CN108922123A - Mine slope slip stability monitoring and early warning method - Google Patents

Mine slope slip stability monitoring and early warning method Download PDF

Info

Publication number
CN108922123A
CN108922123A CN201810871259.1A CN201810871259A CN108922123A CN 108922123 A CN108922123 A CN 108922123A CN 201810871259 A CN201810871259 A CN 201810871259A CN 108922123 A CN108922123 A CN 108922123A
Authority
CN
China
Prior art keywords
slope
inclinometer
explosion
survey line
side slope
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810871259.1A
Other languages
Chinese (zh)
Other versions
CN108922123B (en
Inventor
张拥军
刘思佳
杨登峰
王文
李文韬
马强强
包放歌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Qingdao University of Technology
China Railway 20th Bureau Group Corp
China Railway 19th Bureau Group Mining Investment Co Ltd
Sinosteel Maanshan General Institute of Mining Research Co Ltd
Original Assignee
Qingdao University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Qingdao University of Technology filed Critical Qingdao University of Technology
Priority to CN201810871259.1A priority Critical patent/CN108922123B/en
Publication of CN108922123A publication Critical patent/CN108922123A/en
Application granted granted Critical
Publication of CN108922123B publication Critical patent/CN108922123B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G08SIGNALLING
    • G08BSIGNALLING OR CALLING SYSTEMS; ORDER TELEGRAPHS; ALARM SYSTEMS
    • G08B21/00Alarms responsive to a single specified undesired or abnormal condition and not otherwise provided for
    • G08B21/02Alarms for ensuring the safety of persons
    • G08B21/10Alarms for ensuring the safety of persons responsive to calamitous events, e.g. tornados or earthquakes
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01BMEASURING LENGTH, THICKNESS OR SIMILAR LINEAR DIMENSIONS; MEASURING ANGLES; MEASURING AREAS; MEASURING IRREGULARITIES OF SURFACES OR CONTOURS
    • G01B21/00Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant
    • G01B21/32Measuring arrangements or details thereof, where the measuring technique is not covered by the other groups of this subclass, unspecified or not relevant for measuring the deformation in a solid

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
  • Testing Or Calibration Of Command Recording Devices (AREA)

Abstract

the invention discloses a mine side slope slip stability monitoring and early warning method which comprises the steps of selecting a side slope deformation monitoring section, arranging a vertical measuring line at the position of the monitoring section corresponding to a side slope platform, installing an inclinometer on the vertical measuring line, carrying out scientific analysis according to measured data, respectively adopting different slip stability analysis methods and standards for an initial blasting stage and a later stable development stage of side slope mining, coupling the slip of a mine side slope with blasting response, and enabling the increase rate of blasting displacement to be epsilon with the blasting responseiand rate of change of slip development is ηiAnd determining a displacement threshold value for the parameters and judging the stability state of the mine slope, so as to realize evaluation and early warning on the slope stability. According to the method, the mine side slope slippage can be more accurately and intuitively represented by monitoring the mine side slope slippage in real time and acquiring data and analyzing the data by adopting the Newton interpolation, fitting and other processing processes, the side slope slippage can be early warned in time according to the real-time data analysis, and an effective scientific basis is provided for monitoring the side slope slippage stability.

Description

A kind of mine slope sliding stability monitoring and pre-alarming method
Technical field
The invention belongs to geotechnical engineering field more particularly to the deformation monitorings of mine open slope, and in particular to Yi Zhongkuang Mountain Slope Sliding STABILITY MONITORING method for early warning.
Background technique
China mine landslide disaster threatens seriously, and landslide of high slope accident in mine is sent out in all kinds of accidents in China mine at present The raw accident that frequency is higher, death toll is more.China western part is that mineral resources are mainly distributed ground, while west area is also to collapse It collapses, come down, the multiple area of Geological Hazards of debris, at least causing hundred million yuan of 15-30 losses, serious landslide geology calamity every year on average Evil causes extreme loss to the lives and properties of local resident, how to formulate the maximum conditions of Slope with multi-step local buckling to Multi-edge Prediction and warning work in slope is of great significance.
Currently used mine slope displacement detecting instrument is mainly displacement meter and inclinometer, although the former can be directly easy The shift value for reading out side slope surface, but there is certain limitation due to that cannot reflect side slope internal displacement.The latter is on side More common in the displacement detecting of slope, this method passes through the surveyed inclination angle theta of inclinometeriWith amount segment length LiCalculate the horizontal position of side slope It moves, horizontal displacement total amountThe calculation method is regarded side slope survey line as broken line and is calculated, in inclinometer Position is broken line break, but practical side slope survey line displacement curve should be smoothed curve, often amplifies to drop by error Low monitoring data reliability;Meanwhile this method can only find out the displacement of certain point on survey line by way of linearly seeking difference, have Certain limitation.
It is more for the determination method of slope displacement secure threshold at present, it is mainly the following:Analytic method, numerical analysis The methods of method, Engineering Geological Analogy Method, model test.Analytic method, which is passed through, carries out slope deforming calculating frequently with complex function, due to The features such as lithology, construction, the environment of side slope are different, it is difficult to accurate description, therefore usually it is unable to satisfy calculating accuracy;Numerical value point Analysis method includes FInite Element, boundary element method etc., the method overcome the deficiency of analytic method, but it is often difficult for Discontinuous transmission To solve;Engineering Geological Analogy Method and model testing method overcome the difficulty on calculating, but still deposit with side slope actual conditions In different, to the determination of sliding threshold value, there are still unstable factors.
Therefore, it in order to overcome deficiency and limitation existing for above-mentioned existing monitoring method, slides and develops for mine slope Rule and developing stage, it would be highly desirable to propose a kind of displacement calculation based on mine slope slip mechanism and a kind of based on side slope The threshold value of warning method of determination that itself sliding development is coupled with concussion of blasting carries out the monitoring and early warning of mine slope.
Summary of the invention
Technical problem to be solved by the present invention lies in for the monitoring of existing mine slope and warning data processing method Deficiency proposes a kind of mine slope sliding stability monitoring and pre-alarming method, to overcome the calculating error of traditional slope displacement amount, really The fixed safety analysis being more consistent with side slope self property and alarm mode are led in mine slope safety evaluation and monitoring and warning Domain has important application value.
The present invention, which is that the following technical solution is employed, to be realized:A kind of mine slope sliding stability monitoring and pre-alarming method, Include the following steps:
Step A, select the section perpendicular to Slope Sliding direction for monitoring section, on each monitoring section, on each side At least one vertical survey line is arranged in platform corresponding position in slope;
Step B, multiple inclinometers are installed at interval on the corresponding vertical survey line of each monitoring section respectively, and record deviational survey The data k that instrument initial time measures(0, j)With inclinometer mounting height h, wherein k(0, j)Indicate j-th of inclinometer inspection of initial time The slope value of the current mounting position of survey;
Step C, the data k measured according to inclinometer initial time(0, j)With inclinometer mounting height h, obtain each vertical The tracing pattern of survey line initial time:
By inclinometer measures on the same vertical survey line of initial time slope value and mounting height data by Matlab into Row interpolation operation, and the displacement curve D (0, h) of corresponding vertical survey line is fitted, to indicate the song of the initial time of vertical survey line Line morphology;
Step D, Slope Sliding stability analysis and secure threshold early warning:
(D1) for initial stage mining phase:Due to initial stage of production, explosion is more frequent, and Slope Sliding is influenced by explosion Than more serious, under the concrete analysis process in the stage enters:
(D11) the data k measured according to moment inclinometer each before and after explosion(i, j)And inclinometer mounting height h, k(i, j) The slope value for indicating the current mounting position of i-th of moment, j-th of inclinometer detection obtains vertical survey using the method for step C The displacement curve D (i, h) at line each moment before and after explosion;
(D12) according to i-1 moment shift value D (i-1, h) before moment i slope displacement curve D (i, h) after explosion and explosion it Difference, which is determined, is displaced growth curve Δ D (i, h) after certain separate explosion, i.e. slip value;
(D13) secure threshold is set according to the coupling of the Slope Sliding value Δ D (i, h) of acquisition and separate explosion vibration, When the explosion displacement growth rate on certain separate explosion back slope is more than that the secure threshold just makes secure alarm;
(D2) for later period side slope self-growth state phase:The stable development stage in side slope later period mainly by side slope from The influence of the natural causes such as weight, wind, rainwater is a slow process, which passes through displacement long-run development change rate ηiInto Row determination of stability and early warning:
Using means same as step D11 and step D12, the Slope Sliding value Δ D (i, h) and i-1 at the i-th moment are obtained The Slope Sliding value Δ D (i-1, h) at moment, then:
Wherein, H by the vertical survey line of survey depth, as displacement long-run development change rate ηiWhen value is positive value, show this Locate Slope Sliding and is in acceleration deformation stage;Stablize deformation stage conversely, being then in.
Further, in the step A, one monitoring section of place setting of obvious tomography or sliding occurs in side slope, and According to the mine slope gradient and degree of crushing in other positions with remaining monitoring section of 30m-60m arranged for interval, with preferably Reaction mine slope slides development at any time or as caused by explosion, is the representative position that side slope slides, is easy to Timely monitoring is made to worst position.
Further, in the step dress B, the inclinometer is arranged vertically along the vertical survey line, vertical what is selected It drills at survey line and is put into sleeve conduit, inclinometer is put into along sleeve conduit vertically, 3-5 survey is installed on every vertical survey line Oblique instrument.
Further, in the step C, obtaining the initial configuration of vertical survey line, detailed process is as follows:
(C1) according to embedded instrument when, the read data k of inclinometer initial time(0, j)With inclinometer height h, import Go out the slope curve D ' of vertical survey line in Matlab by Newton interpolation calculationh(0, h), by n times interpolation polynomial to be asked D’h(0, h) is changed to the form with inheritedness, then utilizes interpolation condition (data that the depth and inclinometer of each point measure) Determine D 'hThe undetermined coefficient of (0, h), and then its slope curve is found out, it is sharp on the basis of original calculating by Newton interpolation It is further calculated with the data calculated before, improves analytical calculation efficiency;
(C2) the slope curve D ' based on acquisitionh(0, h), by integral command obtain vertical survey line displacement curve D (0, h);Same mode can be used in the form of survey line vertical for other moment, for example the displacement curve of i moment vertical survey line indicates For D (i, h), herein for be for a vertical survey line, the vertical survey line of other positions is same method, passes through plot (h, D) orders the coordinate that the Drawing of Curve of vertical survey line is come out to and be can be read any point, which is vertical survey line Actual displacement coordinate;
Further, in the step D13, the determination method of secure threshold is:
(D131) energy caused by the explosive equivalent conversion explosion according to used in explosion, and by influence coefficient T h into Row amendment, the influence coefficient that every separate explosion side slope slides are:Th=f (Si, Ei), wherein SiIt is i moment blow-up point away from current The distance of vertical survey line measuring point;EiFor the energy that i moment explosion has, explosion is displaced growth rate ∈i=Δ D (i, h)/Th;
(D132) preceding n-1 monitoring is displaced growth rate (∈1, ∈2, ∈3... ∈n-1) be used as totally, and it is total to set this Body obedience is just distributed very much, i.e. ∈i~N (μ, σ2), then first n-1 times growth rate average value mu and variances sigma can be obtained2
(D133) ∈ i is standardized conversion and obtains statistic F, t distributed area is called according to freedom degree, confidence coefficient Table judges that side slope is in stable state if it is the t test value under α that statistic F, which is less than confidence coefficient,;It is set if statistic F is greater than Believe that coefficient is the t test value under α, then judges the exception of Slope Sliding amount caused by thus separate explosion, detailed examination need to be carried out.
Compared with prior art, the advantages and positive effects of the present invention are:
The deformation mechanism of method combination inclinometer sleeve of the present invention carries out Newton to inclinometer institute's measured data and inserts The analyses such as value, numerical integration, Function Fitting processing obtains slope function by the way that intermittent slope value is carried out interpolation, then will insert The slope function that value obtains integrates to obtain displacement function, realizes more accurate monitoring, and meets Slope Sliding form, can be by position The accurate coordinates that function is fitted processing each point to survey line are moved, energy sound response goes out the deformation curve of inclinometer sleeve And deformation values are calculated, obtain can be used for monitoring in real time mine slope sliding mode and determine the evaluation parameter of secure threshold;
In addition, different sliding stabilities is respectively adopted in side slope initial stage of production blasting stage and stable development stage in later period The sliding of mine slope is coupled with explosion response, is displaced growth rate ∈ with explosion by analysis method and standardi, sliding hair Exhibition change rate is ηiDisplacement threshold value is determined for parameter and judges Mine Slope Stability state, is side slope to make early warning in time Sliding stability monitoring provides effective scientific basis, practical value with higher.
Detailed description of the invention
Fig. 1 is the flow diagram of mine slope of embodiment of the present invention sliding stability monitoring and pre-alarming method;
Fig. 2 is the monitoring section of mine slope and the position view of survey line described in the embodiment of the present invention;
Fig. 3 is vertical arrangement of measuring-line schematic top plan view described in the embodiment of the present invention.
Specific embodiment
In order to which the above objects, features and advantages of the present invention is more clearly understood, with reference to the accompanying drawing and implement The present invention will be further described for example.It should be noted that in the absence of conflict, in embodiments herein and embodiment Feature can be combined with each other.
It should be noted that according to the present invention focus on to mine slope sliding stability monitoring and pre-alarming method It improves, to monitoring device therein, in the case where meeting equipment operational reliability, those skilled in the art should know that it is specific Installation method and application method, for example, for the monitoring analysis and early warning of realizing side slope, some necessary monitoring and warning system modules It needs to install and design, such as:The monitoring and warning system may include power supply unit, acquisition unit, alarm unit, control unit Deng, power supply unit can be used solar panel, battery etc. and be powered for each unit, the acquisition unit include it is some must The cable run wanted is laid, automatic collection case and data processor, described control unit include wireless transport module, GPS receiver Machine processor and PC machine etc. are converged after acquiring the data of the monitoring devices such as data inclinometer by several branch line cables by total cable Always, it is transmitted to automatic collection case, then data are acquired by PC machine and are carried out by GPRS transmission to network by wireless transport module Analysis is realized real-time monitoring and early warning, is only limited the specific setting position of mine slope sliding monitoring device in the application Other brief descriptions fixed, do in the application to it, those skilled in the art are easy to know according to the relevant technologies.
Embodiment, a kind of mine slope sliding stability monitoring and pre-alarming method, as shown in Figure 1, including the following steps:
Step S1, select the section perpendicular to Slope Sliding direction for monitoring section, on each monitoring section, on each side At least one vertical survey line, prison is arranged in the corresponding position of slope platform (on side slope surface along longitudinal direction, there is the platform of one fixed width) The schematic diagram for surveying section 1 and vertical 2 position of survey line is as shown in Figure 2;
Step S2, multiple inclinometers are installed at interval on the corresponding vertical survey line of each monitoring section respectively, and record survey The data k that oblique instrument initial time measures(0, j)With inclinometer mounting height h, wherein k(0, j)Indicate j-th of inclinometer of initial time The slope value of the current mounting position of detection;
Step S3, the data k measured according to inclinometer initial time(0, j)With inclinometer mounting height h, obtain each vertical The tracing pattern of survey line initial time:
By inclinometer measures on the same vertical survey line of initial time slope value and mounting height data by Matlab into Row interpolation operation, and the displacement curve D (0, h) of corresponding vertical survey line is fitted, to indicate the song of the initial time of vertical survey line Line morphology;Due to when making sleeve conduit down, it may occur that inclination or buckling phenomenon, so the initial configuration of vertical survey line It is not completely vertical, so the data by inclinometer show the original state of vertical survey line, passes through judgement point Analyse the variation of later period vertical survey line tracing pattern, so that it may know the displacement that each point generates in corresponding timing node, And then safety is provided for Slope Sliding stability analysis and defines foundation;
Step S4, Slope Sliding stability analysis and secure threshold early warning:
(S41) for initial stage mining phase:Due to initial stage of production, explosion is more frequent, shadow of the Slope Sliding by explosion It rings than more serious, the concrete analysis process of the process is as follows:
(S411) the data k measured according to moment inclinometer each before and after explosion(i, j)And inclinometer mounting height h, k(i, j) The slope value for indicating the current mounting position of i-th of moment, j-th of inclinometer detection obtains vertical survey using the method for step C The displacement curve D (i, h) at line each moment before and after explosion;
(S412) according to i-1 moment shift value D (i-1, h) before moment i slope displacement curve D (i, h) after explosion and explosion Difference determine and be displaced growth curve Δ D (i, h) after certain separate explosion, i.e. slip value;
(S413) safety is set according to the energy coupling of the Slope Sliding value Δ D (i, h) of acquisition and separate explosion vibration Threshold value, when certain separate explosion back slope slip value is more than that the secure threshold just makes secure alarm;
(S42) for later period side slope self-growth state phase:The stable development stage in side slope later period mainly by side slope from The influence of the natural causes such as weight, weathering, rainwater is a slow process;By being displaced long-run development change rate ηiIt carries out steady Qualitative judgement and early warning:
Using means same as step S411 and step S422, obtain the i-th moment Slope Sliding value Δ D (i, h) and The Slope Sliding value Δ D (i-1, h) at i-1 moment, then:
Wherein, H by the vertical survey line of survey depth, as displacement long-run development change rate ηiWhen value is positive value, show this Locate Slope Sliding and is in acceleration deformation stage;Stablize deformation stage conversely, being then in.
For in step S413, in mine slope stage initial stage of production, the mode that secure threshold determines is as follows:
(1) energy caused by the explosive equivalent conversion explosion according to used in explosion, and carried out by influencing coefficient T h Amendment, the influence coefficient that every separate explosion side slope slides are:Th=f (Si, Ei), wherein SiIt hangs down for i moment blow-up point away from current The distance of straight survey line measuring point;EiFor the energy that i moment explosion has, explosion is displaced growth rate ∈i=Δ D (i, h)/Th;
(2) preceding n-1 monitoring is displaced growth rate (∈1, ∈2, ∈3... ∈n-1) be used as totally, and set the totality Obedience is just distributed very much, i.e. ∈i~N (μ, σ2), then first n-1 times growth rate average value mu and variances sigma can be obtained2
(3) by ∈iIt is standardized conversion and obtains statistic F, t distributed area table is called according to freedom degree, confidence coefficient, If it is the t test value under α that statistic F, which is less than confidence coefficient, judge that side slope is in stable state;If statistic F is greater than confidence Coefficient is the t test value under α, then judges the exception of Slope Sliding amount caused by thus separate explosion, need to carry out detailed examination.
It is described in detail by taking certain open mine side slope as an example below, as shown in figure 3, the geology feelings of the open mine side slope Condition investigation is detailed, has the invention application conditions, specifically:
The first step:The arrangement of slope monitoring section, vertical survey line:
Section of the monitoring section perpendicular to Slope Sliding direction, the monitoring section at side slope section setting one, the monitoring are disconnected Poor slope geological condition, side slope type and more complicated, the possible representative Slope Sliding destruction of generation of stress is arranged in face Key position, can be by direct visual perception, remaining monitoring section takes 30m-60m according to the mine slope gradient, degree of crushing etc. Arranged for interval.And on each monitoring section, each plain stage of slope (1768 platforms, 1780 platforms, 1792 platforms, 1816 platforms With 1826 platforms etc.) at least one vertical survey line (the vertical survey line of 1-A -1-E5 item is provided on such as 1768 platforms) should be equipped with.
The arrangement of the position selection and survey line of above-mentioned monitoring section, can preferably react mine slope at any time or by quick-fried Development is slid caused by broken, is the representative position that side slope slides, is easy to make timely prison to worst position It surveys.
Second step:The installation and arrangement of monitoring device:
Monitoring device includes inclinometer, and inclinometer should be arranged vertically along the vertical survey line, high according to locating plain stage of slope 3-5 inclinometer should be equipped with by spending in every survey line, drilled at selected survey line and be put into sleeve, inclinometer is put along sleeve vertically Under, vertical interval is 4m between inclinometer, and top side inclinometer is away from plain stage of slope surface 3.2m.
Third step:Displacement curve D (i, h) is calculated according to measured value;
Under blast action and long-run development effect, slope stability situation will change mine slope with the sliding of side slope And generate variation.It is periodically detected according to detection duration, blast action side slope, records inclinometer institute in each detection phase Measured data k(i, j)And survey line slope function D ' is calculated by Newton interpolating functionh(i, h).
For initial 0 moment, inclinometer measures on same vertical survey line slope value and mounting height data are passed through Matlab carries out interpolation arithmetic, and fits the displacement curve D (0, h) of corresponding vertical survey line, to indicate the initial of vertical survey line The tracing pattern at moment, for other moment in monitoring process, in the same way, and then according to the tracing pattern of survey line Its specific sliding situation of change is learnt in variation.For example the displacement curve of i moment vertical survey line is expressed as D (i, h), herein for Be for a vertical survey line, the vertical survey line of other positions is same method, by plot (h, D) order will vertically survey The Drawing of Curve of line comes out and can be read the coordinate of any point, which is the actual displacement coordinate of vertical survey line, tiltedly The read data k of instrument initial time(0, j)With inclinometer height h, import vertical out by Newton interpolation calculation in Matlab Slope curve D ' the h (0, h) of survey line, by n times interpolation polynomial D ' to be askedh(0, h) is changed to the form with inheritedness, then D ' is determined using interpolation condition (data that the depth and inclinometer of each point measure)hThe undetermined coefficient of (0, h), and then find out it Slope curve, by Newton interpolation, the data calculated before on the basis of original calculating are further calculated, are mentioned High analyte computational efficiency.
Inclinometer records the data of certain a period of time in table 1, it should be noted that letter i indicates institute in the present embodiment The data moment taken, which group data distinguished, mine slope initial stage of production when choosing data, after being every separate explosion Latest data is once analyzed;Later period stability of slope developing stage not explosion, about 1 week update a data.
The monitoring data of 3C survey line in 1 Fig. 3 of table
1 data of table are inputted in Newton interpolation procedure and calculate survey line slope function D 'h(i, h), table 2 are each group monitoring Data interpolating function.
Interpolating function of the table 2 for each group monitoring data in table 1
2 slope function of table progress numerical integration is calculated into Function of side-slope lateral displacement D (i, h).
Table 3 is each group monitoring data displacement function.
4th step:According to displacement curve, side slope total displacement amount Δ D (i, h) in i-th of period is determined.
(1) mining phase initial for side slope:The method according to third step calculates each point coordinate of its cofunction, And the shift value size changed the time, Δ D (i, h)=D (i+1, h)-D (i, h), root are calculated by the difference of coordinate points respective function value The influence coefficient T h of every separate explosion side slope sliding is determined apart from side slope position according to energy caused by explosion and blow-up point;
Th=f (Si, Ei)
Wherein:Si--- i moment distance of the blow-up point away from the measuring point
Ei--- the energy that i moment explosion has
Thereby determine that explosion is displaced growth rate ∈i, ∈i=Δ D (i, h)/Th, for example, 6 times before monitoring point are monitored quick-fried Broken displacement growth rate (∈1, ∈2……∈6) it is used as a totality, it is assumed that totality obedience is just distributed very much, i.e. ∈i~N (μ, σ2), ∈7The totality for being 1 as sample size.
It is calculated from the formula (∈1, ∈2……∈6) sample average μ and variances sigma2
By ∈7It brings following formula into and obtains statistic
T distribution table is looked into, the t test value under confidence coefficient is 0.05 when obtaining freedom degree n=6 is 1.94318, η < 1.94318 judging ∈7Normally, show that side slope is in stable state at this stage.
(2) for the stable development stage in Highwall mining later period, the monitoring of long-term slope slip value is developed by Slope Sliding Change in long term rate η i is judged that value is:
When the Slip change rate value is to illustrate that side slope sliding velocity within the period slowly increases at this on the occasion of 0.0001638 Long, slope sliding is still in developing stage.
The above described is only a preferred embodiment of the present invention, being not that the invention has other forms of limitations, appoint What those skilled in the art changed or be modified as possibly also with the technology contents of the disclosure above equivalent variations etc. It imitates embodiment and is applied to other fields, but without departing from the technical solutions of the present invention, according to the technical essence of the invention Any simple modification, equivalent variations and remodeling to the above embodiments, still fall within the protection scope of technical solution of the present invention.

Claims (5)

1. a kind of mine slope sliding stability monitoring and pre-alarming method, which is characterized in that include the following steps:
Step A, select the section perpendicular to Slope Sliding direction for monitoring section, it is flat in each side slope on each monitoring section At least one vertical survey line is arranged in the corresponding position of platform;
Step B, multiple inclinometers are installed at interval on the corresponding vertical survey line of each monitoring section respectively, and at the beginning of recording inclinometer The data k that moment beginning measures(0, j)With inclinometer mounting height h, wherein k(0, j)Indicate j-th of inclinometer detection of initial time The slope value of current mounting position;
Step C, the data k measured according to inclinometer initial time(0, j)With inclinometer mounting height h, each vertical survey line is obtained The tracing pattern of initial time:
Inclinometer measures on the same vertical survey line of initial time slope value and mounting height data are carried out by Matlab slotting It is worth operation, and fits the displacement curve D (0, h) of corresponding vertical survey line, indicates the curved shape of the initial time of vertical survey line State;Step D, Slope Sliding stability analysis and secure threshold early warning:
(D1) due to initial stage of production, explosion is more frequent, and Slope Sliding is influenced to exploit initial stage than more serious by explosion Phase analysis process is as follows:
(D11) the data k measured according to moment inclinometer each before and after explosion(i, j)And inclinometer mounting height h, k(i, j)Indicate the The slope value of the current mounting position of j-th of inclinometer of i moment detection obtains vertical survey line quick-fried using the method for step C The displacement curve D (i, h) at broken front and back each moment;
(D12) difference according to i-1 moment shift value D (i-1, h) before moment i slope displacement curve D (i, h) after explosion and explosion is true It is displaced growth curve Δ D (i, h) after being scheduled on certain separate explosion, i.e. slip value;
(D13) secure threshold is set according to the coupling of the Slope Sliding value Δ D (i, h) of acquisition and separate explosion vibration, when certain The explosion displacement growth rate of side slope is more than that the secure threshold just makes secure alarm after separate explosion;
(D2) for later period side slope self-growth state phase, by being displaced long-run development change rate ηiCarry out determination of stability with Early warning:
Using means same as step D11 and step D12, Slope Sliding value Δ D (i, h) and the i-1 moment at the i-th moment are obtained Slope Sliding value Δ D (i-1, h), then:
Wherein, H by the vertical survey line of survey depth, as displacement long-run development change rate ηiWhen value is positive value, show side slope at this Sliding is in acceleration deformation stage;Stablize deformation stage conversely, being then in.
2. mine slope sliding stability monitoring and pre-alarming method according to claim 1, it is characterised in that:The step A In, one monitoring section of place setting of obvious tomography or sliding occurs in side slope, and according to the mine slope gradient and degree of crushing In other positions with remaining monitoring section of 30m-60m arranged for interval.
3. mine slope sliding stability monitoring and pre-alarming method according to claim 1, it is characterised in that:The step dress In B, the inclinometer is arranged vertically along the vertical survey line, and 3-5 inclinometer is installed on every vertical survey line.
4. mine slope sliding stability monitoring and pre-alarming method according to claim 1, it is characterised in that:The step C In, obtaining the initial configuration of vertical survey line, detailed process is as follows:
(C1) according to embedded instrument when, the read data k of inclinometer initial time(0, j)With inclinometer height h, Matlab is imported In go out the slope curve D ' of vertical survey line by Newton interpolation calculationh(0, h);
(C2) the slope curve D ' based on acquisitionh(0, h) obtains the displacement curve D (0, h) of vertical survey line by integral command.
5. mine slope sliding stability monitoring and pre-alarming method according to claim 1, it is characterised in that:The step In D13, the determination method of secure threshold is:
(D131) energy caused by the explosive equivalent conversion explosion according to used in explosion, and repaired by influencing coefficient T h Just, the influence coefficient of every separate explosion side slope sliding is:Th=f (Si, Ei), wherein SiIt is i moment blow-up point away from current vertical The distance of survey line measuring point;EiFor the energy that i moment explosion has, explosion is displaced growth rate ∈i=Δ D (i, h)/Th;
(D132) preceding n-1 monitoring is displaced growth rate (∈1, ∈2, ∈3... ... ∈n-1) be used as totally, and set totality obedience It is just distributed very much, i.e. ∈i~N (μ, σ2), then first n-1 times growth rate average value mu and variances sigma can be obtained2
(D133) by ∈iIt is standardized conversion and obtains statistic F, t distributed area table is called according to freedom degree, confidence coefficient, if It is the t test value under α that statistic F, which is less than confidence coefficient, then judges that side slope is in stable state;If statistic F is greater than confidence system Number is the t test value under α, then judges the exception of Slope Sliding amount caused by thus separate explosion.
CN201810871259.1A 2018-08-02 2018-08-02 mine slope slip stability monitoring and early warning method Active CN108922123B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810871259.1A CN108922123B (en) 2018-08-02 2018-08-02 mine slope slip stability monitoring and early warning method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810871259.1A CN108922123B (en) 2018-08-02 2018-08-02 mine slope slip stability monitoring and early warning method

Publications (2)

Publication Number Publication Date
CN108922123A true CN108922123A (en) 2018-11-30
CN108922123B CN108922123B (en) 2019-12-17

Family

ID=64394500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810871259.1A Active CN108922123B (en) 2018-08-02 2018-08-02 mine slope slip stability monitoring and early warning method

Country Status (1)

Country Link
CN (1) CN108922123B (en)

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109781056A (en) * 2018-12-30 2019-05-21 广州海达安控智能科技有限公司 Deformation measurement data methods of exhibiting and storage medium based on internal displacement
CN109782275A (en) * 2019-03-14 2019-05-21 中国电建集团成都勘测设计研究院有限公司 The reference point check system and method for GNSS deformation monitoring
CN110017170A (en) * 2019-04-09 2019-07-16 中国华冶科工集团有限公司 The prevention and control method of underground ore extraction underground hazard
CN110309525A (en) * 2019-03-22 2019-10-08 北京北科安地科技发展有限公司 A kind of side slope geometric distortion and destroy trend calculation method
CN110826141A (en) * 2019-11-29 2020-02-21 广西路桥工程集团有限公司 Low-cost automatic test method for tower linear type and application test system thereof
CN111239254A (en) * 2020-02-12 2020-06-05 青岛理工大学 Rock mass damage monitoring method in rock foundation pit excavation process
CN111931345A (en) * 2020-07-09 2020-11-13 西南交通大学 Monitoring data prediction method, device, equipment and readable storage medium
CN112435486A (en) * 2020-11-13 2021-03-02 辽宁工程技术大学 Automatic monitoring and alarming method and device for landslide and rockfall of road and railway side slopes
CN113096360A (en) * 2021-04-21 2021-07-09 贵州大学 Novel slope fixing monitoring early warning device and analysis monitoring method
CN114117668A (en) * 2021-11-19 2022-03-01 神华准格尔能源有限责任公司 Method for accelerating landslide of strip mine by arranging step pre-buried explosive
CN115376284A (en) * 2022-08-23 2022-11-22 辽宁工程技术大学 Landslide identification and landslide early warning method based on surface and deep displacement monitoring

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000045679A (en) * 1998-07-28 2000-02-15 Ohbayashi Corp Heading collapse alarming system
CN102509420A (en) * 2011-10-12 2012-06-20 北京科技大学 Landslide forecast method based on deformation information of critical-sliding area
TW201317948A (en) * 2011-10-27 2013-05-01 Univ Ching Yun Slope displacement monitoring and early warning system
CN103366512A (en) * 2013-06-28 2013-10-23 华北水利水电大学 Slope instability forecasting method based on equal-dimensional innovation epitaxial model
CN105844859A (en) * 2016-04-19 2016-08-10 南京南瑞集团公司 Highway dangerous rock wireless monitoring and early-warning system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000045679A (en) * 1998-07-28 2000-02-15 Ohbayashi Corp Heading collapse alarming system
CN102509420A (en) * 2011-10-12 2012-06-20 北京科技大学 Landslide forecast method based on deformation information of critical-sliding area
TW201317948A (en) * 2011-10-27 2013-05-01 Univ Ching Yun Slope displacement monitoring and early warning system
CN103366512A (en) * 2013-06-28 2013-10-23 华北水利水电大学 Slope instability forecasting method based on equal-dimensional innovation epitaxial model
CN105844859A (en) * 2016-04-19 2016-08-10 南京南瑞集团公司 Highway dangerous rock wireless monitoring and early-warning system

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109781056A (en) * 2018-12-30 2019-05-21 广州海达安控智能科技有限公司 Deformation measurement data methods of exhibiting and storage medium based on internal displacement
CN109782275A (en) * 2019-03-14 2019-05-21 中国电建集团成都勘测设计研究院有限公司 The reference point check system and method for GNSS deformation monitoring
CN110309525A (en) * 2019-03-22 2019-10-08 北京北科安地科技发展有限公司 A kind of side slope geometric distortion and destroy trend calculation method
CN110017170A (en) * 2019-04-09 2019-07-16 中国华冶科工集团有限公司 The prevention and control method of underground ore extraction underground hazard
CN110826141B (en) * 2019-11-29 2022-09-02 广西路桥工程集团有限公司 Low-cost automatic test method for tower linear type and application test system thereof
CN110826141A (en) * 2019-11-29 2020-02-21 广西路桥工程集团有限公司 Low-cost automatic test method for tower linear type and application test system thereof
CN111239254A (en) * 2020-02-12 2020-06-05 青岛理工大学 Rock mass damage monitoring method in rock foundation pit excavation process
CN111931345A (en) * 2020-07-09 2020-11-13 西南交通大学 Monitoring data prediction method, device, equipment and readable storage medium
CN111931345B (en) * 2020-07-09 2021-11-02 西南交通大学 Monitoring data prediction method, device, equipment and readable storage medium
CN112435486A (en) * 2020-11-13 2021-03-02 辽宁工程技术大学 Automatic monitoring and alarming method and device for landslide and rockfall of road and railway side slopes
CN113096360A (en) * 2021-04-21 2021-07-09 贵州大学 Novel slope fixing monitoring early warning device and analysis monitoring method
CN113096360B (en) * 2021-04-21 2022-09-23 贵州大学 Novel analysis monitoring method for slope fixing monitoring
CN114117668A (en) * 2021-11-19 2022-03-01 神华准格尔能源有限责任公司 Method for accelerating landslide of strip mine by arranging step pre-buried explosive
CN115376284A (en) * 2022-08-23 2022-11-22 辽宁工程技术大学 Landslide identification and landslide early warning method based on surface and deep displacement monitoring
CN115376284B (en) * 2022-08-23 2023-08-18 辽宁工程技术大学 Sliding surface identification and landslide early warning method based on surface and deep displacement monitoring

Also Published As

Publication number Publication date
CN108922123B (en) 2019-12-17

Similar Documents

Publication Publication Date Title
CN108922123A (en) Mine slope slip stability monitoring and early warning method
CN101477207B (en) Intelligent geological calamity synthetic monitoring system and multi-stage prediction analysis method
CN102736124B (en) Tunnel excavation surrounding rock dynamic refined classification method based on integrated parameters
CN110517794A (en) A method of that establishes shale gas reservoir buries-thermal evolution history figure
CN101629799B (en) Non-intervisibility high and steep side slope deformation monitoring method and device thereof
CN106679582B (en) A kind of dynamic monitoring system and its monitoring method of the ship lock back rod based on strain
CN102102533A (en) Method for forecasting real-time measurement of spatial geometrical information of coal rock dynamic disaster
CN111442728B (en) Tunnel rock stratum multipoint displacement synchronous monitoring method based on remote sensing technology
CN112903008B (en) Mountain landslide early warning method based on multi-sensing data fusion technology
CN104483700B (en) Formation fracture is monitored and early warning system and method
Liu et al. Current profile analysis and extreme value prediction in the LH11-1 oil field of the South China Sea based on prototype monitoring
CN107990881B (en) Pile machine construction positioning method based on measuring robot
CN206223144U (en) A kind of monitoring device of the tunnel vault sedimentation based on ultrasonic range finder
CN103472207A (en) Equivalent looseness measuring method used for mountain landslide early warning
CN106777556B (en) Space analysis method for evaluating stable state of side slope in excavation period
CN201540087U (en) Non-visibility deformation monitoring device for high inclination slope
CN105222885A (en) Optical fiber vibration detection method and device
CN109709352A (en) Method for judging and in-situ adjusting monitoring accuracy of underground coal mine wind speed sensor
CN109323684A (en) A kind of inclination measurement system and its tilt measurement
CN112767656B (en) Open mine landslide disaster early warning method and system
CN103954197A (en) Roadway surface displacement and deep displacement same-position measurement method
CN203083557U (en) Monitoring instrument for tunnel bottom void passing through ground fissure zone
Li et al. Tailings dam breach disaster on-line monitoring method and system realization
CN108133582B (en) A kind of important accident alarming method for positioning analyzing for distributed sensing system
CN113090330A (en) Coal mine underground operation safety real-time monitoring and early warning method based on wireless sensor technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Zhang Yongjun

Inventor after: Bao Fangge

Inventor after: Chen Lijun

Inventor after: Liu Sijia

Inventor after: Peng Jun

Inventor after: Wang Qingsong

Inventor after: Yang Dengfeng

Inventor after: Wang Wen

Inventor after: Li Wentao

Inventor after: Ma Qiangqiang

Inventor before: Zhang Yongjun

Inventor before: Liu Sijia

Inventor before: Yang Dengfeng

Inventor before: Wang Wen

Inventor before: Li Wentao

Inventor before: Ma Qiangqiang

Inventor before: Bao Fangge

CB03 Change of inventor or designer information
TR01 Transfer of patent right

Effective date of registration: 20231102

Address after: No.777, Jialingjiang Road, Huangdao District, Qingdao City, Shandong Province

Patentee after: Qingdao University of Technology

Patentee after: MAANSHAN Mine Research Institute Co.,Ltd.

Patentee after: CHINA RAILWAY 19 BUREAU GROUP MINING INVESTMENT Co.,Ltd.

Patentee after: CHINA RAILWAY 20 BUREAU Group Corp.

Address before: No. 11, Fushun Road, North District, Qingdao, Shandong

Patentee before: Qingdao University of Technology

TR01 Transfer of patent right