CN109024628A - A kind of method of quick ecological slope controlling - Google Patents

A kind of method of quick ecological slope controlling Download PDF

Info

Publication number
CN109024628A
CN109024628A CN201810980084.8A CN201810980084A CN109024628A CN 109024628 A CN109024628 A CN 109024628A CN 201810980084 A CN201810980084 A CN 201810980084A CN 109024628 A CN109024628 A CN 109024628A
Authority
CN
China
Prior art keywords
slope protection
pipe
slope
revetment
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810980084.8A
Other languages
Chinese (zh)
Inventor
王磊
温楠
王建军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Hua Guo Shan Ecological Technology Co Ltd
Original Assignee
Shenzhen Hua Guo Shan Ecological Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Hua Guo Shan Ecological Technology Co Ltd filed Critical Shenzhen Hua Guo Shan Ecological Technology Co Ltd
Priority to CN201810980084.8A priority Critical patent/CN109024628A/en
Publication of CN109024628A publication Critical patent/CN109024628A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads

Abstract

The invention discloses a kind of methods of quick ecological slope controlling, comprising: more anchor poles are installed in slopes;It is laid with more slope protection pipes in slope surface, more slope protection pipes is made to connect to form interconnected multiple revetment grids;While forming interconnected multiple revetment grids, multiple revetment grids are fixedly connected with more anchor poles to form three-dimensional slope protection structure;Cementing material is perfused into interconnected multiple revetment grids, keeps the multiple revetment grid cementing integral to form stable three-dimensional slope protection structure;The region surrounded to each revetment grid is modified, and multiple grid planting areas conserved water and soil are formed.The protective slope structure that the present invention is formed is secured, is conducive to stability of slope, and short construction period is at low cost.

Description

A kind of method of quick ecological slope controlling
Technical field
The present invention relates to technical field of ecological slope protection more particularly to a kind of methods of quick ecological slope controlling.
Background technique
Bank protecting method used at present there are many multiplicity, using it is more be to utilize concrete material slope protection.Than earlier It is to use plane template concrete integrated poured, although this method protection effect is pretty good, can not afforests, environmental disruption is serious.
In order to afforest to slope protection, side slope is built by people using prefabricated concrete brick, among brick Space at planting plants, although this method has achieved the effect that greening, but has been hardly formed entirety between brick and brick, be easy Collapsing under the washing away of water flow;Secondly precast concrete block is needed first with mold pouring molding, then is shipped to construction site It constructs, this can extend construction period, increase cost.In addition, there are also a kind of novel protecting slope ecology vegetation is extensive at present Recovering technology -- cast-in-place grid ecological vestige, the technology using mold to revetment grid carry out cast in situs, do not have to it is prefabricated and It carries, speed of application can be accelerated, and protection effect is preferable, but the bulkhead tech remains unchanged and be unable to do without the use of mold, construction period It is long, it is at high cost, it is not able to satisfy the demand of quick ecological slope controlling.
Summary of the invention
The object of the invention is to provide a kind of quick ecological improvement side to overcome the above-mentioned problems of the prior art The method on slope, the casting concrete into using grid made of ready-made pipe fitting, forms firm protective slope structure, and it is steady to be conducive to side slope Fixed, short construction period is at low cost.
In order to realize above-mentioned purpose of the invention, the following technical schemes are provided:
A kind of method of quick ecological slope controlling, comprising: more anchor poles are installed in slopes;More are laid in slope surface Slope protection pipe makes more slope protection pipes connect to form interconnected multiple revetment grids;Forming interconnected multiple slope protection nets While lattice, multiple revetment grids are fixedly connected with more anchor poles to form three-dimensional slope protection structure;To interconnected multiple Cementing material is perfused in revetment grid, keeps the multiple revetment grid cementing integral to form stable three-dimensional slope protection structure; The region surrounded to each revetment grid is modified, and multiple grid planting areas conserved water and soil are formed.
Preferably, slope protection reinforcing bar is equipped in the slope protection pipe.
Preferably, it is described installed in slopes more anchor poles include: into slopes dispose it is more for being connect with slope protection pipe Root anchoring pipe;The anchor bar for connecting with slope protection reinforcing bar is worn in the anchoring pipe;The potting compound into the anchoring pipe Material is tied, keeps the anchoring pipe and the anchor bar worn in it cementing integral.
Preferably, described that more slope protection pipes are laid in slope surface, make more slope protection pipes connect to be formed it is interconnected multiple Revetment grid includes: to make more slope protection pipes connect to be formed using having the pipe fitting joint of several interface tubes to connect more slope protection pipes Interconnected multiple revetment grids;Wherein, when connecting more slope protection pipes using pipe fitting joint, slope protection reinforcing bar is consolidated It is fixed.
Preferably, the revetment grid is quadrangle revetment grid, and the pipe fitting joint includes: four-way union, tool There are four interface tubes being generally aligned in the same plane, for connecting four slope protection pipes;Five-way pipe joint has positioned at the first plane Four interface tubes and an interface tube positioned at the second plane, four interface tubes positioned at the first plane are for connecting four slope protections Pipe, an interface tube positioned at the second plane is for connecting anchoring pipe;Wherein, the second plane is perpendicular to the first plane.
Preferably, the anchor bar is centrally located in the anchoring pipe;The slope protection reinforcing bar is in the slope protection pipe It is centrally located.
Preferably, at least it is respectively arranged to make anchor bar is placed in the middle to determine by the position of two close end in the anchoring pipe Position part;Position at least in the slope protection pipe by two close end is respectively arranged to the locating piece for keeping slope protection reinforcing bar placed in the middle.
Preferably, the region surrounded to each revetment grid is modified, and forms multiple grid kinds conserved water and soil Growing area domain includes: that the region surrounded to revetment grid is excavated, to form plantation hole;It, will during forming plantation hole The remaining mound product excavated is in the slope surface being located at below plantation hole, in order to form the storage for being higher than plantation hole below plantation hole Water soil conservation wall.
Preferably, the slope protection pipe and anchoring pipe are using pvc pipe, PE pipe or stainless steel tube, glass reinforced plastic pipe.
Preferably, the cementing material is using non-metallic bonds materials such as concrete, gypsum or phosphorus magnesium.
The beneficial effects of the present invention are embodied in following aspect:
1) present invention is without using slope protection mold, the casting concrete in the revetment grid built using ready-made pipe fitting, quickly Firm protective slope structure is formed, stability of slope is conducive to, short construction period is at low cost.
2) present invention interts slope protection reinforcing bar in slope protection pipe, and makes revetment grid and be placed in the fixed company of the intracorporal anchor pole in slope It connects, forms stable three-dimensional slope protection structure, improve the stability of slope protection.
3) present invention fix the slope protection reinforcing bar being interspersed in slope protection pipe between two parties, convenient for condense in concrete be centrally formed it is whole Body is conducive to stable structure, improves the stability of slope protection.
4) the grid planting area to be formed and be conserved water and soil is modified in the region that each revetment grid surrounds by the present invention, is conducive to side The ecological construction on slope.
Detailed description of the invention
Fig. 1 is the effect picture that slope protection is carried out using the method for quick ecological slope controlling of the present invention;
Fig. 2 is front view shown in FIG. 1 (slope-protecting vegetation is not shown);
Fig. 3 is the structural schematic diagram of three-dimensional slope protection structure of the invention;
Fig. 4 is one embodiment of the fixed slope protection reinforcing bar of the present invention;
Fig. 5 is the cross-sectional view of an interface tube shown in Fig. 4;
Fig. 6 is another embodiment of the fixed slope protection reinforcing bar of the present invention;
Fig. 7 is the schematic diagram that the present invention disposes slope protection reinforcing bar in single-unit slope protection pipe;
Fig. 8 is geometrical relationship figure of the reinforcing bar fastener in slope protection pipe vertical section;
Fig. 9 a is the schematic diagram of one embodiment of reinforcing bar fastener of the invention;
Fig. 9 b is the schematic diagram of another embodiment of reinforcing bar fastener of the invention.
Description of symbols: 1- anchor pole;2- slope protection pipe;3- pipe fitting joint;31- four-way union;32- five-way pipe joint; 321- outer tube;322- inner tube;323- dowel;32a- upper connection;32b- lower connector;4- slope protection reinforcing bar;5- locating piece;6- Spats;The ground 7-.
Specific embodiment
The engineering that the present invention is suitable for quick ecological slope controlling pours in ready-made pipe fitting without using slope protection mold Concrete forms stable protective slope structure, and short construction period is at low cost.
It as shown in Figures 1 to 3, include: installation using the protective slope structure that the method for quick ecological slope controlling of the present invention is formed In the intracorporal more anchor poles 1 in slope;More slope protection pipes 2 being laid in slope surface, more slope protection pipes 2 connect shape by pipe fitting joint 3 At interconnected multiple revetment grids;It is poured in interconnected multiple revetment grids and is cemented to multiple revetment grids Whole cementing material;The grid planting area conserved water and soil being formed in the region that each revetment grid surrounds.Wherein, such as Shown in Fig. 3, interconnected multiple revetment grids are fixedly connected with more anchor poles, form three-dimensional slope protection structure;The quantity of anchor pole It is determined with spacing according to the plant that the size and Qi Nei of revetment grid are planted.As shown in Fig. 2, forming the shield of revetment grid Slope protection reinforcing bar 4 has also been assigned in the pipe of slope, it is by cementing material that revetment grid and slope protection reinforcing bar 4 is cementing integral, it is formed secured Protective slope structure.
The method of quick ecological slope controlling of the present invention is described in detail with reference to the accompanying drawings and examples.
A kind of method of quick ecological slope controlling, comprising: more anchor poles 1 are installed in slopes;It is laid with simultaneously in slope surface More slope protection pipes 2 are connected, the more connections of slope protection pipe 2 is made to form interconnected multiple revetment grids;Formation is interconnected more While a revetment grid, multiple revetment grids are fixedly connected with more anchor poles 1 to form three-dimensional slope protection structure;To mutually interconnecting Cementing material is perfused in logical multiple revetment grids, keeps multiple revetment grids cementing integral to form stable three-dimensional slope protection knot Structure;It is modified by the region surrounded to each revetment grid, forms multiple grid planting areas conserved water and soil.
Wherein, it before more anchor poles 1 are installed in slopes, needs to flatten slope surface substantially.
Slope surface carries out after flattening substantially, and more anchor poles are installed in slopes.Anchor pole includes: to be mounted on the intracorporal anchoring in slope Pipe;The anchor bar being threaded through in anchoring pipe;The cementing material being poured in anchoring pipe.More anchor poles are installed in slopes includes Step in detail below: it is burrowed first according to anchoring pipe diameter size into slopes in slope surface;Secondly, the placement anchoring pipe in hole, And make to anchor outside tube top end connector stretching slopes, in order to connect slope protection pipe 2;Anchor bar is worn in anchoring pipe again, and Stretch out anchor bar top connector outside slopes, in order to connect slope protection reinforcing bar 4;Cementing material finally is perfused into anchoring pipe, Keep anchoring pipe and the anchor bar worn in it cementing integral.
