CN108798034A - A kind of construction method of high-rise steel structure engineering - Google Patents

A kind of construction method of high-rise steel structure engineering Download PDF

Info

Publication number
CN108798034A
CN108798034A CN201810595958.8A CN201810595958A CN108798034A CN 108798034 A CN108798034 A CN 108798034A CN 201810595958 A CN201810595958 A CN 201810595958A CN 108798034 A CN108798034 A CN 108798034A
Authority
CN
China
Prior art keywords
girder
steel column
steel structure
welding
construction method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810595958.8A
Other languages
Chinese (zh)
Inventor
武士炯
张炳旭
岳艳红
朱文亚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai General Construction Engineering Co Ltd
Original Assignee
Shanghai General Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai General Construction Engineering Co Ltd filed Critical Shanghai General Construction Engineering Co Ltd
Priority to CN201810595958.8A priority Critical patent/CN108798034A/en
Publication of CN108798034A publication Critical patent/CN108798034A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a kind of construction methods of high-rise steel structure engineering, including:Axis and absolute altitude to structural steelwork measure confirmation;Each steel column is fixedly mounted by drawing on ground;Each girder is installed on steel column, forms steel structure frame;It is welded in each welding node of steel column and girder;It carries out an acceptance inspection to the at all levels of steel structure frame by design requirement.The present invention simplifies construction process, and improves construction quality.

Description

A kind of construction method of high-rise steel structure engineering
Technical field
The present invention relates to the construction fields of steel construction.
Background technology
Existing building much all uses steel construction, especially many workshops, because demand space is big and saves building cost Requirement, the mode of big more options structural steelwork built.But existing structural steelwork form of construction work, it is especially high The form of construction work of layer structural steelwork, it is not rigorous enough, it generally requires to adjust repeatedly after construction, many duplications of labour can be done.And And the structural steelwork precision for completing later cannot be ensured well.
Invention content
It is an object of the invention to a kind of construction methods of high-rise steel structure engineering, simplify construction process, and improve construction Quality.
Realizing the technical solution of above-mentioned purpose is:
A kind of construction method of high-rise steel structure engineering, including:
Axis and absolute altitude to structural steelwork measure confirmation;
Each steel column is fixedly mounted by drawing on ground;
Each girder is installed on steel column, forms steel structure frame;
It is welded in each welding node of steel column and girder;
It carries out an acceptance inspection to the at all levels of steel structure frame by design requirement.
It is right in the axis and wrong absolute altitude of structural steelwork in the construction method of above-mentioned high-rise steel structure engineering Absolute altitude and axis are handled.
In the construction method of above-mentioned high-rise steel structure engineering, after installing steel column, check steel column verticality whether It complies with standard, if not being corrected in preset critical field.
In the construction method of above-mentioned high-rise steel structure engineering, after girder and steel column are connected and fixed by bolt, inspection Whether the verticality for looking into steel column complies with standard, if not being corrected in preset critical field.
In the construction method of above-mentioned high-rise steel structure engineering, to each welding node of the steel column and girder that have welded It checks damaged condition, if exceeding preset damage range, is modified.
In the construction method of above-mentioned high-rise steel structure engineering, each girder is installed on steel column, including:
Steel structure frame is divided into many levels from bottom to top by drawing;
The boundary position and girder link position of each level are marked on each steel column;
Each girder is installed by level successively from the bottom up;
The erection of main beam of each level is good to check whether the verticality of steel column complies with standard later;
After the erection of main beam of each level is good, the girder of every two adjacent layer time is connected by connecting rod.
In the construction method of above-mentioned high-rise steel structure engineering, welded in each welding node of steel column and girder It connects, including:
Determine the type of each welding node;
In each welding node, different welding manners is selected by node type, and marks the symbol of corresponding each welding manner;
Corresponding welding manner is selected by label symbol, corresponding welding node is welded;
By the requirement standard of each welding manner, each welding node after welding is checked, to non-compliant heavy New welding.
The beneficial effects of the invention are as follows:The present invention rapidly and accurately realizes steel construction by construction process that is rigorous, simplifying The construction of engineering.Meanwhile by effectively verifying, modified mode, can ensure to a certain extent construction quality.And And built by from bottom to top realizing by different level, meet the work progress of science, avoids the problem that adjusting repeatedly.
Description of the drawings
Fig. 1 is the flow chart of the construction method of the high-rise steel structure engineering of the present invention;
Fig. 2 is the flow chart that girder is installed in the present invention;
Fig. 3 is the flow chart welded in the present invention.
Specific implementation mode
The present invention will be further described with reference to the accompanying drawings.
Referring to Fig. 1, the construction method of the high-rise steel structure engineering of the present invention, includes the following steps:
Step S1, axis and absolute altitude to structural steelwork measure confirmation.In the axis and absolute altitude of structural steelwork When wrong, absolute altitude and axis are handled.
Each steel column is fixedly mounted by drawing on ground in step S2.After installing steel column, check that the verticality of steel column is It is no to comply with standard, if not being corrected in preset critical field.
Step S3 installs each girder on steel column, steel structure frame is formed, specifically as shown in Fig. 2, including:
Steel structure frame is divided into many levels by step S31 from bottom to top by drawing.
Step S32 marks the boundary position and girder link position of each level on each steel column.
Step S33 is installed each girder successively by level from the bottom up.
Step S34, the erection of main beam of each level is good to check whether the verticality of steel column complies with standard later, if not existing In preset critical field, it is corrected.
After the erection of main beam of each level is good, the girder of every two adjacent layer time is connected by connecting rod by step S35.
Step S4 is welded in each welding node of steel column and girder, specifically as shown in figure 3, including:
Step S41 determines the type of each welding node.
Step S42 is selected different welding manners by node type in each welding node, and marks corresponding each welding side The symbol of formula.
Step S43 selects corresponding welding manner by label symbol, is welded to corresponding welding node.
Step S44 checks each welding node after welding, by the requirement standard of each welding manner to not meeting The welding again of standard.It is not inconsistent standardization to refer to:The damaged condition of welding node exceeds preset damage range.
Step S5 carries out an acceptance inspection to the at all levels of steel structure frame by design requirement.
Above example is used for illustrative purposes only rather than limitation of the present invention, the technology people in relation to technical field Member, without departing from the spirit and scope of the present invention, can also make various transformation or modification, therefore all equivalent Technical solution should also belong to scope of the invention, should be limited by each claim.

Claims (7)

1. a kind of construction method of high-rise steel structure engineering, which is characterized in that including:
Axis and absolute altitude to structural steelwork measure confirmation;
Each steel column is fixedly mounted by drawing on ground;
Each girder is installed on steel column, forms steel structure frame;
It is welded in each welding node of steel column and girder;
It carries out an acceptance inspection to the at all levels of steel structure frame by design requirement.
2. the construction method of high-rise steel structure engineering according to claim 1, which is characterized in that in the axis of structural steelwork When line and wrong absolute altitude, absolute altitude and axis are handled.
3. the construction method of high-rise steel structure engineering according to claim 1, which is characterized in that after installing steel column, inspection Whether the verticality for looking into steel column complies with standard, if not being corrected in preset critical field.
4. the construction method of high-rise steel structure engineering according to claim 1, which is characterized in that by bolt by girder and After steel column is connected and fixed, check whether the verticality of steel column complies with standard, if not being corrected in preset critical field.
5. the construction method of high-rise steel structure engineering according to claim 1, which is characterized in that the steel column that has welded and Each welding node of girder checks damaged condition, if exceeding preset damage range, is modified.
6. the construction method of high-rise steel structure engineering according to claim 4, which is characterized in that installed on steel column each Girder, including:
Steel structure frame is divided into many levels from bottom to top by drawing;
The boundary position and girder link position of each level are marked on each steel column;
Each girder is installed by level successively from the bottom up;
The erection of main beam of each level is good to check whether the verticality of steel column complies with standard later;
After the erection of main beam of each level is good, the girder of every two adjacent layer time is connected by connecting rod.
7. the construction method of high-rise steel structure engineering according to claim 5, which is characterized in that in each of steel column and girder A welding node is welded, including:
Determine the type of each welding node;
In each welding node, different welding manners is selected by node type, and marks the symbol of corresponding each welding manner;
Corresponding welding manner is selected by label symbol, corresponding welding node is welded;
By the requirement standard of each welding manner, each welding node after welding is checked, is welded again to non-compliant It connects.
CN201810595958.8A 2018-06-11 2018-06-11 A kind of construction method of high-rise steel structure engineering Pending CN108798034A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810595958.8A CN108798034A (en) 2018-06-11 2018-06-11 A kind of construction method of high-rise steel structure engineering

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810595958.8A CN108798034A (en) 2018-06-11 2018-06-11 A kind of construction method of high-rise steel structure engineering

Publications (1)

Publication Number Publication Date
CN108798034A true CN108798034A (en) 2018-11-13

Family

ID=64088235

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810595958.8A Pending CN108798034A (en) 2018-06-11 2018-06-11 A kind of construction method of high-rise steel structure engineering

Country Status (1)

Country Link
CN (1) CN108798034A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900868A (en) * 2021-01-20 2021-06-04 山东华海塑胶建材有限公司 Construction method of high-rise steel structure engineering

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1261638A (en) * 1999-12-30 2000-08-02 王康强 Mounting method for high-rise building steel structure
CN101886401A (en) * 2010-07-14 2010-11-17 广州永联钢结构有限公司 Segmented assembly component of steel end housings of underwater tunnel immersed segment and construction method
CN106812323A (en) * 2015-11-30 2017-06-09 周子童 The construction method of high-rise steel structure
CN107515953A (en) * 2017-09-27 2017-12-26 武汉龙谷科尔技术有限公司 One kind welding overall process quality tracing and analysis system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1261638A (en) * 1999-12-30 2000-08-02 王康强 Mounting method for high-rise building steel structure
CN101886401A (en) * 2010-07-14 2010-11-17 广州永联钢结构有限公司 Segmented assembly component of steel end housings of underwater tunnel immersed segment and construction method
CN106812323A (en) * 2015-11-30 2017-06-09 周子童 The construction method of high-rise steel structure
CN107515953A (en) * 2017-09-27 2017-12-26 武汉龙谷科尔技术有限公司 One kind welding overall process quality tracing and analysis system

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900868A (en) * 2021-01-20 2021-06-04 山东华海塑胶建材有限公司 Construction method of high-rise steel structure engineering

Similar Documents

Publication Publication Date Title
US20180361511A1 (en) Method for quality control on laser peening correction of aero-engine support
CN105155497B (en) A kind of jack up lifting platform lowering or hoisting gear and its manufacturing process
CN110258803A (en) A kind of dome steel structure construction method of installation based on BIM technology
CN104674665B (en) Large-spatial structures vestibule bridge installation method
CN105383643B (en) Stainless steel groove profile compartment alignment schemes
CN103174302A (en) Construction method for large-diameter barrel cabin top
CN105290724B (en) A kind of bridge lower boom manufacture craft
CN103230965A (en) Welding deformation flatness correction method of finished steel crane beam
CN106624631A (en) Control method of mounting precision of girder tracks of portal crane
CN104668797A (en) Ring beam structure member manufacturing method in hydraulic bolt type platform lifting system
CN107964864A (en) A kind of trapezoidal bending component of gradual change and manufacture method of anchoringwire in vivo
CN203768942U (en) Positioning device for embedded anchor bolts
CN108798034A (en) A kind of construction method of high-rise steel structure engineering
CN114604391B (en) Method for constructing pile fixing frame
CN104405597A (en) Door frame of fan tower, door frame unit, production method of door frame and fan tower
CN104567763A (en) Steel structure detection method based on BIM (building information modeling) system
CN104264589B (en) A kind of Hanging Basket status real time monitor method
CN107419916B (en) Internal moment reinforcing and correcting device for beam structure
CN110704940B (en) Method for processing position deviation of aircraft engine mounting intersection point and engine thrust pin
CN204956849U (en) A construction equipment for turning over dial structure 100MARK line
CN108343843A (en) A kind of oil-gas pipeline defect repair determination method and device
CN112903697B (en) Three-dimensional laser scanning method for tower crane inspection
CN114735157B (en) Ship bow door sectional type main hinge eye plate mounting method
CN109967975A (en) The method of construction of large-scale floating ship service machine
CN105040662B (en) Drilling platform leg and the folding method of shoe

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181113