quotation net or sales platform, convenient for getting real-time pricing information.Cloud Server 1 can be obtained from multiple internet platforms Then data carry out operation by algorithm according to the multi-group data of acquisition and obtain reasonable data.
Step S202: the Cloud Server 1 obtains the corresponding project of internet platform according to the project name for updating list Price, and the item price for updating list is updated.
Specifically, the item price for updating list is updated as that will update the item price of project name in list Item price corresponding with the project name in internet is replaced.
By the process, the available pricing information to internet platform of Cloud Server 1 is obtained by way of big data It is assessed to reasonable prices, updates Engineering Cost Management quickly.It does not need artificially to update, to reduce artificial Error.
It is another reality of another Whole Process Cost dynamic management approach provided in an embodiment of the present invention referring to Fig. 3, Fig. 3 The flow diagram for applying example, from 1 side of Cloud Server to one of embodiment of the present invention Whole Process Cost dynamic management approach into Row detailed description.As shown in figure 3, this method may comprise steps of S301 before step S101;
Step S301: the corresponding item price information of project name for updating list is manually entered.
Specifically, being manually entered makes the update for updating list obtain artificial control, keep the data for updating list more quasi- Really.
Referring to fig. 4, Fig. 4 is a kind of structural representation of Whole Process Cost dynamic management system provided in an embodiment of the present invention Figure, as shown in figure 4, including Cloud Server 1 and user terminal 2.Cloud Server 1 and user terminal 2 include processor and storage The memory of device, Cloud Server 1 and user terminal 2 is used to store instruction, and the processor of Cloud Server 1 is for calling described deposit The instruction that stores in reservoir performs the following operations:
Cloud Server 1 obtains real-time update list and reads the cost list for being stored in Cloud Server 1, wherein the update column Project name and item price are stored in table and cost list.
If judgement updates list and cost list has identical project name, the item price of the cost list is carried out It updates;Wherein, the item price be updated for by the item price of cost list and update list corresponding project name Item price be replaced.
If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server In 1.
Still further, further including user terminal 2, user terminal 2 includes display screen, receives data for showing.It is described The processor of user terminal 2 is for calling the instruction stored in the memory to perform the following operations:
The user terminal 2 sends cost list of the solicited message into Cloud Server 1 and for receiving the transmission of Cloud Server 1.
Still further, the processor of the Cloud Server 1 is also used to:
After the cost list of update is stored in Cloud Server 1, comprising: judge whether Cloud Server 1 receives user The solicited message of terminal 2;Wherein, if Cloud Server 1 receives the solicited message of user terminal 2, Cloud Server 1 will have been stored The cost list of update transfer and be sent in user terminal 2.
If Cloud Server 1 is not received by the solicited message of user terminal 2, Cloud Server 1 does not send data to user In terminal 2.
Still further, the processor of the Cloud Server 1 is also used to:
Before the Cloud Server 1 obtains real-time update list and reading is stored in the cost list of Cloud Server 1, comprising: institute It states Cloud Server 1 and the corresponding item price of internet platform is obtained according to the project name for updating list, and list will be updated Item price is updated;Wherein, the item price for updating list is updated as that will update project name in list Item price item price corresponding with the project name in internet is replaced.
Still further, the processor of the Cloud Server 1 is also used to:
Before the Cloud Server 1 obtains the corresponding item price of internet platform according to the project name for updating list, comprising: Judge whether 1 timing of Cloud Server sends solicited message into internet platform;Wherein, if the Cloud Server 1 is sent Solicited message is into internet platform, then the Cloud Server 1 obtains internet platform pair according to the project name for updating list The item price answered;If the Cloud Server 1 does not send solicited message into internet platform, the Cloud Server 1 is not The corresponding item price of internet platform is obtained according to the project name for updating list.
Still further, the processor of the Cloud Server 1 is also used to:
Cloud Server 1 obtain real-time update list and read be stored in the cost list of Cloud Server 1 before, comprising: it is described more The corresponding item price information of project name of new list is manually entered.

Claims (10)

1. a kind of engineering Whole Process Cost dynamic management approach, which is characterized in that the described method includes:
Cloud Server (1), which obtains real-time update list and simultaneously reads, is stored in the cost list of Cloud Server (1), wherein it is described more Project name and item price are stored in new list and cost list;
If judgement updates list and cost list has identical project name, the item price of the cost list is carried out more Newly;
Wherein, the item price is updated by the item price of cost list and to update the corresponding project name of list Item price is replaced;
If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server (1) In.
2. a kind of engineering Whole Process Cost dynamic management approach according to claim 1, which is characterized in that in the institute of update It states after cost list is stored in Cloud Server (1), comprising: judge whether Cloud Server (1) receives asking for user terminal (2) Seek information;Wherein,
If Cloud Server (1) receives the solicited message of user terminal (2), Cloud Server (1) is by the institute of stored update Cost list is stated to transfer and be sent in user terminal (2);
If Cloud Server (1) is not received by the solicited message of user terminal (2), Cloud Server (1) does not send data to use In family terminal (2).
3. a kind of engineering Whole Process Cost dynamic management approach according to claim 1, which is characterized in that taken in the cloud Before business device (1) acquisition real-time update list and reading are stored in the cost list of Cloud Server (1), comprising: the Cloud Server (1) the corresponding item price of internet platform, and the item price that will update list are obtained according to the project name for updating list It is updated;Wherein, the item price for updating list is updated as that will update the item price of project name in list Item price corresponding with the project name in internet is replaced.
4. a kind of engineering Whole Process Cost dynamic management approach according to claim 3, which is characterized in that taken in the cloud Before device (1) is engaged according to the corresponding item price of project name acquisition internet platform for updating list, comprising: judge the cloud clothes Whether business device (1) timing sends solicited message into internet platform;Wherein, if the Cloud Server (1) sends solicited message Into internet platform, then the Cloud Server (1) obtains the corresponding item of internet platform according to the project name for updating list Mesh price;If the Cloud Server (1) does not send solicited message into internet platform, the Cloud Server (1) not root The corresponding item price of internet platform is obtained according to the project name for updating list.
5. a kind of engineering Whole Process Cost dynamic management approach according to claim 1, which is characterized in that in Cloud Server (1) before acquisition real-time update list and reading are stored in the cost list of Cloud Server (1), comprising: the item for updating list The corresponding item price information of mesh title is manually entered.
6. a kind of engineering Whole Process Cost dynamic management system, which is characterized in that including Cloud Server (1), the Cloud Server (1) include processor and memory, wherein the memory of the Cloud Server (1) for storing instruction, the Cloud Server (1) processor is for calling the instruction stored in the memory to perform the following operations:
Cloud Server (1), which obtains real-time update list and simultaneously reads, is stored in the cost list of Cloud Server (1), wherein it is described more Project name and item price are stored in new list and cost list;
If judgement updates list and cost list has identical project name, the item price of the cost list is carried out more Newly;
Wherein, the item price is updated by the item price of cost list and to update the corresponding project name of list Item price is replaced;
If after the item price of the cost list is updated, the cost list updated is stored in Cloud Server (1) In.
7. a kind of engineering Whole Process Cost dynamic management system according to claim 6, which is characterized in that further include user Terminal (2), the user terminal (2) includes processor and memory, wherein the memory of the user terminal (2) is for depositing Storage instruction, the processor of the user terminal (2) is for calling the instruction stored in the memory to perform the following operations: institute It states user terminal (2) and sends cost list of the solicited message in Cloud Server (1) and for receiving Cloud Server (1) transmission:
The processor of the Cloud Server (1) is also used to:
After the cost list of update is stored in Cloud Server (1), comprising: judge whether Cloud Server (1) receives The solicited message of user terminal (2);Wherein,
If Cloud Server (1) receives the solicited message of user terminal (2), Cloud Server (1) is by the institute of stored update Cost list is stated to transfer and be sent in user terminal (2);
If Cloud Server (1) is not received by the solicited message of user terminal (2), Cloud Server (1) does not send data to use In family terminal (2).
8. a kind of engineering Whole Process Cost dynamic management system according to claim 6, which is characterized in that the cloud service The processor of device (1) is also used to:
Before the Cloud Server (1) obtains real-time update list and reading is stored in the cost list of Cloud Server (1), packet Include: the Cloud Server (1) obtains the corresponding item price of internet platform according to the project name for updating list, and will update The item price of list is updated;Wherein, the item price for updating list is updated as that will update project in list The item price of title item price corresponding with the project name in internet is replaced.
9. a kind of engineering Whole Process Cost dynamic management system according to claim 8, which is characterized in that the cloud service The processor of device (1) is also used to:
Before the Cloud Server (1) obtains the corresponding item price of internet platform according to the project name for updating list, packet It includes: judging whether the Cloud Server (1) timing sends solicited message into internet platform;Wherein, if the Cloud Server (1) solicited message is sent into internet platform, then the Cloud Server (1) obtains interconnection according to the project name for updating list The corresponding item price of net platform;If the Cloud Server (1) does not send solicited message into internet platform, the cloud Server (1) does not obtain the corresponding item price of internet platform according to the project name for updating list.
10. a kind of engineering Whole Process Cost dynamic management system according to claim 6, which is characterized in that the cloud clothes The processor of business device (1) is also used to:
Before Cloud Server (1) obtains real-time update list and reading is stored in the cost list of Cloud Server (1), comprising: institute The corresponding item price information of project name for stating update list is manually entered.
CN201810873649.2A 2018-08-02 2018-08-02 A kind of engineering Whole Process Cost dynamic management approach and system Pending CN109064024A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810873649.2A CN109064024A (en) 2018-08-02 2018-08-02 A kind of engineering Whole Process Cost dynamic management approach and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810873649.2A CN109064024A (en) 2018-08-02 2018-08-02 A kind of engineering Whole Process Cost dynamic management approach and system

Publications (1)

Publication Number Publication Date
CN109064024A true CN109064024A (en) 2018-12-21

Family

ID=64832900

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810873649.2A Pending CN109064024A (en) 2018-08-02 2018-08-02 A kind of engineering Whole Process Cost dynamic management approach and system

Country Status (1)

Country Link
CN (1) CN109064024A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110189175A (en) * 2019-05-29 2019-08-30 广东粤能工程管理有限公司 A kind of project cost consulting system and method
CN110557361A (en) * 2019-03-14 2019-12-10 深圳市丰浩达工程项目管理有限公司 Method and system for dynamically managing overall process cost
CN111553633A (en) * 2020-04-25 2020-08-18 达信建设发展有限公司 Engineering cost management system and method
CN113793126A (en) * 2021-09-18 2021-12-14 河南柏诚工程管理有限公司 Real-time dynamic monitoring method, system, terminal and storage medium for engineering cost

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100800547B1 (en) * 2006-12-28 2008-02-04 주식회사 포스코건설 Method of construction process management connecting cost information by element
CN201689418U (en) * 2010-04-14 2010-12-29 北京喻龙恒瑞科技有限公司 Management data sheet updating device and managing system
CN105260954A (en) * 2015-10-09 2016-01-20 重庆工商职业学院 Construction cost list service system based on Internet-of-things technology
CN106530143A (en) * 2016-11-08 2017-03-22 河南财政税务高等专科学校 Engineering cost list service system
CN206863742U (en) * 2017-04-01 2018-01-09 欧群雍 A kind of construction engineering cost specific information storage system
CN108322341A (en) * 2018-01-30 2018-07-24 上海康斐信息技术有限公司 A kind of method and system in update router configuration data library

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100800547B1 (en) * 2006-12-28 2008-02-04 주식회사 포스코건설 Method of construction process management connecting cost information by element
CN201689418U (en) * 2010-04-14 2010-12-29 北京喻龙恒瑞科技有限公司 Management data sheet updating device and managing system
CN105260954A (en) * 2015-10-09 2016-01-20 重庆工商职业学院 Construction cost list service system based on Internet-of-things technology
CN106530143A (en) * 2016-11-08 2017-03-22 河南财政税务高等专科学校 Engineering cost list service system
CN206863742U (en) * 2017-04-01 2018-01-09 欧群雍 A kind of construction engineering cost specific information storage system
CN108322341A (en) * 2018-01-30 2018-07-24 上海康斐信息技术有限公司 A kind of method and system in update router configuration data library

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
卢凤霞等: "基于BIM技术的电力工程造价管理研究", 《江西建材》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110557361A (en) * 2019-03-14 2019-12-10 深圳市丰浩达工程项目管理有限公司 Method and system for dynamically managing overall process cost
CN110557361B (en) * 2019-03-14 2022-04-26 深圳市丰浩达工程项目管理有限公司 Method and system for dynamically managing overall process cost
CN110189175A (en) * 2019-05-29 2019-08-30 广东粤能工程管理有限公司 A kind of project cost consulting system and method
CN111553633A (en) * 2020-04-25 2020-08-18 达信建设发展有限公司 Engineering cost management system and method
CN113793126A (en) * 2021-09-18 2021-12-14 河南柏诚工程管理有限公司 Real-time dynamic monitoring method, system, terminal and storage medium for engineering cost
CN113793126B (en) * 2021-09-18 2024-01-19 柏诚工程管理有限公司 Real-time dynamic monitoring method, system, terminal and storage medium for engineering cost

Similar Documents

Publication Publication Date Title
CN109064024A (en) A kind of engineering Whole Process Cost dynamic management approach and system
CN109559147B (en) Advertisement traffic prediction method, device, server and readable storage medium
CN107316208B (en) Shared automobile shared network point layout and site selection model
CN109508839A (en) Order allocation method and device
CN113177749A (en) Resource management method and device
CN109600447A (en) For handling the methods, devices and systems of data
CN107241380A (en) For the method and apparatus of the load balancing adjusted based on the time
US20190102746A1 (en) Systems and method for dynamic scheduling of service appointments
CN109816446A (en) A kind of cross-platform advertisement data processing method and device
CN111127154A (en) Order processing method, device, server and nonvolatile storage medium
CN110490440A (en) Service on buses or trains Routing Scheme and value multiply the optimization method and device of the integrated establishment of plan
CN113393060A (en) Task allocation method and device, electronic equipment and storage medium
CN108520329B (en) Accurate automatic allocation method and device for second-hand house clients based on broker portrait
CN111369025A (en) Information display method and device, storage medium and electronic equipment
Ernst et al. Dynamic scheduling of recreational rental vehicles with revenue management extensions
CN114298870A (en) Path planning method and device, electronic equipment and computer readable medium
CN116340841A (en) Data classification model training method based on transverse federal learning and related components thereof
CN104079631B (en) A kind of method for edition management and relevant apparatus
CN114221960B (en) Data pushing method based on automatic driving bus and automatic driving bus
CN115098290A (en) Intelligent artificial service method and device based on automatically updated NLP model
CN111178823B (en) Method and device for canceling residence related transaction
Barbarosoglu et al. Mobile applications for the construction industry
KR101076420B1 (en) Activity based project management apparatus and method
CN111325365A (en) Method and device for pre-selling combined intermodal tickets
CN109474702A (en) Information recommendation method, device, computer equipment and product

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221