CN108808632A - It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature - Google Patents

It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature Download PDF

Info

Publication number
CN108808632A
CN108808632A CN201710307064.XA CN201710307064A CN108808632A CN 108808632 A CN108808632 A CN 108808632A CN 201710307064 A CN201710307064 A CN 201710307064A CN 108808632 A CN108808632 A CN 108808632A
Authority
CN
China
Prior art keywords
execute
switch
fragmentation feature
substation
sides
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710307064.XA
Other languages
Chinese (zh)
Inventor
陈珍辉
寇少霞
王家宁
李超培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HENAN HUASHENG LONGYUAN ELECTRIC CO Ltd
Original Assignee
HENAN HUASHENG LONGYUAN ELECTRIC CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HENAN HUASHENG LONGYUAN ELECTRIC CO Ltd filed Critical HENAN HUASHENG LONGYUAN ELECTRIC CO Ltd
Priority to CN201710307064.XA priority Critical patent/CN108808632A/en
Publication of CN108808632A publication Critical patent/CN108808632A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H7/00Emergency protective circuit arrangements specially adapted for specific types of electric machines or apparatus or for sectionalised protection of cable or line systems, and effecting automatic switching in the event of an undesired change from normal working conditions
    • H02H7/26Sectionalised protection of cable or line systems, e.g. for disconnecting a section on which a short-circuit, earth fault, or arc discharge has occured
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H3/00Emergency protective circuit arrangements for automatic disconnection directly responsive to an undesired change from normal electric working condition with or without subsequent reconnection ; integrated protection
    • H02H3/02Details
    • H02H3/06Details with automatic reconnection
    • H02H3/066Reconnection being a consequence of eliminating the fault which caused disconnection

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention relates to a kind of guard methods and device that coincidence fragmentation feature is adaptive; when some region is broken down in supply line; all switches from substation to fault point can detect fault current and trip; unilateral side is switched after tripping electricity; then illustrate that installation site is substation exit, to execute reclosing function;The equal dead electricity of bilateral, then segmentation position of the explanation after substation exit switch, will execute fragmentation feature;For switch in position and both sides dead electricity is closed, then explanation is mounted on the segmentation position after substation exit switch, to execute fragmentation feature.By switching division position and both sides voltage condition, judges installation site, execute different function, to eliminate the trouble being manually arranged and the serious consequence caused by mistake is arranged.

Description

It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature
Technical field
The present invention relates to a kind of power distribution networks, more particularly, to a kind of isolation of distribution network failure and the method for fault self-recovery.
Background technology
Traditional automatic circuit and sectionaliser is two different products, executes different relay protective schemes.Even if being provided simultaneously with Function and fragmentation feature are overlapped, artificial setting is also depended on, is individually performed and overlaps function or fragmentation feature.Artificial setting is often held It is error-prone, once setting error can cause entire power grid to paralyse it will cause switch malfunction and misaction when serious.
Invention content
The present invention relates to the methods and dress in a kind of medium voltage network distribution network isolated fault region and recovery non-faulting region Set, automatic identification installation site, to execute different defencive functions, for solve it is above-mentioned caused by manually setting error it is tight Weight consequence.
A kind of overlap works as supply lines with the adaptive method and apparatus of fragmentation feature using breaker as executive component When certain region is broken down in road, following steps are executed:
(1)Substation actively trips to the switch between fault point;
(2)Both sides voltage is detected after the completion of tripping;
(3)Both sides voltage arbitrarily has side to have electricity, then explanation is mounted on substation exit, needs to execute reclosing function;
(4)If the equal dead electricity of both sides voltage, illustrates to be mounted in after substation exit switch, execute fragmentation feature.
Further, switch is in position and both sides all dead electricity is closed, then explanation is mounted on point after substation exit switch At section, fragmentation feature is executed.
Coincidence fragmentation feature adaptive approach and device provided by the invention, when some region is broken down in supply line When, all switches from substation to fault point can detect fault current and trip, and unilateral side is switched after tripping electricity, then says Bright installation site is substation exit, to execute coincidence function;The equal dead electricity of bilateral then illustrates to switch it mounted on substation exit Segmentation position afterwards, will execute fragmentation feature;Switch is in position and both sides dead electricity is closed, then explanation is mounted on substation exit and switchs Segmentation position later, will execute fragmentation feature.By switching division position and both sides voltage condition, judges installation site, hold Row different function, to eliminate the trouble being manually arranged and the serious consequence caused by mistake is arranged.
Description of the drawings
Fig. 1 is the flow chart overlapped in embodiment with the adaptive method and apparatus of fragmentation feature;
Fig. 2 is the system diagram of power distribution network in embodiment.
Specific implementation mode
The present invention provides a kind of coincidence fragmentation feature adaptive method and apparatus, can automatic identification installation site, hold The corresponding function of row, to avoid the trouble being manually arranged and the serious consequence caused by mistake is arranged.
Embodiment of the method:
It is provided by the present invention coincidence and the adaptive method and apparatus of fragmentation feature flow chart as shown in Figure 1, specific steps such as Under:
(1)Substation actively trips to the switch between fault point;
(2)Both sides voltage is detected after the completion of tripping;
(3)Both sides voltage arbitrarily has side to have electricity, then explanation is mounted on substation exit, needs to execute reclosing function;
(4)If the equal dead electricity of both sides voltage, illustrates to be mounted in after substation exit switch, execute fragmentation feature.
Further, switch is in position and both sides all dead electricity is closed, then explanation is mounted on point after substation exit switch At section, fragmentation feature is executed.
Below by actually use the above method realize to overlap and fragmentation feature adaptive approach for, to the present embodiment into Row further illustrates.
It is provided by the present invention coincidence and fragmentation feature adaptive approach as shown in Fig. 2, wherein CB1 be substation, KG1, KG2, KG3 are the device of the embodiment of the present invention.Embodiment in order to further illustrate the present invention, it is assumed that the area between KG2 and KG3 Permanent failure occurs for domain, is as follows:
(1)KG1 and KG2 detects fault current, tripping;KG3 can't detect fault current, be failure to actuate;
(2)After tripping, KG1 detects that there is electricity in unilateral side, illustrates that installation at substation exit, next should execute coincidence work( Energy;KG2 detects bilateral dead electricity, illustrates to be mounted at the segmentation after substation exit switchs, next should execute segmentation Function;KG3 illustrates to be installed at the segmentation after substation exit switchs, it should trip also in position and bilateral dead electricity is closed And execute fragmentation feature;
(3)Following KG1, which is executed, overlaps function, and KG2 and KG3 execute fragmentation feature, and separating brake is latched by KG2, and KG3 will be latched reversely Incoming call closes a floodgate, to by the fault section isolation between KG2 and KG3, restore the non-faulting block supply between KG1 and KG2.
Specific implementation mode of the present invention is presented above, but the present invention is not limited to described embodiment. Under the thinking that the present invention provides, to the skill in above-described embodiment by the way of being readily apparent that those skilled in the art Art means are converted, are replaced, are changed, and play the role of with the present invention in relevant art means it is essentially identical, realize Goal of the invention it is also essentially identical, the technical solution formed in this way is finely adjusted above-described embodiment to be formed, this technology Scheme is still fallen in protection scope of the present invention.

Claims (2)

1. a kind of overlapping fragmentation feature adaptive guard method and device, which is characterized in that be used as using breaker and execute member Part executes following steps when certain region is broken down in supply line:
(1)Substation actively trips to the switch between fault point;
(2)Both sides voltage is detected after the completion of tripping;
(3)Both sides voltage arbitrarily has side to have electricity, then explanation is mounted on substation exit, needs to execute reclosing function;
(4)If the equal dead electricity of both sides voltage, illustrates to be mounted in after substation exit switch, execute fragmentation feature;
Further, switch then illustrates in position and both sides all dead electricity is closed at the segmentation after substation exit switch, Execute fragmentation feature.
2. a kind of guard method and device that coincidence fragmentation feature is adaptive according to claim 1, which is characterized in that logical Switch division position and both sides voltage condition are crossed, judges installation site, executes different function.
CN201710307064.XA 2017-05-04 2017-05-04 It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature Pending CN108808632A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710307064.XA CN108808632A (en) 2017-05-04 2017-05-04 It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710307064.XA CN108808632A (en) 2017-05-04 2017-05-04 It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature

Publications (1)

Publication Number Publication Date
CN108808632A true CN108808632A (en) 2018-11-13

Family

ID=64054455

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710307064.XA Pending CN108808632A (en) 2017-05-04 2017-05-04 It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature

Country Status (1)

Country Link
CN (1) CN108808632A (en)

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102005746A (en) * 2010-11-30 2011-04-06 南京南瑞继保电气有限公司 Method based on topology protection of distributing network
CN102570594A (en) * 2012-03-08 2012-07-11 华南理工大学 Spare automatic adaptive switching method for transformer substation based on automatic reclosing information
CN106026051A (en) * 2016-07-26 2016-10-12 国电南瑞科技股份有限公司 Fixed-value adaptive voltage and current time type on-site feeder automation method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102005746A (en) * 2010-11-30 2011-04-06 南京南瑞继保电气有限公司 Method based on topology protection of distributing network
CN102570594A (en) * 2012-03-08 2012-07-11 华南理工大学 Spare automatic adaptive switching method for transformer substation based on automatic reclosing information
CN106026051A (en) * 2016-07-26 2016-10-12 国电南瑞科技股份有限公司 Fixed-value adaptive voltage and current time type on-site feeder automation method

Similar Documents

Publication Publication Date Title
CN108376974B (en) A kind of power distribution network relay protection system based on current limliting Graded coordination
CN106026051B (en) A kind of definite value adaptive voltage current time type feeder automation method on the spot
CN103490392B (en) Fault handling method of power distribution network comprising distributed power supplies and microgrids
EP3306766B1 (en) Direct current power transmission system, central server of same, and method for restoring direct current power transmission pathway after failure
CN106953304B (en) Jack-up unit drilling well frequency conversion drive DC distribution Over Current Protection System and method
CN110932245A (en) Hybrid direct current circuit breaker, control protection device and method
CN103378583A (en) Feeder automation technical scheme based on intelligent rapid vacuum circuit breaker
CN103904626A (en) Method for automatically judging and controlling power distribution network failure in ring main unit power supply
CN102299563A (en) Digital-analog (DA) protection method for intelligent distribution network
CN109818410A (en) A kind of rapidly self-healing method of urban track traffic ac power supply system
CN109245072B (en) Self-adaptive in-situ feeder automation fault processing method based on regional sequence number
CN105552858A (en) Fault processing method applying regional blocking for power distribution network
CN102593798B (en) Comprehensive relay protection method applied to intelligent switch
CN103280780B (en) A kind of system with non effectively earth ed neutral fault self-recovery method
CN108767825A (en) A kind of feeder automation intelligent on the spot is delayed differential fitting method and application entirely
CN104124672A (en) Power restoration method for voltage type fault section front end
CN106374445A (en) Small current grounding fault processing method with line selection device and protection recloser cooperated
CN201549868U (en) Low-voltage switch intelligent controller
KR101609896B1 (en) Automatic load transfer relay for distribution transformer
CN102646966B (en) Three-phase fault processing method of distributing line
CN107611946A (en) A kind of full killer switch feeder fault control method
CN102931644B (en) Regional power grid fault isolation and recovery method
CN108808632A (en) It is a kind of to overlap and the adaptive method and apparatus of fragmentation feature
KR20160039454A (en) Coordination of protection system and coordination of protection method
CN109245071A (en) A kind of intelligent distribution type feeder automation distribution system and control method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181113