CN108951672A - A kind of structure of voltage regulation that catchments for grouting construction - Google Patents

A kind of structure of voltage regulation that catchments for grouting construction Download PDF

Info

Publication number
CN108951672A
CN108951672A CN201810872158.6A CN201810872158A CN108951672A CN 108951672 A CN108951672 A CN 108951672A CN 201810872158 A CN201810872158 A CN 201810872158A CN 108951672 A CN108951672 A CN 108951672A
Authority
CN
China
Prior art keywords
catchment covers
voltage regulation
grouting construction
catchments
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810872158.6A
Other languages
Chinese (zh)
Inventor
王永东
郑儒彬
李晓龙
王冠杰
黄春兰
雷邱
蒋波
向官清
张啟岩
李彦威
王伟
唐华德
张宗欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Original Assignee
CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CRCC Harbour and Channel Engineering Bureau Group Co Ltd filed Critical CRCC Harbour and Channel Engineering Bureau Group Co Ltd
Priority to CN201810872158.6A priority Critical patent/CN108951672A/en
Publication of CN108951672A publication Critical patent/CN108951672A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/22Lining sumps in trenches or other foundation pits

Abstract

The invention discloses a kind of structure of voltage regulation that catchments for grouting construction, it is related to plasma pouring constructing skill field, water burst drives the cement slurry of injection constantly to gush out when for grouting construction, the technical issues of causing grouting quality decline that can not even be in the milk, catch pit is offered using the position of the upper surface seepage point concentration in foundation pit bottom, catchment covers are fixedly installed on catch pit, it is connected at the top of catchment covers with balance pipe, the filler that can be seeped water is provided in catchment covers, fill concrete layer is covered on the scheme on catchment covers.It is interconnected using catch pit, catchment covers and balance pipe, water burst can effectively be collected, when the water in catch pit gradually increases, enter catchment covers and balance pipe by filler gap, water level in balance pipe gradually increases the state being finally reached with water burst hydraulic balance, after hydraulic balance, water burst, which will be reduced, even to disappear, to ensure that going on smoothly and capable of guaranteeing construction quality for grouting works.

