CN108875967A - A kind of distribution network failure processing method - Google Patents
A kind of distribution network failure processing method Download PDFInfo
- Publication number
- CN108875967A CN108875967A CN201810561771.6A CN201810561771A CN108875967A CN 108875967 A CN108875967 A CN 108875967A CN 201810561771 A CN201810561771 A CN 201810561771A CN 108875967 A CN108875967 A CN 108875967A
- Authority
- CN
- China
- Prior art keywords
- distribution network
- record
- practical operation
- simulated
- grid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/20—Administration of product repair or maintenance
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
- G06Q50/06—Electricity, gas or water supply
Abstract
A kind of distribution network failure processing method provided by the invention, it is intended to solve distribution network failure in the prior art and exclude difficult, the technical problem easy to operate by mistake in debugging.A kind of distribution network failure processing method disclosed by the invention, after power distribution network branch breaks down, the grid branch to break down is first identified in grid monitoring system, then, the simulated operation debugged in grid monitoring system, practical operation is carried out to power distribution network again after simulated operation, to exclude the failure in power distribution network.Simulated operation record is generated in simulated operation, practical operation record is generated in practical operation, finally by simulated operation record and practical operation Document Solution, in favor of the subsequent access of related personnel.Due to first carrying out simulated operation before actually debugging in this method, the program be can be effectively avoided when excluding electric network fault to controller switching equipment maloperation, and electric network fault excludes convenient.
Description
Technical field
The present invention relates to power distribution network operating method more particularly to a kind of distribution network failure processing methods.
Background technique
Power distribution network is the infrastructure for conveying electric energy.With the increase of power distribution network area coverage, applied in power distribution network
Controller switching equipment is more and more, and the maintenance work of power distribution network also becomes increasingly complex.Especially be incorporated in power distribution network micro power network with
Afterwards, the attended operation of power distribution network becomes more complicated.Micro power network refers to small hydropower station, solar power plant etc..
After the branch of power distribution network breaks down in the prior art, directly related controller switching equipment is grasped by maintenance personnel
Make, debugging.This operating method can satisfy maintenance needs for relatively simple power distribution network.But for more
Complicated power distribution network only is difficult correctly to tie up power grid since controller switching equipment is more, circuit is complicated with the experience of maintenance personnel
Shield operation is easy to cause related controller switching equipment maloperation distribution network failure to exclude difficult skill when excluding electric network fault
Art problem.
Summary of the invention
A kind of distribution network failure processing method provided by the invention, it is intended to solve distribution network failure in the prior art and exclude to be stranded
Difficulty, the technical problem easy to operate by mistake in debugging.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme that:A kind of distribution network failure processing method, packet
Include following steps:
Step 10:The grid branch to break down is identified in grid monitoring system;
Step 20:Operation of power networks figure in modification grid monitoring system obtains power grid actual motion figure, power grid actual motion
Figure and power grid actual motion state consistency;
Step 30:The simulated operation debugged on power grid actual motion figure, and record simulated operation generation
Simulated operation record;
Step 40:Practical operation debugging is carried out to power grid according to simulated operation record, also, to the practical behaviour of power grid
As when record the actual mechanical process generate practical operation record;
Step 50:The practical operation record that the simulated operation record that step 30 generates is generated with step 40 is associated in one
It rises, and the simulated operation after association is recorded, practical operation Document Solution.
A kind of distribution network failure processing method disclosed by the invention, after power distribution network branch breaks down, first in power system monitor
The grid branch to break down is identified in system, then, the simulated operation debugged in grid monitoring system, simulation
Practical operation is carried out to power distribution network again after end of operation, to exclude the failure in power distribution network.Simulation behaviour is generated in simulated operation
It notes down, practical operation record is generated in practical operation, finally by simulated operation record and practical operation Document Solution, with benefit
In the subsequent access of related personnel.Due to first carrying out simulated operation before actually debugging in this method, the program can be effective
Ground is avoided when excluding electric network fault to controller switching equipment maloperation, and electric network fault excludes convenient.
A kind of optional scheme marks related distribution in the step 10 while the grid branch that mark breaks down
The protection act of equipment, failure are separate, reclosing acts.
The state of related controller switching equipment is identified and is conducive to subsequent operation and analysis, improves the row of distribution network failure
Except efficiency.
A kind of optional scheme, the simulated operation in the step 30 are recorded as video file, and simulated operation record generates
After solidification simulation operation note.
Video file is easy to generate, and, it is not easy to it is modified, improves the accuracy of simulated operation record.To simulation
Operation note is solidified, and can be effectively prevented other personnel and be modified simulated operation record, further improve simulated operation
The accuracy of record.
A kind of optional scheme is completed when in the step 40 to power grid practical operation by least two operators practical
Operation, wherein an operator carries out practical operation to power grid, other operators carry out record life to actual mechanical process
It is recorded at practical operation, practical operation is recorded as video file, and practical operation record solidifies practical operation record after generating.
Be conducive to the practical operation of operator, also, be conducive to the generation of practical operation record.Practical operation records quilt
Related personnel can be effectively avoided after solidification and modify practical operation record, improve the accuracy of practical operation record.
A kind of optional scheme is grasped to after simulated operation record, practical operation Document Solution by filing in the step 50
Make personnel's signature.
Be conducive to subsequent personnel to consult.
Compared with prior art, a kind of distribution network failure processing method provided by the invention, has the following advantages that:In power grid
Branch first identifies the grid branch to break down on grid monitoring system after breaking down, then, on grid monitoring system
The simulated operation debugged, and simulated operation record is generated, finally power distribution network is grasped according to simulated operation record
Make, with debugging.The program efficiently avoids improving power distribution network to power distribution network maloperation when excluding distribution network failure
The exclusion efficiency of failure.
Specific embodiment
A kind of distribution network failure processing method of the invention is described further below.Following embodiment is only used for helping
Those skilled in the art understand that it is of the invention, it is not limitation of the present invention.
A kind of distribution network failure processing method, the program are suitable for after power distribution network breaks down, and exclude distribution network failure,
Operate normally power distribution network.The distribution network failure processing method includes the following steps:
Step 10:The grid branch to break down is identified in grid monitoring system, in the power grid branch that mark breaks down
Mark that the protection act of related controller switching equipment, failure be separate, reclosing movement while road, grid monitoring system can be distribution
Automated system, or other systems with monitoring operation of power networks status function, grid monitoring system is the prior art,
Not reinflated narration herein;
Step 20:Operation of power networks figure in modification grid monitoring system obtains power grid actual motion figure, power grid actual motion
Figure and power grid actual motion state consistency, this step is mainly by the grid branch to break down and relevant controller switching equipment in electricity
Corresponding operation is carried out in net monitoring system, so that the operation of power networks figure in grid monitoring system and power grid actual motion state one
It causes, so that related personnel excludes distribution network failure;
Step 30:The simulated operation debugged on power grid actual motion figure, and record simulated operation generation
Simulated operation record;
Simulated operation record can be video file, and simulated operation records solidification simulation operation note after generation, with
It avoids simulated operation record from being modified, improves the accuracy of simulated operation record, avoid the mistake in subsequent exclusion electric network fault
Operation;
Simulated operation is operated in grid monitoring system, automatically generates simulated operation record by grid monitoring system;
Step 40:Practical operation debugging is carried out to power grid according to simulated operation record, also, to the practical behaviour of power grid
As when record the actual mechanical process generate practical operation record;
Practical operation is completed by least two operators when to power grid practical operation, wherein an operator is to power grid
Practical operation is carried out, other operators carry out record to actual mechanical process and generate practical operation record, practical operation record
It can be video file, practical operation record solidifies practical operation record after generating, repaired to avoid practical operation record
Change, is conducive to the subsequent access of related personnel;
Step 50:The practical operation record that the simulated operation record that step 30 generates is generated with step 40 is associated in one
It rises, and the simulated operation after association is recorded, practical operation Document Solution;
It is signed to after simulated operation record, practical operation Document Solution by archive operation personnel.Simulated operation record and reality
Border operation note is associated together, and is conducive to the subsequent access of related personnel.
Simulated operation record, practical operation record can be associated according to the fault type of power distribution network, alternatively, simulation behaviour
It notes down, practical operation record can also be associated according to fault time.
Section Example of the invention is described in detail above.After those skilled in the art read this specification,
It based on technical solution of the present invention, can modify to above-described embodiment, these modifications still fall within protection scope of the present invention.
Claims (5)
1. a kind of distribution network failure processing method, which is characterized in that include the following steps:
Step 10:The grid branch to break down is identified in grid monitoring system;
Step 20:Operation of power networks figure in modification grid monitoring system obtains power grid actual motion figure, power grid actual motion figure with
Power grid actual motion state consistency;
Step 30:The simulated operation debugged on power grid actual motion figure, and record the simulated operation and generate simulation
Operation note;
Step 40:Practical operation debugging is carried out to power grid according to simulated operation record, also, when to power grid practical operation
It records the actual mechanical process and generates practical operation record;
Step 50:The practical operation record that the simulated operation record that step 30 generates is generated with step 40 is associated together, and
By simulated operation record, the practical operation Document Solution after association.
2. a kind of distribution network failure processing method according to claim 1, it is characterised in that:It is being identified in the step 10
Mark that the protection act of related controller switching equipment, failure be separate, reclosing movement while the grid branch to break down.
3. a kind of distribution network failure processing method according to claim 1, it is characterised in that:Simulation in the step 30
Operation note is video file, solidification simulation operation note after simulated operation record generates.
4. a kind of distribution network failure processing method according to claim 1, it is characterised in that:To power grid in the step 40
Practical operation is completed by least two operators when practical operation, wherein an operator carries out practical operation to power grid,
Other operators carry out record to actual mechanical process and generate practical operation record, and practical operation is recorded as video file, real
Border operation note solidifies practical operation record after generating.
5. a kind of distribution network failure processing method according to claim 1, it is characterised in that:To simulation in the step 50
It is signed after operation note, practical operation Document Solution by archive operation personnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810561771.6A CN108875967A (en) | 2018-06-04 | 2018-06-04 | A kind of distribution network failure processing method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810561771.6A CN108875967A (en) | 2018-06-04 | 2018-06-04 | A kind of distribution network failure processing method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108875967A true CN108875967A (en) | 2018-11-23 |
Family
ID=64336268
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810561771.6A Pending CN108875967A (en) | 2018-06-04 | 2018-06-04 | A kind of distribution network failure processing method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108875967A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110716449A (en) * | 2019-10-21 | 2020-01-21 | 上海科梁信息工程股份有限公司 | Control method and system for simulation power grid, electronic device and storage medium |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101958536A (en) * | 2010-09-20 | 2011-01-26 | 中国电力科学研究院 | Distribution network failure isolation and quick power service restoration decision support system |
CN102751785A (en) * | 2012-05-21 | 2012-10-24 | 中国电力科学研究院 | Modularization sequential control system and realization method thereof |
CN105184442A (en) * | 2015-07-23 | 2015-12-23 | 国网青海省电力公司西宁供电公司 | Power distribution network dispatching management statistical analysis system |
AU2017100148A4 (en) * | 2017-02-08 | 2017-03-09 | Macau University Of Science And Technology | A system, method, computer program and data signal for fault detection and recovery of a network |
-
2018
- 2018-06-04 CN CN201810561771.6A patent/CN108875967A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101958536A (en) * | 2010-09-20 | 2011-01-26 | 中国电力科学研究院 | Distribution network failure isolation and quick power service restoration decision support system |
CN102751785A (en) * | 2012-05-21 | 2012-10-24 | 中国电力科学研究院 | Modularization sequential control system and realization method thereof |
CN105184442A (en) * | 2015-07-23 | 2015-12-23 | 国网青海省电力公司西宁供电公司 | Power distribution network dispatching management statistical analysis system |
AU2017100148A4 (en) * | 2017-02-08 | 2017-03-09 | Macau University Of Science And Technology | A system, method, computer program and data signal for fault detection and recovery of a network |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110716449A (en) * | 2019-10-21 | 2020-01-21 | 上海科梁信息工程股份有限公司 | Control method and system for simulation power grid, electronic device and storage medium |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104155970B (en) | A kind of intelligent substation monitoring host computer closed loop test system and method for testing thereof | |
CN104360228B (en) | Method for improving positioning of fault section of power distribution network including distributed power supply through directional elements | |
CN106026087B (en) | Fault scenes analogy method containing distributed power distribution network | |
CN103607042B (en) | The distribution network failure processing method of long fault indicator for overhead lines towards outskirts of a town | |
CN103427417A (en) | Power distribution network fault processing method based on multi-source information fusion | |
CN101871988A (en) | System and method for positioning medium voltage distribution network using power line carrier communication | |
CN109521348A (en) | A kind of reliability test of dc circuit breaker IGBT module and lifetime estimation method | |
CN102680833A (en) | Load monitoring method and system for medium-voltage line in power distribution network | |
CN105576660A (en) | Region power distribution network on-line simulation analysis device and system | |
CN110989562A (en) | Testing system and method of valve control system | |
CN104242467A (en) | Intelligent self-healing controlling method of feeder line of distribution network | |
CN103401316A (en) | Integrated type monitoring and processing method for state data of intelligent power network equipment | |
CN108875967A (en) | A kind of distribution network failure processing method | |
CN104297676B (en) | Method, device and system for monitoring circuit breaker of wind generating set | |
CN106532692B (en) | A kind of static security analysis method and device of area power grid meter and prepared auto restart | |
CN104951884A (en) | Visual display method of accident emergency repair and inversion based on distribution network | |
CN103679546A (en) | N-1 calculating method for combined calculation of main networks and distribution networks and automatic spare-power switching actions | |
CN109149534B (en) | Method for rapidly diagnosing topological fault of power grid model based on DTS virtual switch | |
CN102508053B (en) | Area backup automatic switch testing system based on digital simulation technology | |
CN104377729A (en) | Reverse power protection method applicable to self-generation self-use grid-connection mode distributed photovoltaic power station | |
CN110189575A (en) | A kind of distribution O&M simulation training system based on big data | |
CN103235224B (en) | Grid fault analytical method | |
CN102832717A (en) | Closed-loop control method of power scheduling operation order and ground wire operation | |
CN106487004A (en) | Intelligent substation one electrical secondary system runs hidden danger Intelligent drainage checking method | |
CN116206499A (en) | Power equipment scene simulation method and device for power grid maintenance training |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181123 |
|
RJ01 | Rejection of invention patent application after publication |