CN109025077A - A kind of construction method of building roofing waterproof layer - Google Patents

A kind of construction method of building roofing waterproof layer Download PDF

Info

Publication number
CN109025077A
CN109025077A CN201810926163.0A CN201810926163A CN109025077A CN 109025077 A CN109025077 A CN 109025077A CN 201810926163 A CN201810926163 A CN 201810926163A CN 109025077 A CN109025077 A CN 109025077A
Authority
CN
China
Prior art keywords
mortar
base course
waterproof layer
course wall
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810926163.0A
Other languages
Chinese (zh)
Inventor
吕宗霞
江玲
叶兴国
吕俊杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hui Du Construction Co Ltd
Original Assignee
Hui Du Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hui Du Construction Co Ltd filed Critical Hui Du Construction Co Ltd
Priority to CN201810926163.0A priority Critical patent/CN109025077A/en
Publication of CN109025077A publication Critical patent/CN109025077A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D7/00Roof covering exclusively consisting of sealing masses applied in situ; Gravelling of flat roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04DROOF COVERINGS; SKY-LIGHTS; GUTTERS; ROOF-WORKING TOOLS
    • E04D13/00Special arrangements or devices in connection with roof coverings; Protection against birds; Roof drainage; Sky-lights
    • E04D13/16Insulating devices or arrangements in so far as the roof covering is concerned, e.g. characterised by the material or composition of the roof insulating material or its integration in the roof structure

Abstract

The invention discloses a kind of construction methods of building roofing waterproof layer, comprising the following steps: prepares putty;Remove base course wall floating ash, greasy dirt, release agent, for protrusion, hollowing, porous spot carry out rejecting and with putty it is levelling;Prepare boundary mortar;Boundary mortar is smeared on the two sides of base course wall;Configured boundary mortar is uniformly applied on base course wall, underlying polymer mortar is obtained, after base course wall is tentatively constructed, in the surface paving macromolecule water-proof sheet material of the boundary mortar layer.The present invention makes improvements conventional construction technique, it is preferred that the formula of adhesive mortar and polymer mortar, construction cost is saved, the rapid hardening rubber asphalt waterproof coating used simultaneously is mixed by emulsified asphalt, polymer rubber modifying agent and additive, has more excellent waterproof quality compared to general water-repellent paint.

Description

A kind of construction method of building roofing waterproof layer
Technical field
The present invention relates to building waterproofing technique field, the construction method of specifically a kind of building roofing waterproof layer.
Background technique
In building field, to prevent water to the infiltration at the certain positions of building and from construction material and structurally taking Waterproof measure.Currently, the measure that people generally take is that coating water-repellent paint or waterproof roll, coiled material advantage are on base's table Thickness is uniform, and thickness is easy to grasp by requirement of setting up defences, and it is accurate to be calculated with material, the disadvantage is that being needed in the construction process according to waterproof matrix Shape and cut the garment according to the figure, need muti-piece to splice the base of complex contour, the bonding difficulty of mutual lap-joint is larger, difficult To be absolutely sealed completely, leakage hidden trouble is big.The bonding of waterproof roll and base either Man Pu, Dian Pu, item paving, empty paving, coiled material All easily become channeling water layer between base, once there is penetrability damaged, degumming, leak adhesive, the water-proof function of entire waterproof layer is all By whole forfeitures, repair very difficult.
The advantages of water-repellent paint be it is easy for construction simple, waterproof layer is there is no overlap joint, the region that coiled material can not construct, especially It is complicated position, coating can be solved perfectly, and water tight integrity is good, but the disadvantage is that the flatness requirement to basal plane is higher, It is influenced by basal plane injustice, is easy became uneven, coating pass when thickness is according to construction determines.
Summary of the invention
The purpose of the present invention is to provide a kind of construction methods of building roofing waterproof layer, to solve above-mentioned background technique The problem of middle proposition.
To achieve the above object, the invention provides the following technical scheme:
A kind of construction method of building roofing waterproof layer, comprising the following steps:
S1: it preparing putty: 50-100 parts of powder of lacquer putty for use on and 30-50 parts of water is added in blender, 20-30rpm stirs 5-10min, Stand 20-30min, then again 20-30rpm stir 5-10min to get;
S2: floating ash, the greasy dirt, release agent of base course wall are removed, protrusion, hollowing, porous spot are rejected and use putty It is levelling;
S3: it prepares boundary mortar: blender is added in 20-50 parts of interfacial agents, 20-50 parts of portland cements, 20-50 parts of quartz sands In, 10-20rpm stir 10-20min to get;
S4: boundary mortar is smeared on the two sides of base course wall;
S5: configured boundary mortar is uniformly applied on base course wall, underlying polymer mortar is obtained, in floor interface Mortar surface punching, 5-10 hole of every square metre of installation, aperture 3-5mm, hole depth 20-40mm, then by glass fibre Grid cloth is exceptionally straight taut flat in the horizontal direction, and is pressed into the floor interface mortar punched, solidifies to surface not to bedding mortar When viscous hand, in fiberglass gridding cloth surface mounting fixing parts, the position of fixing piece installation and the hole of floor interface mortar surface It is corresponding, it installs and smears a bed boundary mortar again on fiberglass gridding cloth surface after fixing piece, smearing thickness is to cover glass Subject to glass fibrous mesh cloth, boundary mortar layer is obtained
S6: after base course wall is tentatively constructed, in the surface paving macromolecule water-proof sheet material of the boundary mortar layer, and Overlapping the slot processing is carried out by welding or gluing or overlap joint between adjacent high-molecular waterproof sheet, in the macromolecule water-proof sheet material Surface sprays rapid hardening rubber asphalt waterproof coating.
In as a further solution of the present invention: step S2), levelling flatness is 0-3mm/2m.
As further scheme of the invention: step S4) in, the applying amount of the base course wall boundary mortar is 0.2- 0.3kg/m2。
As further scheme of the invention: step S5) in, the smearing thickness of the boundary mortar is 1-3mm.
As further scheme of the invention: step S6) in, the rapid hardening rubber asphalt waterproof coating and the high score Sub- waterproof sheet bonding constitutes complex waterproof layer.
As further scheme of the invention: step S6) in, the rapid hardening rubber asphalt waterproof coating is dripped by emulsification Green, polymer rubber modifying agent and additive pass through the quick setting polymeric emulsion form water-repellent paint that emulsification and cross linked is formed.
As further scheme of the invention: the assembling reinforcement on the complex waterproof layer, casting concrete structure sheaf.
Compared with prior art, the beneficial effects of the present invention are: the present invention makes improvements conventional construction technique, preferably The formula of adhesive mortar and polymer mortar, has saved construction cost, at the same the rapid hardening rubber asphalt waterproof coating used be by Emulsified asphalt, polymer rubber modifying agent and additive mix, and have compared to general water-repellent paint more excellent anti- Water quality.
Specific embodiment
The following is a clear and complete description of the technical scheme in the embodiments of the invention, it is clear that described embodiment Only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, the common skill in this field Art personnel every other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
In the embodiment of the present invention, a kind of construction method of building roofing waterproof layer, comprising the following steps:
S1: it preparing putty: 50-100 parts of powder of lacquer putty for use on and 30-50 parts of water is added in blender, 20-30rpm stirs 5-10min, Stand 20-30min, then again 20-30rpm stir 5-10min to get;
S2: floating ash, the greasy dirt, release agent of base course wall are removed, protrusion, hollowing, porous spot are rejected and use putty It is levelling;
S3: it prepares boundary mortar: blender is added in 20-50 parts of interfacial agents, 20-50 parts of portland cements, 20-50 parts of quartz sands In, 10-20rpm stir 10-20min to get;
S4: boundary mortar is smeared on the two sides of base course wall;
S5: configured boundary mortar is uniformly applied on base course wall, underlying polymer mortar is obtained, in floor interface Mortar surface punching, 5-10 hole of every square metre of installation, aperture 3-5mm, hole depth 20-40mm, then by glass fibre Grid cloth is exceptionally straight taut flat in the horizontal direction, and is pressed into the floor interface mortar punched, solidifies to surface not to bedding mortar When viscous hand, in fiberglass gridding cloth surface mounting fixing parts, the position of fixing piece installation and the hole of floor interface mortar surface It is corresponding, it installs and smears a bed boundary mortar again on fiberglass gridding cloth surface after fixing piece, smearing thickness is to cover glass Subject to glass fibrous mesh cloth, boundary mortar layer is obtained;
S6: after base course wall is tentatively constructed, in the surface paving macromolecule water-proof sheet material of the boundary mortar layer, and Overlapping the slot processing is carried out by welding or gluing or overlap joint between adjacent high-molecular waterproof sheet, in the macromolecule water-proof sheet material Surface sprays rapid hardening rubber asphalt waterproof coating.
Preferably, the present embodiment step S2) in, levelling flatness is 0-3mm/2m.
Preferably, the present embodiment step S4) in, the applying amount of the base course wall boundary mortar is 0.2-0.3kg/m2.
Preferably, the present embodiment step S5) in, the smearing thickness of the boundary mortar is 1-3mm.
Preferably, the present embodiment step S6) in, the rapid hardening rubber asphalt waterproof coating and the macromolecule water-proof sheet material Bonding constitutes complex waterproof layer.
Preferably, the present embodiment step S6) in, the rapid hardening rubber asphalt waterproof coating is by emulsified asphalt, macromolecule Rubber modifier and additive pass through the quick setting polymeric emulsion form water-repellent paint that emulsification and cross linked is formed.
Preferably, in the present embodiment, the assembling reinforcement on the complex waterproof layer, casting concrete structure sheaf.
The present invention makes improvements conventional construction technique, preferably the formula of adhesive mortar and polymer mortar, saves Construction cost, while the rapid hardening rubber asphalt waterproof coating used is by emulsified asphalt, polymer rubber modifying agent and additive It mixes, has more excellent waterproof quality compared to general water-repellent paint.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art The other embodiments being understood that.

Claims (7)

1. a kind of construction method of building roofing waterproof layer, which comprises the following steps:
S1: it preparing putty: 50-100 parts of powder of lacquer putty for use on and 30-50 parts of water is added in blender, 20-30rpm stirs 5-10min, Stand 20-30min, then again 20-30rpm stir 5-10min to get;
S2: floating ash, the greasy dirt, release agent of base course wall are removed, protrusion, hollowing, porous spot are rejected and use putty It is levelling;
S3: it prepares boundary mortar: blender is added in 20-50 parts of interfacial agents, 20-50 parts of portland cements, 20-50 parts of quartz sands In, 10-20rpm stir 10-20min to get;
S4: boundary mortar is smeared on the two sides of base course wall;
S5: configured boundary mortar is uniformly applied on base course wall, underlying polymer mortar is obtained, in floor interface Mortar surface punching, 5-10 hole of every square metre of installation, aperture 3-5mm, hole depth 20-40mm, then by glass fibre Grid cloth is exceptionally straight taut flat in the horizontal direction, and is pressed into the floor interface mortar punched, solidifies to surface not to bedding mortar When viscous hand, in fiberglass gridding cloth surface mounting fixing parts, the position of fixing piece installation and the hole of floor interface mortar surface It is corresponding, it installs and smears a bed boundary mortar again on fiberglass gridding cloth surface after fixing piece, smearing thickness is to cover glass Subject to glass fibrous mesh cloth, boundary mortar layer is obtained
S6: after base course wall is tentatively constructed, in the surface paving macromolecule water-proof sheet material of the boundary mortar layer, and Overlapping the slot processing is carried out by welding or gluing or overlap joint between adjacent high-molecular waterproof sheet, in the macromolecule water-proof sheet material Surface sprays rapid hardening rubber asphalt waterproof coating.
2. the construction method of building roofing waterproof layer according to claim 1, which is characterized in that step S2) in, it is levelling Flatness is 0-3mm/2m.
3. the construction method of building roofing waterproof layer according to claim 1, which is characterized in that step S4) in, it is described The applying amount of base course wall boundary mortar is 0.2-0.3kg/m2.
4. the construction method of building roofing waterproof layer according to claim 1, which is characterized in that step S5) in, it is described The smearing thickness of boundary mortar is 1-3mm.
5. the construction method of building roofing waterproof layer according to claim 1, which is characterized in that step S6) in, it is described Rapid hardening rubber asphalt waterproof coating composition complex waterproof layer Nian Jie with the macromolecule water-proof sheet material.
6. the construction method of building roofing waterproof layer according to claim 1, which is characterized in that step S6) in, it is described Rapid hardening rubber asphalt waterproof coating is to pass through the speed that emulsification and cross linked is formed by emulsified asphalt, polymer rubber modifying agent and additive Solidifying macromolecule latex liquid water-repellent paint.
7. the construction method of building roofing waterproof layer according to claim 5, which is characterized in that in the composite water-proof Assembling reinforcement on layer, casting concrete structure sheaf.
CN201810926163.0A 2018-08-15 2018-08-15 A kind of construction method of building roofing waterproof layer Pending CN109025077A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810926163.0A CN109025077A (en) 2018-08-15 2018-08-15 A kind of construction method of building roofing waterproof layer

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810926163.0A CN109025077A (en) 2018-08-15 2018-08-15 A kind of construction method of building roofing waterproof layer

Publications (1)

Publication Number Publication Date
CN109025077A true CN109025077A (en) 2018-12-18

Family

ID=64630299

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810926163.0A Pending CN109025077A (en) 2018-08-15 2018-08-15 A kind of construction method of building roofing waterproof layer

Country Status (1)

Country Link
CN (1) CN109025077A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439158A (en) * 2021-12-21 2022-05-06 河北三棵树涂料有限公司 Waterproof construction method for rubber asphalt waterproof coating roof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104251140A (en) * 2014-09-03 2014-12-31 大禹伟业(北京)国际科技有限公司 Composite waterproof layer for underground construction and manufacturing and construction method thereof
CN104264715A (en) * 2014-09-03 2015-01-07 大禹伟业(北京)国际科技有限公司 Composite waterproof layer for environmental engineering and preparing and constructing method thereof
CN105623508A (en) * 2014-11-05 2016-06-01 大禹伟业(北京)国际科技有限公司 Aqueous flame-retardant rubber asphalt coating film waterproof material and preparation and construction method thereof
CN107023132A (en) * 2017-04-05 2017-08-08 霸州市瑞硕盈装饰装修工程有限公司 Extruded sheet exterior-wall heat insulation construction technology
CN107964362A (en) * 2017-11-23 2018-04-27 大禹伟业(北京)国际科技有限公司 One kind spraying rapid hardening rubber asphalt waterproof coating and its preparation and construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104251140A (en) * 2014-09-03 2014-12-31 大禹伟业(北京)国际科技有限公司 Composite waterproof layer for underground construction and manufacturing and construction method thereof
CN104264715A (en) * 2014-09-03 2015-01-07 大禹伟业(北京)国际科技有限公司 Composite waterproof layer for environmental engineering and preparing and constructing method thereof
CN105623508A (en) * 2014-11-05 2016-06-01 大禹伟业(北京)国际科技有限公司 Aqueous flame-retardant rubber asphalt coating film waterproof material and preparation and construction method thereof
CN107023132A (en) * 2017-04-05 2017-08-08 霸州市瑞硕盈装饰装修工程有限公司 Extruded sheet exterior-wall heat insulation construction technology
CN107964362A (en) * 2017-11-23 2018-04-27 大禹伟业(北京)国际科技有限公司 One kind spraying rapid hardening rubber asphalt waterproof coating and its preparation and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114439158A (en) * 2021-12-21 2022-05-06 河北三棵树涂料有限公司 Waterproof construction method for rubber asphalt waterproof coating roof
CN114439158B (en) * 2021-12-21 2023-11-28 河北三棵树涂料有限公司 Waterproof construction method for rubber asphalt waterproof coating roof

Similar Documents

Publication Publication Date Title
CN103343655B (en) Wall window construction method
CN104251140B (en) Composite waterproof layer for underground construction and manufacturing and construction method thereof
CN102762678B (en) Polymer-based film waterproofing agent mixed with cement, and preparation method thereof
KR100992952B1 (en) Complex waterproofing structure and construction method which use Low melting point polymer modified asphalt Waterproof material and silica sheet
CN108252530A (en) A kind of parapet percolating water repairs technique
CN103669417B (en) Prefabricated outer wall of basement seam crossing epoxy resin cement concrete and construction method thereof
CN106836529A (en) A kind of construction technology for being applied to exterior-wall heat insulation
KR101241940B1 (en) Aliphatic epoxy modified tarurethane waterproofing material and manufacturing method thereof, construction method and structure for complex waterproofing using aliphatic epoxy modified tarurethane waterproofing material and complex sheet with hole
CN112144581B (en) Large integral underground space waterproof construction structure and construction method thereof
KR100315181B1 (en) Two-Package Type Inorganic Membranous Waterproof Stuff Having Excellent Elasticity, Hybrid Membranous Waterproof Sheet and Construction Method therefor
CN112252462A (en) Construction method of concrete roof layer waterproof structure
CN106499066A (en) A kind of method that utilization FS101 mortar waterproof agents carry out building waterproof layer construction
CN108374566A (en) A kind of back side percolating water repairerment technique
CN108951893B (en) Shear wall horizontal construction joint rough surface reserved forming construction process
CN111608280A (en) External wall heat insulation construction method
CN109025077A (en) A kind of construction method of building roofing waterproof layer
KR101998820B1 (en) Complex waterproof structure for concrete slab and construction method thereof
DE10261076A1 (en) A process for coating a cement containing shaped part useful for covering concrete building components, cold rooms, sauna units, controlled tips, sewage treatment plants, tunnels, reactor construction, gas stations, flat roof coatings
CN112408851A (en) Anti-radiation semi-permanent nano-penetration crystallization sealing compacting agent and use method thereof
CN108343164A (en) A kind of expansion joint percolating water repairerment technique
CN107574936A (en) A kind of heat preserving exterior wall construction technology
CN109837894A (en) Anti-float anchor rod end multilayer flashing material mating steel plate for sealing water composite water-proof construction technology
CN105133855A (en) Energy-saving and environment-friendly waterproof warming construction method for existing roof surface
CN108560608A (en) Garbage power plant structures pond body engineering level construction joint construction
KR101212288B1 (en) Primer composition and construction method for waterproof structure using the same

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181218