CN201273188Y - Integrated water exploration pipe column for casing well completion horizontal well - Google Patents
Integrated water exploration pipe column for casing well completion horizontal well Download PDFInfo
- Publication number
- CN201273188Y CN201273188Y CNU2008201228509U CN200820122850U CN201273188Y CN 201273188 Y CN201273188 Y CN 201273188Y CN U2008201228509 U CNU2008201228509 U CN U2008201228509U CN 200820122850 U CN200820122850 U CN 200820122850U CN 201273188 Y CN201273188 Y CN 201273188Y
- Authority
- CN
- China
- Prior art keywords
- oil
- oil pipe
- packer
- centralizer
- pipe
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title abstract description 21
- 238000000605 extraction Methods 0.000 claims abstract description 21
- 239000003129 oil well Substances 0.000 claims abstract description 10
- 238000012360 testing method Methods 0.000 abstract description 14
- 238000004519 manufacturing process Methods 0.000 abstract description 11
- 238000000034 method Methods 0.000 abstract description 7
- 238000005086 pumping Methods 0.000 abstract description 5
- 238000011084 recovery Methods 0.000 abstract description 5
- 238000007789 sealing Methods 0.000 abstract description 3
- 230000008878 coupling Effects 0.000 abstract 6
- 238000010168 coupling process Methods 0.000 abstract 6
- 238000005859 coupling reaction Methods 0.000 abstract 6
- 239000010985 leather Substances 0.000 abstract 1
- 238000001514 detection method Methods 0.000 description 18
- 239000012530 fluid Substances 0.000 description 6
- 238000012856 packing Methods 0.000 description 3
- 238000010276 construction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 235000020681 well water Nutrition 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 239000000126 substance Substances 0.000 description 1
- 239000002349 well water Substances 0.000 description 1
Images
Landscapes
- Earth Drilling (AREA)
Abstract
The integrated water exploration pipe column of the casing well completion horizontal well is applied to water exploration of an oil well in an oil field. Mainly by oil recovery pump, safety joint, coupling chamfer oil pipe, switch, centralizer and packer and direction plug are constituteed, oil pipe sub-unit connection has the oil recovery pump, oil recovery pump sub-unit connection safety joint, and the safety joint sub-unit connection has oil pipe, and oil pipe is connected to the horizontal segment of oil well, and the characteristic is: in the horizontal well section, the lower end of the oil pipe is connected with a coupling chamfer oil pipe, the lower end of the coupling chamfer oil pipe is sequentially connected with a switch, the coupling chamfer oil pipe, a centralizer, a packer and the coupling chamfer oil pipe, and the lowest end of the coupling chamfer oil pipe is connected with a guide screw plug. The effect is as follows: the water exploration test and the oil production are integrated. The bridge oil extraction pump is adopted in the oil pumping process, so that the load under the pump is borne by the bridge plug-in part, and the pump barrel is not loaded; a self-sealing leather cup packer is adopted, and the setting does not need to be pressed; the switch is automatically switched on and off, and underground layer changing is realized without passing through the ground.
Description
Technical field
The utility model relates to oil recovery technique field, oil field, and particularly oil well water detection technology is the process pipe string of a kind of cased hole completion net horizontal section water detection.
Background technology
At present, the oil well searching pipe column only is applicable to straight well, directional well.Oil well intelligent method zonal testing water detection process pipe string has two classes at present.
One class is that production test is the back throwing valve tubing string of one, one-trip string can be finished the water detection test, is to be connected and composed from top to bottom by tubing pump, back throwing valve, telescoping tube, one-level packer, one-level water detection tester, secondary packer, secondary water detection tester, three grades of packers, three grades of water detection testers, level Four packer, level Four water detection tester and plugs.This class tubing string adopts fluid pressure type ZPY341 packer, back to throw faner apparatus and tubing pump, need suppress behind the following intact tubing string to set.Because the special construction of horizontal well, if be used for horizontal well water detection, multistage packing can't be verified in the horizontal segment sealing, tests back deblocking difficulty and easily causes down-hole accident, and load causes the tubing pump operational failure than conference under the pump simultaneously.
Another kind ofly be made up of pumping pipe string and test string two parts, need down twice tubing string to finish, beat hydraulic pressure from oil pipe behind the following intact operating tool string to make packer setting, and then pitching is to back-off sub, pressurization realizes that tubing string gives up again.Trip out and be lowered to pump behind the operating tool string and take out flow string, oil well drops into ordinary production then.Test string adopts the Y341 packer to realize the card layer by giving up, look for Packer for blocking water, intelligent switch and setting ball seat to constitute.Because the special construction of horizontal well, be used for net horizontal section and can occur multistage packing sealing equally and can't verify the deblocking difficulty.
Summary of the invention
The purpose of this utility model is: provide a kind of cased hole completion horizontal well integrated searching pipe column, realize that one-trip string is finished cased hole completion horizontal well in segments water detection test and oil recovery is produced.
The technical solution adopted in the utility model is: the integrated searching pipe column of cased hole completion horizontal well mainly is made up of oil extraction pump, safety joint, box cupling chamfering oil pipe, derailing switch, centralizer and packer and guiding plug, the oil pipe bottom is connected with oil extraction pump, oil extraction pump bottom attachment security joint, the safety joint bottom is connected with oil pipe, and oil pipe is connected to the horizontal segment of oil well.It is characterized in that: at net horizontal section, the lower end of oil pipe connects box cupling chamfering oil pipe, and box cupling chamfering oil pipe lower end is connected with derailing switch, box cupling chamfering oil pipe, centralizer and packer, box cupling chamfering oil pipe in turn, is connected with the guiding plug bottom.
The quantity of described derailing switch is three, and the quantity of centralizer and packer is two, between per two derailing switches a centralizer and packer is arranged.
The quantity of described derailing switch is four, and the quantity of centralizer and packer is three, between per two derailing switches a centralizer and packer is arranged.
Described oil extraction pump is the gap bridge oil extraction pump, and the centralizer of employing and packer are brake pad centralizer and cup packer, and the position of centralizer and packer is between per two perforated intervals of horizontal case.
The integrated searching pipe column of cased hole completion horizontal well can be finished horizontal well in segments water detection test, and behind the following intact tubing string, cup packer directly leaves each perforated interval card, need not suppress the seat envelope; Then, start the production test of pumping continuously of ground oil pumper.The plug-in carrying of passing a bridge of gap bridge oil extraction pump, the pump barrel of oil extraction pump is not subjected to load.
Before tubing string is gone into the well, according to the testing time of each section corresponding derailing switch switch acquisition time is set on ground.Well operations under the searching pipe column, the derailing switch of first section water detection correspondence is in opening, and other derailing switch is a closed condition, and first section output liquid is pumped into ground by the gap bridge oil extraction pump, thereby obtains individual layer production fluid amount, data such as moisture.To closing of fixed time first section water detection correspondence, first section water detection finishes.Second section derailing switch opened on schedule automatically, runs to the predetermined shut-in time to close the creation data that this time period admission is second section automatically.Can obtain each section production fluid amount, data such as moisture successively respectively.
The beneficial effects of the utility model: the integrated searching pipe column water detection test of the utility model cased hole completion horizontal well is one with the production of recovering the oil, and one-trip string can be finished cased hole completion horizontal well in segments water detection test and recover the oil and produce.Oil pumping process adopts the gap bridge oil extraction pump, makes that load is by the plug-in carrying of passing a bridge under the pump, and pump barrel is not subjected to load, has guaranteed the normal pumping of oil well pump.The cup packer of self-styled form is adopted in packing between each perforated interval, need not move tubing string during the seat envelope or suppress the seat envelope.Each perforated interval correspondence is provided with the instruction automatic switch that derailing switch can be provided with according to ground in advance, need not realize that the down-hole changes layer by Ground Operation.
Description of drawings
Fig. 1 is the integrated searching pipe column structural representation of the utility model utility model cased hole completion horizontal well.
Among the figure, 1. oil pipe, 2. oil extraction pump, 3. safety joint, 4. box cupling chamfering oil pipe, 5. derailing switch, 6. centralizer and packer, 7. guiding plug.
The specific embodiment
Embodiment 1: with the net horizontal section sleeve pipe three water detection sections being arranged is example, and the integrated searching pipe column of the utility model cased hole completion horizontal well is described in further detail.
