CN109004610A - 一种电力工程施工方法 - Google Patents
一种电力工程施工方法 Download PDFInfo
- Publication number
- CN109004610A CN109004610A CN201810859876.XA CN201810859876A CN109004610A CN 109004610 A CN109004610 A CN 109004610A CN 201810859876 A CN201810859876 A CN 201810859876A CN 109004610 A CN109004610 A CN 109004610A
- Authority
- CN
- China
- Prior art keywords
- excavation
- construction
- electric power
- phase
- excavated
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G9/00—Installations of electric cables or lines in or on the ground or water
- H02G9/06—Installations of electric cables or lines in or on the ground or water in underground tubes or conduits; Tubes or conduits therefor
Landscapes
- Laying Of Electric Cables Or Lines Outside (AREA)
Abstract
本发明公开了本发明一种电力工程施工方法,所述方法包括如下步骤:S1:开挖前,测量人员根据控制坐标点及高程基准点建立自己的施工控制网,控制点作埋石标记,测量原始地形,确定开挖边线,整理成图后报监理工程师批准;S2:监理工程师批准后,进行边线挖掘,测量人员随时检查开挖各参数,确保基础开挖的高程及边坡的坡比,严禁超欠挖;S3:土方开挖采用反铲进行挖掘,开挖临近设计高程时,预留一定厚度的厚保护层,用人工清挖,修整到设计底板基础高程。易风化崩解的土层,开挖后应保留保护层至下道工序施工前再修整挖除;电力管道施工存在多管组合回拖和压密注浆等施工特点,不仅使得回拖时的阻力增加。
Description
技术领域
本发明涉及一种施工方法,具体涉及一种电力工程施工方法。
背景技术
随着城市经济的快速发展和城市化进程的加快,电力工程建设项目日益增多。不需要在路面架设杆塔和导线,不占地面空间,易于保持市容整齐美观的电力电缆工程也越来越多。
常规电缆工程的施工都是开槽铺设电力管道,造成令市民深恶痛绝的马路“拉链现象”。同时在建设电力通道过程中,不免遇到无法按传统开挖工艺穿越的节点如各类市政管线交叉点、公路、铁路、桥梁、河道和地面建筑物等。因此,常规的大开挖施工技术越来越不适应城市发展的需要。
由于水平定向钻进技术相对于传统开挖的方法有诸多优势,使得其在铺设城市电力管道的应用越来越广泛。
发明内容
本发明所要解决的技术问题是常规电缆工程的施工都是开槽铺设电力管道,造成令市民深恶痛绝的马路“拉链现象”,目的在于提供一种电力工程施工方法,解决上述的问题。
本发明通过下述技术方案实现:
一种电力工程施工方法,所述方法包括如下步骤:S1:开挖前,测量人员根据控制坐标点及高程基准点建立自己的施工控制网,控制点作埋石标记,测量原始地形,确定开挖边线,整理成图后报监理工程师批准;S2:监理工程师批准后,进行边线挖掘,测量人员随时检查开挖各参数,确保基础开挖的高程及边坡的坡比,严禁超欠挖;S3:土方开挖采用反铲进行挖掘,开挖临近设计高程时,预留一定厚度的厚保护层,用人工清挖,修整到设计底板基础高程。易风化崩解的土层,开挖后应保留保护层至下道工序施工前再修整挖除;电力管道施工存在多管组合回拖和压密注浆等施工特点,不仅使得回拖时的阻力增加,而且作用在管道外壁上的注浆压力同时会降低管道抗外压能力,与单根管道的回拖施工有明显差别。为保证管道自身的安全和工程的质量,在回拖管道之前应对施工中的回拖力进行计算,并对电力排管进行受力分析,从而保证管道回拖和注浆施工中的安全。
进一步地,所述步骤S3中的反铲采用1.0m3反铲进行挖掘。
进一步地,所述步骤S3中的预留厚保护层厚度为20~30cm。
本发明与现有技术相比,具有如下的优点和有益效果:
将非开挖技术与电力电缆的敷设相结合,为保证管道自身的安全和工程的质量,在回拖管道之前应对施工中的回拖力进行计算,并对电力排管进行受力分析,从而保证管道回拖和注浆施工中的安全。对当前输变电排管非开挖工程施工方法进行了有效的补充,亦规范了监理人员在非开挖铺设电力管道施工中的监理依据和监理行为。
具体实施方式
为使本发明的目的、技术方案和优点更加清楚明白,下面结合实施例,对本发明作进一步的详细说明,本发明的示意性实施方式及其说明仅用于解释本发明,并不作为对本发明的限定。
实施例
本发明一种电力工程施工方法,一种电力工程施工方法,所述方法包括如下步骤:S1:开挖前,测量人员根据控制坐标点及高程基准点建立自己的施工控制网,控制点作埋石标记,测量原始地形,确定开挖边线,整理成图后报监理工程师批准;S2:监理工程师批准后,进行边线挖掘,测量人员随时检查开挖各参数,确保基础开挖的高程及边坡的坡比,严禁超欠挖;S3:土方开挖采用反铲进行挖掘,开挖临近设计高程时,预留一定厚度的厚保护层,用人工清挖,修整到设计底板基础高程。易风化崩解的土层,开挖后应保留保护层至下道工序施工前再修整挖除;电力管道施工存在多管组合回拖和压密注浆等施工特点,不仅使得回拖时的阻力增加,而且作用在管道外壁上的注浆压力同时会降低管道抗外压能力,与单根管道的回拖施工有明显差别。为保证管道自身的安全和工程的质量,在回拖管道之前应对施工中的回拖力进行计算,并对电力排管进行受力分析,从而保证管道回拖和注浆施工中的安全。
进一步地,所述步骤S3中的反铲采用1.0m3反铲进行挖掘。
进一步地,所述步骤S3中的预留厚保护层厚度为20~30cm。
本发明与现有技术相比,具有如下的优点和有益效果:
将非开挖技术与电力电缆的敷设相结合,为保证管道自身的安全和工程的质量,在回拖管道之前应对施工中的回拖力进行计算,并对电力排管进行受力分析,从而保证管道回拖和注浆施工中的安全。对当前输变电排管非开挖工程施工方法进行了有效的补充,亦规范了监理人员在非开挖铺设电力管道施工中的监理依据和监理行为。。
以上所述的具体实施方式,对本发明的目的、技术方案和有益效果进行了进一步详细说明,所应理解的是,以上所述仅为本发明的具体实施方式而已,并不用于限定本发明的保护范围,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (3)
1.一种电力工程施工方法,其特征在于,所述方法包括如下步骤:
S1:开挖前,测量人员根据控制坐标点及高程基准点建立自己的施工控制网,控制点作埋石标记,测量原始地形,确定开挖边线,整理成图后报监理工程师批准;
S2:监理工程师批准后,进行边线挖掘,测量人员随时检查开挖各参数,确保基础开挖的高程及边坡的坡比,严禁超欠挖;
S3:土方开挖采用反铲进行挖掘,开挖临近设计高程时,预留一定厚度的厚保护层,用人工清挖,修整到设计底板基础高程。易风化崩解的土层,开挖后应保留保护层至下道工序施工前再修整挖除。
2.根据权利要求1所述的一种电力工程施工方法,其特征在于,所述步骤S3中的反铲采用1.0m3反铲进行挖掘。
3.根据权利要求1所述的一种电力工程施工方法,其特征在于,所述步骤S3中的预留厚保护层厚度为20~30cm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810859876.XA CN109004610A (zh) | 2018-08-01 | 2018-08-01 | 一种电力工程施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810859876.XA CN109004610A (zh) | 2018-08-01 | 2018-08-01 | 一种电力工程施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109004610A true CN109004610A (zh) | 2018-12-14 |
Family
ID=64597951
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810859876.XA Withdrawn CN109004610A (zh) | 2018-08-01 | 2018-08-01 | 一种电力工程施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109004610A (zh) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103758084A (zh) * | 2014-01-27 | 2014-04-30 | 浙江水利水电学院 | 一种生态河道联锁型砌块及其构筑护坎的施工工法 |
CN107100171A (zh) * | 2017-05-19 | 2017-08-29 | 中国水利水电第四工程局有限公司 | 一种基坑施工方法 |
-
2018
- 2018-08-01 CN CN201810859876.XA patent/CN109004610A/zh not_active Withdrawn
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103758084A (zh) * | 2014-01-27 | 2014-04-30 | 浙江水利水电学院 | 一种生态河道联锁型砌块及其构筑护坎的施工工法 |
CN107100171A (zh) * | 2017-05-19 | 2017-08-29 | 中国水利水电第四工程局有限公司 | 一种基坑施工方法 |
Non-Patent Citations (2)
Title |
---|
无: "土石方开挖与填筑施工", 《土石方的开挖与回填》 * |
无: "渠道小型渠系建筑物工程施工方法", 《分水口渠系建筑物施工方法》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102734556B (zh) | 一种电力排管的非开挖施工方法 | |
WO2021223573A1 (zh) | 新增暗挖通道与既有站厅层连通接驳施工结构 | |
CN105155563A (zh) | 一种基坑软流塑地层涌水加固治理方法 | |
CN109026064A (zh) | 一种大跨度连拱隧道半明半暗的施工方法 | |
CN103122635A (zh) | 一种基坑抗承压水体系及其突涌稳定性判定方法 | |
CN101638898B (zh) | 顶管竖井悬挂式施工方法 | |
CN103016842B (zh) | 淤泥质软土地基地源热泵直埋换热器逆作法施工工法 | |
CN207512777U (zh) | 装配式地下管廊 | |
CN109594574A (zh) | 基于有限空间的大型顶管沉井逆作施工方法 | |
CN210658436U (zh) | 一种适用于河岸无开挖条件的薄板悬挂式挡土墙 | |
CN109004610A (zh) | 一种电力工程施工方法 | |
CN203821306U (zh) | 一种柔性防冲护垫 | |
CN212277424U (zh) | 一种利用围护结构自然接地的地铁综合接地网系统 | |
CN109004611A (zh) | 用于输电线路现场施工的方法 | |
CN215858114U (zh) | 一种针对既有管道截流改造的沉井组合结构 | |
CN106368211B (zh) | 用于构建管廊侧壁的矩形混凝土桩 | |
CN109113092A (zh) | 地下大直径管道原位通水保护施工方法 | |
CN205421303U (zh) | 一种高水位粉砂土地基的降水处理装置 | |
CN208949825U (zh) | 一种门架式护岸结构 | |
CN209084162U (zh) | 一种大型地下管道镇墩 | |
CN209891255U (zh) | 一种防止地下建筑结构延伸连接部位渗漏结构 | |
CN208023600U (zh) | 一种适用于复杂环境的沉井结构 | |
CN206457856U (zh) | 一种地面防开裂结构 | |
CN214033745U (zh) | 用于长输管道顺坡敷设水工保护的生态结构 | |
CN212480336U (zh) | 一种基坑边临水临电综合布置结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20181214 |
|