CN108980802A - A kind of boiling water or steam generation device quickly heated using heating pipe - Google Patents
A kind of boiling water or steam generation device quickly heated using heating pipe Download PDFInfo
- Publication number
- CN108980802A CN108980802A CN201810492379.0A CN201810492379A CN108980802A CN 108980802 A CN108980802 A CN 108980802A CN 201810492379 A CN201810492379 A CN 201810492379A CN 108980802 A CN108980802 A CN 108980802A
- Authority
- CN
- China
- Prior art keywords
- water
- switch
- container
- heating pipe
- boiling
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B1/00—Methods of steam generation characterised by form of heating method
- F22B1/28—Methods of steam generation characterised by form of heating method in boilers heated electrically
- F22B1/282—Methods of steam generation characterised by form of heating method in boilers heated electrically with water or steam circulating in tubes or ducts
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F22—STEAM GENERATION
- F22B—METHODS OF STEAM GENERATION; STEAM BOILERS
- F22B35/00—Control systems for steam boilers
- F22B35/005—Control systems for instantaneous steam boilers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H1/00—Water heaters, e.g. boilers, continuous-flow heaters or water-storage heaters
- F24H1/10—Continuous-flow heaters, i.e. heaters in which heat is generated only while the water is flowing, e.g. with direct contact of the water with the heating medium
- F24H1/101—Continuous-flow heaters, i.e. heaters in which heat is generated only while the water is flowing, e.g. with direct contact of the water with the heating medium using electric energy supply
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H9/00—Details
- F24H9/18—Arrangement or mounting of grates or heating means
- F24H9/1809—Arrangement or mounting of grates or heating means for water heaters
- F24H9/1818—Arrangement or mounting of electric heating means
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24H—FLUID HEATERS, e.g. WATER OR AIR HEATERS, HAVING HEAT-GENERATING MEANS, e.g. HEAT PUMPS, IN GENERAL
- F24H9/00—Details
- F24H9/20—Arrangement or mounting of control or safety devices
- F24H9/2007—Arrangement or mounting of control or safety devices for water heaters
- F24H9/2014—Arrangement or mounting of control or safety devices for water heaters using electrical energy supply
- F24H9/2028—Continuous-flow heaters
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Mechanical Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Combustion & Propulsion (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Apparatus For Making Beverages (AREA)
Abstract
A kind of boiling water or steam generation device quickly heated using heating pipe of disclosure of the invention, including water pump are connected to container, heating pipe, the first and second relay, Boiling start-up switch, boiling water heater switch, activated vapor switch, steam heater switch and selection control circuit;Feature is: Boiling start-up switch, mounted in higher position in container is connected to, constitutes first group of control switch with boiling water heater switch;Activated vapor switch, mounted in lower position in container is connected to, constitutes second group of control switch with steam heater switch;Steam heater switch is located at heating pipe mid-height vicinity;Control circuit is selected to select the control switch work of one of first and second group of control switch;It further include empty control component, it is placed in connection container, occupies connection container major part volume, constitutes runner between water inlet and water outlet by empty control component with vessel clearance is connected to.Device can adjust rapidly the water level of connection container in the selection of boiling water and steam generation transformation.
Description
Technical field
The invention belongs to quickly heat the device of water in the places such as a kind of family, office, industrial and mineral, army, school, application
In water dispenser, be related to providing it is a kind of quickly heated using heating pipe to water therein is injected, can be from heating pipe nozzle
When obtain the device of boiling water or water vapour, it has multiple functions selective, can choose and generates a large amount of or a small amount of boiled water, water steams
Vapour, with realize it is to boil water, brew or decoct beverage, make tea, make coffee and decoct pack etc., can be extracted from beverage or pack
Effective component therein.
Background technique
Existing water dispenser or making tea machine widely enter daily life.In these utensils, have using jug with heating disk
, also have using the heating of immersion electrothermal tube, there are also using electromagnetic oven heating, heating process is adopted in all these utensils
With compared with the integrated mode to boil water of big yield, thus it is required to take a long time and boiling could be boiled, what user needed to wait for
Time is also longer, is unable to satisfy and can be obtained the hot water or boiling water for meeting temperature requirement within the vertical equal short time, functionally
It is more single.
In real life, in more times, there are a small amount of need in the occasion for needing boiled water regularly in people
It wants, kung fu tea is such as steeped by boiling water, or be mixed into the water, etc. of suitable consumption temperature by boiling water and cold boiling water, thereby result in
Due to a small amount of hot water needs and be meet heat must boiled a certain amount of water, then again remaining boiled water is wasted in vain
Fall.
