CN108978463A - A kind of construction technology carrying out anticollision barrier piling using special mould clamp - Google Patents

A kind of construction technology carrying out anticollision barrier piling using special mould clamp Download PDF

Info

Publication number
CN108978463A
CN108978463A CN201810794944.9A CN201810794944A CN108978463A CN 108978463 A CN108978463 A CN 108978463A CN 201810794944 A CN201810794944 A CN 201810794944A CN 108978463 A CN108978463 A CN 108978463A
Authority
CN
China
Prior art keywords
positioning branch
main pipe
branch pipe
steel upright
joist steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810794944.9A
Other languages
Chinese (zh)
Inventor
乔培明
柳延江
张小燕
李旭峰
方利
孙冬磊
徐刚平
郭忠茂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, No 1 Engineering Co Ltd of CCCC First Harbor Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201810794944.9A priority Critical patent/CN108978463A/en
Publication of CN108978463A publication Critical patent/CN108978463A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/10Railings; Protectors against smoke or gases, e.g. of locomotives; Maintenance travellers; Fastening of pipes or cables to bridges
    • E01D19/103Parapets, railings ; Guard barriers or road-bridges
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The present invention discloses a kind of construction technology that anticollision barrier piling is carried out using special mould clamp, belongs to anticollision barrier piling field, comprising the following steps: 1) blocks the locating slot formed between two positioning branch pipes of main pipe one end on mounted joist steel upright;2) joist steel upright to be installed is squeezed into the locating slot then formed between two positioning branch pipes of the main pipe other end;3) operation according to step 1), step 2 is recycled, the installation of subsequent joist steel upright is carried out.The application of special mould clamp provided by the invention and construction technology not only facilitates transverse slat installation, while also improving the speed of application of joist steel upright piling so that the control of joist steel upright spacing is very accurate.At the same time, the whole circular arc degree for joist steel upright on loop and the problem of the bad control of vertical direction, the present invention also provides arc fixtures, and not only piling quality control is good, but also circular arc entirety lines are beautiful.

Description

A kind of construction technology carrying out anticollision barrier piling using special mould clamp
Technical field
The present invention relates to a kind of construction technologies that anticollision barrier piling is carried out using special mould clamp, belong to anticollision barrier piling Field.
Background technique
Currently, frequently encountering different landform in viaduct highway anti-collision guardrail joist steel upright piling construction.And it is right In anticollision barrier joist steel upright piling construction, it is desirable that spacing must control strictly, and deviation is no more than ± 1cm, otherwise rear Bolt hole not correspond on when phase waveform transverse slat is installed, can only expanding treatment again, not only increase construction cost and influence beauty;Separately Outside, it is desirable that verticality must control strictly, and deviation will lead to spacing and deviation occur no more than ± 1cm, front and back verticality, influence The installation of waveform transverse slat, left and right verticality will affect the beauty after the installation of waveform transverse slat;Certain sections, such as loop guardrail are pacified Dress is entirely arc section, not only increases difficulty of construction in the control of joist steel upright spacing, but also guardrail is required to install out Smooth circular arc effect, it is apparently neat and beautiful.
Currently, aiming at the problem that being encountered in above-mentioned anticollision barrier joist steel upright piling construction, generally use ruler according to Required spacing row ruler carries out stud location, and then piling machine directly carries out joist steel upright to squeeze into construction.Specifically exist as follows Problem:
1) joist steel upright positioning directly is carried out according to required spacing row's ruler using ruler, the control of joist steel upright spacing can exist Error squeezes into front position with regard to inaccurate in column.
2) when joist steel upright squeezes into construction, due to not having spacing tool, column will appear offset during squeezing into Phenomenon, spacing changes after the completion of causing column to be driven piles.
3) joist steel upright on loop is on circular arc line, and not only column distance measurement control difficulty is big, Er Qieli The whole circular arc degree and vertical direction of column are also not easily controlled.
Summary of the invention
Anticollision barrier piling is carried out using special mould clamp in view of the above existing problems in the prior art, the present invention provides a kind of Construction technology, effectively prevent resetting of post phenomenon generation.
To achieve the goals above, a kind of construction work that anticollision barrier piling is carried out using special mould clamp that the present invention uses Skill, the special mould clamp include a main pipe and four positioning branch pipes being separately mounted on main pipe, the positioning branch pipe It is divided into two groups of both ends for being separately fixed at main pipe, and is located at one positioning of formation between the two positioning branch pipes of main pipe the same end Slot;
The spacing for two locating slots that four positioning branch pipes are formed is with the clipping room of joist steel upright away from identical;
Specific construction technology is as follows:
1) locating slot formed between two positioning branch pipes of main pipe one end is blocked on mounted joist steel upright;
2) joist steel upright to be installed is squeezed into the locating slot then formed between two positioning branch pipes of the main pipe other end;
3) operation according to step 1), step 2 is recycled, the installation of subsequent joist steel upright is carried out.
As an improvement, rectangular steel tube is respectively adopted in the main pipe, positioning branch pipe, the side length of the rectangular steel tube is 60mm, wall thickness 3mm.
As an improvement, the special mould clamp includes a main pipe and four are respectively perpendicular to be welded on main pipe and determine Position branch pipe;
The positioning branch pipe includes the identical positioning branch pipe one of structure, positioning branch pipe two, positioning branch pipe three and positioning branch pipe four, institute State positioning branch pipe one, positioning branch pipe two cooperatively forms locating slot one, the positioning branch pipe three and positioning branch pipe four cooperatively form and determine Position slot two.
As an improvement, the main pipe uses linear main pipe one or cambered main pipe two.
As an improvement, the spacing of locating slot one and locating slot two is 1.9m.
Compared with prior art, the application of special mould clamp provided by the invention and construction technology, so that between joist steel upright It is very accurate away from controlling, transverse slat installation is not only facilitated, while also improving the speed of application of joist steel upright piling.It is same with this When, the problem of whole circular arc degree and the bad control of vertical direction for joist steel upright on loop, the present invention also provides arcs Shape fixture, not only piling quality control is good, but also circular arc entirety lines are beautiful.
Detailed description of the invention
Fig. 1 is a kind of structural schematic diagram of special mould clamp of the present invention;
Fig. 2 is the structural schematic diagram of another special mould clamp of the present invention;
In figure: 1, positioning branch pipe one, 2, locating slot one, 3, positioning branch pipe two, 4, positioning branch pipe three, 5, locating slot two, 6, positioning Branch pipe four, 7, main pipe one, 8, column one, 9, column two, 10, main pipe two.
Specific embodiment
In order to make the objectives, technical solutions and advantages of the present invention clearer, the present invention is carried out below further detailed It describes in detail bright.However, it should be understood that the specific embodiments described herein are merely illustrative of the present invention, it is not limited to this hair Bright range.
Unless otherwise defined, all technical terms and scientific terms used herein are led with technology of the invention is belonged to The normally understood meaning of the technical staff in domain is identical, and term as used herein in the specification of the present invention is intended merely to retouch State the purpose of specific embodiment, it is not intended that in the limitation present invention.
A kind of construction technology carrying out anticollision barrier piling using special mould clamp, the special mould clamp include a trunk Pipe and four positioning branch pipes being separately mounted on main pipe, the positioning branch pipe are divided into two groups and are separately fixed at main pipe Both ends, and it is located at one locating slot of formation between the two positioning branch pipes of main pipe the same end;
The spacing for two locating slots that four positioning branch pipes are formed is with the clipping room of joist steel upright away from identical;
Specific construction technology is as follows:
4) locating slot formed between two positioning branch pipes of main pipe one end is blocked on mounted joist steel upright;
5) joist steel upright to be installed is squeezed into the locating slot then formed between two positioning branch pipes of the main pipe other end;
6) operation according to step 1), step 2 is recycled, the installation of subsequent joist steel upright is carried out.
As the improvement of embodiment, rectangular steel tube is respectively adopted in the main pipe, positioning branch pipe, the rectangular steel tube Side length is 60mm, wall thickness 3mm.
As the improvement of embodiment, as shown in Figure 1 and Figure 2, the special mould clamp includes a main pipe and four difference The positioning branch pipe being vertically welded on main pipe;
The positioning branch pipe includes the identical positioning branch pipe 1 of structure, positioning branch pipe 23, positioning branch pipe 34 and positioning branch pipe four 6, the positioning branch pipe 1, positioning branch pipe 23 cooperatively form locating slot 1, and the positioning branch pipe 34 and positioning branch pipe 46 are matched Conjunction forms locating slot 25.
As the improvement of embodiment, the main pipe uses linear main pipe 1 or cambered main pipe two 10.Main pipe 1 therein can be used for the installation of joist steel upright on straight line;Cambered main pipe 2 10 is suitable for solving The whole circular arc degree of joist steel upright and the problem of the bad control of vertical direction on loop, not only piling quality control is good, and And circular arc entirety lines are beautiful.The fixture of above two structure, structural stability is strong, during joist steel upright is squeezed into very well Ground prevents the generation of column shifting phenomena, guarantees that from start to finish stud is constant.
As the improvement of embodiment, by taking Saudi Arabia prolongs the installation of 7507 viaduct anticollision barrier of cloth as an example, locating slot 1 and fixed The spacing control of position slot 25 is required 1.9m.When column piling construction, the locating slot 1 of fixture one end is snapped into and is completed Column 1 on, the locating slot 25 of the other end, which snaps into, to be prepared on the column 29 squeezed into, and new column 29 is blocked when squeezing into The positioning of locating slot 25, prevents the generation of resetting of post phenomenon well in having.
In addition, prolonging the camber line requirement of 7507 viaduct intermediate ring road of cloth according to Saudi Arabia, the main pipe 2 10 of suitable radian is designed, Then positioning branch pipe is fixed on to the design for completing the arc fixture on main pipe 2 10, efficiently solved on loop The problem of the bad control of whole circular arc degree and vertical direction of joist steel upright, not only piling quality control is good, but also circular arc Whole lines are beautiful.
The application of special mould clamp provided by the invention and construction technology, so that the control of joist steel upright spacing is very accurate, Transverse slat installation is not only facilitated, while also improving the speed of application of joist steel upright piling.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention Made any modification, equivalent replacement or improvement etc., should all be included in the protection scope of the present invention within mind and principle.

Claims (5)

1. a kind of construction technology for carrying out anticollision barrier piling using special mould clamp, which is characterized in that the special mould clamp includes One main pipe and four positioning branch pipes being separately mounted on main pipe, the positioning branch pipe are divided into two groups and are separately fixed at The both ends of main pipe, and it is located at one locating slot of formation between the two positioning branch pipes of main pipe the same end;
The spacing for two locating slots that four positioning branch pipes are formed is with the clipping room of joist steel upright away from identical;
Specific construction technology is as follows:
The locating slot formed between two positioning branch pipes of main pipe one end is blocked on mounted joist steel upright;
Then joist steel upright to be installed is squeezed into the locating slot formed between two positioning branch pipes of the main pipe other end;
Circulation carries out the installation of subsequent joist steel upright according to the operation of step 1), step 2.
2. a kind of construction technology for being carried out anticollision barrier piling using special mould clamp according to claim 1, feature are existed In rectangular steel tube is respectively adopted in the main pipe, positioning branch pipe, and the side length of the rectangular steel tube is 60mm, wall thickness 3mm.
3. a kind of construction technology for being carried out anticollision barrier piling using special mould clamp according to claim 2, feature are existed In the special mould clamp includes that a main pipe and four are respectively perpendicular the positioning branch pipe being welded on main pipe;
The positioning branch pipe includes the identical positioning branch pipe one (1) of structure, positioning branch pipe two (3), positioning branch pipe three (4) and positions Branch pipe four (6), the positioning branch pipe one (1), positioning branch pipe two (3) cooperatively form locating slot one (2), the positioning branch pipe three (4) and positioning branch pipe four (6) cooperatively forms locating slot two (5).
4. a kind of construction technology for being carried out anticollision barrier piling using special mould clamp according to claim 3, feature are existed In the main pipe uses linear main pipe one (7) or cambered main pipe two (10).
5. a kind of construction technology for being carried out anticollision barrier piling using special mould clamp according to claim 3, feature are existed In the spacing of locating slot one (2) and locating slot two (5) is 1.9m.
CN201810794944.9A 2018-07-19 2018-07-19 A kind of construction technology carrying out anticollision barrier piling using special mould clamp Pending CN108978463A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810794944.9A CN108978463A (en) 2018-07-19 2018-07-19 A kind of construction technology carrying out anticollision barrier piling using special mould clamp

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810794944.9A CN108978463A (en) 2018-07-19 2018-07-19 A kind of construction technology carrying out anticollision barrier piling using special mould clamp

Publications (1)

Publication Number Publication Date
CN108978463A true CN108978463A (en) 2018-12-11

Family

ID=64550255

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810794944.9A Pending CN108978463A (en) 2018-07-19 2018-07-19 A kind of construction technology carrying out anticollision barrier piling using special mould clamp

Country Status (1)

Country Link
CN (1) CN108978463A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090133041A (en) * 2008-06-23 2009-12-31 김동규 Apparatus for vegetation growth control and interception of animal on roadside
CN203308157U (en) * 2013-05-22 2013-11-27 国家电网公司 Electric pole distance locating device
CN103821380A (en) * 2014-02-25 2014-05-28 中天建设集团有限公司 Construction method for installing steel railing on site through positioning fixture
CN203918845U (en) * 2014-06-20 2014-11-05 中建五局第三建设有限公司 Accurate positioner of hot and cold water head
CN204035893U (en) * 2014-09-16 2014-12-24 武汉一冶钢结构有限责任公司 The auxiliary jig of anticollision barrier sinew adding strip

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20090133041A (en) * 2008-06-23 2009-12-31 김동규 Apparatus for vegetation growth control and interception of animal on roadside
CN203308157U (en) * 2013-05-22 2013-11-27 国家电网公司 Electric pole distance locating device
CN103821380A (en) * 2014-02-25 2014-05-28 中天建设集团有限公司 Construction method for installing steel railing on site through positioning fixture
CN203918845U (en) * 2014-06-20 2014-11-05 中建五局第三建设有限公司 Accurate positioner of hot and cold water head
CN204035893U (en) * 2014-09-16 2014-12-24 武汉一冶钢结构有限责任公司 The auxiliary jig of anticollision barrier sinew adding strip

Similar Documents

Publication Publication Date Title
US20050238443A1 (en) Continuous connecting profile for attachment of sheet piles to supporting elements
US6629681B1 (en) Flexible form assembly
CN205399157U (en) Template device for concrete placement
CN108978463A (en) A kind of construction technology carrying out anticollision barrier piling using special mould clamp
CN208501492U (en) Fixture for anticollision barrier piling construction
CN104563495A (en) Special-shaped beam column node template and engineering template equipping method thereof
CN205894586U (en) Joint construction of externally -hanging wallboard and structure
CN209854516U (en) Curve linear control device
CN106065698A (en) The connecting structure of out-hung panel and structure and assembly method thereof
CN104453256A (en) Positioning device for embedding bolts
CN208815512U (en) Engineering method stake stake heart positioning auxiliary device and engineering method pile driving construction system
CN205894305U (en) Joint construction of hollow externally -hanging wallboard and structure
CN204252557U (en) For the positioner of pre-embedded bolt
CN209369046U (en) The connection component of wallboard and structural body
CN109024577A (en) Engineering method stake stake heart positioning auxiliary device and engineering method stake stake heart localization method
KR101828322B1 (en) Assembling structure for road guiding sign board
CN105625424A (en) Device used for controlling perpendicularity and azimuth angle of rectangular bracket pile and construction method
CN211421895U (en) Building site unwrapping wire mark template
CN216276857U (en) Scaffold
CN206732010U (en) Pretreatment unit for reinforcement metal straightening
CN104963510B (en) Device and method for positioning center line of wing plate of arc-shaped structure
CN211472496U (en) SMW pile H-shaped steel insertion verticality control device
CN213836775U (en) Special structure foundation reinforcement structure
CN205296411U (en) Truss connection spare and curtain truss
CN207647078U (en) A kind of cylindrical surface aluminum alloy decoration plate mounting structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181211