Consult Fig. 1.The integrated searching pipe column of cased hole completion horizontal well mainly is made up of oil extraction pump 2, safety joint 3, box cupling chamfering oil pipe 4, derailing switch 5, centralizer and packer 6 and guiding plug 7, and oil pipe 1 bottom is connected with an oil extraction pump 2, and oil extraction pump 2 is a gap bridge oil extraction pump 2.Gap bridge oil extraction pump 2 bottoms connect a safety joint 3, and safety joint 3 bottoms are connected with oil pipe 1, and oil pipe 1 is connected to the horizontal segment of oil well.At net horizontal section, the lower end of oil pipe 1 is connected with box cupling chamfering oil pipe 4, and box cupling chamfering oil pipe 4 lower ends are connected with derailing switch 5, box cupling chamfering oil pipe 4, centralizer and packer 6, box cupling chamfering oil pipe 4 in turn, is connected with guiding plug 7 bottom.
The quantity of derailing switch 5 is three, and the quantity of centralizer and packer 6 is two, between per two derailing switches 5 centralizer and packer 6 is arranged.One section box cupling chamfering oil pipe 4 is arranged, 4 interconnect functions of box cupling chamfering oil pipe between derailing switch 5 and centralizer and packer 6.The centralizer and the packer 6 that adopt are brake pad centralizer and cup packer 6, and the position of centralizer and packer 6 is between per two perforated intervals of horizontal case.
Searching pipe column is gone into the well: according to horizontal well well bore parameter situation, the integrated searching pipe column of design splicing sleeve completion horizontal well utilizes two centralizers and packer 6 that three oil reservoir cards are opened.At derailing switch of each oil reservoir (well-case perforating section) position serial connection, between per two derailing switches a brake pad centralizer and cup packer 6 are arranged, be lowered in the horizontal well together.
The water detection process: according to the sectionalization test requirement of horizontal well down-hole, be provided with the switch time on ground to derailing switch.In stage of finding, have only a derailing switch to open in the same time, each layer is opened independent production several days in turn.The ground staff determines the production fluid flow volume property of each layer by to every layer of production fluid metering chemical examination, obtains the data such as production fluid flow, moisture content of this layer.
Claims (4)
1, the integrated searching pipe column of a kind of cased hole completion horizontal well, mainly by oil extraction pump (2), safety joint (3), box cupling chamfering oil pipe (4), derailing switch (5), centralizer and packer (6) and guiding plug (7) are formed, oil pipe (1) bottom is connected with oil extraction pump (2), oil extraction pump (2) bottom attachment security joint (3), safety joint (3) bottom is connected with oil pipe (1), oil pipe (1) is connected to the horizontal segment of oil well, it is characterized in that: at net horizontal section, the lower end of oil pipe (1) connects box cupling chamfering oil pipe (4), box cupling chamfering oil pipe (4) lower end is connected with derailing switch (5) in turn, box cupling chamfering oil pipe (4), centralizer and packer (6), box cupling chamfering oil pipe (4) is connected with guiding plug (7) bottom.
2, the integrated searching pipe column of cased hole completion horizontal well according to claim 1, it is characterized in that: the quantity of described derailing switch (5) is three, the quantity of centralizer and packer (6) is two, and a centralizer and packer (6) are arranged between per two derailing switches (5).
3, the integrated searching pipe column of cased hole completion horizontal well according to claim 1, it is characterized in that: the quantity of described derailing switch (5) is four, the quantity of centralizer and packer (6) is three, and a centralizer and packer (6) are arranged between per two derailing switches (5).
4, according to claim 1, the integrated searching pipe column of 2 or 3 described cased hole completion horizontal wells, it is characterized in that: described oil extraction pump (2) is a gap bridge oil extraction pump (2), the centralizer and the packer (6) that adopt are brake pad centralizer and cup packer (6), and the position of centralizer and packer (6) is between per two perforated intervals of horizontal case.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008201228509U CN201273188Y (en) | 2008-10-08 | 2008-10-08 | Integrated water exploration pipe column for casing well completion horizontal well |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNU2008201228509U CN201273188Y (en) | 2008-10-08 | 2008-10-08 | Integrated water exploration pipe column for casing well completion horizontal well |
Publications (1)
Publication Number | Publication Date |
---|---|
CN201273188Y true CN201273188Y (en) | 2009-07-15 |
Family
ID=40883536
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNU2008201228509U Expired - Lifetime CN201273188Y (en) | 2008-10-08 | 2008-10-08 | Integrated water exploration pipe column for casing well completion horizontal well |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN201273188Y (en) |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102505921A (en) * | 2011-11-04 | 2012-06-20 | 中国石油天然气股份有限公司 | Open hole horizontal well water exploration pipe column |
CN102747967A (en) * | 2012-07-10 | 2012-10-24 | 中国石油天然气股份有限公司 | Multi-stage segmented release water exploration pipe column and method for casing completion multi-stage fractured horizontal well |
CN103382835A (en) * | 2013-07-25 | 2013-11-06 | 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 | Water exploration and plugging technology by adopting intelligent switches |
CN101701518B (en) * | 2009-09-15 | 2014-03-12 | 中国海洋石油总公司 | Pipe string used for high-speed test of pressure control and water stabilization of horizontal well |
CN103998783A (en) * | 2011-12-15 | 2014-08-20 | 雷兹生产有限公司 | Horizontal and vertical well fluid pumping system |
CN104278988A (en) * | 2013-07-05 | 2015-01-14 | 天津大港油田钻采技术开发公司 | Sidetracking well three-layer water finding and blocking and production operation integrated tubular column and operating method thereof |
CN104420868A (en) * | 2013-08-30 | 2015-03-18 | 中国石油天然气股份有限公司 | Horizontal well oil casing annulus fluid return fast water exploration pipe column and water exploration method thereof |
CN104632195A (en) * | 2013-11-08 | 2015-05-20 | 中国石油天然气股份有限公司 | Gas lift flow aiding horizontal well water exploration pipe column and method |
CN105178947A (en) * | 2015-09-18 | 2015-12-23 | 中国石油天然气股份有限公司 | Horizontal well water finding and plugging integrated method |
CN105569635A (en) * | 2015-12-31 | 2016-05-11 | 中国石油天然气股份有限公司 | Horizontal well liquid production section testing technology process pipe column and testing method |
CN110206531A (en) * | 2019-05-23 | 2019-09-06 | 广州海洋地质调查局 | A kind of oil pipe of horizontal well production profile test method and device |
CN111852449A (en) * | 2020-09-09 | 2020-10-30 | 哈尔滨艾拓普科技有限公司 | Continuous dragging type horizontal well produced liquid sectional test system |
CN112360387A (en) * | 2020-12-08 | 2021-02-12 | 中国石油天然气股份有限公司 | Balanced production water control pipe column and method for casing completion horizontal well |
CN112943182A (en) * | 2021-01-11 | 2021-06-11 | 中国石油天然气股份有限公司 | Free layer changing device and method for horizontal well |
-
2008
- 2008-10-08 CN CNU2008201228509U patent/CN201273188Y/en not_active Expired - Lifetime
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101701518B (en) * | 2009-09-15 | 2014-03-12 | 中国海洋石油总公司 | Pipe string used for high-speed test of pressure control and water stabilization of horizontal well |
CN102505921A (en) * | 2011-11-04 | 2012-06-20 | 中国石油天然气股份有限公司 | Open hole horizontal well water exploration pipe column |
CN102505921B (en) * | 2011-11-04 | 2014-02-05 | 中国石油天然气股份有限公司 | Open hole horizontal well water exploration pipe column |
CN103998783A (en) * | 2011-12-15 | 2014-08-20 | 雷兹生产有限公司 | Horizontal and vertical well fluid pumping system |
CN102747967A (en) * | 2012-07-10 | 2012-10-24 | 中国石油天然气股份有限公司 | Multi-stage segmented release water exploration pipe column and method for casing completion multi-stage fractured horizontal well |
CN104278988A (en) * | 2013-07-05 | 2015-01-14 | 天津大港油田钻采技术开发公司 | Sidetracking well three-layer water finding and blocking and production operation integrated tubular column and operating method thereof |
CN103382835B (en) * | 2013-07-25 | 2016-05-04 | 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 | Intelligent switch is looked for, water-plugging technique |
CN103382835A (en) * | 2013-07-25 | 2013-11-06 | 中国石油集团川庆钻探工程有限公司长庆井下技术作业公司 | Water exploration and plugging technology by adopting intelligent switches |
CN104420868A (en) * | 2013-08-30 | 2015-03-18 | 中国石油天然气股份有限公司 | Horizontal well oil casing annulus fluid return fast water exploration pipe column and water exploration method thereof |
CN104420868B (en) * | 2013-08-30 | 2017-12-01 | 中国石油天然气股份有限公司 | Horizontal well oil casing annulus fluid return fast water exploration pipe column and water exploration method thereof |
CN104632195B (en) * | 2013-11-08 | 2017-12-19 | 中国石油天然气股份有限公司 | Gas lift flow aiding horizontal well water exploration pipe column and method |
CN104632195A (en) * | 2013-11-08 | 2015-05-20 | 中国石油天然气股份有限公司 | Gas lift flow aiding horizontal well water exploration pipe column and method |
CN105178947A (en) * | 2015-09-18 | 2015-12-23 | 中国石油天然气股份有限公司 | Horizontal well water finding and plugging integrated method |
CN105569635A (en) * | 2015-12-31 | 2016-05-11 | 中国石油天然气股份有限公司 | Horizontal well liquid production section testing technology process pipe column and testing method |
CN110206531A (en) * | 2019-05-23 | 2019-09-06 | 广州海洋地质调查局 | A kind of oil pipe of horizontal well production profile test method and device |
CN110206531B (en) * | 2019-05-23 | 2024-04-09 | 广州海洋地质调查局 | Method and device for testing output profile of horizontal well oil pipe |
CN111852449A (en) * | 2020-09-09 | 2020-10-30 | 哈尔滨艾拓普科技有限公司 | Continuous dragging type horizontal well produced liquid sectional test system |
CN111852449B (en) * | 2020-09-09 | 2022-11-25 | 哈尔滨艾拓普科技有限公司 | Continuous dragging type horizontal well produced liquid sectional test system |
CN112360387A (en) * | 2020-12-08 | 2021-02-12 | 中国石油天然气股份有限公司 | Balanced production water control pipe column and method for casing completion horizontal well |
CN112943182A (en) * | 2021-01-11 | 2021-06-11 | 中国石油天然气股份有限公司 | Free layer changing device and method for horizontal well |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201273188Y (en) | Integrated water exploration pipe column for casing well completion horizontal well | |
CN201546710U (en) | Segmented water exploration test pipe column for casing completion horizontal well | |
US7789163B2 (en) | Dual-stage valve straddle packer for selective stimulation of wells | |
CN202596684U (en) | Multi-stage segmented yield-seeking and water-finding testing process pipe column for casing well completion horizontal well | |
US8162060B2 (en) | Gas-lift valve and method of use | |
CN103380258B (en) | System and method for the positioning of bottom BHA in horizontal well | |
CA2833992C (en) | Method of controlling a failed well with a ported packer | |
CN104179485B (en) | Cementation and fracture technique string | |
RU2485290C1 (en) | Development method by horizontal well of formation with zones of various permeability | |
CN103184859A (en) | Exploitation device and method for injection and production in same well | |
CN101250987A (en) | Method for testing and dislodging oil well intelligent delamination | |
CN104832143B (en) | Water injection well umbilical pipe full-horizon injection regulation device | |
US20220098955A1 (en) | Method for filling oil-gas well of fractured oil-gas reservoir with isolation particles to reduce water and increase oil production | |
CN106661927A (en) | Junction-conveyed completion tooling and operations | |
CN103643931A (en) | Completion and fracture integrated pipe column of offshore openhole horizontal well and construction method of pipe column | |
CN110295879A (en) | A kind of staged fracturing horizontal well in segments period note adopts dual string | |
US20160084079A1 (en) | Fast-Setting Retrievable Slim-Hole Test Packer and Method of Use | |
US20240167361A1 (en) | Systems for Inter-Fracture Flooding of Wellbores and Methods of Using the Same | |
US7819193B2 (en) | Parallel fracturing system for wellbores | |
CN103470233B (en) | Heavy oil reservoir natural gas huff-puff oil production process system and oil production method | |
EP2840227A2 (en) | Wellbore annular safety valve and method | |
RU2598256C1 (en) | Method for hydrodynamic tests of exploitation well formation (versions) | |
CN103321626B (en) | A kind of fracturing sand control integration completion tubular column and application process thereof | |
CN202718655U (en) | Accurate quantification injection seal-examination integrated tubular column | |
US20150041129A1 (en) | Steam injection and production completion system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CX01 | Expiry of patent term |
Granted publication date: 20090715 |
|
CX01 | Expiry of patent term |