Currently, being had already appeared using the quick device to boil water of heating pipe, it solves the above problems, and a small amount of water is allowed to flow
It is heated rapidly while heated pipeline, people can obtain boiling water standing in the short time waited.In this kind of device, China is practical
New patent 201220377340.2 is one of representative device.
But these devices only met the requirement for being used to heat water in the past, for the steam generated in heating process, but
It cannot select for soaking beverage.Water vapour has the characteristics that heat and air pressure, can further be utilized, for example, can be by water
Steam takes high speed cooking food, decocts pack, soaking beverage, alternatively, heating liquid in impregnating etc. by water vapour.
For this purpose, the applicant improves above-mentioned technology, and ZL201410761546.9 is applied for Patent Office of the People's Republic of China
Patent of invention, it discloses a kind of boiling water or steam generation device quickly heated using heating pipe, may be selected to generate steam
Come the needs for meeting boiling, decocting and brewing, more convenience are brought in use to people.
But in the two schemes of foregoing invention, a kind of scheme is using two pipelines and solenoid valve and check-valves come real
Existing, structure is complex, and when being transformed into steam generation state by boiling water, it is necessary to by heating pipe middle and upper part great quantities of spare
Water consumption fall, a large amount of moisture content could not be contained in the steam then generated;Another scheme is then transformed into steam in boiling water
In the selection of generation, water extra in linker and heating pipe is drawn back by water tank using another water pump, structure is still more
Complexity, and need to undergo the process drawn water, increasing people is the time for obtaining steam and needing to wait, and it is temporal slow to occur
Prolong.
In addition, lead must be drawn outward since water level switch has certain volume again, and container is connected to because of difference
Water level control needs to be additionally provided with several water level switches, constitutes limitation to the design of connection container, makes to be connected to container
Must have a constant volume and a moulding, it is internal to be configured with ladder again, these adjusting of water and water level will certainly be brought compared with
Big influence.
Summary of the invention
The purpose of the present invention is to provide a kind of boiling water quickly heated using heating pipe or water vapour generation device, it
A kind of simple structure is provided, can generate in boiling water in the selection of steam generation transformation, adjust the water of connection container rapidly
Position, to adapt to founding the needs for meeting steam generation or boiling water generation in the short time waited.
The purpose of the present invention is realized by following scheme:
A kind of boiling water or steam generation device quickly heated using heating pipe, including water pump, connection container, heating pipe,
First relay, the second relay, Boiling start-up switch, boiling water heater switch, activated vapor switch, steam heater switch and
Select control circuit;
Wherein:
Connection container is provided with water inlet, and water is sent to connection container from water inlet by water pump;Connection container is provided with water outlet,
It is supplied water from water outlet through communicating pipe to heating pipe;
Its main feature is that:
Boiling start-up switch is mounted on boiling water heater switch to be connected in container on higher water level position, and first group of control is constituted
Switch;Boiling start-up switch is normally closed water level switch, it makes its movement by the first upper limit water level of connection container, by Boiling start-up
Switch control power supply is powered on to water pump;Boiling water heater switch be normally opened water level switch, it by connection container the first lower limit water level
Make its movement, and is powered on from boiling water heater switch by the first power source for relay control to heating pipe;
Activated vapor switch is mounted on steam heater switch to be connected in container on lower water level position, and second group of control is constituted
Switch;Activated vapor switch is normally closed water level switch, it makes its movement by the second upper limit water level of connection container, control power supply to
Water pump power-up;Steam heater switch is normally opened water level switch, it makes its movement by the second lower limit water level of connection container, and passes through
Second power source for relay control is powered on to heating pipe;
Second upper limit water level is lower than the first lower limit water level, and the second lower limit water level is higher than water outlet;
Steam heater switch is located near heating pipe mid-height;
Selection control circuit is for selecting the control switch of one of first group of control switch and second group of control switch to work;
It further include free control component, sky control component is set in connection container, in occupation of the connection most volume of container, by sky
The runner controlling component and being connected between container between gap composition water inlet and water outlet.
In this way, boiling water quickly can be generated by first group of control switch, by second group of control switch come instantaneously producing steam,
And the work of first group of control switch or second group of control switch can be selected by selection control circuit.
The boiling water or steam generation device that the invention utilizes heating pipe quickly to heat, due to being set in connection container
Empty control component is set, so that connection container water is greatly reduced, then, boiling water is generated or the water potential of steam generation exists to meet
It is able to adjustment conversion in the extremely short time, is suitable for founding the needs for meeting steam or boiling water generation in the short time waited.
