CN108985605A - Progress management-control method for construction plan establishment - Google Patents
Progress management-control method for construction plan establishment Download PDFInfo
- Publication number
- CN108985605A CN108985605A CN201810724673.XA CN201810724673A CN108985605A CN 108985605 A CN108985605 A CN 108985605A CN 201810724673 A CN201810724673 A CN 201810724673A CN 108985605 A CN108985605 A CN 108985605A
- Authority
- CN
- China
- Prior art keywords
- construction
- supplemental characteristic
- engineering
- work step
- establishes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
- G06Q10/063—Operations research, analysis or management
- G06Q10/0633—Workflow analysis
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/10—Office automation; Time management
- G06Q10/103—Workflow collaboration or project management
Landscapes
- Business, Economics & Management (AREA)
- Human Resources & Organizations (AREA)
- Engineering & Computer Science (AREA)
- Strategic Management (AREA)
- Entrepreneurship & Innovation (AREA)
- Economics (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Operations Research (AREA)
- Quality & Reliability (AREA)
- Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Game Theory and Decision Science (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Data Mining & Analysis (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The invention proposes a kind of progress management-control methods for construction plan establishment, include the following steps: first, obtain current construction speed and original construction network figure, and construction cell set is defined according to current construction speed, and then new network is constructed, the new construction plan for remaining construction cell is obtained finally by the method for construction plan establishment.
Description
Technical field
The present invention relates to construction plan establishment field more particularly to a kind of progress control sides for construction plan establishment
Method.
Background technique
There are no a scientific, reasonable decision making approach to come to work before construction, in construction for large scale civil engineering at present
Journey construction scheme is organized.The owner of requirement and expectation with construction investment quotient and to(for) engineering construction are increasingly
Height and the complexity of engineering construction, more propertys of participation, whether Project Construction Organization scheme scientific and reasonable to directly affect engineering and applies
The quality of work process, engineering construction duration, also affect the economic benefit of building enterprise.
Construction plan establishment refers to before an architectural engineering starts construction, according to the definition and engineering of associated construction technique
The demand of design carries out the planning of time dimension and resource dimension based on the logical relation of construction cell to complete construction process
Work.In construction industry, the logical relation between construction cell is often defined as a network, is mainly wrapped in network
The logical relation contained between each construction cell (including starts (FS) after the completion, starts (SS) after starting, complete after starting
(SF), (FF) four kinds of logical relations are completed after the completion), the plan of construction cell executes temporal information, and construction plan works out work
Make, it is necessary to be arranged out the timetable constructed, i.e. Gantt chart, and root according to the construction plan that the requirement of technique and network define
The working sources input amount defined according to Gantt chart and technique carrys out rendering resource histogram to indicate the resources consumption on time dimension
Situation.
During practice of construction, with the gradually implementation of engineering, actual construction speed will be with formulation before construction
Construction plan gradually generate deviation, such as the construction cell having may it is not in place due to working sources or construction teams and groups' low efficiency
Inferior reason causes the practice of construction time considerably longer than to be planned the construction time, and or since construction teams and groups are experienced, efficiency
It is high that the practice of construction time is caused significantly shorter than to plan the construction time.And for work progress management, it needs to a work
The practice of construction process of journey is adequately understood, and is made reasonably according to actual condition of construction to the plan of subsequent construction
Adjustment is even planned again, to guarantee to complete engineering before the duration of plan.
Summary of the invention
The present invention is directed at least solve the technical problems existing in the prior art, in order to realize above-mentioned purpose of the invention,
The present invention especially innovatively provides a kind of progress management-control method for construction plan establishment, and process is as shown in Figure 1, include
Following steps:
Step S0: start;
Step S100: actual construction speed information and original construction network figure are obtained;
Step S200: defining construction cell set to be managed: " being completed ", " progress ", " not yet going into operation ", according to applying
The definition of work unit set and the virtual condition of each construction cell, are put into corresponding set for each construction cell;
Step S300: the set according to belonging to construction cell constructs new network;
Step S400: it according to the Projected completion time of new network, current time and engineering, is constructed by other
Planning device obtains the construction plan of the new construction cell for completion of not yet constructing;
Step S500: terminate.
Wherein for described in step S100, " actual construction speed information " includes completed construction cell,
The progress percentage of the construction cell of construction, is indicated with wi, and i indicates the construction cell of i-th of hot work in progress, and not yet starts
The construction cell of construction;" original construction network figure " includes the logical relation (packet between the construction cell defined before construction
It includes, tight forward and backward sequence logical relation is specific to be divided into beginning (FS) after the completion again, starts (SS) after starting, completes after starting
(SF), (FF) four kinds of logical relations are completed after the completion) and each construction cell plan construction time Ti, indicate to apply for i-th
The plan construction time of work order member.
For described in step S200, " defining construction cell set to be managed " includes: " being completed " set for storing
Terminated the construction cell of construction, " progress " set is for storing the work order for having begun construction but not yet terminating construction
Member, " not yet going into operation " set is for storing the construction cell for not yet starting construction.
For described in step S300, " constructing new network " detailed process is as shown in Fig. 2, specific as follows:
Step S301 rejects all construction cells in set " being completed ";
The planned time of construction cell all in set " progress " is updated to T' by step S302i=(1-wi)
Ti;
Step S303 sets the start node of new network;
Step S304 closes the logic that the construction cell in all set " progress " establishes FS=0 with start node
System;
Step S305, for the construction cell in set " not yet going into operation ", if construction cell is " complete in set before it is tight
At " in, then according to original network, enable the construction cell and start node establish identical logical relation, if applying before its is tight
Work order member then retains the logical relation in its primitive network figure in set " progress " or " not yet going into operation ".
So far the foundation of new network is completed.
Preferably, the S100 further include:
S101 carries out the division of engineering structure according to BIM model data engineering branch subitem structure and forms information data,
Original construction network figure is formed, S102 is executed;
S102 carries out construction BIM mould according to the design BIM model that engineering branch subitem Structural Guidelines engineering construction figure is established
The fractionation of type forms engineering construction BIM model data practice of construction scheduling network figure.
Preferably, the current engineering branch subitem structural parameters data of the S101 include:
The supplemental characteristic for establishing ongoing engineering branch subitem structured coding PCod, establishes ongoing engineering point
The supplemental characteristic of subitem structure type PTyp establishes the parameter number that ongoing engineering branch subitem structure describes PDes
According to;The supplemental characteristic of the material classification MATCat of ongoing engineering branch subitem structure construction material is set, and setting is
The supplemental characteristic of the material model MATTyp of the engineering branch subitem structure construction material of progress, establishes ongoing engineering point
The supplemental characteristic of the project amount PAmo of subitem structure construction material;Supplemental characteristic importing database is formed ongoing
Construction cell set to be managed;
The supplemental characteristic for establishing the engineering branch subitem structured coding PCod not yet to go into operation, establishes the engineering point not yet to go into operation
The supplemental characteristic of subitem structure type PTyp establishes the parameter number that the engineering branch subitem structure not yet to go into operation describes PDes
According to;The supplemental characteristic of the material classification MATCat of the engineering branch subitem structure construction material not yet to go into operation is set, and setting is not yet
The supplemental characteristic of the material model MATTyp of the engineering branch subitem structure construction material to go into operation, establishes the engineering point not yet to go into operation
The supplemental characteristic of the project amount PAmo of subitem structure construction material;The supplemental characteristic is imported what database formation not yet went into operation
Construction cell set to be managed;
The supplemental characteristic for establishing completed works branch subitem structured coding PCod, establishes completed works branch point
The supplemental characteristic of item structure type PTyp establishes the supplemental characteristic that completed works branch subitem structure describes PDes;Setting
The supplemental characteristic of the material classification MATCat of completed works branch subitem structure construction material, setting completed works point
The supplemental characteristic of the material model MATTyp of subitem structure construction material establishes completed works branch subitem structure construction
The supplemental characteristic of the project amount PAmo of material;Supplemental characteristic importing database is formed into completed work order metaset to be managed
It closes.
Preferably, the engineering construction BIM model of the S102 includes:
It is real that construction BIM model is carried out according to the design BIM model that engineering branch subitem Structural Guidelines engineering construction figure is established
Border construction speed network forms construction BIM model practice of construction scheduling network figure;
According to S101, arranging according to the subitem structured data definition of engineering branch to engineering BIM model is construction BIM model
In, form the practice of construction scheduling network figure of engineering construction organizational planning design BIM data.
Preferably, further includes:
S103, according to engineering construction type finishing engineering parameters of construction technology data, wherein parameters of construction technology data packet
Include: technology category, process names, work step title and work step logical relation supplemental characteristic, form original construction network figure;
Each engineering construction process work step supplemental characteristic is arranged in S104, and wherein engineering construction process work step supplemental characteristic includes:
Construction material, construction teams and groups, construction work team, construction equipment supplemental characteristic, and according to the construction material of setting, construction teams and groups, apply
Work work team, construction equipment supplemental characteristic form the working hour system parameter number under specified construction working hour, specified construction work amount mode
According to forming original construction network figure.
Preferably, the S103 engineering construction process supplemental characteristic includes:
The supplemental characteristic for establishing ongoing engineering construction process classification PROTyp, establishes ongoing engineering construction
The supplemental characteristic of process names PRONam is established the supplemental characteristic of ongoing engineering construction process coding PROCod, is established
The supplemental characteristic of ongoing engineering construction process work step title PROSTEPNam;Establish ongoing engineering construction process
Work step logic tightly before relationship PROSTEPPre supplemental characteristic, establish the ongoing next pass of engineering construction process work step logic
It is the supplemental characteristic of PROSTEPTig;Supplemental characteristic importing database is formed into ongoing work order metaset to be managed
It closes;
The supplemental characteristic of the engineering construction process classification PROTyp not yet to go into operation is established, the engineering construction not yet to go into operation is established
The supplemental characteristic of process names PRONam is established the supplemental characteristic of the engineering construction process coding PROCod not yet to go into operation, is established
The supplemental characteristic of the engineering construction process work step title PROSTEPNam not yet to go into operation;Establish the engineering construction process not yet to go into operation
Work step logic tightly before relationship PROSTEPPre supplemental characteristic, establish the next pass of engineering construction process work step logic not yet to go into operation
It is the supplemental characteristic of PROSTEPTig;The supplemental characteristic is imported into database and forms the work order metaset to be managed not yet to go into operation
It closes;
The supplemental characteristic for establishing completed works construction technology classification PROTyp, establishes completed works construction technology
The supplemental characteristic of title PRONam, establishes the supplemental characteristic of completed works construction technology coding PROCod, and foundation is completed
Engineering construction process work step title PROSTEPNam supplemental characteristic;It is tight to establish completed works construction technology work step logic
The supplemental characteristic of preceding relationship PROSTEPPre establishes the next relationship PROSTEPTig of completed works construction technology work step logic
Supplemental characteristic;Supplemental characteristic importing database is formed into completed construction cell set to be managed.
Preferably, the S104 engineering construction process work step supplemental characteristic includes:
Establish the supplemental characteristic of ongoing engineering construction process work step work team PROSTEPClasT;Foundation is carrying out
Engineering construction process start the supplemental characteristic of work step PROSTEPSta, establishing ongoing engineering construction process terminates work step
The supplemental characteristic of PROSTEPEnd;Supplemental characteristic importing database is formed into ongoing construction cell set to be managed;
Wherein the first heavy duty is other: establishing the ginseng of ongoing engineering construction process work step quantitative-type PROSTEPTypV
Number data;The supplemental characteristic for establishing ongoing engineering construction process work step equipment PROSTEPEQU, is established ongoing
Engineering construction process work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, establishes ongoing engineering construction work
The supplemental characteristic of skill work step equipment maximum investment PROSTEPEQUMax;Establish ongoing engineering construction process work step teams and groups
The supplemental characteristic of PROSTEPTEA establishes ongoing engineering construction process work step teams and groups' minimum investment PROSTEPTEAMin
Supplemental characteristic, establish ongoing engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax supplemental characteristic;
The supplemental characteristic for establishing ongoing engineering construction process work step material PROSTEPMAV, establishes ongoing engineering construction
The supplemental characteristic of the specified construction volume PROSTEPMATValV of technique work step material, establishes ongoing engineering construction process work step
Material is constructed the supplemental characteristic of sequencing PROSTEPOrd, establishes that ongoing engineering construction process work step material is specified to be applied
The supplemental characteristic of the optimistic standard time PROSTEPTgV (h) of work amount establishes ongoing engineering construction process work step material
The supplemental characteristic of the pessimistic standard time PROSTEPTbV (h) of specified construction volume establishes ongoing engineering construction process work
Walk the supplemental characteristic of the most probable standard time PROSTEPTpV (h) of the specified construction volume of material;The supplemental characteristic is imported into data
Library forms ongoing construction cell set to be managed;
Second heavy duty is other: establishing the parameter number of ongoing engineering construction process work step timing-type PROSTEPTypT
According to establishing the supplemental characteristic of ongoing engineering construction process work step timing standard time PROSTEPTT;By the supplemental characteristic
It imports database and forms ongoing construction cell set to be managed;
Establish the supplemental characteristic of the engineering construction process work step work team PROSTEPClasT not yet to go into operation;Foundation not yet goes into operation
Engineering construction process start the supplemental characteristic of work step PROSTEPSta, establishing the engineering construction process not yet to go into operation terminates work step
The supplemental characteristic of PROSTEPEnd;The supplemental characteristic is imported into database and forms the construction cell set to be managed not yet to go into operation;
Third heavy duty is other: establishing the parameter number of the engineering construction process work step quantitative-type PROSTEPTypV not yet to go into operation
According to;The supplemental characteristic of the engineering construction process work step equipment PROSTEPEQU not yet to go into operation is established, the engineering not yet to go into operation is established
Construction technology work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, establishes the engineering construction process work not yet to go into operation
Walk the supplemental characteristic of equipment maximum investment PROSTEPEQUMax;Establish the engineering construction process work step teams and groups not yet to go into operation
The supplemental characteristic of PROSTEPTEA establishes the engineering construction process work step teams and groups' minimum investment PROSTEPTEAMin not yet to go into operation
Supplemental characteristic, establish not yet go into operation engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax supplemental characteristic;
The supplemental characteristic of the engineering construction process work step material PROSTEPMAV not yet to go into operation is established, the engineering construction not yet to go into operation is established
The supplemental characteristic of the specified construction volume PROSTEPMATValV of technique work step material establishes the engineering construction process work step not yet to go into operation
The supplemental characteristic of material construction sequencing PROSTEPOrd, the engineering construction process work step material that foundation not yet goes into operation is specified to be applied
The supplemental characteristic of the optimistic standard time PROSTEPTgV (h) of work amount establishes the engineering construction process work step material not yet to go into operation
The supplemental characteristic of the pessimistic standard time PROSTEPTbV (h) of specified construction volume establishes the engineering construction process work not yet to go into operation
Walk the supplemental characteristic of the most probable standard time PROSTEPTpV (h) of the specified construction volume of material;The supplemental characteristic is imported into data
Library forms the construction cell set to be managed not yet to go into operation;
Quadruple rank: the parameter number of the engineering construction process work step timing-type PROSTEPTypT not yet to go into operation is established
According to the supplemental characteristic for the engineering construction process work step timing standard time PROSTEPTT that foundation not yet goes into operation;By the supplemental characteristic
It imports database and forms the construction cell set to be managed not yet to go into operation;
Establish the supplemental characteristic of completed works construction technology work step work team PROSTEPClasT;Establish completed work
Journey construction technology starts the supplemental characteristic of work step PROSTEPSta, and establishing completed works construction technology terminates work step
The supplemental characteristic of PROSTEPEnd;Supplemental characteristic importing database is formed into completed construction cell set to be managed;
5th heavy duty is other: establishing the supplemental characteristic of completed works construction technology work step quantitative-type PROSTEPTypV;
The supplemental characteristic for establishing completed works construction technology work step equipment PROSTEPEQU, establishes completed works construction technology
Work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, and it is maximum to establish completed works construction technology work step equipment
Put into the supplemental characteristic of PROSTEPEQUMax;Establish the parameter of completed works construction technology work step teams and groups PROSTEPTEA
Data are established the supplemental characteristic of completed works construction technology work step teams and groups' minimum investment PROSTEPTEAMin, are established complete
At engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax supplemental characteristic;Establish completed works construction
The supplemental characteristic of technique work step material PROSTEPMAV establishes the specified construction volume of completed works construction technology work step material
The supplemental characteristic of PROSTEPMATValV establishes completed works construction technology work step material construction sequencing
The supplemental characteristic of PROSTEPOrd establishes the optimistic standard time of the specified construction volume of completed works construction technology work step material
The supplemental characteristic of PROSTEPTgV (h), the pessimism for establishing the specified construction volume of completed works construction technology work step material are specified
The supplemental characteristic of working hour PROSTEPTbV (h) establishes most may be used for the completed works construction technology specified construction volume of work step material
The supplemental characteristic of energy standard time PROSTEPTpV (h);Supplemental characteristic importing database is formed and completed is applied wait manage
Work unit set;
Sixfold rank: establishing the supplemental characteristic of completed works construction technology work step timing-type PROSTEPTypT,
Establish the supplemental characteristic of completed works construction technology work step timing standard time PROSTEPTT;The supplemental characteristic is imported
Database forms completed construction cell set to be managed.
In conclusion by adopting the above-described technical solution, the beneficial effects of the present invention are:
In limited step and shorter time, according to actual construction speed, one can be obtained and meet target work
The effective construction plan of phase.
Additional aspect and advantage of the invention will be set forth in part in the description, and will partially become from the following description
Obviously, or practice through the invention is recognized.
Detailed description of the invention
Above-mentioned and/or additional aspect of the invention and advantage will become from the description of the embodiment in conjunction with the following figures
Obviously and it is readily appreciated that, in which:
Fig. 1 is that progress manages flow diagram;
Fig. 2 is to construct new network flow diagram.
Specific embodiment
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings, wherein from beginning to end
Same or similar label indicates same or similar element or element with the same or similar functions.Below with reference to attached
The embodiment of figure description is exemplary, and for explaining only the invention, and is not considered as limiting the invention.
In the description of the present invention, it is to be understood that, term " longitudinal direction ", " transverse direction ", "upper", "lower", "front", "rear",
The orientation or positional relationship of the instructions such as "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside" is based on attached drawing institute
The orientation or positional relationship shown, is merely for convenience of description of the present invention and simplification of the description, rather than the dress of indication or suggestion meaning
It sets or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as to limit of the invention
System.
In the description of the present invention, unless otherwise specified and limited, it should be noted that term " installation ", " connected ",
" connection " shall be understood in a broad sense, for example, it may be mechanical connection or electrical connection, the connection being also possible to inside two elements can
, can also indirectly connected through an intermediary, for the ordinary skill in the art to be to be connected directly, it can basis
Concrete condition understands the concrete meaning of above-mentioned term.
The present invention is directed at least solve the technical problems existing in the prior art, in order to realize above-mentioned purpose of the invention,
The present invention especially innovatively provides a kind of progress management-control method for construction plan establishment, and specifically used process is as follows:
As illustrated in fig. 1 and 2, firstly, obtaining actual construction speed information and original construction network figure, mainly include,
Completed construction cell, the progress percentage of the construction cell of hot work in progress, is indicated with wi, and i indicates i-th of hot work in progress
Construction cell, and not yet start the construction cell of construction;" original construction network figure " includes the construction defined before construction
Between unit logical relation (including tight forward and backward sequence logical relation, it is specific can be divided into again after the completion of start (FS), start after starting
(SS), after starting complete (SF), after the completion complete (FF) four kinds of logical relations) and each construction cell the plan construction time
Ti indicates the plan construction time of i-th of construction cell;
Secondly, defining construction cell set to be managed: " being completed " set is for storing the work order for being over construction
Member, " progress " set is for storing the construction cell for having begun construction but not yet terminating construction, " not yet going into operation " set
For storing the construction cell for not yet starting construction, and each construction cell is put into corresponding set;
In next step, the set according to belonging to construction cell, constructs new network, and main flow includes:
The first step rejects all construction cells in set " being completed ";
The planned time of construction cell all in set " progress " is updated to T' by second stepi=(1-wi)Ti;
T'iFor updated construction cell planned time, TiFor the planned time of basic construction cell, wiFor time parameter, subscript i is
Positive integer;
Third step sets the start node of new network;
Construction cell in all set " progress " is established the logical relation of FS=0 by the 4th step with start node;
5th step, for the construction cell in set " not yet going into operation ", if construction cell " is completed " in set before it is tight
In, then according to original network, the construction cell and start node is enabled to establish identical logical relation, if work order before it is tight
Member then retains the logical relation in its primitive network figure in set " progress " or " not yet going into operation ";So far it completes new
Network foundation;
Finally, passing through other construction plans according to the Projected completion time of new network, current time and engineering
Preparing method obtains the construction plan of the new construction cell for completion of not yet constructing.
Preferably, the S100 further include:
S101 carries out the division of engineering structure according to BIM model data engineering branch subitem structure and forms information data,
Original construction network figure is formed, S102 is executed;
S102 carries out construction BIM mould according to the design BIM model that engineering branch subitem Structural Guidelines engineering construction figure is established
The fractionation of type forms engineering construction BIM model data practice of construction scheduling network figure.
Preferably, the current engineering branch subitem structural parameters data of the S101 include:
The supplemental characteristic for establishing ongoing engineering branch subitem structured coding PCod, establishes ongoing engineering point
The supplemental characteristic of subitem structure type PTyp establishes the parameter number that ongoing engineering branch subitem structure describes PDes
According to;The supplemental characteristic of the material classification MATCat of ongoing engineering branch subitem structure construction material is set, and setting is
The supplemental characteristic of the material model MATTyp of the engineering branch subitem structure construction material of progress, establishes ongoing engineering point
The supplemental characteristic of the project amount PAmo of subitem structure construction material;Supplemental characteristic importing database is formed ongoing
Construction cell set to be managed;
The supplemental characteristic for establishing the engineering branch subitem structured coding PCod not yet to go into operation, establishes the engineering point not yet to go into operation
The supplemental characteristic of subitem structure type PTyp establishes the parameter number that the engineering branch subitem structure not yet to go into operation describes PDes
According to;The supplemental characteristic of the material classification MATCat of the engineering branch subitem structure construction material not yet to go into operation is set, and setting is not yet
The supplemental characteristic of the material model MATTyp of the engineering branch subitem structure construction material to go into operation, establishes the engineering point not yet to go into operation
The supplemental characteristic of the project amount PAmo of subitem structure construction material;The supplemental characteristic is imported what database formation not yet went into operation
Construction cell set to be managed;
The supplemental characteristic for establishing completed works branch subitem structured coding PCod, establishes completed works branch point
The supplemental characteristic of item structure type PTyp establishes the supplemental characteristic that completed works branch subitem structure describes PDes;Setting
The supplemental characteristic of the material classification MATCat of completed works branch subitem structure construction material, setting completed works point
The supplemental characteristic of the material model MATTyp of subitem structure construction material establishes completed works branch subitem structure construction
The supplemental characteristic of the project amount PAmo of material;Supplemental characteristic importing database is formed into completed work order metaset to be managed
It closes.
Preferably, the engineering construction BIM model of the S102 includes:
It is real that construction BIM model is carried out according to the design BIM model that engineering branch subitem Structural Guidelines engineering construction figure is established
Border construction speed network forms construction BIM model practice of construction scheduling network figure;
According to S101, arranging according to the subitem structured data definition of engineering branch to engineering BIM model is construction BIM model
In, form the practice of construction scheduling network figure of engineering construction organizational planning design BIM data.
Preferably, further includes:
S103, according to engineering construction type finishing engineering parameters of construction technology data, wherein parameters of construction technology data packet
Include: technology category, process names, work step title and work step logical relation supplemental characteristic, form original construction network figure;
Each engineering construction process work step supplemental characteristic is arranged in S104, and wherein engineering construction process work step supplemental characteristic includes:
Construction material, construction teams and groups, construction work team, construction equipment supplemental characteristic, and according to the construction material of setting, construction teams and groups, apply
Work work team, construction equipment supplemental characteristic form the working hour system parameter number under specified construction working hour, specified construction work amount mode
According to forming original construction network figure.
Preferably, the S103 engineering construction process supplemental characteristic includes:
The supplemental characteristic for establishing ongoing engineering construction process classification PROTyp, establishes ongoing engineering construction
The supplemental characteristic of process names PRONam is established the supplemental characteristic of ongoing engineering construction process coding PROCod, is established
The supplemental characteristic of ongoing engineering construction process work step title PROSTEPNam;Establish ongoing engineering construction process
Work step logic tightly before relationship PROSTEPPre supplemental characteristic, establish the ongoing next pass of engineering construction process work step logic
It is the supplemental characteristic of PROSTEPTig;Supplemental characteristic importing database is formed into ongoing work order metaset to be managed
It closes;
The supplemental characteristic of the engineering construction process classification PROTyp not yet to go into operation is established, the engineering construction not yet to go into operation is established
The supplemental characteristic of process names PRONam is established the supplemental characteristic of the engineering construction process coding PROCod not yet to go into operation, is established
The supplemental characteristic of the engineering construction process work step title PROSTEPNam not yet to go into operation;Establish the engineering construction process not yet to go into operation
Work step logic tightly before relationship PROSTEPPre supplemental characteristic, establish the next pass of engineering construction process work step logic not yet to go into operation
It is the supplemental characteristic of PROSTEPTig;The supplemental characteristic is imported into database and forms the work order metaset to be managed not yet to go into operation
It closes;
The supplemental characteristic for establishing completed works construction technology classification PROTyp, establishes completed works construction technology
The supplemental characteristic of title PRONam, establishes the supplemental characteristic of completed works construction technology coding PROCod, and foundation is completed
Engineering construction process work step title PROSTEPNam supplemental characteristic;It is tight to establish completed works construction technology work step logic
The supplemental characteristic of preceding relationship PROSTEPPre establishes the next relationship PROSTEPTig of completed works construction technology work step logic
Supplemental characteristic;Supplemental characteristic importing database is formed into completed construction cell set to be managed.
Preferably, the S104 engineering construction process work step supplemental characteristic includes:
Establish the supplemental characteristic of ongoing engineering construction process work step work team PROSTEPClasT;Foundation is carrying out
Engineering construction process start the supplemental characteristic of work step PROSTEPSta, establishing ongoing engineering construction process terminates work step
The supplemental characteristic of PROSTEPEnd;Supplemental characteristic importing database is formed into ongoing construction cell set to be managed;
Wherein the first heavy duty is other: establishing the ginseng of ongoing engineering construction process work step quantitative-type PROSTEPTypV
Number data;The supplemental characteristic for establishing ongoing engineering construction process work step equipment PROSTEPEQU, is established ongoing
Engineering construction process work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, establishes ongoing engineering construction work
The supplemental characteristic of skill work step equipment maximum investment PROSTEPEQUMax;Establish ongoing engineering construction process work step teams and groups
The supplemental characteristic of PROSTEPTEA establishes ongoing engineering construction process work step teams and groups' minimum investment PROSTEPTEAMin
Supplemental characteristic, establish ongoing engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax supplemental characteristic;
The supplemental characteristic for establishing ongoing engineering construction process work step material PROSTEPMAV, establishes ongoing engineering construction
The supplemental characteristic of the specified construction volume PROSTEPMATValV of technique work step material, establishes ongoing engineering construction process work step
Material is constructed the supplemental characteristic of sequencing PROSTEPOrd, establishes that ongoing engineering construction process work step material is specified to be applied
The supplemental characteristic of the optimistic standard time PROSTEPTgV (h) of work amount establishes ongoing engineering construction process work step material
The supplemental characteristic of the pessimistic standard time PROSTEPTbV (h) of specified construction volume establishes ongoing engineering construction process work
Walk the supplemental characteristic of the most probable standard time PROSTEPTpV (h) of the specified construction volume of material;The supplemental characteristic is imported into data
Library forms ongoing construction cell set to be managed;
Second heavy duty is other: establishing the parameter number of ongoing engineering construction process work step timing-type PROSTEPTypT
According to establishing the supplemental characteristic of ongoing engineering construction process work step timing standard time PROSTEPTT;By the supplemental characteristic
It imports database and forms ongoing construction cell set to be managed;
Establish the supplemental characteristic of the engineering construction process work step work team PROSTEPClasT not yet to go into operation;Foundation not yet goes into operation
Engineering construction process start the supplemental characteristic of work step PROSTEPSta, establishing the engineering construction process not yet to go into operation terminates work step
The supplemental characteristic of PROSTEPEnd;The supplemental characteristic is imported into database and forms the construction cell set to be managed not yet to go into operation;
Third heavy duty is other: establishing the parameter number of the engineering construction process work step quantitative-type PROSTEPTypV not yet to go into operation
According to;The supplemental characteristic of the engineering construction process work step equipment PROSTEPEQU not yet to go into operation is established, the engineering not yet to go into operation is established
Construction technology work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, establishes the engineering construction process work not yet to go into operation
Walk the supplemental characteristic of equipment maximum investment PROSTEPEQUMax;Establish the engineering construction process work step teams and groups not yet to go into operation
The supplemental characteristic of PROSTEPTEA establishes the engineering construction process work step teams and groups' minimum investment PROSTEPTEAMin not yet to go into operation
Supplemental characteristic, establish not yet go into operation engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax supplemental characteristic;
The supplemental characteristic of the engineering construction process work step material PROSTEPMAV not yet to go into operation is established, the engineering construction not yet to go into operation is established
The supplemental characteristic of the specified construction volume PROSTEPMATValV of technique work step material establishes the engineering construction process work step not yet to go into operation
The supplemental characteristic of material construction sequencing PROSTEPOrd, the engineering construction process work step material that foundation not yet goes into operation is specified to be applied
The supplemental characteristic of the optimistic standard time PROSTEPTgV (h) of work amount establishes the engineering construction process work step material not yet to go into operation
The supplemental characteristic of the pessimistic standard time PROSTEPTbV (h) of specified construction volume establishes the engineering construction process work not yet to go into operation
Walk the supplemental characteristic of the most probable standard time PROSTEPTpV (h) of the specified construction volume of material;The supplemental characteristic is imported into data
Library forms the construction cell set to be managed not yet to go into operation;
Quadruple rank: the parameter number of the engineering construction process work step timing-type PROSTEPTypT not yet to go into operation is established
According to the supplemental characteristic for the engineering construction process work step timing standard time PROSTEPTT that foundation not yet goes into operation;By the supplemental characteristic
It imports database and forms the construction cell set to be managed not yet to go into operation;
Establish the supplemental characteristic of completed works construction technology work step work team PROSTEPClasT;Establish completed work
Journey construction technology starts the supplemental characteristic of work step PROSTEPSta, and establishing completed works construction technology terminates work step
The supplemental characteristic of PROSTEPEnd;Supplemental characteristic importing database is formed into completed construction cell set to be managed;
5th heavy duty is other: establishing the supplemental characteristic of completed works construction technology work step quantitative-type PROSTEPTypV;
The supplemental characteristic for establishing completed works construction technology work step equipment PROSTEPEQU, establishes completed works construction technology
Work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, and it is maximum to establish completed works construction technology work step equipment
Put into the supplemental characteristic of PROSTEPEQUMax;Establish the parameter of completed works construction technology work step teams and groups PROSTEPTEA
Data are established the supplemental characteristic of completed works construction technology work step teams and groups' minimum investment PROSTEPTEAMin, are established complete
At engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax supplemental characteristic;Establish completed works construction
The supplemental characteristic of technique work step material PROSTEPMAV establishes the specified construction volume of completed works construction technology work step material
The supplemental characteristic of PROSTEPMATValV establishes completed works construction technology work step material construction sequencing
The supplemental characteristic of PROSTEPOrd establishes the optimistic standard time of the specified construction volume of completed works construction technology work step material
The supplemental characteristic of PROSTEPTgV (h), the pessimism for establishing the specified construction volume of completed works construction technology work step material are specified
The supplemental characteristic of working hour PROSTEPTbV (h) establishes most may be used for the completed works construction technology specified construction volume of work step material
The supplemental characteristic of energy standard time PROSTEPTpV (h);Supplemental characteristic importing database is formed and completed is applied wait manage
Work unit set;
Sixfold rank: establishing the supplemental characteristic of completed works construction technology work step timing-type PROSTEPTypT,
Establish the supplemental characteristic of completed works construction technology work step timing standard time PROSTEPTT;The supplemental characteristic is imported
Database forms completed construction cell set to be managed.
In conclusion by adopting the above-described technical solution, the beneficial effects of the present invention are:
It can obtain obtaining one according to current construction speed and meeting target in limited step and shorter time
The effective construction plan of duration.
Although an embodiment of the present invention has been shown and described, it will be understood by those skilled in the art that: not
A variety of change, modification, replacement and modification can be carried out to these embodiments in the case where being detached from the principle of the present invention and objective, this
The range of invention is defined by the claims and their equivalents.
Claims (8)
1. a kind of progress management-control method for construction plan establishment, which comprises the steps of:
S0: start;
S100: actual construction speed network and original construction network figure are obtained;
S200: construction cell set to be managed: " being completed ", " progress ", " not yet going into operation " is defined, according to work order metaset
The definition of conjunction and the virtual condition of each construction cell, are put into corresponding set for each construction cell;
S300: the set according to belonging to construction cell constructs new network;
S400: it according to the Projected completion time of new network, current time and engineering, is worked out by other construction plans
Method obtains the construction plan of the new construction cell for completion of not yet constructing;
S500: terminate.
2. the progress management-control method according to claim 1 for construction plan establishment, which is characterized in that the S300,
The set according to construction cell constructs new network and includes:
S301 rejects all construction cells in set " being completed ";
The planned time of construction cell all in set " progress " is updated to T' by S302i=(1-wi)Ti, T'iFor more
Construction cell planned time after new, TiFor the planned time of basic construction cell, wiFor time parameter, subscript i is positive integer;
S303 sets the start node of new network;
Construction cell in all set " progress " is established the logical relation of FS=0 by S304 with start node;
S305, for the construction cell in set " not yet going into operation ", if construction cell is in set " being completed " before it is tight, root
According to original network, the construction cell and start node is enabled to establish identical logical relation, if construction cell is collecting before it is tight
It closes in " progress " or " not yet going into operation ", then retains the logical relation in its primitive network figure.
3. the progress management-control method according to claim 1 for construction plan establishment, which is characterized in that the S100 is also
Include:
S101 carries out the division of engineering structure according to BIM model data engineering branch subitem structure and forms information data, formed
Original construction network figure executes S102;
S102 carries out construction BIM model according to the design BIM model that engineering branch subitem Structural Guidelines engineering construction figure is established
It splits, forms engineering construction BIM model data practice of construction scheduling network figure.
4. the progress management-control method according to claim 2 for construction plan establishment, which is characterized in that the S101 works as
Preceding engineering branch subitem structural parameters data include:
The supplemental characteristic for establishing ongoing engineering branch subitem structured coding PCod, establishes ongoing engineering branch point
The supplemental characteristic of item structure type PTyp establishes the supplemental characteristic that ongoing engineering branch subitem structure describes PDes;If
The supplemental characteristic for setting the material classification MATCat of ongoing engineering branch subitem structure construction material, is arranged ongoing
The supplemental characteristic of the material model MATTyp of engineering branch subitem structure construction material establishes ongoing engineering branch subitem
The supplemental characteristic of the project amount PAmo of structure construction material;Supplemental characteristic importing database is formed ongoing wait manage
Construction cell set;
The supplemental characteristic for establishing the engineering branch subitem structured coding PCod not yet to go into operation, establishes the engineering branch point not yet to go into operation
The supplemental characteristic of item structure type PTyp establishes the supplemental characteristic that the engineering branch subitem structure not yet to go into operation describes PDes;If
The supplemental characteristic of the material classification MATCat of the engineering branch subitem structure construction material not yet to go into operation is set, what setting not yet went into operation
The supplemental characteristic of the material model MATTyp of engineering branch subitem structure construction material establishes the engineering branch subitem not yet to go into operation
The supplemental characteristic of the project amount PAmo of structure construction material;By the supplemental characteristic import database formed not yet go into operation wait manage
Construction cell set;
The supplemental characteristic for establishing completed works branch subitem structured coding PCod establishes completed works branch subitem knot
The supplemental characteristic of structure type PTyp establishes the supplemental characteristic that completed works branch subitem structure describes PDes;It is arranged complete
At engineering branch subitem structure construction material material classification MATCat supplemental characteristic, setting completed works branch point
The supplemental characteristic of the material model MATTyp of item structure construction material establishes completed works branch subitem structure construction material
Project amount PAmo supplemental characteristic;Supplemental characteristic importing database is formed into completed construction cell set to be managed.
5. the progress management-control method according to claim 2 for construction plan establishment, which is characterized in that the S102's
Engineering construction BIM model includes:
It carries out construction according to the engineering branch design BIM model that Structural Guidelines engineering construction figure is established of itemizing BIM model is practical applies
Work scheduling network figure forms construction BIM model practice of construction scheduling network figure;
According to S101, arranging according to the subitem structured data definition of engineering branch to engineering BIM model is shape in construction BIM model
At the practice of construction scheduling network figure of engineering construction organizational planning design BIM data.
6. the progress management-control method according to claim 2 for construction plan establishment, which is characterized in that further include:
S103, according to engineering construction type finishing engineering parameters of construction technology data, wherein parameters of construction technology data include: work
Skill classification, process names, work step title and work step logical relation supplemental characteristic, form original construction network figure;
Each engineering construction process work step supplemental characteristic is arranged in S104, and wherein engineering construction process work step supplemental characteristic includes: construction
Material, construction teams and groups, construction work team, construction equipment supplemental characteristic, and according to the construction material of setting, construction teams and groups, construction work
Class, construction equipment supplemental characteristic, form the working hour system parameter data under specified construction working hour, specified construction work amount mode,
Form original construction network figure.
7. the progress management-control method according to claim 5 for construction plan establishment, which is characterized in that the S103 work
Journey parameters of construction technology data include:
The supplemental characteristic for establishing ongoing engineering construction process classification PROTyp, establishes ongoing engineering construction process
The supplemental characteristic of title PRONam is established the supplemental characteristic of ongoing engineering construction process coding PROCod, is established
The supplemental characteristic of the engineering construction process work step title PROSTEPNam of progress;Establish ongoing engineering construction process work step
Logic tightly before relationship PROSTEPPre supplemental characteristic, establish the ongoing next relationship of engineering construction process work step logic
The supplemental characteristic of PROSTEPTig;Supplemental characteristic importing database is formed into ongoing construction cell set to be managed;
The supplemental characteristic of the engineering construction process classification PROTyp not yet to go into operation is established, the engineering construction process not yet to go into operation is established
The supplemental characteristic of title PRONam is established the supplemental characteristic of the engineering construction process coding PROCod not yet to go into operation, is established not yet
The supplemental characteristic of the engineering construction process work step title PROSTEPNam to go into operation;Establish the engineering construction process work step not yet to go into operation
Logic tightly before relationship PROSTEPPre supplemental characteristic, establish the next relationship of engineering construction process work step logic not yet to go into operation
The supplemental characteristic of PROSTEPTig;The supplemental characteristic is imported into database and forms the construction cell set to be managed not yet to go into operation;
The supplemental characteristic for establishing completed works construction technology classification PROTyp establishes completed works construction technology title
The supplemental characteristic of PRONam establishes the supplemental characteristic of completed works construction technology coding PROCod, establishes completed work
The supplemental characteristic of journey construction technology work step title PROSTEPNam;Establish the tight preceding pass of completed works construction technology work step logic
It is the supplemental characteristic of PROSTEPPre, establishes the ginseng of the next relationship PROSTEPTig of completed works construction technology work step logic
Number data;Supplemental characteristic importing database is formed into completed construction cell set to be managed.
8. the progress management-control method according to claim 5 for construction plan establishment, which is characterized in that the S104 work
Journey construction technology work step supplemental characteristic includes:
Establish the supplemental characteristic of ongoing engineering construction process work step work team PROSTEPClasT;Establish ongoing work
Journey construction technology starts the supplemental characteristic of work step PROSTEPSta, and establishing ongoing engineering construction process terminates work step
The supplemental characteristic of PROSTEPEnd;Supplemental characteristic importing database is formed into ongoing construction cell set to be managed;
Wherein the first heavy duty is other: establishing the parameter number of ongoing engineering construction process work step quantitative-type PROSTEPTypV
According to;The supplemental characteristic for establishing ongoing engineering construction process work step equipment PROSTEPEQU, establishes ongoing engineering
Construction technology work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, establishes ongoing engineering construction process work
Walk the supplemental characteristic of equipment maximum investment PROSTEPEQUMax;Establish ongoing engineering construction process work step teams and groups
The supplemental characteristic of PROSTEPTEA establishes ongoing engineering construction process work step teams and groups' minimum investment PROSTEPTEAMin
Supplemental characteristic, establish ongoing engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax supplemental characteristic;
The supplemental characteristic for establishing ongoing engineering construction process work step material PROSTEPMAV, establishes ongoing engineering construction
The supplemental characteristic of the specified construction volume PROSTEPMATValV of technique work step material, establishes ongoing engineering construction process work step
Material is constructed the supplemental characteristic of sequencing PROSTEPOrd, establishes that ongoing engineering construction process work step material is specified to be applied
The supplemental characteristic of the optimistic standard time PROSTEPTgV (h) of work amount establishes ongoing engineering construction process work step material
The supplemental characteristic of the pessimistic standard time PROSTEPTbV (h) of specified construction volume establishes ongoing engineering construction process work
Walk the supplemental characteristic of the most probable standard time PROSTEPTpV (h) of the specified construction volume of material;The supplemental characteristic is imported into data
Library forms ongoing construction cell set to be managed;
Second heavy duty is other: establishing the supplemental characteristic of ongoing engineering construction process work step timing-type PROSTEPTypT, builds
Found the supplemental characteristic of ongoing engineering construction process work step timing standard time PROSTEPTT;The supplemental characteristic is imported
Database forms ongoing construction cell set to be managed;
Establish the supplemental characteristic of the engineering construction process work step work team PROSTEPClasT not yet to go into operation;Establish the work not yet to go into operation
Journey construction technology starts the supplemental characteristic of work step PROSTEPSta, and establishing the engineering construction process not yet to go into operation terminates work step
The supplemental characteristic of PROSTEPEnd;The supplemental characteristic is imported into database and forms the construction cell set to be managed not yet to go into operation;
Third heavy duty is other: establishing the supplemental characteristic of the engineering construction process work step quantitative-type PROSTEPTypV not yet to go into operation;It builds
The supplemental characteristic of the vertical engineering construction process work step equipment PROSTEPEQU not yet to go into operation, establishes the engineering construction work not yet to go into operation
Skill work step equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, establishes the engineering construction process work step equipment not yet to go into operation
The supplemental characteristic of maximum investment PROSTEPEQUMax;Establish the engineering construction process work step teams and groups PROSTEPTEA not yet to go into operation
Supplemental characteristic, establish not yet go into operation engineering construction process work step teams and groups' minimum investment PROSTEPTEAMin supplemental characteristic,
Establish the supplemental characteristic of the engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax not yet to go into operation;Foundation is not yet opened
The supplemental characteristic of the engineering construction process work step material PROSTEPMAV of work establishes the engineering construction process work step material not yet to go into operation
Expect the supplemental characteristic of specified construction volume PROSTEPMATValV, establishes the engineering construction process work step material construction not yet to go into operation first
The supplemental characteristic of sequence PROSTEPOrd afterwards establishes the optimism of the specified construction volume of engineering construction process work step material not yet to go into operation
The supplemental characteristic of standard time PROSTEPTgV (h) establishes the specified construction volume of engineering construction process work step material not yet to go into operation
Pessimistic standard time PROSTEPTbV (h) supplemental characteristic, it is specified to establish the engineering construction process work step material that not yet goes into operation
The supplemental characteristic of the most probable standard time PROSTEPTpV (h) of construction volume;The supplemental characteristic is imported database to be formed not yet
The construction cell set to be managed to go into operation;
Quadruple rank: the supplemental characteristic of the engineering construction process work step timing-type PROSTEPTypT not yet to go into operation is established, is built
The supplemental characteristic of the vertical engineering construction process work step timing standard time PROSTEPTT not yet to go into operation;The supplemental characteristic is imported
Database forms the construction cell set to be managed not yet to go into operation;
Establish the supplemental characteristic of completed works construction technology work step work team PROSTEPClasT;Completed works is established to apply
Work technique starts the supplemental characteristic of work step PROSTEPSta, and establishing completed works construction technology terminates work step PROSTEPEnd
Supplemental characteristic;Supplemental characteristic importing database is formed into completed construction cell set to be managed;
5th heavy duty is other: establishing the supplemental characteristic of completed works construction technology work step quantitative-type PROSTEPTypV;It establishes
The supplemental characteristic of completed works construction technology work step equipment PROSTEPEQU, establishes completed works construction technology work step
Equipment normally puts into the supplemental characteristic of PROSTEPEQUMin, establishes completed works construction technology work step equipment maximum investment
The supplemental characteristic of PROSTEPEQUMax;The supplemental characteristic of completed works construction technology work step teams and groups PROSTEPTEA is established,
The supplemental characteristic for establishing completed works construction technology work step teams and groups' minimum investment PROSTEPTEAMin, is established completed
The supplemental characteristic of engineering construction process work step teams and groups' maximum investment PROSTEPTEAMax;Establish completed works construction technology
The supplemental characteristic of work step material PROSTEPMAV establishes the specified construction volume of completed works construction technology work step material
The supplemental characteristic of PROSTEPMATValV establishes completed works construction technology work step material construction sequencing
The supplemental characteristic of PROSTEPOrd establishes the optimistic standard time of the specified construction volume of completed works construction technology work step material
The supplemental characteristic of PROSTEPTgV (h), the pessimism for establishing the specified construction volume of completed works construction technology work step material are specified
The supplemental characteristic of working hour PROSTEPTbV (h) establishes most may be used for the completed works construction technology specified construction volume of work step material
The supplemental characteristic of energy standard time PROSTEPTpV (h);Supplemental characteristic importing database is formed and completed is applied wait manage
Work unit set;
Sixfold rank: establishing the supplemental characteristic of completed works construction technology work step timing-type PROSTEPTypT, establishes
The supplemental characteristic of completed works construction technology work step timing standard time PROSTEPTT;The supplemental characteristic is imported into data
Library forms completed construction cell set to be managed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810724673.XA CN108985605B (en) | 2018-07-04 | 2018-07-04 | Progress control method for construction planning |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810724673.XA CN108985605B (en) | 2018-07-04 | 2018-07-04 | Progress control method for construction planning |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108985605A true CN108985605A (en) | 2018-12-11 |
CN108985605B CN108985605B (en) | 2023-08-08 |
Family
ID=64536192
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810724673.XA Active CN108985605B (en) | 2018-07-04 | 2018-07-04 | Progress control method for construction planning |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108985605B (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR19990088345A (en) * | 1998-05-12 | 1999-12-27 | 메구로 가즈오 | Construction management system and construction management method |
CN103337004A (en) * | 2013-05-27 | 2013-10-02 | 李庆吉 | Open engineering implementation dynamic monitoring system and open engineering implementation dynamic monitoring method |
CN103455878A (en) * | 2013-08-28 | 2013-12-18 | 哈尔滨工业大学 | Method and device for construction progress network diagram real-time adjustment based on internet of things technology |
CN103699939A (en) * | 2013-11-15 | 2014-04-02 | 中国空间技术研究院 | Component application validation process establishment method for space navigation |
CN106408171A (en) * | 2016-08-31 | 2017-02-15 | 中国人民解放军海军航空工程学院青岛校区 | Heuristic activity-on-arrow diagram automatic drawing method |
CN107918831A (en) * | 2017-11-23 | 2018-04-17 | 深圳拎得清软件有限公司 | BIM Schedule managements method and its system based on browser |
-
2018
- 2018-07-04 CN CN201810724673.XA patent/CN108985605B/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR19990088345A (en) * | 1998-05-12 | 1999-12-27 | 메구로 가즈오 | Construction management system and construction management method |
CN103337004A (en) * | 2013-05-27 | 2013-10-02 | 李庆吉 | Open engineering implementation dynamic monitoring system and open engineering implementation dynamic monitoring method |
CN103455878A (en) * | 2013-08-28 | 2013-12-18 | 哈尔滨工业大学 | Method and device for construction progress network diagram real-time adjustment based on internet of things technology |
CN103699939A (en) * | 2013-11-15 | 2014-04-02 | 中国空间技术研究院 | Component application validation process establishment method for space navigation |
CN106408171A (en) * | 2016-08-31 | 2017-02-15 | 中国人民解放军海军航空工程学院青岛校区 | Heuristic activity-on-arrow diagram automatic drawing method |
CN107918831A (en) * | 2017-11-23 | 2018-04-17 | 深圳拎得清软件有限公司 | BIM Schedule managements method and its system based on browser |
Non-Patent Citations (1)
Title |
---|
张黎明;: "道路工程监理三控网络计划编制的程序", 民营科技 * |
Also Published As
Publication number | Publication date |
---|---|
CN108985605B (en) | 2023-08-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110503325B (en) | Construction progress resource automatic optimization method based on building information model | |
Wang et al. | Improved precast production–scheduling model considering the whole supply chain | |
Lu et al. | Resource-activity critical-path method for construction planning | |
Liu et al. | Optimizing linear project scheduling with multi-skilled crews | |
US20130335413A1 (en) | System and method for estimating construction duration | |
CN104573182B (en) | A kind of design method for aircraft Multimode Control System | |
CN106156408A (en) | The building of the classification of a kind of Component-Based Development and combination works in coordination with constructing system and method | |
CN108932383B (en) | Engineering construction organization scheme comprehensive aid decision-making method based on BIM technology | |
CN104407576A (en) | Realization method for general type production and manufacturing unit and control system thereof | |
CN106951621B (en) | A kind of simulation optimization method carrying Plan rescheduling for ship | |
CN112307548A (en) | BIM-based rail transit construction visualization progress management method and system | |
CN105243237A (en) | Assembly technology structure tree and building method thereof | |
CN113505418A (en) | Bridge construction method based on BIM | |
CN116127551A (en) | Bridge construction progress refined control method based on digital twin multidimensional model | |
Jiang et al. | Interoperability of cross-organizational workflows based on process-view for collaborative product development | |
CN114077765B (en) | Dynamo project data management method and device based on Dynamo project data management method and device, and computer equipment | |
CN115689464A (en) | Assembly type building EPC general contract project management method and system based on BIM | |
CN111581700A (en) | Method for adding BIM attribute and outputting BIM attribute table based on CATIA model | |
CN107729620A (en) | A kind of embedded software power consumption Forecasting Methodology based on level Colored Petri Net | |
CN109034551A (en) | Equilibrium of stock method for construction plan establishment | |
Stanilov | Bridging the gap between urban morphology and urban modelling K. Stanilov | |
CN101261694A (en) | A simulation validation method for virtualization dispatching optimization in process industry | |
CN108985605A (en) | Progress management-control method for construction plan establishment | |
CN114896677B (en) | BIM (building information modeling) -based construction simulation method and system | |
CN104252552A (en) | Process simulation method for final assembly technology |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |