CN108868744A - A kind of multistage pressure break horizontal well production profile real-time testing system and test method - Google Patents

A kind of multistage pressure break horizontal well production profile real-time testing system and test method Download PDF

Info

Publication number
CN108868744A
CN108868744A CN201810715214.5A CN201810715214A CN108868744A CN 108868744 A CN108868744 A CN 108868744A CN 201810715214 A CN201810715214 A CN 201810715214A CN 108868744 A CN108868744 A CN 108868744A
Authority
CN
China
Prior art keywords
horizontal well
well
water cut
signal amplifier
test
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810715214.5A
Other languages
Chinese (zh)
Inventor
朱洪征
吕亿明
周志平
黄伟
常莉静
甘庆明
王百
崔文昊
苏祖波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Petroleum and Natural Gas Co Ltd
Original Assignee
China Petroleum and Natural Gas Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Petroleum and Natural Gas Co Ltd filed Critical China Petroleum and Natural Gas Co Ltd
Priority to CN201810715214.5A priority Critical patent/CN108868744A/en
Publication of CN108868744A publication Critical patent/CN108868744A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/12Means for transmitting measuring-signals or control signals from the well to the surface, or from the surface to the well, e.g. for logging while drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B49/00Testing the nature of borehole walls; Formation testing; Methods or apparatus for obtaining samples of soil or well fluids, specially adapted to earth drilling or wells
    • E21B49/08Obtaining fluid samples or testing fluids, in boreholes or wells

Abstract

The present invention provides a kind of multistage pressure break horizontal well production profile real-time testing system and test methods, are related to oil extraction in oil field technical field.System includes the pumping system and receiving system that horizontal well straight well section is arranged in, and the test string system being arranged in horizontal well horizontal segment;Pumping system pumps to connected pipes, so that the fluid of different test zones enters corresponding comprehensive water cut flow tester;Every level-one comprehensive water cut flow tester measures the water-contained flow parameter of the fluid of corresponding test zone, and is transmitted to the signal amplifier by multicore cable;Receiving system carries out real-time reception to the water-contained flow parameter at signal amplifier, and obtains the Liquid output and water content of different test zones according to pre-set test plate.As it can be seen that the present invention can solve to use the prior art, and caused by site operation heavy workload, measure long construction period, when leveraging well recovery the problem of the performance of rate and production capacity.

Description

A kind of multistage pressure break horizontal well production profile real-time testing system and test method
Technical field
The present invention relates to one of oil extraction in oil field technical fields more particularly to a kind of oilfield horizontal well exploitation production process Multistage pressure break horizontal well production profile real-time testing system and test method.
Background technique
Currently, Horizontal Well number gradually increases with the extension of oil field development time, during horizontal wells, need It often to test segmentation production profile to grasp underground in time and go out liquid situation, be provided for water injection of horizontal well modification scenario and later period water blockoff Foundation.
When testing at present the especially low liquid measure horizontal well of horizontal well, generally pass through tripping in producing profile testing pipe first Column, ground pumping unit continuous production, upper lifting pipe post takes out tester after test, and playback of data finds out each section of Liquid output, contains The data such as water, pressure and temperature obtain the Liquid output of each test zone and aqueous.Site operation workload in this way Greatly, measure long construction period, the performance of rate and production capacity when leveraging well recovery.
Summary of the invention
The embodiment of the present invention provides a kind of multistage pressure break horizontal well production profile real-time testing system and test method, with Solve site operation heavy workload in the prior art, measure long construction period, rate and production capacity when leveraging well recovery The problem of performance.
In order to achieve the above objectives, the present invention adopts the following technical scheme that:
A kind of multistage pressure break horizontal well production profile real-time testing system, the pumping system including horizontal well straight well section is arranged in System and receiving system, and the test string system being arranged in horizontal well horizontal segment;The test string system includes: Connected pipes, multiple packers, multicore cable, signal amplifier, are oriented to silk plug and give up multistage comprehensive water cut flow tester Connector;Comprehensive water cut flow testers at different levels are arranged on the outside of the tubing string of the connected pipes, so that every level-one comprehensive water cut flow Tester is corresponding with a test zone;The multicore cable concatenates comprehensive water cut flow testers at different levels, and described in connection Signal amplifier;Each packer is by each test zone card Fengkai;What the guiding silk plug was arranged in connected pipes gos deep into horizontal well One that connected pipes are located at the boundary of horizontal well horizontal segment and straight well section is arranged in one end inside horizontal segment, the back-off sub End;One packer is set on the downside of the back-off sub, and the packer on the downside of back-off sub is arranged in the signal amplifier Downside;The pumping system is arranged on the upside of the back-off sub;The receiving system is arranged in pumping system and pit shaft In oil jacket annulus between casing;
The pumping system pumps to connected pipes, contains so that the fluid of different test zones enters corresponding synthesis Water flow tester;
Every level-one comprehensive water cut flow tester measures the water-contained flow parameter of the fluid of corresponding test zone, and leads to Multicore cable transmission is crossed to the signal amplifier;
The receiving system carries out real-time reception to the water-contained flow parameter at signal amplifier, and according to setting in advance The test plate set obtains the Liquid output and water content of different test zones.
Specifically, the pumping system includes screen casing, oil well pump, oil pipe and sucker rod;The screen casing is arranged in pumping system System lower end, the oil well pump and sucker rod are arranged inside the oil pipe;
The sucker rod drives the oil well pump to pump, so that each fluid of horizontal well horizontal segment is under back-off sub Enter the screen casing after the packer top mixing of side, and by oil pumping from oil pipe pumping to ground.
Specifically, the receiving system includes the signal receiver of wire connection;The signal receiver is logical It crosses the wire and transfers to back-off sub upper end, close to the signal amplifier.
Specifically, the packer being arranged on the downside of the back-off sub is Y445 back-off packer in each packer, His each packer is Y441 packer.
A kind of multistage pressure break horizontal well production profile method for real-timely testing produces liquid applied to above-mentioned multistage pressure break horizontal well Section real-time testing system, the method includes:
Multistage comprehensive water cut flow tester is lowered into the horizontal segment of horizontal well by oil pipe, so that every level-one synthesis contains Water flow tester is corresponding with a test zone;
It is suppressed in well mouth oil pipe so that each packer setting is by different test zone cards Fengkai, so that each test layer Section, which is set, puts a comprehensive water cut flow tester;
Continue to suppress in well mouth oil pipe, and operation of giving up is carried out by releasing tool, and after giving up successfully, rises Oil pipe more than back-off sub;
Pumping system is transferred to the straight well section of horizontal well, and opens oil well pump and pumps, so that different test zones Fluid enter corresponding comprehensive water cut flow tester, to measure corresponding water-contained flow parameter, and pass through multicore cable biography Transport to the signal amplifier;
Receiving system is transferred in the oil jacket annulus between pumping system and wellbore casing, signal amplifier is adopted The water-contained flow parameter of collection carries out real-time reception, and obtains the Liquid output of different test zones according to pre-set test plate And water content.
A kind of multistage pressure break horizontal well production profile real-time testing system provided in an embodiment of the present invention and test method are more Section pressure break horizontal well production profile real-time testing system includes that the pumping system that horizontal well straight well section is arranged in and signal receive system System, and the test string system being arranged in horizontal well horizontal segment;It is pumped by pumping system to connected pipes, so that The fluid of different test zones enters corresponding comprehensive water cut flow tester;Every level-one comprehensive water cut flow tester is surveyed later The water-contained flow parameter of the fluid of corresponding test zone is taken, and the signal amplifier is transmitted to by multicore cable;Later, believe Number receiving system carries out real-time reception to the water-contained flow parameter at signal amplifier, and is obtained according to pre-set test plate To the Liquid output and water content of different test zones.As it can be seen that the present invention can be surveyed in real time by multistage pressure break horizontal well production profile Test system carries out the test of convenient and fast production profile, avoids and uses the prior art, and caused by site operation heavy workload, arrange Long construction period is applied, when leveraging well recovery the problem of the performance of rate and production capacity.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention without any creative labor, may be used also for those of ordinary skill in the art To obtain other drawings based on these drawings.
