A kind of electric power pylon basis top surface brushes flat method
Technical field
The present invention relates to field of electrical equipment, in particular to a kind of electric power pylon basis top surface brushes flat method.
Background technique
In the high-voltage power transmission tower of 110kV or more, it is divided into tangent tower and angle tower.Tangent tower only supports conducting wire, and
Angle tower is to stand in corner, to bear biggish lateral force.Angle tower generally wants the opposite direction of guiding line lateral force to incline
Tiltedly certain pre- inclination angle, the equalizing contactor pulling force after erection make it keep vertical.So the basic top surface of tangent tower is level
Face, and the basic top surface of angle tower will be made into clinoplain, gradient is the pre- inclination rake angle of steel tower.
In the foundation construction of horizontal plane, base surface is carried out with horizontal ruler to grasp gentle detection, qualification rate is relatively higher.But
To angle tower, common construction method is to determine the difference in height of basic slope face two sides, is scraped with plate, but basic top surface is vertical has
Multiple foundation bolts cannot continuously strike off.Cause basic top surface uneven, flange and basic face bonding are bad, and steel tower is pre- partially
Direction and angle inaccuracy, directly affect tower body force request.
Summary of the invention
The technical problem to be solved by the present invention is to:One kind is provided to be able to achieve to electric power pylon basis top surface progress special angle
The method brushed flat.
The solution that the present invention solves its technical problem is:
A kind of electric power pylon basis top surface brushes flat method, includes the following steps, namely:
Step a) builds electric power pylon basis, and the stud for having several annulars to lay is found in the top surface on electric power pylon basis, and
The concrete of electric power pylon basis top surface is allowed to be in non-condensing state;
Two guide rails are arranged in top face of the step b) on electric power pylon basis, and all guide rails are mutually arranged in parallel,
It is set on guide rail there are two connector sleeve, the connection plate that the connector sleeve is equipped with set rail set, connect with the outer wall of set rail set covers rail
It puts on and is equipped with sets of holes, connection plate is equipped with connecting hole, and connection plate is connected with connection plate by connecting hole and Stud connection
Stud be known as fixed column, set in fixed column there are two fixture nut, the connection plate is sandwiched in described two fixture nuts
Between, set rail set covers on guide rail;
Step c) placement operation bar on described two guide rails, the upper and lower surfaces of the operating stick be plane and
It is parallel to each other;Horizontal ruler is placed in the upper surface of operating stick to cover by adjusting set rail in stud then according to the data of horizontal ruler
On position, to realize the height distance adjusted separately between the angle of guide rail itself and ground, two guide rails, up to by two
The angle of the plane and horizontal plane that determine where a guide rail is pre- inclination rake angle;
Step d) operating stick is equipped with across hole, and the height-regulating axis vertical with operating stick is equipped in hole, the upper of axis is turned up
End extends through the upside in hole, and the lower end that axis is turned up, which is equipped with, brushes flat plate, brushes flat plate and is mutually perpendicular to axis is turned up, and axis is turned up and is equipped with
Two binding nuts, operating stick are located between described two binding nuts, are adjusted binding nut in the position that axis is turned up, are allowed and brush flat
The height of plate is in suitable position;
Step e) allows operating stick to move back and forth along the extending direction of operating stick, guide rail, so that ferroelectric tower foundation top surface is mixed
Solidifying soil is brushed flat in pre- inclination rake angle.
As a further improvement of the foregoing solution, step c1 is additionally provided between step c) and step d)), described two
At least one guide rail is added between guide rail again, so that the guide rail added is located at plane determined by two guide rails in step c)
On.
As a further improvement of the foregoing solution, the quantity of several studs is even number.
As a further improvement of the foregoing solution, guide rail is cylindrical.
As a further improvement of the foregoing solution, the jacket wall of set rail set is equipped with threaded hole, and threaded hole, which is equipped with, compresses spiral shell
Bolt, the end of hold-down bolt are protruded into sets of holes and are abutted with the outer wall of guide rail, are equipped with adjustment gap between guide rail and set rail set.
The beneficial effects of the invention are as follows:A kind of electric power pylon basis top surface brushes flat method, includes the following steps, namely:Step a)
Electric power pylon basis, the vertical stud for there are several annulars to lay in the top surface on electric power pylon basis are built, and makes electric power pylon basic
The concrete of top surface is in non-condensing state;Two guide rails are arranged in top face of the step b) on electric power pylon basis, all
Guide rail is mutually arranged in parallel, and is set on guide rail there are two connector sleeve, and the connector sleeve is equipped with set rail set, the outer wall with set rail set
The connection plate of connection, set rail are put on equipped with sets of holes, are connected plate and are equipped with connecting hole, connection plate passes through connecting hole and stud
Connection, the stud for being connected with connection plate are known as fixed column, are set in fixed column there are two fixture nut, the connection plate is pressed from both sides
Between described two fixture nuts, set rail set covers on guide rail;Step c) placement operation bar on described two guide rails, it is described
The upper and lower surfaces of operating stick are plane and are parallel to each other;Horizontal ruler is placed in the upper surface of operating stick, then basis
The data of horizontal ruler cover the position on stud by adjusting set rail, to realize the folder for adjusting separately guide rail itself Yu ground
Height distance between angle, two guide rails, until being pre- inclination by the angle of the plane and horizontal plane that are determined where two guide rails
Rake angle;Step d) operating stick is equipped with across hole, and the height-regulating axis vertical with operating stick is equipped in hole, the upper end of axis is turned up
The upside for extending through hole, the lower end that axis is turned up, which is equipped with, brushes flat plate, brushes flat plate and is mutually perpendicular to axis is turned up, and axis is turned up and is equipped with two
A binding nut, operating stick are located between described two binding nuts, are adjusted binding nut in the position that axis is turned up, are allowed and brush flat plate
Height be in suitable position;Step e) allows operating stick to move back and forth along the extending direction of operating stick, guide rail, so that ferroelectric tower
The concrete of basic top surface is brushed flat in pre- inclination rake angle.Such construction method can ensure that electric power pylon basis top surface can quilt
It accurately brushes flat in pre- inclination angle.The present invention is used for the construction of power transmission tower.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment
Attached drawing is briefly described.Obviously, described attached drawing is a part of the embodiments of the present invention, rather than is all implemented
Example, those skilled in the art without creative efforts, can also be obtained according to these attached drawings other designs
Scheme and attached drawing.
Fig. 1 is the schematic perspective view of the embodiment of the present invention;
Fig. 2 is the schematic perspective view of the set rail set of the embodiment of the present invention.
Specific embodiment
It is carried out below with reference to technical effect of the embodiment and attached drawing to design of the invention, specific structure and generation clear
Chu is fully described by, to be completely understood by the purpose of the present invention, feature and effect.Obviously, described embodiment is this hair
Bright a part of the embodiment, rather than whole embodiments, based on the embodiment of the present invention, those skilled in the art are not being paid
Other embodiments obtained, belong to the scope of protection of the invention under the premise of creative work.In addition, be previously mentioned in text
All connection/connection relationships not singly refer to that component directly connects, and referring to can be added deduct according to specific implementation situation by adding
Few couple auxiliary, to form more preferably coupling structure.Each technical characteristic in the present invention, in the premise of not conflicting conflict
Under can be with combination of interactions.
Referring to Figures 1 and 2, this is the embodiment of the present invention, specifically:
A kind of electric power pylon basis top surface brushes flat method, includes the following steps, namely:
Step a) builds electric power pylon basis, and the stud 1 for having several annulars to lay is found in the top surface on electric power pylon basis, and
The concrete of electric power pylon basis top surface is allowed to be in non-condensing state;
Two guide rails 2 are arranged in top face of the step b) on electric power pylon basis, and all guide rails 2 are mutually set in parallel
It sets, is set on guide rail 2 there are two connector sleeve 3, the company that the connector sleeve 3 is equipped with set rail set 31, connect with the outer wall of set rail set 31
Connect plate 32, set rail set 31 is equipped with sets of holes, and connection plate 32 is equipped with connecting hole 33, connection plate 32 by connecting hole 33 with
Stud 1 connects, and the stud for being connected with connection plate 32 is known as fixed column, and the connection there are two fixture nut 4 is set in fixed column
Plate 32 is sandwiched between described two fixture nuts 4, and set rail covers 31 sets on guide rail 2;
Step c) placement operation bar 5 on described two guide rails 2, the upper and lower surfaces of the operating stick 5 are flat
It face and is parallel to each other;Horizontal ruler, which is placed, in the upper surface of operating stick 5 passes through adjusting set rail set then according to the data of horizontal ruler
31 position on stud 1, thus realize adjust separately height between the angle of guide rail 2 itself and ground, two guide rails 2 away from
From until being pre- inclination rake angle by the angle of the plane and horizontal plane that are determined where two guide rails 2;
Step d) operating stick 5 is equipped with across hole, and the height-regulating axis 6 vertical with operating stick 5 is equipped in hole, and axis 6 is turned up
Upper end extend through the upside in hole, the lower end that axis 6 is turned up, which is equipped with, brushes flat plate 7, brush flat plate 7 and axis 6 be turned up and be mutually perpendicular to, height-regulating
It is set on axis 6 there are two binding nut 61, operating stick 5 is located between described two binding nuts 61, is adjusted binding nut 61 and is being adjusted
The position of high axis 6 allows the height for brushing flat plate 7 to be in suitable position;
Step e) allows operating stick 5 to move back and forth along the extending direction of operating stick 5, guide rail 2, so that ferroelectric tower foundation top surface
Concrete is brushed flat in pre- inclination rake angle.Such construction method can ensure that electric power pylon basis top surface can accurately be brushed flat
In pre- inclination angle, the error of manual operation generation is avoided, easy to operate, the construction time is short.
Step c1 is additionally provided between step c) and step d)), at least one is added again between described two guide rails 2 leads
Rail 2, so that the guide rail 2 added is located in plane determined by two guide rails 2 in step c).Operating stick mistake is avoided in this way
Long problem makes operating stick easy to carry.
The quantity of the stud 1 of the present embodiment is even number.
The guide rail 2 of the present embodiment is cylindrical, and such guide rail and slide surface are line face contact, can ensure operating stick well
Movement it is smooth.
The jacket wall of the set rail set 31 of the present embodiment is equipped with threaded hole 34, and threaded hole 34 is equipped with hold-down bolt 35, compresses
The end of bolt 35 is protruded into sets of holes and is abutted with the outer wall of guide rail 2, is equipped with adjustment gap between guide rail 2 and set rail set 31, in this way
It can easily allow guide rail ground in pre- inclination angle, and guide rail can be compressed tightly against in sets of holes by hold-down bolt 35, from
And adapt to the demand of various pre- inclination angles.
Better embodiment of the invention is illustrated above, but the present invention is not limited to the embodiment,
Those skilled in the art can also make various equivalent modifications or replacement on the premise of without prejudice to spirit of the invention, this
Equivalent variation or replacement are all included in the scope defined by the claims of the present application a bit.