After the completion of rockbolt installation, more slope protection pipes 2 are connected using the pipe fitting joint with several interface tubes, make more slope protections The connection of pipe 2 forms interconnected multiple revetment grids.So that multiple revetment grids is interconnected, be convenient for overall perfusion into it, Improve charging efficiency;The one-piece casting structure formed after perfusion, stable structure, it is ensured that stability of slope.As shown in figure 3, this implementation The revetment grid of example is equilateral quadrangle revetment grid.As shown in figure 3, pipe fitting joint 3 includes: four for connecting slope protection pipe 2 Connection for bbreather pipe 31;For connecting slope protection pipe 2 and anchoring the five-way pipe joint 32 of pipe.Wherein, four-way union 31, which has, is located at together Four interface tubes of one plane, for connecting be laid in slope surface four slope protection pipes;Five-way pipe joint 32, which has, is located at first Four interface tubes of plane and an interface tube positioned at the second plane, four interface tubes positioned at the first plane are for connecting paving Four slope protection pipes being located in slope surface, an interface tube positioned at the second plane is for connecting anchoring tube top end connector;Wherein, Two planes are perpendicular to the first plane.
The shape of revetment grid is not limited to equilateral quadrangle, can be according to the interface tube quantity and slope protection pipe 2 of pipe fitting joint Length be adjusted.The specification of slope protection pipe 2 is determined according to slope matter and the gradient;The specification of the slope protection reinforcing bar 4 worn in slope protection pipe 2 And quantity is determined according to slope matter and the gradient.
Wherein, as shown in fig. 7, the slope protection reinforcing bar 4 of the present embodiment is centrally located in slope protection pipe 2.Specifically, at least protecting Locating piece 5 is respectively set in position in slope pipe 2 by two close end, for keeping slope protection reinforcing bar placed in the middle;Agglutination material is perfused into slope protection pipe 2 When material, the slope protection reinforcing bar being centrally located is convenient for cementing integral with cementing material, conducive to stable structure.
As shown in figure 8, the locating piece 5 of the present embodiment uses reinforcing bar fastener.Specifically, reinforcing bar fastener is with certain length steel Muscle is made, and the length 2L of the reinforcing bar fastener to complete, two half of angle αs and slope protection pipe 2 and slope protection reinforcing bar 4 Geometrical relationship shown in Fig. 8 need to be met, just can ensure that slope protection reinforcing bar 4 is located at 2 center of slope protection pipe, specific geometrical relationship Are as follows:
Wherein, R is the radius of slope protection pipe 2;R is the radius of slope protection reinforcing bar 4;θ be slope protection pipe 2 radius and reinforcing bar fastener it Between angle;α is the angle between two one side of something of reinforcing bar fastener;L is the half of reinforcing bar fastener length.
When it is implemented, reinforcing bar fastener can be fabricated to " V " font reinforcing bar fastener as illustrated in fig. 9 and as shown in figure 9b Containing circle reinforcing bar fastener.
When positioning slope protection reinforcing bar 4 using " V " font reinforcing bar fastener, first by two " V " font reinforcing bar fastener bindings in slope protection On reinforcing bar 4, then the slope protection reinforcing bar 4 for being banded with " V " font reinforcing bar fastener interted in slope protection pipe 2, and makes two " V " Zee bar steel Zs Muscle fastener is located at the position that two close end is leaned in slope protection pipe 2.As illustrated in fig. 9, " V " font reinforcing bar fastener is by certain length Bending is made reinforcing bar at its center, and when binding slope protection reinforcing bar 4, the binding of slope protection reinforcing bar 4 is arrived to the bending of " V " font reinforcing bar fastener Place.
The method and the method phase of " V " font reinforcing bar fastener positioning slope protection reinforcing bar 4 of the positioning slope protection reinforcing bar 4 of the reinforcing bar fastener containing circle Together, it repeats no more.As shown in figure 9b, the reinforcing bar fastener containing circle crimps a lasso system by the reinforcing bar of certain length at its center At set loop diameter is slightly larger than the diameter of slope protection reinforcing bar 4, and when binding slope protection reinforcing bar 4, set snare on slope protection reinforcing bar 4 and is bound.
Wherein, the anchor bar of the present embodiment is also centrally located in anchoring pipe.Specifically, at least close in anchoring pipe The position at both ends is respectively arranged to the locating piece for keeping anchor bar placed in the middle.Be arranged the mode of locating piece with it is right in slope protection pipe 2 The mode that locating piece is arranged in slope protection reinforcing bar 4 is identical, repeats no more.
As shown in Figures 2 and 3, slope protection pipe 2 gradually is laid with to top of the slope since the bottom of slope of adjacent spats 6.Utilize four-way pipe connector First 31 connection slope protection pipe 2, connects slope protection pipe 2 using five-way pipe joint 32 and anchoring is managed, and to the slope protection being interspersed in slope protection pipe 2 Reinforcing bar 4 is fixed.Slope protection reinforcing bar of the invention utilizes the fixation of pipe fitting joint 3 or binding and fixing.
The method that slope protection reinforcing bar 4 is fixed is described in detail with reference to the accompanying drawings and examples.
Embodiment one
The slope protection reinforcing bar of the present embodiment is fixed using pipe fitting joint 3.Specifically, a slope protection pipe 2 is correspondingly arranged a shield Slope reinforcing bar 4, and the length of slope protection reinforcing bar 4 is equal to or the length of slightly longer than slope protection pipe 2, and the both ends of slope protection reinforcing bar 4 is made to be all exposed shield Outside slope pipe 2, in order to which slope protection reinforcing bar 4 is fixed.
32 integrated injection molding of five-way pipe joint of the present embodiment, as shown in Figures 4 and 5, any interface tube includes: to be used for Connect the outer tube 321 of slope protection pipe 2;For connecting the inner tube 322 of slope protection reinforcing bar 4, it is located at 321 center of outer tube;For by inner tube 322 are fixed on the dowel 323 at 321 center of outer tube.Wherein, slope protection pipe 2 and outer tube 321 are interference fitted, slope protection reinforcing bar 4 and inner tube 322 interference fits.The shape of inner tube 322 can be determined according to the specification and quantity of the slope protection reinforcing bar 4 worn in slope protection pipe 2.
When connecting slope protection pipe 2 using the five-way pipe joint 32 of the present embodiment, the nozzle insertion of slope protection pipe 2 is located at the first plane Outer tube 321 in, while in the end insertion inner tube 322 of slope protection reinforcing bar 4, to realize fixation to slope protection reinforcing bar 4.With anchor pole When being fixedly connected, the nozzle insertion for anchoring pipe is located in the outer tube 321 of the second plane, while the end of anchor bar is inserted into and is corresponded to Inner tube 322 in.
Interface tube structure of the four interface tube structures of the four-way union 31 of the present embodiment with five-way pipe joint 32.
Embodiment two
The slope protection reinforcing bar 4 of the present embodiment passes through binding and fixing.Specifically, the length of slope protection reinforcing bar 4 is longer than slope protection pipe 2 Length can be arranged two or more even more slope protection pipes 2 outside a slope protection reinforcing bar 4.At this point, being fixedly connected with slope protection Before pipe 2 and slope protection reinforcing bar 4, slope protection pipe 2 is first arranged on slope protection reinforcing bar 4;Recycle the present embodiment four-way union 31 or Five-way pipe joint 32 connects slope protection pipe 2.The slope protection reinforcing bar 4 of the slope protection reinforcing bar 4 or intersection that intersect at the node of revetment grid Binding and fixing are carried out by the method for binding reinforcing steel bars of the prior art between anchor bar.
As shown in fig. 6, the five-way pipe joint 32 of the present embodiment includes: upper connection 32a;With upper connection 32a snapping Lower connector 32b.After upper connection 32a and lower connector 32b fastening, four interface tubes for holding slope protection pipe 2 tightly are formed.Its In, the lower connector 32b of five-way pipe joint 32 also has the interface tube for connecting anchoring pipe.Utilize the Five-way tube of the present embodiment When connector 32 connects slope protection pipe 2 and anchoring pipe, after first lower connector 32b and anchoring pipe are connected, then by anchor bar top Connector and slope protection reinforcing bar 4 carry out binding and fixing, finally fasten upper connection 32a and lower connector 32b.
Wherein, upper connection of the structure of the upper connection of the four-way union 31 of the present embodiment with five-way pipe joint 32 32a, its underpart connector and upper connection be symmetrical and snapping.Before connecting slope protection pipe 2 using the four-way union 31 of the present embodiment, first Slope protection reinforcing bar 4 is subjected to binding and fixing, then the upper connection of four-way union 31 is fastened with lower connector and connect slope protection pipe 2。
After being fixedly connected with slope protection pipe 2 and slope protection reinforcing bar 4, agglutination material is perfused into interconnected multiple revetment grids Material, specifically includes the following steps: to the not connected slope protection pipe 2 for the four-way union 31 or five-way pipe joint 32 for being located at top of the slope Cementing material is perfused in interface tube;Under gravity, cementing material flows from above to below, until filling up all slope protection nets Lattice.Cementing material of the invention using non-metallic bond material, such as concrete, phosphorus magnesium or gypsum etc., is matched by the label of concrete Than being determined according to slope matter and the gradient.
After the completion of concreting, the region surrounded to each revetment grid is modified, and forms multiple conserve water and soil Grid planting area, specifically includes the following steps: the region surrounded to revetment grid is excavated, to form plantation hole;In shape During at plantation hole, by the remaining mound excavated product in the slope surface being located at below plantation hole, in order under plantation hole The rectangular wall of conserving water and soil at higher than plantation hole.On the one hand the grid planting area formed in the above manner can plant Planting plants in cheating carry out ecological recovery, water and soil conservation;On the other hand it can use wall accumulation rainwater of conserving water and soil, carry out water Soil is kept.
Slope protection pipe and anchoring pipe of the invention uses pvc pipe, is also possible to the hoses such as PE pipe, PC pipe, PEC pipe;It can also be with It is stainless steel tube, glass reinforced plastic pipe etc..
Although above-mentioned elaborate the present invention, however, the present invention is not limited thereto, those skilled in the art can It is modified with principle according to the present invention, therefore, the various modifications that all principles according to the invention carry out all should be understood as Fall into protection scope of the present invention.

Claims (10)

1. a kind of method of quick ecological slope controlling, comprising: install more anchor poles in slopes;It is characterized by further comprising:
It is laid with more slope protection pipes in slope surface, more slope protection pipes is made to connect to form interconnected multiple revetment grids;
While forming interconnected multiple revetment grids, multiple revetment grids are fixedly connected with more anchor poles to be formed Three-dimensional slope protection structure;
Cementing material is perfused into interconnected multiple revetment grids, keeps the multiple revetment grid cementing integral to be formed Stable three-dimensional slope protection structure;
The region surrounded to each revetment grid is modified, and multiple grid planting areas conserved water and soil are formed.
2. the method for quick ecological slope controlling according to claim 1, which is characterized in that be equipped in the slope protection pipe Slope protection reinforcing bar.
3. the method for quick ecological slope controlling according to claim 2, which is characterized in that the installation in slopes is more Root anchor pole includes:
More piece anchorings pipe of the placement for being connect with slope protection pipe into slopes;
The anchor bar for connecting with slope protection reinforcing bar is worn in the anchoring pipe;
Cementing material is perfused into the anchoring pipe, keeps the anchoring pipe and the anchor bar worn in it cementing integral.
4. the method for quick ecological slope controlling according to claim 3, which is characterized in that the laying in slope surface is more Root slope protection pipe connects more slope protection pipes to form interconnected multiple revetment grids and include:
Connect more slope protection pipes using the pipe fitting joint with several interface tubes, make more slope protection pipes connect to be formed it is interconnected Multiple revetment grids;
Wherein, when connecting more slope protection pipes using pipe fitting joint, slope protection reinforcing bar is fixed.
5. the method for quick ecological slope controlling according to claim 4, which is characterized in that the revetment grid is four sides Shape revetment grid, the pipe fitting joint include:
Four-way union has four interface tubes being generally aligned in the same plane, for connecting four slope protection pipes;
Five-way pipe joint has an interface tube positioned at four interface tubes of the first plane and positioned at the second plane, is located at Four interface tubes of the first plane are for connecting four slope protection pipes, and an interface tube positioned at the second plane is for connecting anchoring Pipe;
Wherein, the second plane is perpendicular to the first plane.
6. the method for quick ecological slope controlling according to claim 5, which is characterized in that the anchor bar is described It is centrally located in anchoring pipe;The slope protection reinforcing bar is centrally located in the slope protection pipe.
7. the method for quick ecological slope controlling according to claim 6, which is characterized in that at least in the anchoring pipe The locating piece for keeping anchor bar placed in the middle is respectively arranged to by the position of two close end;By two close end at least in the slope protection pipe Position is respectively arranged to the locating piece for keeping slope protection reinforcing bar placed in the middle.
8. the method for quick ecological slope controlling according to claim 7, which is characterized in that described to each revetment grid The region of encirclement is modified, and is formed multiple grid planting areas conserved water and soil and is included:
The region surrounded to revetment grid is excavated, to form plantation hole;
During forming plantation hole, by the remaining mound excavated product be located at plantation hole below slope surface on, in order to The wall of conserving water and soil for being higher than plantation hole is formed below plantation hole.
9. the method for quick ecological slope controlling according to claim 3, which is characterized in that the slope protection pipe and anchoring pipe Using pvc pipe, PE pipe or stainless steel tube, glass reinforced plastic pipe.
10. the method for quick ecological slope controlling according to claim 1, which is characterized in that the cementing material uses Non-metallic bond material.
CN201810980084.8A 2018-08-27 2018-08-27 A kind of method of quick ecological slope controlling Pending CN109024628A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810980084.8A CN109024628A (en) 2018-08-27 2018-08-27 A kind of method of quick ecological slope controlling