Fig. 1 is that a kind of structure of multistage pressure break horizontal well production profile real-time testing system provided in an embodiment of the present invention is shown It is intended to;
Fig. 2 is a kind of process of multistage pressure break horizontal well production profile method for real-timely testing provided in an embodiment of the present invention Figure.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1, the embodiment of the present invention provides a kind of multistage pressure break horizontal well production profile real-time testing system 10, packet The pumping system 11 and receiving system 12 that horizontal well straight well section 20 is set are included, and is arranged in horizontal well horizontal segment 21 Test string system 13;The test string system 13 includes:Connected pipes 131, multistage comprehensive water cut flow tester 132, multiple packers 133, multicore cable 134, signal amplifier 135, guiding silk plug 136 and back-off sub 137.The connection Comprehensive water cut flow testers 132 at different levels are arranged on the outside of the tubing string of oil pipe 131, so that every level-one comprehensive water cut flow tester 132 is corresponding with a test zone;The multicore cable 134 concatenates comprehensive water cut flow testers 132 at different levels, and connects institute State signal amplifier 135;Each packer 133 is by each test zone card Fengkai;The guiding silk plug 136 is arranged in connected pipes 131 one end goed deep into inside horizontal well horizontal segment, the back-off sub 137, which is arranged, is located at horizontal well water in connected pipes 131 One end of the boundary of flat section and straight well section;One packer 133, the signal amplifier are set on the downside of the back-off sub 137 135 are arranged in the downside of the packer 133 of 137 downside of back-off sub;The pumping system 11 is arranged in the back-off sub 137 Upside;The receiving system 12 is arranged in the oil jacket annulus between pumping system 11 and wellbore casing 22.
The pumping system 11 pumps to connected pipes 131 so that the fluid of different test zone enter it is corresponding comprehensive Close water-contained flow tester 132.
Every level-one comprehensive water cut flow tester 132 measures the water-contained flow parameter of the fluid of corresponding test zone, and The signal amplifier 135 is transmitted to by multicore cable 134.
The receiving system 12 carries out real-time reception to the water-contained flow parameter at signal amplifier 135, and according to pre- The test plate being first arranged obtains the Liquid output and water content of different test zones.
Specifically, as shown in Figure 1, the pumping system 11 includes screen casing 111, oil well pump 112, oil pipe 113 and sucker rod 114;The setting of screen casing 111 is arranged in 11 lower end of pumping system, the oil well pump 112 and sucker rod 114 in the oil pipe 113 It is internal;
The sucker rod 114 drives the oil well pump 112 to pump, so that each fluid of horizontal well horizontal segment is being given up Enter screen casing 111 after 133 top of the packer mixing of the downside of connector 137, and by oil pumping from oil pipe 113 pumping to ground.
Specifically, as shown in Figure 1, the receiving system 12 includes the signal of a wire 121 (such as steel wire) connection Receiver 122.The signal receiver 122 is transferred to give up and be connect by wire 121 by the self gravity of signal receiver 122 First 137 upper end, close to the signal amplifier 135.
Specifically, in each packer 133, the packer 133 being arranged on the downside of the back-off sub 137 is that Y445 gives up packing Device, other each packers 133 are Y441 packer.
Corresponding to above-mentioned multistage pressure break horizontal well production profile real-time testing shown in FIG. 1, as shown in Fig. 2, the present invention is real It applies example and a kind of multistage pressure break horizontal well production profile method for real-timely testing is also provided, produced applied to above-mentioned multistage pressure break horizontal well Liquid section real-time testing system, the method includes:
Step 201, the horizontal segment that multistage comprehensive water cut flow tester is lowered into horizontal well by oil pipe, so that each Grade comprehensive water cut flow tester is corresponding with a test zone.
Step 202 is suppressed in well mouth oil pipe so that each packer setting is by different test zone cards Fengkai, so that often One test zone, which is set, puts a comprehensive water cut flow tester.
Step 203 continues to suppress, and carries out operation of giving up by releasing tool, and giving up into well mouth oil pipe After function, act the oil pipe of back-off sub or more.
Step 204, the straight well section that pumping system is transferred to horizontal well, and open oil well pump and pump, so that different The fluid of test zone enters corresponding comprehensive water cut flow tester, to measure corresponding water-contained flow parameter, and by more Core cable transmission is to the signal amplifier.
Step 205 transfers to receiving system in the oil jacket annulus between pumping system and wellbore casing, to signal The water-contained flow parameter of amplifier acquisition carries out real-time reception, and obtains different test zones according to pre-set test plate Liquid output and water content.
The present invention realizes flow and aqueous test using comprehensive water cut flow tester, in real time using underground segmentation card envelope Understand each test zone of horizontal well and produce liquid information, while not needing well head admission data, greatly reduces site operation workload, Shortening measure long construction period, saves Contraction in Site cost.
A kind of multistage pressure break horizontal well production profile real-time testing system provided in an embodiment of the present invention and test method are more Section pressure break horizontal well production profile real-time testing system includes that the pumping system that horizontal well straight well section is arranged in and signal receive system System, and the test string system being arranged in horizontal well horizontal segment;It is pumped by pumping system to connected pipes, so that The fluid of different test zones enters corresponding comprehensive water cut flow tester;Every level-one comprehensive water cut flow tester is surveyed later The water-contained flow parameter of the fluid of corresponding test zone is taken, and the signal amplifier is transmitted to by multicore cable;Later, believe Number receiving system carries out real-time reception to the water-contained flow parameter at signal amplifier, and is obtained according to pre-set test plate To the Liquid output and water content of different test zones.As it can be seen that the present invention can be surveyed in real time by multistage pressure break horizontal well production profile Test system carries out the test of convenient and fast production profile, avoids and uses the prior art, and caused by site operation heavy workload, arrange Long construction period is applied, when leveraging well recovery the problem of the performance of rate and production capacity.
Specific embodiment is applied in the present invention, and principle and implementation of the present invention are described, above embodiments Explanation be merely used to help understand method and its core concept of the invention;At the same time, for those skilled in the art, According to the thought of the present invention, there will be changes in the specific implementation manner and application range, in conclusion in this specification Appearance should not be construed as limiting the invention.

