CN109024283A - A kind of rack construction precompressed loading device - Google Patents

A kind of rack construction precompressed loading device Download PDF

Info

Publication number
CN109024283A
CN109024283A CN201810745704.XA CN201810745704A CN109024283A CN 109024283 A CN109024283 A CN 109024283A CN 201810745704 A CN201810745704 A CN 201810745704A CN 109024283 A CN109024283 A CN 109024283A
Authority
CN
China
Prior art keywords
loading device
precompressed
plate
side wall
fixing axle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810745704.XA
Other languages
Chinese (zh)
Inventor
刘弘博
陈�胜
何锋
罗翱
黄卫国
龙峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guizhou Xinlian Blasting Engineering Group Co Ltd
Original Assignee
Guizhou Xinlian Blasting Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guizhou Xinlian Blasting Engineering Group Co Ltd filed Critical Guizhou Xinlian Blasting Engineering Group Co Ltd
Priority to CN201810745704.XA priority Critical patent/CN109024283A/en
Publication of CN109024283A publication Critical patent/CN109024283A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of rack construction precompressed loading devices, whole precompressed loading device and branch's precompressed loading device are both placed on bridge, it is characterized by: whole precompressed loading device includes side wall, loading blocks, top support, lifting hole and bottom support bracket, side wall is located at the upper surface surrounding of bottom support bracket, the bottom of side wall and the upper surface of bottom support bracket pass through welded connecting, it is located in side wall on bottom support bracket and is equipped with loading blocks, the top of side wall and top support are welded to connect, four corners of top support are equipped with lifting hole, branch's precompressed loading device includes supporting walls, concrete plate, top plate, lifting hole(eyelet), middle part fixing axle, columnar through holes and bottom plate, the upper surface surrounding of bottom plate is welded with side supporting walls, top plate is fixedly welded at the top of supporting walls, four corners of top plate are equipped with lifting hole(eyelet).Present invention construction is more convenient, and progress is improved, and the load of pre-pressing bracket method is relatively uniform, and effect is more satisfactory, can reuse.

Description

A kind of rack construction precompressed loading device
Technical field
The present invention relates to rack construction precompressed loading device technical field, specially a kind of rack construction precompressed load dress It sets.
Background technique
Pre-pressing bracket is carried out before the construction of construction with brackets bridge superstructure, data are obtained by settlement observation, is subsequent Cast-in-situ bridge Superstructure Construction provide authentic data, but it there are still following drawbacks during actual use:
Most of pre-pressing bracket uses concrete block, clump weight etc., since Cast-in-Situ Continuous Beam counterweight is larger, material requested at present It is more, a large amount of artificial, mechanical equipments are expended when implementation.
Summary of the invention
The purpose of the present invention is to provide a kind of rack construction precompressed loading devices, to solve to propose in above-mentioned background technique The problem of.
To achieve the above object, the invention provides the following technical scheme: a kind of rack construction precompressed loading device, including it is whole Body precompressed loading device and branch's precompressed loading device, the entirety precompressed loading device and branch's precompressed loading device are placed On bridge, it is characterised in that: the entirety precompressed loading device includes side wall, loading blocks, top support, lifting hole and bottom Support, the side wall are located at the upper surface surrounding of bottom support bracket, and the bottom of the side wall and the upper surface of bottom support bracket pass through weldering It connects in succession, is located in side wall on the bottom support bracket and is equipped with loading blocks, the top of the side wall and top support are welded to connect, institute Four corners for stating top support are equipped with lifting hole, and branch's precompressed loading device includes supporting walls, concrete plate, top Plate, lifting hole(eyelet), middle part fixing axle, columnar through holes and bottom plate, the upper surface surrounding of the bottom plate are welded with supporting walls, the supporting walls Top be fixedly welded with top plate, four corners of top plate are equipped with lifting hole(eyelet).
Preferably, the upper surface center position of the bottom plate is equipped with middle part fixing axle, is socketed in the middle part fixing axle There is concrete plate, the middle part fixing axle is located in the columnar through holes on concrete plate.
Preferably, the two sides of the concrete plate are equipped with loading blocks and load and unload handle, set on the loading blocks handling handle There is rubber antiskid set.
Preferably, the middle part fixing axle is equipped with ball, and the ball is equipped with multiple groups, and ball described in multiple groups is solid at middle part The surface of dead axle is arranged around the central axis of middle part fixing axle in equidistant ring.
Preferably, the concrete plate is equipped with multiple groups, and the quality and volume of concrete plate described in multiple groups are on bottom plate It is descending from bottom to top successively to successively decrease.
Compared with prior art, the beneficial effects of the present invention are: structure of the invention setting rationally, functional, have with Lower advantage:
1. present invention construction is more convenient, progress is improved, and the load of pre-pressing bracket method is relatively uniform, and effect is more satisfactory, It can reuse;
2. the present invention carries out precompressed to bracket together using whole precompressed loading device and branch's precompressed loading device, can be by changing It is pre- to entirety to become the number of loading blocks and the number of branch's precompressed loading device inner concrete plate in whole precompressed loading device The severe of pressure loading device and branch's precompressed loading device is adjusted, so that on-load pressure is accurately controlled, so that precompressed is imitated Fruit is more preferable.
Detailed description of the invention
Fig. 1 is whole precompressed loading device main view;
Fig. 2 is whole precompressed loading device top view;
Fig. 3 is branch's precompressed loading device main view;
Fig. 4 is branch's precompressed loading device top view;
Fig. 5 is whole precompressed loading device and placement status figure of branch's precompressed loading device on bridge.
In figure: whole precompressed loading device 1, side wall 3, loading blocks 4, top support 5, is promoted branch's precompressed loading device 2 Hole 6, middle part fixing axle 7, loading blocks handling handle 8, ball 9, columnar through holes 10, rubber antiskid set 11, bottom support bracket 12, support Wall 13, concrete plate 14, top plate 15, lifting hole(eyelet) 16, bottom plate 17.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1-5 is please referred to, the present invention provides a kind of technical solution: a kind of rack construction precompressed loading device, including entirety Precompressed loading device 1 and branch's precompressed loading device 2, whole precompressed loading device 1 and branch's precompressed loading device 2 are both placed in On bridge, whole precompressed loading device 1 includes side wall 3, loading blocks 4, top support 5, lifting hole 6 and bottom support bracket 12, side wall 3 Positioned at the upper surface surrounding of bottom support bracket 12, the bottom of side wall 3 and the upper surface of bottom support bracket 12 are by being welded to connect, bottom branch It is located in side wall 3 on seat 12 and is equipped with loading blocks 4, the top of side wall 3 and top support 5 is welded to connect, four sides of top support 5 Angle is equipped with lifting hole 6, and branch's precompressed loading device 2 is solid including supporting walls 13, concrete plate 14, top plate 15, lifting hole(eyelet) 16, middle part Dead axle 7, columnar through holes 10 and bottom plate 17, the upper surface surrounding of bottom plate 17 are welded with supporting walls 13, and the top of supporting walls 13 is fixed It is welded with top plate 15, four corners of top plate 15 are equipped with lifting hole(eyelet) 16.
Further, the upper surface center position of bottom plate 17 is equipped with middle part fixing axle 7, is socketed in middle part fixing axle 7 Concrete plate 14, middle part fixing axle 7 are located in the columnar through holes 10 on concrete plate 14;
Further, the two sides of concrete plate 14 are equipped with loading blocks and load and unload handle 8, and loading blocks load and unload handle 8 and are equipped with rubber Anti-slip cover 11, rubber antiskid set 11 can prevent the loading blocks handling handle 8 when carrying concrete plate 14 from skidding;
Further, middle part fixing axle 7 is equipped with ball 9, and ball 9 is equipped with multiple groups, table of the multiple groups ball 9 in middle part fixing axle 7 Face is arranged around the central axis of middle part fixing axle 7 in equidistant ring, so as to reduce middle part fixing axle 7 and concrete plate 14 On dirty 10 inner wall of through-hole of resident between frictional resistance;
Further, concrete plate 14 is equipped with multiple groups, and the quality and volume of multiple groups concrete plate 14 are on bottom plate 17 under It is up descending successively to successively decrease.
Working principle: the present invention in use, after bridge formwork is installed, is added according to setting load It carries, since loading blocks 4 are different with the material of concrete plate 14, the density and volume of loading blocks 4 and concrete plate 14 is changed It is counted as severe, the final quantity for converting required loading blocks 4 and concrete plate 14, whole 1 severe of precompressed loading device is integer, Remaining load is completed by branch's precompressed loading device 2, is then first lifted whole precompressed loading device 1, is divided finally by changing The different of the number for the concrete plate 14 placed in portion's precompressed loading device 2 carry out accurate adjustment load to meet design load It is required that top support 5 is weldingly fixed on to the upper end of supporting walls 13 after adjustment, it then will by the lifting hole(eyelet) 16 on top plate 15 Branch's precompressed loading device 2 after adjustment carries out lifting precompressed and is loaded with completing construction with brackets bridge superstructure precompressed, After load whole precompressed loading device 1 and the unloading of branch's precompressed loading device 2 are transported to spare at the free time of building site, are suitble to push away Extensively.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (5)

1. a kind of rack construction precompressed loading device, including whole precompressed loading device (1) and branch's precompressed loading device (2), The entirety precompressed loading device (1) and branch's precompressed loading device (2) are both placed on bridge, it is characterised in that: described whole Body precompressed loading device (1) includes side wall (3), loading blocks (4), top support (5), lifting hole (6) and bottom support bracket (12), institute State the upper surface surrounding that side wall (3) is located at bottom support bracket (12), the bottom of the side wall (3) and the upper surface of bottom support bracket (12) By being welded to connect, be located in side wall (3) on the bottom support bracket (12) and be equipped with loading blocks (4), the top of the side wall (3) with Top support (5) is welded to connect, and four corners of the top support (5) are equipped with lifting hole (6), branch's precompressed load dress Setting (2) includes supporting walls (13), concrete plate (14), top plate (15), lifting hole(eyelet) (16), middle part fixing axle (7), columnar through holes (10) it is welded with supporting walls (13) with bottom plate (17), the upper surface surrounding of the bottom plate (17), the top of the supporting walls (13) It is fixedly welded with top plate (15), four corners of top plate (15) are equipped with lifting hole(eyelet) (16).
2. a kind of rack construction precompressed loading device according to claim 1, it is characterised in that: the bottom plate (17) it is upper Middle part fixing axle (7) are equipped at centre of surface position, are socketed with concrete plate (14) on the middle part fixing axle (7), it is described Middle part fixing axle (7) is located at the columnar through holes (10) on concrete plate (14) Nei.
3. a kind of rack construction precompressed loading device according to claim 1, it is characterised in that: the concrete plate (14) two sides are equipped with loading blocks handling handle (8), and loading blocks handling handle (8) are equipped with rubber antiskid set (11).
4. a kind of rack construction precompressed loading device according to claim 1, it is characterised in that: the middle part fixing axle (7) ball (9) are equipped with, the ball (9) is equipped with multiple groups, and ball (9) described in multiple groups is on the surface of middle part fixing axle (7) in The central axis of portion's fixing axle (7) is arranged in equidistant ring.
5. a kind of rack construction precompressed loading device according to claim 2, it is characterised in that: the concrete plate (14) multiple groups are equipped with, the quality and volume of concrete plate (14) described in multiple groups on bottom plate (17) it is descending from bottom to top according to It is secondary to successively decrease.
CN201810745704.XA 2018-07-09 2018-07-09 A kind of rack construction precompressed loading device Pending CN109024283A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810745704.XA CN109024283A (en) 2018-07-09 2018-07-09 A kind of rack construction precompressed loading device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810745704.XA CN109024283A (en) 2018-07-09 2018-07-09 A kind of rack construction precompressed loading device

Publications (1)

Publication Number Publication Date
CN109024283A true CN109024283A (en) 2018-12-18

Family

ID=64641231

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810745704.XA Pending CN109024283A (en) 2018-07-09 2018-07-09 A kind of rack construction precompressed loading device

Country Status (1)

Country Link
CN (1) CN109024283A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111560862A (en) * 2020-04-29 2020-08-21 南京林业大学 Pre-pressing self-balancing support replacing method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4456402A (en) * 1979-09-07 1984-06-26 Gusto Engineering B.V. Method for increasing the stability of an artificial island by means of pre-loading
CN103697110A (en) * 2013-12-05 2014-04-02 铜陵晟王铁路装备股份有限公司 Heavy gravity loading block
CN204435444U (en) * 2015-02-05 2015-07-01 葛洲坝集团第五工程有限公司 Bridge construction multipurpose prefabricated section
CN206015524U (en) * 2016-06-28 2017-03-15 山东省路桥集团有限公司 A kind of pre- briquetting
CN206256499U (en) * 2016-12-13 2017-06-16 重庆永重重工有限公司 A kind of loading machine balance weight
CN107460827A (en) * 2017-08-09 2017-12-12 中国十七冶集团有限公司 A kind of method of cast-in-situ box girder form bracing system precompressed
CN208586527U (en) * 2018-07-09 2019-03-08 保利新联爆破工程集团有限公司 A kind of rack construction precompressed loading device

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4456402A (en) * 1979-09-07 1984-06-26 Gusto Engineering B.V. Method for increasing the stability of an artificial island by means of pre-loading
CN103697110A (en) * 2013-12-05 2014-04-02 铜陵晟王铁路装备股份有限公司 Heavy gravity loading block
CN204435444U (en) * 2015-02-05 2015-07-01 葛洲坝集团第五工程有限公司 Bridge construction multipurpose prefabricated section
CN206015524U (en) * 2016-06-28 2017-03-15 山东省路桥集团有限公司 A kind of pre- briquetting
CN206256499U (en) * 2016-12-13 2017-06-16 重庆永重重工有限公司 A kind of loading machine balance weight
CN107460827A (en) * 2017-08-09 2017-12-12 中国十七冶集团有限公司 A kind of method of cast-in-situ box girder form bracing system precompressed
CN208586527U (en) * 2018-07-09 2019-03-08 保利新联爆破工程集团有限公司 A kind of rack construction precompressed loading device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
"支架预压方案", 百度文库 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111560862A (en) * 2020-04-29 2020-08-21 南京林业大学 Pre-pressing self-balancing support replacing method

Similar Documents

Publication Publication Date Title
CN206188192U (en) Hoist of steel sheet is hung in steelmaking with dress
CN107288353A (en) Equipment hoisting transition supporting platform on ultrahigh building floor and construction method thereof
CN107628080A (en) A kind of stroller for being used to load heavy steel
CN109024283A (en) A kind of rack construction precompressed loading device
CN208586527U (en) A kind of rack construction precompressed loading device
CN203639095U (en) Inner-side-column lifting device for reverse installation method
CN106628315A (en) Gantry hydraulic brick making machine stacking and packaging machine
CN106629105A (en) Flip-chip separation type bucket formula spills material device
CN108636796A (en) A kind of high-elastic sieve plate of band self-cleaning device and preparation method thereof
CN212956146U (en) Continuous beam hanging basket prepressing device for bridge construction
CN208996201U (en) Construction steel structure support device
CN215516568U (en) Feeding and discharging device for coiled materials
CN113401782B (en) Hoisting deformation control method for large-opening straight cavity structure block
CN104458177B (en) Earthquake simulation shaking table test bearing model counterweight device and construction method thereof
CN206048465U (en) Isolated footing concreting mould
CN213563178U (en) Cold pressing device for core plate adhesion
CN108225896A (en) No. 0 segment bracket static loading prepressing test device of cast-in-situ continuous beam and test method
CN108035355A (en) A kind of building concrete, which pours, uses automatic positioning equipment
CN209034855U (en) A kind of high-elastic sieve plate of band self-cleaning device
CN106956367A (en) A kind of steel fibre transport metering mechanism applied to concrete-agitating
CN207714158U (en) Bridge pier unloads balanced structure
CN209956561U (en) Mold storage device
EP0417079A1 (en) System for die-casting of concrete products such as block stones in a cellular mould
CN209723032U (en) One kind being used for the field erected multi-functional fashioned iron flip beam of prefabricated pipe gallery
CN206188193U (en) Gallows has been used in prefabricated piping lane drawing of patterns

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20181218