The boiling water or steam generation device that the present invention utilizes heating pipe quickly to heat control component from connection container using sky
Inside realizes the quick adjustment of water level to tie up space manner, and structure is particularly simple, compared with prior art, without setting
Extra water is drawn back water tank by the second water pump, and two pipelines and the components such as solenoid valve and check-valves, manufacturing cost need not also be arranged
It will be less expensive.
This boiling water or steam generation device that utilize heating pipe quickly to heat, the structure for being connected to container itself need not be into one
Step variation, thus to water level switches such as Boiling start-up switch, boiling water heater switch, activated vapor switch and steam heater switch
Design and installation will not constitute any influence.
In above scheme, the heating device column section grouping on heating pipe makes to heat using the connection of structure in parallel or series
The heating power of pipeline is adjustable, in this way, being adapted to different needs.For example, when needing a large amount of boiling water or a large amount of water vapours,
It can choose increasing heating power;When needing a small amount of boiling water or a small amount of water vapour, lower heating power can be used.
Detailed description of the invention
Fig. 1 is a kind of schematic diagram of specific embodiment sectional structure of the present invention;
The schematic diagram of another side sectional structure when Fig. 2 is Fig. 1 device cutting;
Fig. 3 is linker structural schematic diagram in Fig. 1 device;
Fig. 4 is Fig. 3 linker overlooking structure diagram;
Fig. 5 is the hollow control modular construction schematic diagram of Fig. 1 device;
Fig. 6 is Fig. 5 sky control component overlooking structure diagram.
Specific embodiment
Specific detailed description is made to the present invention with reference to the accompanying drawing:
Referring to figs. 1 to Fig. 6, this boiling water or steam generation device that utilize heating pipe quickly to heat, including water tank 1, water pump 2,
Heating pipe 3, the first relay 41, the second relay 42 are connected to container 5, Boiling start-up switch 6, and boiling water heater switch 7 is steamed
Vapour starts switch 8, and steam heater switch 9 selects control circuit (not shown);Wherein, connection its internal cavities of container 5 tool
There is ladder 53, ladder 53 is in higher position than logical 5 bottom 54 of container, and water inlet 51 may be provided at the ladder of connection container 5
At 53, water inlet 51 and water tank 1 are connected by water pipe, and water can be sent to connection container 5 from water tank 1 by water pump 2;Water outlet
Mouth 52 is arranged at the bottom 54 of connection container 5, is supplied water from water outlet 52 through communicating pipe to heating pipe 3;Boiling start-up switch 6
It is mounted on the ladder 53 for being connected to container 5 with boiling water heater switch 7, constitutes first group of control switch;Boiling start-up switch 6 is normal
Water level switch is closed, it makes its movement by the first upper limit water level of connection container, controls power supply to water pump 2 from Boiling start-up switch 6
Power-up;Boiling water heater switch 7 is normally opened water level switch, it makes its movement by the first lower limit water level of connection container 5, and by boiling water
Heater switch 7 controls power supply by the first relay 41 and is powered on to heating pipe 3;Activated vapor switch 8 and steam heater switch 9
It is mounted on the bottom 54 of connection container 5, constitutes second group of control switch;Activated vapor switch 8 be normally closed water level switch, it by
Second upper limit water level of connection container 5 makes its movement, and control power supply is powered on to water pump 2;Steam heater switch 9 is that normally opened water level is opened
It closes, it makes its movement by the second lower limit water level of connection container 5, and controls power supply to heating pipe 3 by the second relay 42
Power-up;First upper limit water level is lower than the bend of the top of heating pipe 3, and the second upper limit water level is lower than the first lower limit water level, under second
Position of restricting water supply then is higher than water outlet 52;Steam heater switch 9 is located near 3 mid-height of heating pipe;Select control circuit
For selecting the control switch of one of first group of control switch and second group of control switch to work;The shape of sky control component 11 and company
Cavity inside logical container 5 is similar, be placed in empty control component 11 can at connection 5 center of container, and in occupation of being connected to the big portion of container 5
Point volume, the runner a between water inlet 51 and water outlet 52 is constituted with the gap being connected between container 5 by empty control component 11
。
The process that device generates boiling water is described below:
Device is for when generating boiling water, selecting control circuit to select first group of control switch work, and second group of control switch is then
Failure, at this moment, if not having water in connection container 5, since Boiling start-up switch 6 is normally closed water level switch, pump 2 can power on
And extract the water in water tank 1 out, connection container 5 is entered by water inlet 51, and heating pipe 3 is entered by water outlet 52, works as connection
When the water level of container 5 is higher than the first lower limit water level, boiling water heater switch 7 will be closed, and the first relay 41 is made to obtain electric and realize electricity
Source powers to heating pipe 3, and then, heating pipe 3 rapidly heats water, at the first upper limit water level and the first lower limit water level
In on higher water level line, thus, it is possible to maintain higher water level in heating pipe 3, guarantee to have in heating pipe 3 enough
Water to meet the generation and outflow of boiling water, simultaneously, moreover it is possible to prevent heating pipe 3 from empty burning occur.
In addition, the water level of connection container 5 constantly rises, and works as water as water is constantly evacuated to connection container 5 from water tank 1 by pump 2
When position rising reaches the first upper limit water level, Boiling start-up switch 6 goes off state by closed state, and power supply just stops to pump 2
The water inlet of power supply, connection container 5 stops, and can prevent the spilling of water.
Furthermore it is constantly heated and flows out with dampening, the water in heating pipe 3 can be reduced constantly, but heating pipe 3 and company
The water that logical container 5 links together, thus is connected in container 5 can flow into the supplement that heating pipe 3 carries out water, to guarantee boiling water source
Source constantly generates.
In addition, boiling water continuously outflows from winding pipe exit, while the water being connected in container 5 constantly flows into heating pipe 3,
Water level in connection container 5 can constantly decline, and when water level is down to the first upper limit water level or less, Boiling start-up switch 6 is closed again,
Make the work once electrified again of pump 2, allows water constantly to flow to connection container 5 from water tank 1 again and supplemented, ensure that the use in heating pipe 3
Water.
If flowing to connection container 5 from water tank 1 without water to be supplemented, the water level of connection container 5 be will be further compromised, when
When water level is down to the first lower limit water level or less, boiling water heater switch 7 is disconnected, and heating pipe 3 no longer obtains power supply and stops to water
It is heated, then, boiling water generation just stops, it is ensured that safety in use.
So far, the whole process that boiling water generates has been completed.
The process that device generates steam is described below:
Device is for when generating steam, selecting control circuit to select second group of control switch work, and first group of control switch is then
Failure, at this moment, if not having water in connection container 5, since activated vapor switch 8 is normally closed water level switch, pump 2 can power on
And extract the water in water tank 1 out, connection container 5 is entered by water inlet 51, and heating pipe 3 is entered by water outlet 52, works as connection
When the water level of container 5 is higher than the second lower limit water level, steam heater switch 9 will be closed, and the second relay 42 is made to obtain electric and realize electricity
Source powers to heating pipe 3, and then, heating pipe 3 rapidly heats water, at the second upper limit water level and the second lower limit water level
In on lower water level line, thus, it is possible to maintain lower water level in heating pipe, guarantee only about one in heating pipe 3
Half water, water can be heated to boiling and become steam and evaporate outward, meet the generation and outflow of steam, simultaneously, moreover it is possible to anti-
Only there is completely empty burn in heating pipe 3.
In addition, the water level of connection container 5 constantly rises, and works as water as water is constantly evacuated to connection container 5 from water tank 1 by pump 2
When position rising reaches the second upper limit water level, activated vapor switch 8 goes off state by closed state, and power supply just stops to pump 2
The water inlet of power supply, connection container 5 stops, it is ensured that there was only the water of about half in heating pipe 3, boils and evaporate to be heated.
Furthermore it is constantly heated and evaporates with dampening, the water in heating pipe 3 can be reduced constantly, but heating pipe 3 and company
The water that logical container 5 links together, thus is connected in container 5 can flow into the supplement that heating pipe 3 carries out water, guarantee steam in a steady stream
It is continuous to generate.
In addition, steam continuously outflows from winding pipe exit, while the water being connected in container 5 constantly flows into heating pipe 3,
Water level in connection container 5 can constantly decline, and when water level is down to the second upper limit water level or less, activated vapor switch 8 is closed again,
Make the work once electrified again of pump 2, allows water constantly to flow to connection container 5 from water tank 1 again and supplemented, ensure that the use in heating pipe 3
Water.
If flowing to connection container 5 from water tank 1 without water to be supplemented, the water level of connection container 5 be will be further compromised, when
When water level is down to the second lower limit water level or less, steam heater switch 9 is disconnected, and heating pipe 3 no longer obtains power supply and stops to water
It is heated, then, steam generation just stops, it is ensured that safety in use.
So far, the whole process of steam generation has been completed.
When the control that the control that device is in steam generation is converted to boiling water generation at this moment will be by 6 He of Boiling start-up switch
Boiling water heater switch 7 carries out control, and Boiling start-up switch 6 can power at once powers to water pump 2, makes water rapid from water tank 1
To connection 5 amount of makeup water of container, to maintain heating pipe 3 to remain with higher water level, this will be completed in a very short period of time.
When the control that the control that device is in boiling water generation is converted to steam generation at this moment will be by 8 He of activated vapor switch
Steam heater switch 9 carries out control, and activated vapor switch 8 can be cut off the power at once to the power supply of water pump 2, does not allow temporarily water from water tank
1 to connection 5 amount of makeup water of container, meanwhile, steam heater switch 9 is connected to rapidly power supply to heating pipe by the second relay 42
3 power supplies, since water is few in connection container 5, heating pipe 3 will consume quickly extra water, and make in heating pipe 3
Water level is rapidly decreased near mid-height, and heating pipe 3 is maintained to maintain lower water level.
It follows that water is in water inlet 51 and water outlet since sky control component 11 is in occupation of the connection most volume of container 5
Steam generation can be flowed and switched rapidly in runner a between mouth 52 rapidly and boiling water generates the water level for respectively needing to maintain,
To ensure that and can complete in a very short period of time, meanwhile, the journey that connection 5 cavity of container can be inserted by adjusting empty control component 11
Degree to adjust the spare water in connection container 5, and can allow equilibrium relation of the user between waiting time and guarantee water
In make better choice.
Claims (2)
1. a kind of boiling water or steam generation device quickly heated using heating pipe, including water pump are connected to container, heating tube
Road, the first relay, the second relay, Boiling start-up switch, boiling water heater switch, activated vapor switch, steam heater switch
And selection control circuit;
Wherein:
Connection container is provided with water inlet, and water is sent to connection container from water inlet by water pump;Connection container is provided with water outlet,
It is supplied water from water outlet through communicating pipe to heating pipe;
It is characterized in that:
Boiling start-up switch is mounted on boiling water heater switch to be connected in container on higher water level position, and first group of control is constituted
Switch;Boiling start-up switch is normally closed water level switch, it makes its movement by the first upper limit water level of connection container, by Boiling start-up
Switch control power supply is powered on to water pump;Boiling water heater switch be normally opened water level switch, it by connection container the first lower limit water level
Make its movement, and is powered on from boiling water heater switch by the first power source for relay control to heating pipe;
Activated vapor switch is mounted on steam heater switch to be connected in container on lower water level position, and second group of control is constituted
Switch;Activated vapor switch is normally closed water level switch, it makes its movement by the second upper limit water level of connection container, control power supply to
Water pump power-up;Steam heater switch is normally opened water level switch, it makes its movement by the second lower limit water level of connection container, and passes through
Second power source for relay control is powered on to heating pipe;
Second upper limit water level is lower than the first lower limit water level, and the second lower limit water level is higher than water outlet;
Steam heater switch is located near heating pipe mid-height;
Selection control circuit is for selecting the control switch of one of first group of control switch and second group of control switch to work;
It further include free control component, sky control component is set in connection container, in occupation of the connection most volume of container, by sky
The runner controlling component and being connected between container between gap composition water inlet and water outlet.
The hair 2. boiling water or steam generation device according to claim 1 quickly heated using heating pipe, on heating pipe
The grouping of thermal device column section, is connected using structure in parallel or series, keeps the heating power of heating pipe adjustable.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810492379.0A CN108980802A (en) | 2018-05-22 | 2018-05-22 | A kind of boiling water or steam generation device quickly heated using heating pipe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810492379.0A CN108980802A (en) | 2018-05-22 | 2018-05-22 | A kind of boiling water or steam generation device quickly heated using heating pipe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108980802A true CN108980802A (en) | 2018-12-11 |
Family
ID=64542068
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810492379.0A Pending CN108980802A (en) | 2018-05-22 | 2018-05-22 | A kind of boiling water or steam generation device quickly heated using heating pipe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108980802A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101660835A (en) * | 2009-09-22 | 2010-03-03 | 杭州热威机电有限公司 | Instantaneous spiral flow channel heater |
CN101839551A (en) * | 2010-04-09 | 2010-09-22 | 叶广团 | Water heater tank |
CN201652835U (en) * | 2010-04-22 | 2010-11-24 | 宁波方太厨具有限公司 | Water-flow regulating device |
CN201719072U (en) * | 2010-05-26 | 2011-01-26 | 应雄峰 | Coffee maker boiler |
US20120061378A1 (en) * | 2009-05-16 | 2012-03-15 | Michael George Colburn | Food Steamer Containers with Sequential Ohmic Water Heating |
CN102793472A (en) * | 2012-08-28 | 2012-11-28 | 宁波家尚电器有限公司 | Water heating machine capable of rapidly providing boiling water |
CN103431767A (en) * | 2013-09-09 | 2013-12-11 | 汕头经济特区和通电讯有限公司 | Heating pipeline and instant heating type water dispenser comprising same |
CN104545476A (en) * | 2014-10-08 | 2015-04-29 | 汕头经济特区和通电讯有限公司 | Boiling water or steam production device utilizing heating pipeline for quick heating |
CN206755598U (en) * | 2017-05-08 | 2017-12-15 | 佛山市玖冠宇科技有限公司 | The synthesis cisten mechanism of instant electric boiler |
-
2018
- 2018-05-22 CN CN201810492379.0A patent/CN108980802A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20120061378A1 (en) * | 2009-05-16 | 2012-03-15 | Michael George Colburn | Food Steamer Containers with Sequential Ohmic Water Heating |
CN101660835A (en) * | 2009-09-22 | 2010-03-03 | 杭州热威机电有限公司 | Instantaneous spiral flow channel heater |
CN101839551A (en) * | 2010-04-09 | 2010-09-22 | 叶广团 | Water heater tank |
CN201652835U (en) * | 2010-04-22 | 2010-11-24 | 宁波方太厨具有限公司 | Water-flow regulating device |
CN201719072U (en) * | 2010-05-26 | 2011-01-26 | 应雄峰 | Coffee maker boiler |
CN102793472A (en) * | 2012-08-28 | 2012-11-28 | 宁波家尚电器有限公司 | Water heating machine capable of rapidly providing boiling water |
CN103431767A (en) * | 2013-09-09 | 2013-12-11 | 汕头经济特区和通电讯有限公司 | Heating pipeline and instant heating type water dispenser comprising same |
CN104545476A (en) * | 2014-10-08 | 2015-04-29 | 汕头经济特区和通电讯有限公司 | Boiling water or steam production device utilizing heating pipeline for quick heating |
CN206755598U (en) * | 2017-05-08 | 2017-12-15 | 佛山市玖冠宇科技有限公司 | The synthesis cisten mechanism of instant electric boiler |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20130126514A1 (en) | Food Steamer | |
CN104545476B (en) | A kind of boiling water of the quick heating of utilization heating pipe or steam generation device | |
CN209090865U (en) | A kind of boiling water or steam generation device quickly heated using heating pipe | |
CN101639284B (en) | Electric heater | |
CN102216693A (en) | Integrated heating device for storage water heater | |
CN101290160A (en) | Electric water heater | |
CN203609272U (en) | Water dispenser | |
CN108980802A (en) | A kind of boiling water or steam generation device quickly heated using heating pipe | |
CN202457933U (en) | Quick-heating type water heater | |
CN208925933U (en) | A kind of device quickly heating water using heating pipe | |
CN202489782U (en) | Pipeline heating quick boiling type water dispenser | |
CN202630360U (en) | Device for quick water boiling by means of heating pipeline | |
CN201724372U (en) | Temperature-regulated instantly opened water dispenser | |
CN202452661U (en) | Drinking water heating device convenient in filling water in water storage tank | |
CN112790585A (en) | Dynamic compensation system for generating stable steam or constant-temperature liquid by using battery to heater | |
CN208925932U (en) | A kind of device quickly heating water using heating pipe | |
CN208658965U (en) | Field steam-type food heating kettle | |
CN201607011U (en) | Double-lining combination composite washing cabinet type water heater | |
CN201542404U (en) | Water-circulation tail-gas utilizing device | |
CN205560685U (en) | High -efficient steam generator of vertical heating | |
CN201675730U (en) | Two-stage hot water valve water dispenser | |
CN108720601B (en) | Device for rapidly heating water by using heating pipeline | |
CN109008646A (en) | A kind of device quickly heating water using heating pipe | |
CN209136221U (en) | It is a kind of with the speed heat drinking equipment for boiling module in advance | |
TWI558958B (en) | Energy-saving instantaneous hot water supply |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20181211 |