Description

A kind of structure of voltage regulation that catchments for grouting construction
Technical field
The present invention relates to plasma pouring constructing skill field, in particular to a kind of structure of voltage regulation that catchments for grouting construction.
Background technique
Consolidation grouting be in order to improve developmental joint fissure or have crushed zone rock physical and mechanical property and carry out Grouting works.For karst as the natural phenomena formed under a kind of special geological conditions, it is each that karst can form scale in rock mass Different weak structural face or cave, weakens the globality of rock foundation, and there are leakage problems, underground chamber is collapsed and gushed suddenly Water gushes mud, roof fall problem, and the engineering problems such as foundation stability bring many hazards to engineering construction.
Development of resources, great infrastructure development project with the needs of socio-economic development, in above-mentioned karst area It will be more and more.Water conservancy, traffic and urban operating mechanism project are mainly characterized by high to ground requirement for bearing capacity;Ground generallys use Under the action of earth's surface and ground water pressure, it is mixed to be located at backfill since construction location is lower than earth's surface for the form of heavy excavation, deep basal pit Often there is water burst at solidifying soil layer, these water bursts drive the cement slurry injected when grouting construction constantly to gush out, and lead to grouting quality Decline can not even be in the milk.
Summary of the invention
The present invention provides a kind of structure of voltage regulation that catchments for grouting construction, opens greatly to solve to generally use in ground It digs, under the form of deep basal pit, since construction location is lower than earth's surface, fill concrete is located under the action of earth's surface and ground water pressure Often there is water burst at layer, these water bursts drive the cement slurry injected when grouting construction constantly to gush out, and grouting quality is caused to decline The technical issues of can not being even in the milk.
To solve the above problems, the present invention adopts the following technical scheme that realization:
A kind of structure of voltage regulation that catchments for grouting construction is equipped with backfill coagulation including foundation pit and in the upper surface of foundation pit bottom Soil layer, and the grout hole opened up in foundation pit bottom are opened up in the position that the upper surface seepage point of the foundation pit bottom is concentrated There is catch pit;
Catchment covers are fixedly installed on the catch pit;
It is connected at the top of the catchment covers with balance pipe;
The filler that can be seeped water is provided in the catchment covers, the fill concrete layer is covered on the catchment covers.
It is interconnected, water burst can effectively be collected, when the water in catch pit using catch pit, catchment covers and balance pipe When gradually increasing, enter catchment covers and balance pipe by filler gap, the water level in balance pipe gradually increase be finally reached with The state of water burst hydraulic balance, after hydraulic balance, water burst, which will be reduced, even to disappear, to ensure that the smooth of grouting works It carries out and can guarantee construction quality.
Preferably, the catchment covers are funnel-shaped structure, and big open end is downward.
Water burst is collected convenient for more large area using funnel structure and is introduced in balance pipe convenient for concentrating.
Preferably, the catchment covers are made using steel.
Catchment covers are made using steel, are able to bear biggish pressure, very helpful for the stabilization of structure.
Preferably, the balance pipe is steel pipe, and described steel pipe one end and the catchment covers top are welded.
Steel pipe is common engineered building materials, can be faster using welding manner using steel pipe convenient for construction and operation Speed is more efficiently constructed.
Preferably, the diameter of steel tube is 150mm, thickness of pipe wall 6mm.
Preferably, the catch pit depth is less than 3m.
Catch pit depth is less than 3m, and this is the best practices value summed up in long-term engineering practice, and such depth can expire The existing duty requirements of foot.
Preferably, the balance pipe upper end is provided with screw thread, is connected through a screw thread the length for being able to extend the balance pipe.
The length of balance pipe can be quicklyd increase using thread connecting mode, improve working efficiency.
Preferably, the filler includes sand, stone.
Sand, stone are the most common materials in building site, and they have certain load-bearing capacity and water permeable ability.
Preferably, the filler is constituted using geotextiles package gravel.
Preferably, the fill concrete layer uses C15 concrete.
Beneficial effect of the present invention includes:
Structure is simple, low in cost, easy to operate, and stability is good, convenient for assembling.
Detailed description of the invention
Fig. 1 is embodiment construction scene figure provided by the invention;
Fig. 2 is example structure schematic diagram provided by the invention.
In figure, each label is respectively indicated:
Foundation pit bottom 1, seepage point 11, catch pit 12, fill concrete layer 2, balance pipe 3, catchment covers 30, is filled out penetrating passage 10 Fill object 31, grout hole 4.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached in the embodiment of the present invention Figure, technical scheme in the embodiment of the invention is clearly and completely described, it is clear that described embodiment is the present invention A part of the embodiment, instead of all the embodiments.The embodiment of the present invention being usually described and illustrated herein in the accompanying drawings Detailed description is not intended to limit the range of claimed invention, but is merely representative of selected embodiment of the invention.Base Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts it is all its His embodiment, shall fall within the protection scope of the present invention.
As depicted in figs. 1 and 2, a kind of structure of voltage regulation that catchments for grouting construction, foundation pit bottom 1 in foundation pit it is upper The position that surface seepage point 11 is concentrated offers catch pit 12, and the depth of general catch pit 12 is no more than 3 meters, and the diameter view in hole is existing Depending on seepage point is how many, if seepage point mostly just excavate it is big some seepage point can be excavated a little bit smaller if lacking, do not do and have herein Body limits.
It is placed with the filler 31 that water penetration can be allowed to cross gap using geotextiles package gravel in catch pit 12, needs to infuse Meaning, as long as the filler 31 can seep water and have certain load-bearing capacity can be have to be not necessarily geotextiles Wrap up the mode of gravel.Filler 31 is covered by catchment covers 30, and catchment covers 30 are the funnel-shaped structures made of steel, big Opening is fixedly connected and is connected to balance pipe 3 by welding manner in small opening towards covered with filler 31.Balance pipe 3 is Use diameter made of steel pipe for 150mm, thickness of pipe wall is the tubing of 6mm, is vertically established on foundation pit bottom 1, the upper end of pipe Mode can be connected through a screw thread and realize extension.The upper surface of foundation pit bottom 1 and catchment covers 30 pass through the backfill of model C15 Concrete layer 2 wraps.
In use, as shown in Figure 1, underground water is along the water in the entrance catch pit 12 of penetrating passage 10, in catch pit 12 When gradually increasing, enter catchment covers 30 and balance pipe 3 by 31 gap of filler, the water level in balance pipe 3 gradually increases finally Reach the state with water burst hydraulic balance, after hydraulic balance, water burst, which will be reduced, even to disappear, at this time can be toward grout hole Cement slurry is poured into 4, because of hydraulic balance, therefore water flow will not be occurred without very big infiltration water flow and be asked what cement slurry was taken away Topic, to ensure that going on smoothly and capable of guaranteeing construction quality for grouting works.

Claims (10)

1. a kind of structure of voltage regulation that catchments for grouting construction is equipped with back including foundation pit and in the upper surface of foundation pit bottom (1) It fills out concrete layer (2), and the grout hole (4) opened up in foundation pit bottom (1), it is characterised in that:
Catch pit (12) are offered in the position that the upper surface seepage point (11) of the foundation pit bottom (1) is concentrated;
Catchment covers (30) are fixedly installed on the catch pit (12);
It is connected at the top of the catchment covers (30) with balance pipe (3);
The filler (31) that can be seeped water is provided in the catchment covers (30), the fill concrete layer (2) is covered on described On catchment covers (30).
2. the structure of voltage regulation that catchments according to claim 1 for grouting construction, it is characterised in that:
The catchment covers (30) are funnel-shaped structure, and big open end is downward.
3. the structure of voltage regulation that catchments according to claim 2 for grouting construction, it is characterised in that:
The catchment covers (30) are made using steel.
4. the structure of voltage regulation that catchments according to claim 1 for grouting construction, it is characterised in that:
The balance pipe (3) is steel pipe, and described steel pipe one end and the catchment covers (30) top are welded.
5. the structure of voltage regulation that catchments according to claim 4 for grouting construction, it is characterised in that:
The diameter of steel tube is 150mm, thickness of pipe wall 6mm.
6. the structure of voltage regulation that catchments according to claim 1 for grouting construction, it is characterised in that:
Catch pit (12) depth is less than 3m.
7. the structure of voltage regulation that catchments according to claim 1 for grouting construction, it is characterised in that:
Balance pipe (3) upper end is provided with screw thread, is connected through a screw thread the length for being able to extend the balance pipe (3).
8. the structure of voltage regulation that catchments according to claim 1 for grouting construction, it is characterised in that:
The filler (31) includes sand, stone.
9. the structure of voltage regulation that catchments according to claim 1 for grouting construction, it is characterised in that:
The filler (31) is constituted using geotextiles package gravel.
10. the structure of voltage regulation that catchments according to claim 1 for grouting construction, it is characterised in that:
The fill concrete layer (2) uses C15 concrete.
CN201810872158.6A 2018-08-02 2018-08-02 A kind of structure of voltage regulation that catchments for grouting construction Pending CN108951672A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810872158.6A CN108951672A (en) 2018-08-02 2018-08-02 A kind of structure of voltage regulation that catchments for grouting construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810872158.6A CN108951672A (en) 2018-08-02 2018-08-02 A kind of structure of voltage regulation that catchments for grouting construction

Publications (1)

Publication Number Publication Date
CN108951672A true CN108951672A (en) 2018-12-07

Family

ID=64467187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810872158.6A Pending CN108951672A (en) 2018-08-02 2018-08-02 A kind of structure of voltage regulation that catchments for grouting construction

Country Status (1)

Country Link
CN (1) CN108951672A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101245886A (en) * 2008-03-13 2008-08-20 武汉京冶地基基础工程有限责任公司 Processing method for deep building pit piping
CN102041810A (en) * 2010-12-22 2011-05-04 中国水电顾问集团华东勘测设计研究院 Construction method for pouring dam foundation concrete in zone with centralized water gushing
CN205387712U (en) * 2016-02-04 2016-07-20 上海建浩工程顾问有限公司 Quick treatment device of foundation pit piping
CN105780793A (en) * 2016-04-06 2016-07-20 中建交通建设集团有限公司 Emergency treatment method for sudden gushing of high confined water stratum foundation pit
CN208870062U (en) * 2018-08-02 2019-05-17 中国铁建港航局集团有限公司 A kind of structure of voltage regulation that catchments for grouting construction

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101245886A (en) * 2008-03-13 2008-08-20 武汉京冶地基基础工程有限责任公司 Processing method for deep building pit piping
CN102041810A (en) * 2010-12-22 2011-05-04 中国水电顾问集团华东勘测设计研究院 Construction method for pouring dam foundation concrete in zone with centralized water gushing
CN205387712U (en) * 2016-02-04 2016-07-20 上海建浩工程顾问有限公司 Quick treatment device of foundation pit piping
CN105780793A (en) * 2016-04-06 2016-07-20 中建交通建设集团有限公司 Emergency treatment method for sudden gushing of high confined water stratum foundation pit
CN208870062U (en) * 2018-08-02 2019-05-17 中国铁建港航局集团有限公司 A kind of structure of voltage regulation that catchments for grouting construction

Similar Documents

Publication Publication Date Title
CN108589718B (en) Piles in Karst Region base construction method
CN102518135B (en) Horizontal jet grouting soil anchor and castinplace pile Composite Foundation Pit supporting construction engineering method
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
US20140026518A1 (en) Construction method for root-type foundation anchorage and bored, root-type cast in-situ pile with anchor bolts
CN105239586B (en) Method for supporting foundation pit by adopting support structure
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN102852141A (en) Rock-socketed pipe pile foundation with pile core by concrete pouring and pile side by static pressure grouting and construction method for rock-socketed pipe pile foundation
CN106948340A (en) A kind of construction method of the Manual excavated pile structure of high polymer grouting protection
CN102808407B (en) Construction method of soft-foundation reinforced concrete cast-in-place pile
CN103572764A (en) Watertight structure for retaining wall of ultra-deep manually excavated pile and construction method thereof
CN104988914A (en) Cast-in-situ bored pile breakage processing method under water area environment
CN111364449A (en) Construction method and structure for penetrating karst cave of precast tubular pile
CN103015408A (en) Cast-in-place pile synchronous casing hole-forming constructing method
CN208201874U (en) A kind of open-cell cloth bag grouting structure
CN102174818A (en) Controlled impermeable leaking stoppage grout-extruding water-stopping technology of strong water permeable stratum of quaternary system
CN202644591U (en) A reinforced bridge pile foundation in tunnel construction under the geological condition of water-rich quicksand
CN101586341B (en) Water sealing method for civil engineering groundwork
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN208870062U (en) A kind of structure of voltage regulation that catchments for grouting construction
CN102425179B (en) Structure of reinforced soil sewer supported by bored concrete piles of mini steel tubes
CN111042161A (en) Slope collapse high slope flexible processing structure and construction method thereof
CN109024621A (en) The compound retaining wall supporting construction of embankment high slope tubular pole and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination