CN109061046A - A method of detection building waste composition - Google Patents

A method of detection building waste composition Download PDF

Info

Publication number
CN109061046A
CN109061046A CN201810601623.2A CN201810601623A CN109061046A CN 109061046 A CN109061046 A CN 109061046A CN 201810601623 A CN201810601623 A CN 201810601623A CN 109061046 A CN109061046 A CN 109061046A
Authority
CN
China
Prior art keywords
building waste
rubbish
heap
composition
sampling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810601623.2A
Other languages
Chinese (zh)
Other versions
CN109061046B (en
Inventor
邰俊
许碧君
余召辉
陈善平
金宁奔
余毅
鲁海林
王轶厦
赵俊卿
李晓勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Environment Health Engineering Designing Institute Co Ltd
Shanghai Institute for Design and Research on Environmental Engineering Co Ltd
Original Assignee
Shanghai Environment Health Engineering Designing Institute Co Ltd
Shanghai Institute for Design and Research on Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Environment Health Engineering Designing Institute Co Ltd, Shanghai Institute for Design and Research on Environmental Engineering Co Ltd filed Critical Shanghai Environment Health Engineering Designing Institute Co Ltd
Priority to CN201810601623.2A priority Critical patent/CN109061046B/en
Publication of CN109061046A publication Critical patent/CN109061046A/en
Application granted granted Critical
Publication of CN109061046B publication Critical patent/CN109061046B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N33/00Investigating or analysing materials by specific methods not covered by groups G01N1/00 - G01N31/00

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Food Science & Technology (AREA)
  • Medicinal Chemistry (AREA)
  • Physics & Mathematics (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Processing Of Solid Wastes (AREA)

Abstract

The present invention provides a kind of method of detection building waste composition, includes the following steps: to be no more than 1m when the total volume of the building waste heap of composition to be detected3When: using whole building rubbish heap as rubbish to be analyzed, the composition for being analysed to rubbish is detected, and is analysed to composition of the testing result of rubbish composition as the building waste heap;When the total volume of the building waste heap of composition to be detected is more than 1m3When: 1) in the building waste heap of to be detected composition sampling obtain several sampling rubbish;Several sampling rubbish are uniformly mixed, 2) the total amount quartering of several sampling rubbish is formed into 1m3Rubbish to be analyzed, 3) by 1m3The composition of rubbish to be analyzed detected, 4) be analysed to composition of the testing result of rubbish composition as the building waste heap.Method provided herein has the advantages that applicability is wide, easy to operate, feasibility is strong;The composition in building waste heap can effectively be analyzed.

Description

A method of detection building waste composition
Technical field
The present invention relates to a kind of detection methods, more particularly to a kind of method of detection building waste composition.
Background technique
Building waste refers to that construction, unit in charge of construction or individual build all kinds of buildings, structures, pipe network etc., spread If or removing, generated dregs, spoir, rejected material, mud and other wastes in reparative processes.According to generate origin classification, Building waste can be divided into engineering rubbish, engineering dregs, decoration garbage, removal rubbish, engineering slurry etc.;Classify by constituent, Dregs, concrete block, crushed stone, brick and tile fragment, waste mortar, mud, asphalt blocks, waste plastics, non-gold can be divided into building waste Category, useless bamboo wood etc..By taking decoration garbage as an example, residential households are generally originated from, can also be mixed with house refuse component, such as food rubbish The components such as rubbish, textile clothes class rubbish, rubber plastic class rubbish, wood, bamboo class rubbish.
Building waste occupies a large amount of soils, will cause environmental pollution, and landfill can destroy soil texture in underground, cause ground Table sedimentation.It can also be recycled after building waste is categorized.Such as thickness bone is produced using discarded building concrete and discarded masonry Material can be used for producing the building materials such as the concrete, mortar or preparation building block, wallboard, floor tile of respective strengths grade.Thickness After aggregate addition solidification class material, it can also be used to highway road surface.Aggregate is produced using useless brick and tile, can be used for producing regeneration The building materials such as brick, building block, wallboard, floor.Dregs can be used for road construction, pile foundation filler, foundation etc..For discarded wood Material class building waste, the timber not yet obviously destroyed can be reused directly for rebuilding building, and the wooden building of badly broken can be made For the raw material of wooden regenerated plates or papermaking etc..Discarded pavement asphalt mixture can be directly used in regeneration drip according to proper proportion Green concrete.Unmade road concrete can be processed into recycled aggregate for preparing regeneration concrete.Scrap steel, steel scrap muscle and other Old metal material can directly recycle or melt down processing.The building wastes such as cullet, waste plastics, waste ceramic optionally distinguish benefit With.
Since difference is huge in terms of size, density for different classes of building waste, and the density of building waste generally surpasses General house refuse is crossed, therefore house refuse sampling and component detection method can not be indiscriminately imitated.But there has been no one kind to be suitble at present Method or standard, representational sampling is carried out to the component of the building waste comprising numerous classifications, classifies and analyzes all kinds of The method of other content.
Summary of the invention
In view of the foregoing deficiencies of prior art, the purpose of the present invention is to provide a kind of detection building waste compositions Method, for solve in the prior art the building waste scale of construction is big, sampling representativeness caused by complicated components is insufficient, classification standard not The problem of unified, content of all categories effectively can not be detected quickly.
In order to achieve the above objects and other related objects, the present invention obtains by the following technical programs.
The present invention provides a kind of method of detection building waste composition, includes the following steps:
When the total volume of the building waste heap of composition to be detected is no more than 1m3When: using whole building rubbish heap as wait divide Rubbish is analysed, the testing result of rubbish composition to be analyzed is the composition of the building waste heap;
When the total volume of the building waste heap of composition to be detected is more than 1m3When: 1) in the building waste heap of to be detected composition Middle sampling obtains several sampling rubbish;Several sampling rubbish are uniformly mixed;2) several are sampled into rubbish quartering Form 1m3Rubbish to be analyzed;3) by 1m3The composition of rubbish to be analyzed detected;4) it is analysed to the detection of rubbish composition As a result the composition as the building waste heap.
Building waste heap described in method is included in building waste and stacks in place or building waste sorting in the application The building waste heap that the heart is stacked.
Preferably, in step 1), several are taken to sample rubbish using isometric(al) sampling method when sampling, the isometric(al) is adopted Sample method refers to that the volume for the sampling rubbish taken every time is identical.
Preferably, in step 1), the volume of each sampling rubbish is 1m3
Preferably, in step 1), use standardised container when sampling, the standardised container be length, width and height be 1m just Cube container.
Preferably, in step 1), when sampling, in the sample determined, building waste is grabbed using tool, is filled to In standardised container, make building waste natural packing in container, do not use pressed by external force, to building waste top planes and holds When device mouth rim is equal, stop filling building waste.Think at this time in the collected building waste volume of sample institute For 1m3
When being sampled to building waste heap, in order to enable the sampling rubbish taken has certain representativeness, for How to sample and sampled point etc. will be further determined that.The general characteristic of building waste heap is the shape of different building waste heap bodies Shape differs greatly, and due to factors such as itself building waste frictional force, (refers to when stacked in nature and be deposited in spacious level land completely On, surrounding does not have enclosing), generally in divide, the shape of cone or cylinder table, without there are proper cube The shapes such as body, cylindrical body.When the building waste heap of composition to be detected is stacked against a face wall, the stereoscopic nature of making of heap is stacked into heap The half of body, is sampled referring to this method;When building waste heap is stacked against the vertical wall in two sides, certainly by the stereoscopic work of heap The a quarter for so stacking heap body, is sampled referring to this method.
Preferably, it in step 1), is sampled using gridding method and/or periphery method.
It is highly preferred that the method for sampling of the gridding method are as follows: according to the heap body occupied area of building waste heap, rubbish will be built Rubbish heap is divided equally into several subregion;It is sampled in the central point of all subregion.
It is highly preferred that the heap body occupied area when building waste heap is less than 50m2When, the number of the subregion is at least 9 It is a.
It is highly preferred that being equal to 50m when the heap body occupied area of building waste heap is greater than2Less than 100m2When, the subregion Number be at least 16.
It is highly preferred that being equal to 100m when the heap body occupied area of building waste heap is greater than2When, the number of the subregion is most It is less 25.
Preferably, in step 2), the periphery method refers in the position of upper, middle and lower three on each side of surrounding of building waste heap Set sampling.Total digit of sampling is no less than 6.
Preferably, when being sampled using periphery method, building waste heap is stacked naturally and forms cone or circular cone Platform.
Preferably, when the average thickness of building waste heap be no more than 1m, and the occupied area of building waste heap be no more than 1m2 When, is directly sampled and analyzed using the building waste heap as rubbish to be analyzed.
Preferably, when the average thickness of building waste heap is no more than 1m, and the occupied area of building waste heap is more than 1m2 When, it is sampled using gridding method.
Preferably, when the average thickness of building waste heap is more than 1m, and the occupied area of building waste heap is no more than 1m2 When, it is sampled using periphery method.Building waste heap is considered as cone at this time.
Preferably, when the average thickness of building waste heap is more than 1m, and the occupied area of building waste heap is more than 1m2When, Building waste heap is considered as the frustum of a cone, is sampled in the top surface of the frustum of a cone according to gridding method, in the side of the frustum of a cone according to periphery method Sampling;At the annulus of top surface and unilateral copulation, the sample of coincidence is calculated according to a sampled point.
Preferably, the quartering in step 2), which refers to sample several, piles round or side after rubbish is mixed together uniformly Then shape gives up wherein diagonal two parts according to the cross quartering at random, remaining part repeats aforementioned to pave and be divided into four Equal part gives up half, until forming 1m3Rubbish to be analyzed.
Preferably, the composition includes the mass fraction of constituent species and each component within the scope of different-grain diameter.
Preferably, the constituent species include food, stationery, rubber and plastic class, bamboo and wood class, textile, common brick, aerating coagulation In earth building blocks, concrete or stone, ceramic tile or ceramics, metal class, category of glass, grey great soil group, Harmful Waste class and electronic waste class It is one or more.
Preferably, when be also not belonging to above-mentioned classification containing constituent species in the component of the building waste heap of composition to be detected will It is classified as other classes.
Food described herein includes various discarded food materials and with the perishable rubbish such as postprandial residue Rubbish;Such as melon and fruit vegetable skin, leftovers and expired food.
Stationery described herein is various discarded paper and paper products, such as office paper, express delivery carton, sanitary paper Deng.
Rubber and plastic class described herein is various discarded plastics, rubber or leather and fur products;Such as plastic package material, tire Deng.
Bamboo and wood class described herein is various discarded Bamboo and wood products and flowers and trees;As wooden or bamboo furniture, chopsticks, The dry branches and fallen leaves etc. that afforestation generates.
Textile described herein is the textile of various discarded dry goods and yarn etc.;Such as curtain, sofa housing, bed Pad, waste and old clothing etc..
Common brick described herein is the red brick and its fragment that clay is fired.
Air-entrained concrete building block described herein is light porous, insulation, the good coagulation civil engineering of fire protecting performance Build material.
Concrete or stone described herein are to pour the construction of structures to be formed together using cement, sand and reinforcing bar, such as Concrete road or concrete structures etc..
Ceramic tile described herein or ceramics are the metal oxide and half-metal oxide with fire resisting, via grinding, are mixed The porcelain of the most red acid and alkali-resistance close, formed after compacting, glazing and sintering or the building or ornament materials of stone matter etc.;It such as draws water horse The ceramics such as bucket, hand washing sink, waterproof, anti-skidding floor tile, dish made of ceramics.
Metal class described herein refers to various discarded metals and metal product etc., such as pop can, metal material Door or window.
Category of glass described herein refers to various discarded glass or glassware, such as the glass or glass on door and window Bottle.
Grey great soil group in the application refers to the fragment of dust, great soil group substance, brick and tile stone.
Harmful Waste class in the application includes discarded battery, canister, Expired drug or natural gas tank.
Electronic waste class in the application includes the electronic products such as electric appliance, mobile phone, computer.
Constituent species in the application further include other classes, other classes in the application, which refer to, is not belonging to above-mentioned any kind The remaining ingredient of rubbish.
Preferably, the size distribution of each component refers to mass fraction of each component within the scope of different-grain diameter.Specifically Ground, for the 1m obtained by quartering3Rubbish to be analyzed is first sorted according to different-grain diameter range, is then weighed different The weight of every class building waste in size range can calculate the size distribution of every class building waste.
It is highly preferred that the different-grain diameter range includes following range: greater than 450mm, is less than or equal to greater than 300mm 450mm, it is greater than 100mm and is less than or equal to 300mm, is greater than 60mm and is less than or equal to 100mm, is greater than 31.5mm and is less than or equal to 60mm, big It is less than or equal to 31.5mm in 16mm, 16mm is less than or equal to greater than 5mm, is greater than 2mm less than or equal to 5mm and is less than or equal to 2mm.
It is highly preferred that being analysed to one-component in rubbish when being detected to the composition of rubbish to be analyzed and utilizing mesh screen Carry out the same component that screening forms different-grain diameter range.
A kind of method of detection building waste composition provided herein can be used for building different shape and the different scale of constructions Building refuse carries out representational sampling, classification and quantitative analysis, has the advantages that applicability is wide, easy to operate, feasibility is strong; The composition in building waste heap can effectively be analyzed.
Detailed description of the invention
Fig. 1 is the schematic diagram of quartering described herein.
Fig. 2 is periphery method described herein sampling location schematic diagram.
Specific embodiment
Illustrate embodiments of the present invention below by way of specific specific example, those skilled in the art can be by this specification Other advantages and efficacy of the present invention can be easily understood for disclosed content.The present invention can also pass through in addition different specific realities The mode of applying is embodied or practiced, the various details in this specification can also based on different viewpoints and application, without departing from Various modifications or alterations are carried out under spirit of the invention.
It should be clear that in the following example not specifically dated process equipment or device be all made of conventional equipment in the art or Device.
In addition, it should also be understood that, one or more method and step mentioned in the present invention does not repel before and after the combination step It can also be inserted into other methods step there may also be other methods step or between these explicitly mentioned steps, unless separately It is described;It should also be understood that the combination connection relationship between one or more equipment/device mentioned in the present invention is not repelled The two equipment/devices specifically mentioned before and after the unit equipment/device there may also be other equipment/device or at these it Between can also be inserted into other equipment/device, unless otherwise indicated.Moreover, unless otherwise indicated, the number of various method steps is only Identify the convenient tool of various method steps, rather than for the arrangement order of limitation various method steps or limits the enforceable model of the present invention It encloses, relativeness is altered or modified, and without material changes in technical content, when being also considered as, the present invention is enforceable Scope.
In the embodiment of the present application, index is predominantly detected when detecting using composition of the method in the application to building waste Referring to following table table 1.
Index is predominantly detected when table 1 detects the composition of building waste
The component of building waste is specifically shown in Table 2 in the embodiment of the present application.
Table 2 is the constituent classification situation table of building waste in the application
In the embodiment of the present application quartering refer to several sampling rubbish are piled after mixing it is round or rectangular, according to The cross quartering, then gives up wherein diagonal two parts at random, remaining part repeat it is aforementioned pave and quadrisection, house Half is abandoned, until forming 1m3Rubbish to be analyzed.Quartering is as shown in Figure 1.
Embodiment 1
The present embodiment is to carry out sampling and group using the method disclosed in the present application to the building waste heap of composition to be detected The method of analysis.
The total volume of the building waste heap of composition to be detected is no more than 1m in the present embodiment3
Using whole building rubbish heap as rubbish to be analyzed, the testing result of rubbish composition to be analyzed is the building rubbish The composition of rubbish heap.
The composition includes the size distribution of constituent species and each component.
The component for being analysed to rubbish is detected and is recorded according to Tables 1 and 2.
Testing result in table 1 is the composition of the building waste heap of composition to be detected in the present embodiment.
Embodiment 2
The present embodiment is to carry out sampling and group using the method disclosed in the present application to the building waste heap of composition to be detected The method of analysis.
The total volume of the building waste heap of composition to be detected is more than 1m in the present embodiment3, more specifically, in the present embodiment The average thickness of building waste heap is no more than 1m, and the occupied area of building waste heap is more than 1m2
Several sampling rubbish are obtained using gridding method sampling to the building waste heap of composition to be detected;Several are sampled Rubbish is mixed evenly;If just a will sample rubbish point forms 1m with quartering3Rubbish to be analyzed;By 1m3Rubbish to be analyzed The composition of rubbish is detected;The testing result of rubbish composition to be analyzed is the composition of the building waste heap.
The method of sampling of the gridding method are as follows: according to the heap body occupied area of building waste heap, building waste heap is averaged It is divided into several subregion;It is sampled in the central point of all subregion.
Specifically, when the heap body occupied area of building waste heap is less than 50m2When, the number of the subregion is at least 9 It is a.
Specifically, it is equal to 50m when the heap body occupied area of building waste heap is greater than2Less than 100m2When, the subregion Number is at least 16.
Specifically, it is equal to 100m when the heap body occupied area of building waste heap is greater than2When, the number of the subregion is minimum It is 25.
1m in the present embodiment3The composition detection of rubbish to be analyzed is carried out referring to Tables 1 and 2.
Embodiment 3
The present embodiment is to carry out sampling and group using the method disclosed in the present application to the building waste heap of composition to be detected At the method for analysis.
The total volume of the building waste heap of composition to be detected is more than 1m in the present embodiment3, more specifically, in the present embodiment The average thickness of building waste heap is more than 1m, and the occupied area of building waste heap is no more than 1m2When, it is sampled using periphery method. Building waste heap is considered as cone at this time.
Several sampling rubbish are obtained using the sampling of periphery method to the building waste heap of composition to be detected;Several are sampled Rubbish is mixed evenly;If just a will sample rubbish point forms 1m with quartering3Rubbish to be analyzed;By 1m3Rubbish to be analyzed The composition of rubbish is detected;The testing result of rubbish composition to be analyzed is the composition of the building waste heap.
1m in the present embodiment3The composition detection of rubbish to be analyzed is carried out referring to Tables 1 and 2.
Embodiment 4
The present embodiment is to carry out sampling and group using the method disclosed in the present application to the building waste heap of composition to be detected At the method for analysis.
The total volume of the building waste heap of composition to be detected is more than 1m in the present embodiment3, more specifically, in the present embodiment The average thickness of building waste heap is more than 1m, and the occupied area of building waste heap is more than 1m2When, building waste heap is considered as circle Frustum is sampled in the top surface of the frustum of a cone according to gridding method, is sampled in the side of the frustum of a cone according to periphery method;It is handed in top surface and side At the annulus connect, the sample of coincidence is calculated according to a sampled point.
Several sampling rubbish are obtained using the sampling of periphery method to the building waste heap of composition to be detected;Several are sampled Rubbish is mixed evenly;If just a will sample rubbish point forms 1m with quartering3Rubbish to be analyzed;By 1m3Rubbish to be analyzed The composition of rubbish is detected;The testing result of rubbish composition to be analyzed is the composition of the building waste heap.
1m in the present embodiment3The composition detection of rubbish to be analyzed is carried out referring to Tables 1 and 2.
Embodiment 5
When the shape of the building waste heap of composition to be detected is uncertain, also can according to need or actual conditions, it will be to The building waste heap of detection composition changes into the shape of cone or frustum of a cone etc. in order to utilize gridding method and/or the progress of periphery method Sampling.
When the heap body occupied area of building waste heap is less than 50m2When, the number of the subregion is at least 9.
It is equal to 50m when the heap body occupied area of building waste heap is greater than2Less than 100m2When, the number of the subregion is minimum It is 16.
It is equal to 100m when the heap body occupied area of building waste heap is greater than2When, the number of the subregion is at least 25.
The periphery method refers to be sampled in the position of upper, middle and lower three on each side of surrounding of building waste heap.Specific such as Fig. 2 It is shown.
1m in the present embodiment3The composition detection of rubbish to be analyzed is carried out referring to Tables 1 and 2.
The above-described embodiments merely illustrate the principles and effects of the present invention, and is not intended to limit the present invention.It is any ripe The personage for knowing this technology all without departing from the spirit and scope of the present invention, carries out modifications and changes to above-described embodiment.Cause This, institute is complete without departing from the spirit and technical ideas disclosed in the present invention by those of ordinary skill in the art such as At all equivalent modifications or change, should be covered by the claims of the present invention.

Claims (10)

1. a kind of method of detection building waste composition, includes the following steps:
When the total volume of the building waste heap of composition to be detected is no more than 1m3When:
Using whole building rubbish heap as rubbish to be analyzed, the testing result of rubbish composition to be analyzed is the building waste heap Composition;
When the total volume of the building waste heap of composition to be detected is more than 1m3When:
1) sampling obtains several sampling rubbish in the building waste heap of composition to be detected;Several sampling rubbish are mixed equal It is even,
2) several sampling rubbish quarterings are formed into 1m3Rubbish to be analyzed,
3) by 1m3The composition of rubbish to be analyzed detected,
4) it is analysed to composition of the testing result of rubbish composition as the building waste heap.
2. the method according to claim 1, wherein in step 1), when sampling, is taken using isometric(al) sampling method Several sampling rubbish, the isometric(al) sampling method refer to that the volume for the sampling rubbish taken every time is identical.
3. according to the method described in claim 2, it is characterized in that, the volume of each sampling rubbish is 1m in step 1)3
4. according to the method described in claim 2, it is characterized in that, in step 1), when sampling, uses standardised container, the mark Standardization container is the square container that length, width and height are 1m.
5. method according to any one of claims 1 to 4, which is characterized in that in step 1), using gridding method and/or week The sampling of side method.
6. according to the method described in claim 5, it is characterised in that it includes one of following feature or a variety of:
The method of sampling of the gridding method are as follows: according to the heap body occupied area of building waste heap, building waste heap is averagely divided At several subregion;It is sampled in the central point of all subregion;
When the heap body occupied area of building waste heap is less than 50m2When, the number of the subregion is at least 9;
It is equal to 50m when the heap body occupied area of building waste heap is greater than2And it is less than 100m2When, the number of the subregion is at least 16;
It is equal to 100m when the heap body occupied area of building waste heap is greater than2When, the number of the subregion is at least 25.
7. according to the method described in claim 5, it is characterised in that it includes one of following feature or a variety of:
When the average thickness of building waste heap is no more than 1m, and the occupied area of building waste heap is more than 1m2When, using gridding method Sampling;
When the average thickness of building waste heap is more than 1m, and the occupied area of building waste heap is no more than 1m2When, using periphery method Sampling;
When the average thickness of building waste heap is more than 1m, and the occupied area of building waste heap is more than 1m2When, by building waste heap It is considered as the frustum of a cone, is sampled in the top surface of the frustum of a cone according to gridding method, is sampled in the side of the frustum of a cone according to periphery method;Top surface with At the annulus of unilateral copulation, the sample of coincidence is calculated according to a sampled point.
8. method according to any one of claims 1 to 4, which is characterized in that composition includes constituent species and each component Size distribution.
9. according to the method described in claim 8, it is characterized in that, the constituent species include food, stationery, rubber and plastic class, Bamboo and wood class, textile, common brick, air-entrained concrete building block, concrete or stone, ceramic tile or ceramics, metal class, category of glass, grey great soil group, One of Harmful Waste class and electronic waste class are a variety of.
10. according to the method described in claim 8, it is characterized in that, the size distribution of each component refers to each component in different grains Mass fraction within the scope of diameter.
CN201810601623.2A 2018-06-12 2018-06-12 Method for detecting composition of construction waste Active CN109061046B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810601623.2A CN109061046B (en) 2018-06-12 2018-06-12 Method for detecting composition of construction waste

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810601623.2A CN109061046B (en) 2018-06-12 2018-06-12 Method for detecting composition of construction waste

Publications (2)

Publication Number Publication Date
CN109061046A true CN109061046A (en) 2018-12-21
CN109061046B CN109061046B (en) 2022-02-08

Family

ID=64820269

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810601623.2A Active CN109061046B (en) 2018-06-12 2018-06-12 Method for detecting composition of construction waste

Country Status (1)

Country Link
CN (1) CN109061046B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101913788A (en) * 2010-07-07 2010-12-15 云南省建筑科学研究院 Method for comprehensively treating construction waste
CN102838307A (en) * 2012-08-27 2012-12-26 首钢总公司 Method and system for treating construction waste
CN104261715A (en) * 2014-08-27 2015-01-07 广东新谷科技有限公司 Construction waste recycling technology
CN104511472A (en) * 2013-10-08 2015-04-15 中国建筑第四工程局有限公司 On-site recycle method of construction waste
CN104671684A (en) * 2013-12-30 2015-06-03 王明斌 Recovery processing method for construction garbage
CN105478214A (en) * 2015-10-21 2016-04-13 苏州市建筑材料再生资源利用有限公司 Construction waste integration and separation method
CN104307840B (en) * 2014-08-27 2016-06-15 国网山东省电力公司无棣县供电公司 Building waste classification recoverying and utilizing method
CN105755909A (en) * 2014-12-17 2016-07-13 刘庆国 Method using building garbage to produce railway roadbed filling material
CN104034720B (en) * 2014-06-05 2016-08-17 同济大学 Heavy metal detection method in a kind of waste material of buildings
CN105461249B (en) * 2016-02-01 2017-10-10 西安建筑科技大学 A kind of building waste prepares the production technology and equipments of renewable building material
CN107540254A (en) * 2016-06-23 2018-01-05 王志凤 A kind of method to building waste integrated treatment

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101913788A (en) * 2010-07-07 2010-12-15 云南省建筑科学研究院 Method for comprehensively treating construction waste
CN102838307A (en) * 2012-08-27 2012-12-26 首钢总公司 Method and system for treating construction waste
CN104511472A (en) * 2013-10-08 2015-04-15 中国建筑第四工程局有限公司 On-site recycle method of construction waste
CN104671684A (en) * 2013-12-30 2015-06-03 王明斌 Recovery processing method for construction garbage
CN104034720B (en) * 2014-06-05 2016-08-17 同济大学 Heavy metal detection method in a kind of waste material of buildings
CN104261715A (en) * 2014-08-27 2015-01-07 广东新谷科技有限公司 Construction waste recycling technology
CN104307840B (en) * 2014-08-27 2016-06-15 国网山东省电力公司无棣县供电公司 Building waste classification recoverying and utilizing method
CN105755909A (en) * 2014-12-17 2016-07-13 刘庆国 Method using building garbage to produce railway roadbed filling material
CN105478214A (en) * 2015-10-21 2016-04-13 苏州市建筑材料再生资源利用有限公司 Construction waste integration and separation method
CN105461249B (en) * 2016-02-01 2017-10-10 西安建筑科技大学 A kind of building waste prepares the production technology and equipments of renewable building material
CN107540254A (en) * 2016-06-23 2018-01-05 王志凤 A kind of method to building waste integrated treatment

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
全国勘察设计注册工程师环保专业管理委员会 等: "《注册环保工程师专业考试复习教材 固体废弃物处理处置工程技术与实践 下 第4版》", 31 March 2017, 中国环境出版社 *
王晓燕 等: "建筑固体废弃物分类应用的研究", 《建筑施工》 *

Also Published As

Publication number Publication date
CN109061046B (en) 2022-02-08

Similar Documents

Publication Publication Date Title
CN104261715A (en) Construction waste recycling technology
CN101913788A (en) Method for comprehensively treating construction waste
CN203803790U (en) Machine-made sand production line soil removing device for buildings
CN102218435A (en) Method for recycling waste clay
CN109020430A (en) A kind of construction refuse regenerated mixture of two ash stability and preparation method thereof
CN107352907A (en) A kind of preparation method of colliery filling slurry
CN102206054A (en) Renewable active powder and preparation method thereof
CN107540254A (en) A kind of method to building waste integrated treatment
CN106278088A (en) A kind of environmental protection is non-burning brick and preparation method thereof
CN108395128B (en) Full-circulation recycling method for urban construction waste, machine-made sand, concrete and building blocks thereof prepared by full-circulation recycling method
CN108505409B (en) Solidified muddy soil and construction waste regenerated aggregate composite inorganic material and forming method thereof
CN108689659A (en) A kind of construction refuse regenerated mixture of cement stabilizing and preparation method thereof
CN103848584A (en) Co-production process for recycling micropowder and fine sands from construction wastes
Soltani-Jigheh et al. Effects of tire chips on shrinkage and cracking characteristics of cohesive soils
CN109061046A (en) A method of detection building waste composition
CN107020290A (en) A kind of site construction building waste treatment in situ system
CN110125133A (en) A kind of building waste separation and recovery and reutilization system and technique
US20130089692A1 (en) Concrete Tile and Method of Manufacturing the Same
Okonkwo et al. Lateritic soil treated with polyvinyl waste powder as a potential material for liners and cover in waste containment
CN110204280A (en) A kind of technique using building waste manufacture hollow brick
CN108545976A (en) A kind of preparation method of regenerated coarse aggregate that mixing gravel
CN204564743U (en) A kind of building waste crushing and classification treating apparatus
Adebayo et al. Effects of guinea corn husk ash and lime mixtures on lateritic soil for highway construction
Kelley Use of recycled oyster shells as aggregate for pervious concrete
CN208033266U (en) A kind of building waste separation and recovery and reutilization system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Tai Jun

Inventor after: Li Xiaoyong

Inventor after: Xu Bijun

Inventor after: Yu Zhaohui

Inventor after: Chen Shanping

Inventor after: Jin Ningben

Inventor after: Yu Yi

Inventor after: Lu Hailin

Inventor after: Wang Diexia

Inventor after: Zhao Junqing

Inventor before: Tai Jun

Inventor before: Li Xiaoyong

Inventor before: Xu Bijun

Inventor before: Yu Zhaohui

Inventor before: Chen Shanping

Inventor before: Jin Ningben

Inventor before: Yu Yi

Inventor before: Lu Hailin

Inventor before: Wang Diexia

Inventor before: Zhao Junqing

GR01 Patent grant