Claims (5)

1. a kind of multistage pressure break horizontal well production profile real-time testing system, which is characterized in that including being arranged in horizontal well straight well The pumping system and receiving system of section, and the test string system being arranged in horizontal well horizontal segment;The testing tube Column system includes:Connected pipes, multiple packers, multicore cable, signal amplifier, are led at multistage comprehensive water cut flow tester To silk plug and back-off sub;Comprehensive water cut flow testers at different levels are arranged on the outside of the tubing string of the connected pipes, so that every level-one Comprehensive water cut flow tester is corresponding with a test zone;The multicore cable is by comprehensive water cut flow tester strings at different levels It connects, and connects the signal amplifier;Each packer is by each test zone card Fengkai;The guiding silk plug is arranged in connected pipes The one end goed deep into inside horizontal well horizontal segment, the back-off sub, which is arranged, is located at horizontal well horizontal segment and straight well in connected pipes One end of the boundary of section;One packer is set on the downside of the back-off sub, and the signal amplifier is arranged under back-off sub The downside of the packer of side;The pumping system is arranged on the upside of the back-off sub;The receiving system setting is being taken out It draws in the oil jacket annulus between system and wellbore casing;
The pumping system pumps to connected pipes, so that the fluid of different test zones enters corresponding comprehensive water cut stream Tester;
Every level-one comprehensive water cut flow tester measures the water-contained flow parameter of the fluid of corresponding test zone, and by more Core cable transmission is to the signal amplifier;
The receiving system carries out real-time reception to the water-contained flow parameter at signal amplifier, and according to pre-set Test plate obtains the Liquid output and water content of different test zones.
2. multistage pressure break horizontal well production profile real-time testing system according to claim 1, which is characterized in that the pumping The system of drawing includes screen casing, oil well pump, oil pipe and sucker rod;The screen casing is arranged in pumping system lower end, the oil well pump and pumping Beam hanger is arranged inside the oil pipe;
The sucker rod drives the oil well pump to pump, so that each fluid of horizontal well horizontal segment is on the downside of back-off sub Enter the screen casing after the mixing of packer top, and by oil pumping from oil pipe pumping to ground.
3. multistage pressure break horizontal well production profile real-time testing system according to claim 1, which is characterized in that the letter Number reception system includes the signal receiver of wire connection;The signal receiver is transferred to by the wire and is given up Upper end of joint, close to the signal amplifier.
4. multistage pressure break horizontal well production profile real-time testing system according to claim 1, which is characterized in that described each In packer, the packer being arranged on the downside of the back-off sub is Y445 back-off packer, other each packers are Y441 packing Device.
5. a kind of multistage pressure break horizontal well production profile method for real-timely testing, which is characterized in that it is any to be applied to claim 1-4 Multistage pressure break horizontal well production profile real-time testing system described in, the method includes:
Multistage comprehensive water cut flow tester is lowered into the horizontal segment of horizontal well by oil pipe, so that every level-one comprehensive water cut stream Tester is corresponding with a test zone;
It is suppressed in well mouth oil pipe so that each packer setting is by different test zone cards Fengkai, so that each test zone is set Put a comprehensive water cut flow tester;
Continue to suppress in well mouth oil pipe, and operation of giving up is carried out by releasing tool, and after giving up successfully, rises and to give up Oil pipe more than connector;
Pumping system is transferred to the straight well section of horizontal well, and opens oil well pump and pumps, so that the stream of different test zones Body enters corresponding comprehensive water cut flow tester, to measure corresponding water-contained flow parameter, and is transmitted to by multicore cable The signal amplifier;
Receiving system is transferred in the oil jacket annulus between pumping system and wellbore casing, to signal amplifier acquisition Water-contained flow parameter carries out real-time reception, and obtains the Liquid output of different test zones according to pre-set test plate and contain Water.
CN201810715214.5A 2018-07-03 2018-07-03 A kind of multistage pressure break horizontal well production profile real-time testing system and test method Pending CN108868744A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810715214.5A CN108868744A (en) 2018-07-03 2018-07-03 A kind of multistage pressure break horizontal well production profile real-time testing system and test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810715214.5A CN108868744A (en) 2018-07-03 2018-07-03 A kind of multistage pressure break horizontal well production profile real-time testing system and test method

Publications (1)

Publication Number Publication Date
CN108868744A true CN108868744A (en) 2018-11-23

Family

ID=64298391

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810715214.5A Pending CN108868744A (en) 2018-07-03 2018-07-03 A kind of multistage pressure break horizontal well production profile real-time testing system and test method

Country Status (1)

Country Link
CN (1) CN108868744A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201810299U (en) * 2010-09-15 2011-04-27 中国石油天然气股份有限公司 Horizontal well produced fluid cross section tester
CN102747967A (en) * 2012-07-10 2012-10-24 中国石油天然气股份有限公司 Multi-stage segmented release water exploration pipe column and method for casing well completion multi-stage fractured horizontal well
US20130087325A1 (en) * 2011-10-09 2013-04-11 Saudi Arabian Oil Company Method For Real-Time Monitoring and Transmitting Hydraulic Fracture Seismic Events to Surface Using the Pilot Hole of the Treatment Well as the Monitoring Well
US20130087321A1 (en) * 2011-10-09 2013-04-11 Saudi Arabian Oil Company System For Real-Time Monitoring and Transmitting Hydraulic Fracture Seismic Events to Surface Using the Pilot Hole of the Treatment Well as the Monitoring Well
CN103628864A (en) * 2013-11-22 2014-03-12 中国石油天然气股份有限公司 Multi-segment fractured horizontal well intelligent test system and method
CN104100254A (en) * 2013-04-03 2014-10-15 中国石油天然气股份有限公司 Sectional synchronous flow rate and water content monitoring and water exploration tubular column of multi-section fracturing horizontal well and working method thereof
US20140352968A1 (en) * 2013-06-03 2014-12-04 Cameron International Corporation Multi-well simultaneous fracturing system
CN106593422A (en) * 2016-12-01 2017-04-26 中国石油天然气股份有限公司 Storage type test method and pipe column in horizontal well oil pipe
CN206617162U (en) * 2016-12-01 2017-11-07 中国石油天然气股份有限公司 A kind of oil pipe of horizontal well memory storage formula test string

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201810299U (en) * 2010-09-15 2011-04-27 中国石油天然气股份有限公司 Horizontal well produced fluid cross section tester
US20130087325A1 (en) * 2011-10-09 2013-04-11 Saudi Arabian Oil Company Method For Real-Time Monitoring and Transmitting Hydraulic Fracture Seismic Events to Surface Using the Pilot Hole of the Treatment Well as the Monitoring Well
US20130087321A1 (en) * 2011-10-09 2013-04-11 Saudi Arabian Oil Company System For Real-Time Monitoring and Transmitting Hydraulic Fracture Seismic Events to Surface Using the Pilot Hole of the Treatment Well as the Monitoring Well
CN102747967A (en) * 2012-07-10 2012-10-24 中国石油天然气股份有限公司 Multi-stage segmented release water exploration pipe column and method for casing well completion multi-stage fractured horizontal well
CN104100254A (en) * 2013-04-03 2014-10-15 中国石油天然气股份有限公司 Sectional synchronous flow rate and water content monitoring and water exploration tubular column of multi-section fracturing horizontal well and working method thereof
US20140352968A1 (en) * 2013-06-03 2014-12-04 Cameron International Corporation Multi-well simultaneous fracturing system
CN103628864A (en) * 2013-11-22 2014-03-12 中国石油天然气股份有限公司 Multi-segment fractured horizontal well intelligent test system and method
CN106593422A (en) * 2016-12-01 2017-04-26 中国石油天然气股份有限公司 Storage type test method and pipe column in horizontal well oil pipe
CN206617162U (en) * 2016-12-01 2017-11-07 中国石油天然气股份有限公司 A kind of oil pipe of horizontal well memory storage formula test string

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
CHAO ZHENG: "Numerical simulation of the conveyance characteristics of fracturing ball in the horizontal section", 《JOURNAL OF NATURAL GAS SCIENCE AND ENGINEERING》 *
翟庆红: "一趟管柱多段压裂完井工艺技术", 《采油工程文集》 *

Similar Documents

Publication Publication Date Title
CN105114061B (en) A kind of horizontal well fixed tubular column Multi-parameter Combined Tool tests quick searching pipe column and method
CN201273188Y (en) Integrated water exploration pipe column of casing tube well-completion horizontal well
CN106050201B (en) Downhole flow, the cable-free type layered water injection method that pressure and temperature monitors can be achieved
CN103075143B (en) Method for testing fluid-producing section of horizontal pump well
CN108104801A (en) A kind of horizontal well tracer producing profile testing tubing string and method
CN202596684U (en) Testing process pipe column for casing pipe well completion horizontal well multistage subsection production and water detection
CN107795304B (en) A kind of multilayer is same to adopt tubing string and its application method
CN105507865A (en) Re-fracturing method for oil, gas and water wells
CN110284876A (en) A kind of method and apparatus carrying out multiple water-bearing layer bailing tests in single gun drilling
US20110241897A1 (en) System and method for real time data transmission during well completions
CN107725013A (en) A kind of method that zonal testing and oil production by layer connection is made
CN102852490A (en) High gas suction and discharge process method for complex well
CN106014379A (en) Layered simultaneous production testing string
CN104100254A (en) Sectional synchronous flow rate and water content monitoring and water exploration tubular column of multi-section fracturing horizontal well and working method thereof
CN202152643U (en) Layering production pressure measuring tubular column for exploiting oil wells in multilayer mode
CN204804820U (en) Dynamic logging technology pole tubular column is carried to horizontal well pole pipe
CN201620785U (en) Pressure-controlled hydraulic pushing tool
CN104420836B (en) Horizontal well in segments setting type well head discharge method searching pipe column and its groundwater prospecting method
CN205445599U (en) Two single deck tape -recorder technology tubular columns that seal of spike agent water detection are annotated to high moisture horizontal well
CN107339096A (en) A kind of quick groundwater prospecting method of horizontal well
CN204804819U (en) Dynamic logging technology pole tubular column is carried to horizontal well pole
CN108868744A (en) A kind of multistage pressure break horizontal well production profile real-time testing system and test method
CN205225206U (en) A pumping device for beam -pumping unit well surveying well
CN105386743A (en) Swabbing device for well logging of rod pumped well and well logging method based on device
CN104481527B (en) Sectional sampling control method under a kind of Horizontal Well

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181123