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810980084.8A CN109024628A (en) 2018-08-27 2018-08-27 A kind of method of quick ecological slope controlling

Publications (1)

Publication Number Publication Date
CN109024628A true CN109024628A (en) 2018-12-18

Family

ID=64625060

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810980084.8A Pending CN109024628A (en) 2018-08-27 2018-08-27 A kind of method of quick ecological slope controlling

Country Status (1)

Country Link
CN (1) CN109024628A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116876533A (en) * 2023-06-30 2023-10-13 济南黄河路桥建设集团有限公司 Mountain reinforcement and restoration method

Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5685029A (en) * 1979-12-14 1981-07-10 Raito Kogyo Kk Protection work for slope
JPS5862223A (en) * 1981-10-09 1983-04-13 Furii Kogyo Kk Slope protection work
JPS58143020A (en) * 1982-02-19 1983-08-25 Furii Kogyo Kk Slope protection work
JPS61229024A (en) * 1985-04-02 1986-10-13 Kensetsu Kiso Eng Kk Slope stabilizing method
US5337532A (en) * 1990-10-11 1994-08-16 Reid Robert C Concrete floor system
JPH07180157A (en) * 1993-12-22 1995-07-18 Tekken Constr Co Ltd Slope protection method
JPH0813502A (en) * 1994-07-01 1996-01-16 Kajima Corp Cut slope face stabilizing construction method
JP2002227213A (en) * 2001-01-30 2002-08-14 Suzuki Kinzoku Kogyo Kk Slope-stabilizing method and its reinforced frame
JP2002309585A (en) * 2001-04-12 2002-10-23 Hara Sogyo Kk Slope protection frame structure with permanent anchor
KR20040101137A (en) * 2004-11-05 2004-12-02 주식회사 오륙개발 A method of construction for stability and afforestation of a sloping surface
KR100560440B1 (en) * 2005-07-14 2006-03-13 주식회사 우지스 The foundation reinforcement method of having used composite fiberglass reinforced plastic reinforcement type grouting equipment and this equipment method for a tunnel and slope
KR20070068991A (en) * 2006-07-31 2007-07-02 주식회사 아이콘텍이앤씨 Bar type anchor
US20080172975A1 (en) * 2007-01-22 2008-07-24 Hickory Springs Manufacturing Company Rod positioner and associated method
US20120304586A1 (en) * 2011-06-06 2012-12-06 Masonry Reinforcing Corporation Of America Bond beam rebar positioner
JP3197576U (en) * 2015-01-09 2015-05-28 由伍 小宮 Protection walls and protection dams to prevent landslides.
CN104947694A (en) * 2015-05-18 2015-09-30 兰泽民 Earth slope grouting reinforcement construction method

Patent Citations (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5685029A (en) * 1979-12-14 1981-07-10 Raito Kogyo Kk Protection work for slope
JPS5862223A (en) * 1981-10-09 1983-04-13 Furii Kogyo Kk Slope protection work
JPS58143020A (en) * 1982-02-19 1983-08-25 Furii Kogyo Kk Slope protection work
JPS61229024A (en) * 1985-04-02 1986-10-13 Kensetsu Kiso Eng Kk Slope stabilizing method
US5337532A (en) * 1990-10-11 1994-08-16 Reid Robert C Concrete floor system
JPH07180157A (en) * 1993-12-22 1995-07-18 Tekken Constr Co Ltd Slope protection method
JPH0813502A (en) * 1994-07-01 1996-01-16 Kajima Corp Cut slope face stabilizing construction method
JP2002227213A (en) * 2001-01-30 2002-08-14 Suzuki Kinzoku Kogyo Kk Slope-stabilizing method and its reinforced frame
JP2002309585A (en) * 2001-04-12 2002-10-23 Hara Sogyo Kk Slope protection frame structure with permanent anchor
KR20040101137A (en) * 2004-11-05 2004-12-02 주식회사 오륙개발 A method of construction for stability and afforestation of a sloping surface
KR100560440B1 (en) * 2005-07-14 2006-03-13 주식회사 우지스 The foundation reinforcement method of having used composite fiberglass reinforced plastic reinforcement type grouting equipment and this equipment method for a tunnel and slope
KR20070068991A (en) * 2006-07-31 2007-07-02 주식회사 아이콘텍이앤씨 Bar type anchor
US20080172975A1 (en) * 2007-01-22 2008-07-24 Hickory Springs Manufacturing Company Rod positioner and associated method
US20120304586A1 (en) * 2011-06-06 2012-12-06 Masonry Reinforcing Corporation Of America Bond beam rebar positioner
JP3197576U (en) * 2015-01-09 2015-05-28 由伍 小宮 Protection walls and protection dams to prevent landslides.
CN104947694A (en) * 2015-05-18 2015-09-30 兰泽民 Earth slope grouting reinforcement construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116876533A (en) * 2023-06-30 2023-10-13 济南黄河路桥建设集团有限公司 Mountain reinforcement and restoration method
CN116876533B (en) * 2023-06-30 2024-03-26 济南黄河路桥建设集团有限公司 Mountain reinforcement and restoration method

Similar Documents

Publication Publication Date Title
CN102900088B (en) Cast-in-place ecological slope protection and construction method thereof
CN102619229B (en) Ecological supporting and protecting system and construction method using flexible cladding soil nailing wall combined with reinforced earth
CN207295737U (en) Suitable for the ecological revetment system in plateau mountainous region
CN102605793B (en) Moisture transfer and ecological management method for loess slope
CN204000904U (en) A kind of mesh duct for solid slope water storage
CN208949898U (en) A kind of quick ecological protective slope structure
CN208183653U (en) A kind of slope protection structure
CN109024628A (en) A kind of method of quick ecological slope controlling
CN109972638A (en) The construction method of prefabricated assembled thin-wall mould-shell lattice girder ecological slope protection
CN107119631B (en) A kind of hydraulic engineering ecological supporting structure
CN103122640A (en) Slope protective structure and protective method
CN202543951U (en) Flexible surface layer soil nailing wall combined reinforced soil ecological supporting system
CN102031759A (en) Novel method for stabilizing and controlling sand by multifunctional windbreak wall
CN210013240U (en) Interlocking type ecological retaining wall building block
CN209194550U (en) Side slope ecological protection structure
CN100435616C (en) Re-greening technology of high gradient slope in stone pit
CN108775019A (en) A kind of quick ecological protective slope structure
CN208956593U (en) A kind of plant watering device based on cast-in-place ecological slope protection
CN210507481U (en) Ecological environmental protection's side slope reinforced structure
CN212896398U (en) Ecological slope protection
CN101235646A (en) Building slope ecological supporting technique
CN209243751U (en) A kind of low-rise building
CN108934972A (en) A kind of plant watering device and its implementation based on cast-in-place ecological slope protection
CN207176626U (en) A kind of protection slope net of convenient installation
CN105297746B (en) Greening system and greening method for prefabricated arch body bearing-type vegetation concrete side slope

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination