CN109040270A - A kind of formwork jumbo construction monitoring method - Google Patents

A kind of formwork jumbo construction monitoring method Download PDF

Info

Publication number
CN109040270A
CN109040270A CN201810926928.0A CN201810926928A CN109040270A CN 109040270 A CN109040270 A CN 109040270A CN 201810926928 A CN201810926928 A CN 201810926928A CN 109040270 A CN109040270 A CN 109040270A
Authority
CN
China
Prior art keywords
data
formwork jumbo
monitoring
management
central server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810926928.0A
Other languages
Chinese (zh)
Other versions
CN109040270B (en
Inventor
徐剑安
张杨杨
秦志远
焦妮
刘恒超
王会朴
朱永超
荆留杰
徐受天
于太彰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Engineering Equipment Group Co Ltd CREG
Original Assignee
China Railway Engineering Equipment Group Co Ltd CREG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Engineering Equipment Group Co Ltd CREG filed Critical China Railway Engineering Equipment Group Co Ltd CREG
Priority to CN201810926928.0A priority Critical patent/CN109040270B/en
Publication of CN109040270A publication Critical patent/CN109040270A/en
Application granted granted Critical
Publication of CN109040270B publication Critical patent/CN109040270B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04LTRANSMISSION OF DIGITAL INFORMATION, e.g. TELEGRAPHIC COMMUNICATION
    • H04L67/00Network arrangements or protocols for supporting network services or applications
    • H04L67/01Protocols
    • H04L67/02Protocols based on web technology, e.g. hypertext transfer protocol [HTTP]
    • H04L67/025Protocols based on web technology, e.g. hypertext transfer protocol [HTTP] for remote control or remote monitoring of applications
    • HELECTRICITY
    • H04ELECTRIC COMMUNICATION TECHNIQUE
    • H04NPICTORIAL COMMUNICATION, e.g. TELEVISION
    • H04N7/00Television systems
    • H04N7/18Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast

Landscapes

  • Engineering & Computer Science (AREA)
  • Signal Processing (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Multimedia (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a kind of formwork jumbo construction monitoring methods.The method comprising the steps of has: site operation monitoring, monitoring data convergence, remote centralized control, formwork jumbo construction site can be monitored in real time through the above steps, it obtains real time data and central server is connected to by convergence, engineering data base is installed on central server, central server also with the remote monitoring terminal network interconnection, for remote monitoring terminal by calling the data being stored in the engineering data base, real-time working parameter and work video to formwork jumbo work progress carry out centralized management.The formwork jumbo construction work for being distributed various regions has been carried out information-based monitoring by network by the monitoring method, it backs up in realtime with teledata realization local, improve the safety of data, facilitate the management to formwork jumbo construction, in addition it can monitor in real time in several ways, reduce the cost of formwork jumbo construction comprehensively monitoring.

Description

A kind of formwork jumbo construction monitoring method
Technical field
The present invention relates to tunnels to equip construction informational control technical field, and in particular to a kind of formwork jumbo construction monitoring Method.
Background technique
Formwork jumbo is a kind of to improve tunnel-liner surface smoothness and lining cutting speed, and reduces labor intensity and design The dedicated construction equipment of manufacture.
In traditional form of construction work, operator realizes the control of formwork jumbo by Purely mechanical or simple button System.Such mode of operation not only can lead to the consumption of a large amount of construction times due to adjusting parameter repeatedly, it is also possible to because accidentally grasping Make and delay the duration or even jeopardize the life security of operator, another aspect mechanical operation be unable to complete data acquisition, The reason of transmission is stored, is unable to complete to historical problem is tracked and analysis, is not easy to the management of construction and the improvement of equipment.
Therefore, in order to allow construction personnel and administrative staff that can accurately and timely check the work of tunnel inner template trolley State, running parameter and log ensure that construction is more stable, efficiently and safely carry out, and it is neat to be equipped with function to construction site Full comprehensive monitoring system is extremely urgent.The present invention is mainly for solving the problems, such as this.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of formwork jumbo construction monitoring methods, solve in the prior art The problem of accurately monitoring data collection, network transmission, centrally stored and long-range monitoring are lacked to formwork jumbo site operation.
In order to solve the above technical problems, the technical solution adopted by the present invention is that providing a kind of formwork jumbo construction monitoring side Comprising steps of site operation is monitored site operation Monitor And Control Subsystem is arranged in formwork jumbo construction site, to site operation in method Acquire real time data;Site operation Monitor And Control Subsystem convergence is connected to center service by network by monitoring data convergence Device, is equipped with engineering data base on the central server, and the site operation Monitor And Control Subsystem is by the real time data of acquisition To the central server and the engineering data base is stored in by the network transmission;Remote centralized control, the center Also with the remote monitoring terminal network interconnection, the remote monitoring terminal passes through to call to be stored in the engineering data base server Data, centralized management is carried out to the real-time working parameter of formwork jumbo work progress and work video.
In another embodiment of formwork jumbo construction monitoring method of the present invention, the acquisition real time data includes setting to scene Standby progress parameter setting and running state data collect formwork jumbo running parameter data, carry out shooting note to work video Record obtains formwork jumbo work video data, and to the formwork jumbo staff's statistics of data acquisition for participating in construction site.
It is described existing in monitoring data convergence in another embodiment of formwork jumbo construction monitoring method of the present invention Field construction monitoring subsystem creates local parameter data folder to store the formwork jumbo running parameter data, and according to this The corresponding required data format of ground formwork jumbo configuration, memory gap and storage parameter, then work to the formwork jumbo and join Number data carry out data encryption, then by the network transmission to the central server, after central server decryption It stores to the engineering data base.
In another embodiment of formwork jumbo construction monitoring method of the present invention, in monitoring data convergence, through described Site operation Monitor And Control Subsystem creates local video data file also to store the formwork jumbo work video data, and root According to the configuration of local formwork jumbo corresponding required storage mode, out-of-service time and compression coding mode, then pass through the network It is transmitted to the central server, is stored by the central server to the engineering data base.
It is described remote in remote centralized control in another embodiment of formwork jumbo construction monitoring method of the present invention Range monitoring terminal includes computer monitor terminal, and the computer monitor terminal includes complete machine locking management, orientation management, pours pipe Reason, demoulding management, fault inquiry management, video management, logs in management at maintenance management, in formwork jumbo construction monitoring of the present invention In another embodiment of method, in remote centralized control, the remote monitoring terminal includes mobile data terminals, the hand Machine monitoring terminal includes that mobile phone logs in management, remote control management, remote inquiry management.
The beneficial effects of the present invention are: the method comprising the steps of has: site operation monitoring, monitoring data convergence, long-range collection Middle control can monitor formwork jumbo construction site in real time through the above steps, obtain real time data and pass through convergence Be connected to central server, engineering data base be installed on central server, central server also with remote monitoring terminal net Network interconnection, remote monitoring terminal is by calling the data being stored in the engineering data base, to formwork jumbo work progress Real-time working parameter and work video carry out centralized management.The monitoring method is constructed the formwork jumbo for being distributed various regions by network Engineering has carried out information-based monitoring, realizes local backing up in realtime with teledata, improves the safety of data, facilitates pair Formwork jumbo construction management, in addition can monitor in real time in several ways, reduce formwork jumbo construction comprehensively monitoring at This.
Detailed description of the invention
Fig. 1 is the system composition schematic diagram of one embodiment of formwork jumbo construction monitoring method of the present invention;
Fig. 2 is the composition signal of on-site supervision subsystem in another embodiment of formwork jumbo construction monitoring method of the present invention Figure;
Fig. 3 is main frame structure composition schematic diagram in another embodiment of formwork jumbo construction monitoring method of the present invention;
Fig. 4 is template composition schematic diagram in another embodiment of formwork jumbo construction monitoring method of the present invention;
Fig. 5 is running gear composition schematic diagram in another embodiment of formwork jumbo construction monitoring method of the present invention;
Fig. 6 is network interconnection schematic diagram in another embodiment of formwork jumbo construction monitoring method of the present invention;
Fig. 7 is network interconnection schematic diagram in another embodiment of formwork jumbo construction monitoring method of the present invention;
Fig. 8 is computer monitor terminal composition block diagram in another embodiment of formwork jumbo construction monitoring method of the present invention;
Fig. 9 is mobile data terminals composition block diagram in another embodiment of formwork jumbo construction monitoring method of the present invention;
Figure 10 is the flow chart of another embodiment of formwork jumbo construction monitoring method of the present invention.
Specific embodiment
With reference to the accompanying drawing, various embodiments of the present invention are described in detail.
To facilitate the understanding of the present invention, with reference to the accompanying drawing and specific embodiment, the present invention is carried out more detailed Explanation.A better embodiment of the invention is given in the attached drawing, but the invention can be realized in many different forms, not It is limited to this specification described embodiment.On the contrary, purpose of providing these embodiments is makes to the disclosure Understanding it is more thorough and comprehensive.
It should be noted that unless otherwise defined, all technical and scientific terms used in this specification with belong to The normally understood meaning of those skilled in the art of the invention is identical.Used term in the description of the invention It is the purpose in order to describe specific embodiment, is not intended to the limitation present invention.Term "and/or" packet used in this specification Include arbitrary all combinations of one or more relevant listed items.
Fig. 1 is the composition schematic diagram of one embodiment of formwork jumbo construction monitoring system of the present invention.Formwork jumbo is applied in Fig. 1 The site operation Monitor And Control Subsystem 11 is passed through the convergence connection of network 12 by the site operation Monitor And Control Subsystem 11 that work is monitored Central server 13, and the engineering data base being mounted on central server 13, the site operation Monitor And Control Subsystem 11 The real time data of acquisition is transferred to the central server 13 by the network 12 and is stored in the engineering data base.
Preferably, as shown in Fig. 2, the hardware device that the site operation Monitor And Control Subsystem 11 includes has WST-200BY to take the photograph 113,8 mouthfuls of camera 111, DS-7808 video recorder 112,4T harddisk memory POE interchangers 114, wherein video recorder, hard-disc storage Device, interchanger are fixed on electrical dedicated box by special stand, and video camera has multiple, are separately fixed at the top of formwork jumbo, step Ladder, master operating station, foot passage position.By disposing video camera at the construction field (site), by NVR (Network Video The abbreviation of Recorder, that is, network hard disk video recorder) data storage and transfer are carried out, NVR is passed through into NAT (Network Address Translation, network address translation) technology-mapped externally provide data call and transmission storage service.Thus As it can be seen that site operation Monitor And Control Subsystem, which is mainly based upon computer network, carries out the network interconnection for monitoring device, and to make The position of the setting of video camera is able to carry out all standing on formwork jumbo, guarantees the comprehensive of monitoring.
It is further preferred that also passing through the real-time acquisition module trolley of PLC115 in the site operation Monitor And Control Subsystem Each 116 data of sensor, are transferred to industrial computer 118 by IP network 117, are collected according to site operation situation to PLC The linkage of construction site demand is realized in middle control.
It can be seen that the real time data that site operation Monitor And Control Subsystem generates trolley work progress is acquired.These Real time data is mainly the data obtained to the real time monitoring of the working status parameter of trolley, video, demographic data's information.Cause This, on the one hand site operation Monitor And Control Subsystem to be acquired in the different work stage to the parameter setting of equipment working state and On the other hand Parameters variation carries out recording acquisition to each video source monitor video collected of construction site installation.
Fig. 3 shows the composition schematic diagram of formwork jumbo, wherein internal main frame structure is that entire formwork jumbo is mainly held Part is reconstructed, for meeting rigidity, intensity and stability in the entire trolley course of work.Mainly by bottom girder 201, top beam 202, The components such as herringbone frame 203, crossbeam 204, brace 205 composition.Fig. 4 is the template on the outside of main frame structure, the template assembly It is made of the side form 303 of two pieces of backforms 301, two sides, two pieces of backforms 301 are connected by bolt 302, and backform 301 and side form 303 are cut with scissors It connects, is bolted between longitudinal direction by web.For example, template longitudinal direction overall length 12.1m, is divided into 6 pieces, including 5 pieces long 2m template And 1 piece long 2.1m template, wherein lap of splice 0.1m can also be provided with working window on form surfacing.
Formwork jumbo further includes running gear, specifically includes two sets of active running gears and two sets of passive walking systems, peace Below main frame structure bottom girder, active running gear by traveling box 401, motor reducer 402, sprocket wheel 403, chain 404, The composition such as wheel shaft 405, traveling wheel 406, two XWD7-43-7.5Kw motor reducer drivings, makes driving wheel by chain drive Complete machine walking is driven, follower is servo-actuated, and movable motor has advance, retrogressing, braking function, as shown in Figure 5.
Further, for the trolley working stage that can be divided into of construction or workflow have latch stage, positioning stage, Pour stage, maintenance stage, ejection phase, fault inquiry stage.It is wherein latched, positions, pouring, conserving, demoulding each state Between function be mutually latched.Refer to that trolley is in working condition in latch stage, the various components of trolley are in locking lock Determine state, for change-over switch in blocking, all operations are ineffective, change-over switch should be rotated when all process steps do not operate So far position.Orientation management carries out auxiliary positioning using total station, checks whether the systems such as hydraulic, electrical are normal before positioning, platform After truck position determines, fixed station garage is walked, and is operated jacking cylinder, so that door frame is raised to calibrated altitude and level, then operate traversing Trolley middle line is overlapped by oil cylinder with tunnel middle line, and oil cylinder is touched on last operation side, so that side form bottom end is close to abutment wall basis, and by surveying Amount personnel check size, and then positioning is completed, and tighten studdle, and go through, last installed plug plate;Positioning stage pair Station where the various components of trolley are adjusted to controls the operation of related valve, motor, and wherein valve has side form positioning protection Valve, laterally adjusts protection valve at backform positioning protection valve, and motor has a main movable motor, main oil pump motor, and the parameter for needing to be arranged Including jacking original vertical height, jacking front end climb, jacking rear end climb, traversing left dislocation, it is traversing it is right displacement, It is traversing to positive error, accumulative positioning time.
It pours management change-over switch first and switches to the state of pouring, when pumping starting starts accumulative timing, pumping is shut down temporary Stop timing, run distributor first under this state, allows placement layer by layer pipeline to corresponding position, then start pumping mechanism and start to pour It builds, is pouring window equipped with over-pressure safety device, when injection pressure herein is greater than the pressure value of setting, switch protection is dynamic Make, pumping mechanism is out of service.The stage of pouring refers to the process of that the tunnel face to trolley work pours, including tired to pouring Between timing, the accumulative statistics just measured is poured, pumping start time, pumping shutdown moment are configured, and to the sky poured Hole number is configured, and carries out parameter monitoring to the real-time running state for pouring pump, concrete dispenser.
All power-equipments cannot operate when maintenance management, and concrete adds up curing time and starts timing, until switching to Other state timing stop;The maintenance stage refer to complete pour after tunnel face is conserved, including to maintenance start time, The maintenance stop timing is configured, and counts to accumulative curing time.
Demoulding management starts hydraulic station first, and operation corresponding mechanism allows template to be detached from concrete, and starting walking mechanism allows mould Pallet garage sails to subsequent cycle station, subsequent cycle lap-joint manually be arranged overlap joint test point, formwork jumbo travel to Stop moving on when monitoring point, walks start subsequent cycle in place at once.Ejection phase refers to after completing to pour and conserve, right Various components remove the process of demoulding, control the advance of main movable motor, retrogressing, to the real-time fortune of main oil pump motor Row state is monitored, and is counted etc. to accumulative demoulding time.The fault inquiry stage mainly to after failure to alarm The information such as variable, annotation, time of fire alarming, PLC variable, address information carry out record statistics, can be used for inquiry alarm history Information.
Mainly the condition of construction of trolley construction site carries out video acquisition, the usual cloth of camera for monitor video Multiple observation positions are located at, trolley working site can be enabled to from multi-angle observation scene, the mutual cooperation of these cameras Video monitoring is without dead angle.
It is further preferred that as shown in Figure 1, the central server 13 also with the remote monitoring terminal network interconnection, remotely Monitor terminal includes computer monitor terminal 141 and mobile data terminals 142, and the remote monitoring terminal is stored in institute by calling The data in engineering data base are stated, the real-time working parameter and work video to formwork jumbo work progress carry out centralized management.
Preferably, the real time data includes formwork jumbo running parameter data, formwork jumbo work video data and mould Demographic data is made in pallet turner.
Preferably, the site operation Monitor And Control Subsystem 11 creates local parameter data folder to store the Schaltisch Supplemental characteristic is made in turner, and according to the corresponding required data format of local formwork jumbo configuration, memory gap and storage parameter, so Data encryption is carried out to the formwork jumbo running parameter data afterwards, then passes through the network transmission to the central server 13, by storing after the central server 13 decryption to the engineering data base.
Preferably, the site operation Monitor And Control Subsystem 11 creates local video data file to store the Schaltisch Video data is made in turner, and according to the configuration of local formwork jumbo corresponding required storage mode, out-of-service time and compressed encoding side Formula is stored by the central server 13 to the engineering number then by the network transmission to the central server 13 According to library.
It is further preferred that the central server 13 also with the remote monitoring terminal network interconnection, remote monitoring terminal packet Computer monitor terminal 141 and mobile data terminals 142 are included, the remote monitoring terminal is stored in the project data by calling Data in library, real-time working parameter and work video to formwork jumbo work progress carry out centralized management.
Preferably, it is based on Fig. 2 embodiment, as shown in fig. 6, site operation Monitor And Control Subsystem 11 can also directly pass through network 12 with computer monitor terminal 141 and mobile data terminals 142, wherein site operation Monitor And Control Subsystem 11 include video camera 111, Video recorder 112, harddisk memory 113, interchanger 114, and the site monitoring computer 119 with 114 network interconnection of interchanger, Concrete composition can also refer to Fig. 2 embodiment explanation.It can directly be constructed to a specific formwork jumbo based on Fig. 6 embodiment Scene is monitored.
Preferably, the central server 13 can also have big data service centre with correspondence establishment.As shown in fig. 7, respectively applying The site operation Monitor And Control Subsystem 11 at work scene is by providing VPN certificate server, by construction site data access to big data Service centre 131 can externally be provided in data service and data by the big data service centre 131 by privately owned cloud service platform Turn, externally provides and stablize service and supplied with data, Fig. 7 shows big data service centre 131 also by SDH mode to higher level-one General headquarters 132 provide data service.
The remote monitoring terminal includes computer monitor terminal, as shown in figure 8, the computer monitor terminal 141 includes whole Machine lock modules 1411, locating module 1412 pour built module 1413, maintenance module 1414, striping module 1415, fault inquiry mould Block 1416, video module 1417, login module 1418.It wherein, can when the corresponding trolley of complete machine lock modules 1411 stops working To inquire positioning time, the time of pouring, service time, demoulding time, the side's of pouring amount, this class of numbering cycle of previous trolley work Etc. historical informations.Locating module 1412 is mainly that side form positioning protection valve, the backform to trolley position protection valve, laterally adjust guarantor Shield valve carries out selection setting, such as side form positioning protection valve, backform positioning protection valve include 4 protection valves, and when positioning is usual It needs to choose these positioning protection valves, jacking parameter can be configured including to original vertical height, top on this basis Liter front end climb, jacking rear end climb are configured, and the precision of parameter setting can be as accurate as rice.In another example horizontal Include 2 protection valves to adjustment protection valve, can to traversing left dislocation, traversing right displacement, traversing positive error parameter is set It sets, the precision of parameter setting can be as accurate as rice.Furthermore it is also possible to the real time execution shape of main movable motor, main oil pump motor State is monitored, such as can advance to main movable motor or fallback state is configured or status display, inquiry etc..It pours Built module 1413 include to pouring the cumulative time, pour the accumulative statistics just measured, to pumping start time, pumping shut down the moment into Row setting, and the cavity number poured is configured, and to pour the real-time running state of pump, concrete dispenser into Row parameter monitoring.For example, to pour it is accumulative count, it is such as accumulative to pour the time and be set as corresponding the number of minutes, or display To complete the time number used poured, for another example adds up the side's of pouring amount and be set as corresponding cubic meter, or display to complete to pour The side's of the pouring amount used built.It can also show at the beginning of pouring pump used in pouring and shut down the moment.It is possible thereby to It to casting process, the cubic amount of concrete that pours consumption, pours the time and is precisely controlled, improve engineer operation quality.Conserve mould Block 1414, which refers to, conserves tunnel face after completing to pour, including sets to maintenance start time, maintenance stop timing It sets, and accumulative curing time is counted.For example, how many minute is the accumulated time for completing maintenance correspond to, maintenance is opened Moment beginning and setting and the inquiry of historical data for conserving the stop timing.Striping module 1415 is used for after completing to pour and conserve, The process that various components remove with demoulding carries out control and status display to the advance of main movable motor, retrogressing, to main oil pump The real-time running state of motor is monitored and shows, counts etc. to accumulative demoulding time.For example, completing accumulation demoulding How many minute time corresponds to, and is monitored to the operating status at longitudinal resetting 100mm.Fault inquiry module 1416 is main If carrying out record statistics to information such as alarm variable, annotation, time of fire alarming, PLC variable, address informations to after failure, It can be used for inquiry alarm history information.Video module 1417, can be according to platform for providing the display of real time video data Vehicle construction site is by camera number set interface split screen display available;Special time period video is chosen as needed carries out particular video frequency Storage;It can be according to period playback history video data;It plays back and the operations selection such as pause, former speed, slow play is set, put fastly.It logs in Module 1418 is mainly used for being logged in and exited operation in computer monitor terminal 141, for example inputs user name or teams and groups number, And enter password accordingly and can be logged in, it is possible thereby into modules above-mentioned, realize to some trolley or The operating condition of some teams and groups carries out remote control and guarantees the safety of remote control it is possible thereby to which performance level is arranged.
The remote monitoring terminal includes mobile data terminals, as shown in figure 9, the mobile data terminals 142 include hand Machine login module 1421, remote control module 1422, remote query module 1423.Mobile phone login module 1421 mainly by Mobile data terminals pass through the APP softward interview network address of installation or carry out concern entrance by scanning the two-dimensional code, and can pass through User account and password login.Remote control module 1422 includes entering site operation Monitor And Control Subsystem 11 by network, is grasped Control data file is uploaded to central server.The detailed number that each teams and groups can also be worked according to each formwork jumbo situation According to being uploaded to central server, time and accumulation curing time are poured for example including accumulation timing, accumulation, wherein can be with Theoretical value and actual value are set, assessment can be monitored to the working efficiency of each teams and groups in this way.Furthermore it is also possible to remotely more Change data parameters, the setting of formwork jumbo real-time parameter can be remotely changed by handheld terminal, realizes handheld terminal Centralized Monitoring and management. For remote query module 1423, the specific of same day formwork jumbo mainly can be checked according to ring number or selection corresponding date Operating parameter.Such as click " please select circulation ID " button, the dialog box selection respective cycle ID that is then popped up on the page or Date.
Based on same design, the present invention also provides a kind of formwork jumbo construction monitoring methods, as shown in Figure 10, this method Specifically including step has:
Step S101: site operation Monitor And Control Subsystem is arranged in formwork jumbo construction site, to scene in site operation monitoring Construction acquisition real time data;
Preferably, acquisition real time data includes collecting mould to field device progress parameter setting and running state data Supplemental characteristic is made in pallet turner, carries out shooting record to work video and obtains formwork jumbo work video data, and to participation Formwork jumbo staff's statistics of data acquisition of construction site.
Step S102: site operation Monitor And Control Subsystem convergence is connected to center by network by monitoring data convergence Server, is equipped with engineering data base on the central server, and the site operation Monitor And Control Subsystem is by the real-time of acquisition Data to the central server and are stored in the engineering data base by the network transmission;
Step S103: remote centralized control, the central server are described long-range also with the remote monitoring terminal network interconnection Monitor terminal is by calling the data being stored in the engineering data base, to the real-time working parameter of formwork jumbo work progress Centralized management is carried out with work video.
Preferably, in the step S102, the site operation Monitor And Control Subsystem creates local parameter data folder To store the formwork jumbo running parameter data, and required data format, storage are corresponded to according to the configuration of local formwork jumbo Then the formwork jumbo running parameter data are carried out data encryption, then pass through the network transmission by interval and storage parameter To the central server, by storing after central server decryption to the engineering data base;Preferably, in the step In S102, the site operation Monitor And Control Subsystem creates local video data file also to store the formwork jumbo work view Frequency evidence, and according to the configuration of local formwork jumbo corresponding required storage mode, out-of-service time and compression coding mode, then lead to The network transmission is crossed to the central server, is stored by the central server to the engineering data base.
Preferably, in the step S103, the remote monitoring terminal includes computer monitor terminal, the computer monitor Terminal includes complete machine locking management, orientation management, pours management, maintenance management, demoulding management, fault inquiry management, video tube Reason logs in management.Based on same design, these specific corresponding references of management contents are aforementioned to complete machine lock modules 1411, positioning Module 1412 pours built module 1413, maintenance module 1414, striping module 1415, fault inquiry module 1416, video module 1417, the explanation of login module 1418, which is not described herein again.
Preferably, in the step S103, the remote monitoring terminal includes mobile data terminals, the monitoring mobile phone Terminal includes that mobile phone logs in management, remote control management, remote inquiry management.These specific management contents are corresponding with reference to aforementioned right Mobile phone login module 1421, remote control module 1422, the explanation of remote query module 1423, which is not described herein again.
Since the formwork jumbo construction monitoring method and formwork jumbo construction monitoring system above-mentioned are to be based on same design, The relevant technologies content is with reference to aforementioned, and which is not described herein again.
It can be seen that the present invention relates to a kind of formwork jumbo construction monitoring methods.The method comprising the steps of has: site operation Monitoring, monitoring data convergence, remote centralized control, can supervise formwork jumbo construction site in real time through the above steps Control obtains real time data and is connected to central server by convergence, engineering data base, center are equipped on central server Server is also with the remote monitoring terminal network interconnection, and remote monitoring terminal is by calling the number being stored in the engineering data base According to real-time working parameter and work video to formwork jumbo work progress carry out centralized management.The monitoring method passes through network The formwork jumbo construction work for being distributed various regions information-based monitoring is subjected to, realization local is backed up in realtime with teledata, mentioned The high safety of data, facilitates the management to formwork jumbo construction, in addition can monitor in real time, reduce in several ways The cost of formwork jumbo construction comprehensively monitoring.
The foregoing is merely several embodiments of the invention, are not intended to limit the scope of the invention, all utilizations Equivalent structure transformation made by description of the invention and accompanying drawing content is applied directly or indirectly in other relevant technology necks Domain is included in scope of patent protection of the invention.

Claims (6)

1. a kind of formwork jumbo construction monitoring method, which is characterized in that comprising steps of
Site operation monitoring is arranged site operation Monitor And Control Subsystem in formwork jumbo construction site, acquires to site operation real-time Data;
Site operation Monitor And Control Subsystem convergence is connected to central server by network, described by monitoring data convergence Engineering data base is installed, the real time data of acquisition is passed through the net by the site operation Monitor And Control Subsystem on central server Network is transferred to the central server and is stored in the engineering data base;
Remote centralized control, also with the remote monitoring terminal network interconnection, the remote monitoring terminal passes through the central server Call the data that are stored in the engineering data base, the real-time working parameter and work video to formwork jumbo work progress into Row centralized management.
2. formwork jumbo construction monitoring method according to claim 1, which is characterized in that the acquisition real time data includes pair Field device carries out parameter setting and running state data collects formwork jumbo running parameter data, carries out to work video Shooting record obtains formwork jumbo work video data, and acquires to the formwork jumbo staff's data for participating in construction site Statistics.
3. formwork jumbo construction monitoring method according to claim 2, which is characterized in that converged in the monitoring data In, the site operation Monitor And Control Subsystem creates local parameter data folder to store the formwork jumbo running parameter number According to, and according to the corresponding required data format of local formwork jumbo configuration, memory gap and storage parameter, then to the template Trolley running parameter data carry out data encryption, then by the network transmission to the central server, by genuinely convinced in described It stores after business device decryption to the engineering data base.
4. formwork jumbo construction monitoring method according to claim 3, which is characterized in that converged in the monitoring data In, the site operation Monitor And Control Subsystem creates local video data file also to store the formwork jumbo work video counts According to, and according to the configuration of local formwork jumbo corresponding required storage mode, out-of-service time and compression coding mode, then pass through institute Network transmission is stated to the central server, is stored by the central server to the engineering data base.
5. formwork jumbo construction monitoring method according to claim 4, which is characterized in that managed in the remote centralized In, the remote monitoring terminal includes computer monitor terminal, and the computer monitor terminal includes complete machine locking management, positioning pipe It manages, pours management, maintenance management, demoulding management, fault inquiry management, video management, logs in management.
6. formwork jumbo construction monitoring method according to claim 5, which is characterized in that managed in the remote centralized In, the remote monitoring terminal includes mobile data terminals, and the mobile data terminals include that mobile phone logs in management, remote control Management, remote inquiry management.
CN201810926928.0A 2018-08-15 2018-08-15 Construction monitoring method for formwork trolley Active CN109040270B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810926928.0A CN109040270B (en) 2018-08-15 2018-08-15 Construction monitoring method for formwork trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810926928.0A CN109040270B (en) 2018-08-15 2018-08-15 Construction monitoring method for formwork trolley

Publications (2)

Publication Number Publication Date
CN109040270A true CN109040270A (en) 2018-12-18
CN109040270B CN109040270B (en) 2021-08-31

Family

ID=64631267

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810926928.0A Active CN109040270B (en) 2018-08-15 2018-08-15 Construction monitoring method for formwork trolley

Country Status (1)

Country Link
CN (1) CN109040270B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115002570A (en) * 2022-04-18 2022-09-02 武汉毳雨环保科技有限责任公司 Remote monitoring system of construction equipment based on 5G network

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103744358A (en) * 2013-10-28 2014-04-23 武汉瑞芯科微电子技术有限公司 System and method for monitoring subway tunnel construction management based on Internet of Things
CN104216365A (en) * 2014-08-22 2014-12-17 山东大学 Cloud-based remote tunnel surrounding rock displacement monitoring and warning system
US20150058916A1 (en) * 2011-08-31 2015-02-26 Palo Alto Networks, Inc. Detecting encrypted tunneling traffic
CN105006131A (en) * 2015-07-30 2015-10-28 中铁工程装备集团有限公司 Shield-tunneling-machine wireless data collecting system based on mobile phone
CN105134183A (en) * 2015-10-13 2015-12-09 四川隧唐科技股份有限公司 Remote and real-time monitoring system for tunnel leakage water and implementation method of remote and real-time monitoring system
CN106776679A (en) * 2016-11-04 2017-05-31 中交第二航务工程局有限公司工程装备分公司 Shield machine tunneling construction remote centralized control method
CN107194601A (en) * 2017-05-31 2017-09-22 上海应用技术大学 A kind of method for managing and monitoring of shield machine
CN107222574A (en) * 2017-07-13 2017-09-29 合肥引力波数据科技有限公司 A kind of shield machine data collecting system based on mobile terminal
EP3247082A1 (en) * 2016-05-18 2017-11-22 Zscaler, Inc. Cloud-based virtual private access systems and methods
CN107483889A (en) * 2017-08-24 2017-12-15 北京融通智慧科技有限公司 The tunnel monitoring system of wisdom building site control platform
CN107527082A (en) * 2017-09-27 2017-12-29 国网上海市电力公司 A kind of electric power tunnel management system based on Cloud Server and mobile terminal
CN207117833U (en) * 2017-08-14 2018-03-16 河南省鸿联通信建设工程有限公司 Highway construction on-site supervision network system
CN107966988A (en) * 2017-12-11 2018-04-27 中交第二航务工程局有限公司 The control system of shield machine construction electric locomotive
CN108055512A (en) * 2017-12-30 2018-05-18 中煤科工集团上海有限公司 Mating long distance tunnel continuous conveyor system monitoring and control device after a kind of shield
CN108104838A (en) * 2017-11-01 2018-06-01 中铁隧道勘察设计研究院有限公司 A kind of automation control method of lining construction
CN207472722U (en) * 2017-11-09 2018-06-08 中交上海三航科学研究院有限公司 Constructing metro tunnel security information comprehensive management system
CN108388791A (en) * 2018-03-22 2018-08-10 中铁工程装备集团机电工程有限公司 A kind of shield machine uses authentication management system

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150058916A1 (en) * 2011-08-31 2015-02-26 Palo Alto Networks, Inc. Detecting encrypted tunneling traffic
CN103744358A (en) * 2013-10-28 2014-04-23 武汉瑞芯科微电子技术有限公司 System and method for monitoring subway tunnel construction management based on Internet of Things
CN104216365A (en) * 2014-08-22 2014-12-17 山东大学 Cloud-based remote tunnel surrounding rock displacement monitoring and warning system
CN105006131A (en) * 2015-07-30 2015-10-28 中铁工程装备集团有限公司 Shield-tunneling-machine wireless data collecting system based on mobile phone
CN105134183A (en) * 2015-10-13 2015-12-09 四川隧唐科技股份有限公司 Remote and real-time monitoring system for tunnel leakage water and implementation method of remote and real-time monitoring system
EP3247082A1 (en) * 2016-05-18 2017-11-22 Zscaler, Inc. Cloud-based virtual private access systems and methods
CN106776679A (en) * 2016-11-04 2017-05-31 中交第二航务工程局有限公司工程装备分公司 Shield machine tunneling construction remote centralized control method
CN107194601A (en) * 2017-05-31 2017-09-22 上海应用技术大学 A kind of method for managing and monitoring of shield machine
CN107222574A (en) * 2017-07-13 2017-09-29 合肥引力波数据科技有限公司 A kind of shield machine data collecting system based on mobile terminal
CN207117833U (en) * 2017-08-14 2018-03-16 河南省鸿联通信建设工程有限公司 Highway construction on-site supervision network system
CN107483889A (en) * 2017-08-24 2017-12-15 北京融通智慧科技有限公司 The tunnel monitoring system of wisdom building site control platform
CN107527082A (en) * 2017-09-27 2017-12-29 国网上海市电力公司 A kind of electric power tunnel management system based on Cloud Server and mobile terminal
CN108104838A (en) * 2017-11-01 2018-06-01 中铁隧道勘察设计研究院有限公司 A kind of automation control method of lining construction
CN207472722U (en) * 2017-11-09 2018-06-08 中交上海三航科学研究院有限公司 Constructing metro tunnel security information comprehensive management system
CN107966988A (en) * 2017-12-11 2018-04-27 中交第二航务工程局有限公司 The control system of shield machine construction electric locomotive
CN108055512A (en) * 2017-12-30 2018-05-18 中煤科工集团上海有限公司 Mating long distance tunnel continuous conveyor system monitoring and control device after a kind of shield
CN108388791A (en) * 2018-03-22 2018-08-10 中铁工程装备集团机电工程有限公司 A kind of shield machine uses authentication management system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
牛云鹏: "盾构施工长距离斜井数字化远程监控系统", 《工矿自动化》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115002570A (en) * 2022-04-18 2022-09-02 武汉毳雨环保科技有限责任公司 Remote monitoring system of construction equipment based on 5G network

Also Published As

Publication number Publication date
CN109040270B (en) 2021-08-31

Similar Documents

Publication Publication Date Title
CN208718682U (en) A kind of formwork jumbo construction monitoring system
CN107423865A (en) BIM-based high-speed railway informatization management system
CN103901869A (en) Quality monitoring method for concrete construction
CN104944240A (en) Elevator equipment state monitoring system based on large data technology
CN110703709A (en) Smart environmental sanitation cloud platform integrated management system
CN102385367A (en) Remote intelligent monitoring and feedback system and method of hoist
CN106097148A (en) A kind of Utilities Electric Co.'s emergency command and on-site examination system and checking method
CN109040270A (en) A kind of formwork jumbo construction monitoring method
CN111325949A (en) Water conservancy information management system applied to flood situation monitoring and early warning
CN113315838A (en) Intelligent building site comprehensive safe operation informatization supervision platform
CN108643939A (en) A kind of formwork jumbo construction monitoring system and monitoring method
CN103500377A (en) Integrated maintenance-operation management method and system for electric service ATP (Automatic Train Protection) vehicle-mounted equipment in railway
CN111815122A (en) Intelligent scheduling decision method and decision system for vehicles in port operation field
CN115871091A (en) Integrated application construction method for precast beam production line of intelligent beam factory based on informatization management
KR101531672B1 (en) System of providing integration management under division by charging-districts for plurality of salt water sprinklers using internet network
CN106193069A (en) A kind of equipment integrating for side slope concrete protection
CN109426864A (en) A kind of charging pile operational system
CN111428299A (en) Engineering whole-course monitoring system
CN113556377B (en) Ship external field coating environment monitoring system
CN112523307A (en) Secondary water supply system integrating data monitoring, analysis, operation and maintenance management and control
CN106677035A (en) Worming sliding form device
CN204904358U (en) Masses help network synthesis management system of highway inspection
CN203644221U (en) Parking guidance management system with monitoring camera shooting
CN207117833U (en) Highway construction on-site supervision network system
CN115115196A (en) Wisdom beam yard management and control system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant