CN108798031A - 厨卫间靠墙主立管pvc防水预埋套管施工方法 - Google Patents
厨卫间靠墙主立管pvc防水预埋套管施工方法 Download PDFInfo
- Publication number
- CN108798031A CN108798031A CN201810544094.7A CN201810544094A CN108798031A CN 108798031 A CN108798031 A CN 108798031A CN 201810544094 A CN201810544094 A CN 201810544094A CN 108798031 A CN108798031 A CN 108798031A
- Authority
- CN
- China
- Prior art keywords
- installation
- template
- casing
- pvc
- kitchen
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F17/00—Vertical ducts; Channels, e.g. for drainage
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G15/00—Forms or shutterings for making openings, cavities, slits, or channels
- E04G15/06—Forms or shutterings for making openings, cavities, slits, or channels for cavities or channels in walls of floors, e.g. for making chimneys
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明公开了一种厨卫间靠墙主立管PVC防水预埋套管施工方法,包括安装PVC防水套管、后期安装、检查验收等步骤;首层PVC防水套管安装在土建底排钢筋绑扎前安装,采用自攻螺丝与模板固定,当钢筋隐蔽验收后,混泥土浇筑前,对套管位置和垂直度进行复核;确认无误后,对套管上口采用黄胶带严密封口,防止砼浇筑时混凝土进入,在砼浇筑过程中安排专人看护;第二层乃至整栋楼的顶层,采用逆作吊线施工法确定第二个PVC防水套管的安装位置。本发明方便快捷、效果好。
Description
技术领域
本发明涉及一种厨卫间靠墙主立管PVC防水预埋套管施工方法。
背景技术
近年来,在建设工程领域,我司已成功的将《PVC防水预埋套管施工工法》(Hgf2013-032)应用于施工工程中,解决了厨(卫)间地漏、洗脸盆、坐便器、浴缸下水等部位出现渗漏现象的问题,但由于该工法只适用于落水口终端位置,在不影响使用功能的情况下,可适当允许偏差。但是,厨(卫)间的主立管安装,存在上下连通的关系,在安装精度上有较高的要求,同时,排水主立管一般安装在厨(卫)间的靠墙部位,由于离墙距离过近,且因为墙体模板的存在,不能正常施展垂直仪,不得不采用传统的预留孔洞做法,不能彻底解决厨(卫)间渗漏难题,留下了质量隐患。
发明内容
本发明的目的在于提供一种方便快捷、效果好的厨卫间靠墙主立管PVC防水预埋套管施工方法。
本发明的技术解决方案是:
一种厨卫间靠墙主立管PVC防水预埋套管施工方法,其特征是:包括下列步骤:
(一)安装PVC防水套管
(1)首层PVC防水套管安装:
模板安装完成并通过验收,确保模板面平整度5mm以内,并有足够的刚度,由于此项预埋套管为一次性成型,又是整栋楼主立管安装的起点,因此,安装位置必须正确;根据安装施工图的尺寸和土建结构尺寸,仔细核对后放线定位并做好标记,在土建底排钢筋绑扎前安装,采用自攻螺丝与模板固定,当钢筋隐蔽验收后,混泥土浇筑前,对套管位置和垂直度进行复核;确认无误后,对套管上口采用黄胶带严密封口,防止砼浇筑时混凝土进入,在砼浇筑过程中安排专人看护;
(2)第二层乃至整栋楼的顶层,采用逆作吊线施工法确定第二个PVC防水套管的安装位置;首先将第一个已经成活的预埋PVC套管圆心激光靶作为基准点,用撑杆带着线坠,在顶模下来回移动,当线坠的坠尖与套管的圆心激光靶重合时,在顶模板下做上标记,然后用Φ12的钻头,在模板上向上钻孔,将模板打穿,在模板上以孔为圆心,确定套管安装位置,安装时用顺作吊线法再次核实与下一层套管的同心度,当准确无误时安装固定;用同样的方法安装后续的楼层;为了避免出现累计施工误差而导致套管安装偏差,在土建拆模后进行复核,此时,已有空间条件可用垂直仪测定防水套管的安装精度,使套管安装的精度始终控制在允许的偏差范围内;
数据碰撞验算:
立管中心距墙面:工程采用Φ100立管,中心距墙面距离130mm;
墙体模板方钢龙骨支撑体系单侧总厚度:模板厚度14mm+方钢次龙骨40mm+方钢主龙骨50mm=104mm<130mm,可行;
结论:采用新型墙体模板方钢龙骨支撑体系,不影响逆作法施工和顺作法施工,从数据上支持了本方法的可行性;
(二)后期安装
按照建筑1m线或0.5m线,安装支架;立管上安装三通或四通、伸缩节后,连接上下套管即可;
(三)检查验收
排水立管安装完毕后,对其管道进行垂直度验收和管根部位进行渗漏试验。
本发明与传统的预留孔洞相比,具有一次成活的优点,不仅减少了后期人工封堵的工序,而且,在立管安装施工时,方便快捷,省略了立管安装找正的工序(立管垂直度校正),缩短了施工工期,节约了成本。同时,又能确保管道与砼楼板的自然结合,避免了因根部砼振捣不密实造成的渗漏。
本发明适用于各类多层及高层建筑内厨(卫)间PVC排水主立管安装部位或其它PVC立管的安装。
下面结合实施例对本发明作进一步说明。
具体实施方式
一种厨卫间靠墙主立管PVC防水预埋套管施工方法,包括下列步骤:
(一)安装PVC防水套管
(1)首层PVC防水套管安装:
模板安装完成并通过验收,确保模板面平整度5mm以内,并有足够的刚度,由于此项预埋套管为一次性成型,又是整栋楼主立管安装的起点,因此,安装位置必须正确;根据安装施工图的尺寸和土建结构尺寸,仔细核对后放线定位并做好标记,在土建底排钢筋绑扎前安装,采用自攻螺丝与模板固定,当钢筋隐蔽验收后,混泥土浇筑前,对套管位置和垂直度进行复核;确认无误后,对套管上口采用黄胶带严密封口,防止砼浇筑时混凝土进入,在砼浇筑过程中安排专人看护;
(2)第二层乃至整栋楼的顶层,采用逆作吊线施工法确定第二个PVC防水套管的安装位置;首先将第一个已经成活的预埋PVC套管圆心激光靶作为基准点,用撑杆带着线坠,在顶模下来回移动,当线坠的坠尖与套管的圆心激光靶重合时,在顶模板下做上标记,然后用Φ12的钻头,在模板上向上钻孔,将模板打穿,在模板上以孔为圆心,确定套管安装位置,安装时用顺作吊线法再次核实与下一层套管的同心度,当准确无误时安装固定;用同样的方法安装后续的楼层;为了避免出现累计施工误差而导致套管安装偏差,在土建拆模后进行复核,此时,已有空间条件可用垂直仪测定防水套管的安装精度,使套管安装的精度始终控制在允许的偏差范围内;
数据碰撞验算:
立管中心距墙面:工程采用Φ100立管,中心距墙面距离130mm;
墙体模板方钢龙骨支撑体系单侧总厚度:模板厚度14mm+方钢次龙骨40mm+方钢主龙骨50mm=104mm<130mm,可行;
结论:采用新型墙体模板方钢龙骨支撑体系,不影响逆作法施工和顺作法施工,从数据上支持了本方法的可行性;
(二)后期安装
按照建筑1m线或0.5m线,安装支架;立管上安装三通或四通、伸缩节后,连接上下套管即可;
(三)检查验收
排水立管安装完毕后,对其管道进行垂直度验收和管根部位进行渗漏试验。
Claims (1)
1.一种厨卫间靠墙主立管PVC防水预埋套管施工方法,其特征是:包括下列步骤:
(一)安装PVC防水套管
(1)首层PVC防水套管安装:
模板安装完成并通过验收,确保模板面平整度5mm以内,并有足够的刚度,由于此项预埋套管为一次性成型,又是整栋楼主立管安装的起点,因此,安装位置必须正确;根据安装施工图的尺寸和土建结构尺寸,仔细核对后放线定位并做好标记,在土建底排钢筋绑扎前安装,采用自攻螺丝与模板固定,当钢筋隐蔽验收后,混泥土浇筑前,对套管位置和垂直度进行复核;确认无误后,对套管上口采用黄胶带严密封口,防止砼浇筑时混凝土进入,在砼浇筑过程中安排专人看护;
(2)第二层乃至整栋楼的顶层,采用逆作吊线施工法确定第二个PVC防水套管的安装位置;首先将第一个已经成活的预埋PVC套管圆心激光靶作为基准点,用撑杆带着线坠,在顶模下来回移动,当线坠的坠尖与套管的圆心激光靶重合时,在顶模板下做上标记,然后用Φ12的钻头,在模板上向上钻孔,将模板打穿,在模板上以孔为圆心,确定套管安装位置,安装时用顺作吊线法再次核实与下一层套管的同心度,当准确无误时安装固定;用同样的方法安装后续的楼层;为了避免出现累计施工误差而导致套管安装偏差,在土建拆模后进行复核,此时,已有空间条件可用垂直仪测定防水套管的安装精度,使套管安装的精度始终控制在允许的偏差范围内;
数据碰撞验算:
立管中心距墙面:工程采用Φ100立管,中心距墙面距离130mm;
墙体模板方钢龙骨支撑体系单侧总厚度:模板厚度14mm+方钢次龙骨40mm+方钢主龙骨50mm=104mm<130mm,可行;
结论:采用新型墙体模板方钢龙骨支撑体系,不影响逆作法施工和顺作法施工,从数据上支持了本方法的可行性;
(二)后期安装
按照建筑1m线或0.5m线,安装支架;立管上安装三通或四通、伸缩节后,连接上下套管即可;
(三)检查验收
排水立管安装完毕后,对其管道进行垂直度验收和管根部位进行渗漏试验。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810544094.7A CN108798031B (zh) | 2018-05-31 | 2018-05-31 | 厨卫间靠墙主立管pvc防水预埋套管施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810544094.7A CN108798031B (zh) | 2018-05-31 | 2018-05-31 | 厨卫间靠墙主立管pvc防水预埋套管施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108798031A true CN108798031A (zh) | 2018-11-13 |
CN108798031B CN108798031B (zh) | 2021-04-23 |
Family
ID=64089603
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810544094.7A Active CN108798031B (zh) | 2018-05-31 | 2018-05-31 | 厨卫间靠墙主立管pvc防水预埋套管施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108798031B (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111022757A (zh) * | 2019-05-20 | 2020-04-17 | 安徽省中功立业建设工程有限责任公司 | 一种建筑给排水及采暖工程用防水与保温施工方法 |
CN116065821A (zh) * | 2023-02-14 | 2023-05-05 | 梁颖 | 一种新型给排水管道套管预埋施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101392560A (zh) * | 2008-09-25 | 2009-03-25 | 陕西省第三建筑工程公司 | 建筑安装管道套管一次到位施工方法 |
JP2009264025A (ja) * | 2008-04-25 | 2009-11-12 | Takasago Thermal Eng Co Ltd | 立て管施工方法および立て管ユニット |
CN103089014A (zh) * | 2013-02-05 | 2013-05-08 | 浙江新东阳建设集团有限公司 | 一种穿楼板管道的施工方法 |
CN103603492A (zh) * | 2013-10-22 | 2014-02-26 | 重庆建工第三建设有限责任公司 | 穿楼层管道预留孔洞施工工艺 |
CN205808414U (zh) * | 2016-07-11 | 2016-12-14 | 新蒲建设集团有限公司 | 一种建筑施工用垂直度检测装置 |
CN206801018U (zh) * | 2017-06-07 | 2017-12-26 | 中建三局集团有限公司 | 一种可循环封闭式放线洞预留定位装置 |
-
2018
- 2018-05-31 CN CN201810544094.7A patent/CN108798031B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2009264025A (ja) * | 2008-04-25 | 2009-11-12 | Takasago Thermal Eng Co Ltd | 立て管施工方法および立て管ユニット |
CN101392560A (zh) * | 2008-09-25 | 2009-03-25 | 陕西省第三建筑工程公司 | 建筑安装管道套管一次到位施工方法 |
CN103089014A (zh) * | 2013-02-05 | 2013-05-08 | 浙江新东阳建设集团有限公司 | 一种穿楼板管道的施工方法 |
CN103603492A (zh) * | 2013-10-22 | 2014-02-26 | 重庆建工第三建设有限责任公司 | 穿楼层管道预留孔洞施工工艺 |
CN205808414U (zh) * | 2016-07-11 | 2016-12-14 | 新蒲建设集团有限公司 | 一种建筑施工用垂直度检测装置 |
CN206801018U (zh) * | 2017-06-07 | 2017-12-26 | 中建三局集团有限公司 | 一种可循环封闭式放线洞预留定位装置 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111022757A (zh) * | 2019-05-20 | 2020-04-17 | 安徽省中功立业建设工程有限责任公司 | 一种建筑给排水及采暖工程用防水与保温施工方法 |
CN116065821A (zh) * | 2023-02-14 | 2023-05-05 | 梁颖 | 一种新型给排水管道套管预埋施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN108798031B (zh) | 2021-04-23 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US9631339B2 (en) | Rehabilitation of deteriorated manhole and other sewer structures | |
CN101392560A (zh) | 建筑安装管道套管一次到位施工方法 | |
CN108798031A (zh) | 厨卫间靠墙主立管pvc防水预埋套管施工方法 | |
CN108301466B (zh) | 整体预制卫生间沉箱和卫生间沉箱构造及其施工方法 | |
CN110424455A (zh) | 地下有限空间无肥槽结构侧墙大钢模板体系及施工方法 | |
CN110594493A (zh) | 适用于已有池壁后埋套管的结构及施工方法 | |
CN104975614B (zh) | 型钢组合式单侧支模加固施工工法 | |
CN105442629A (zh) | 一种大型设备t型台隔振底座施工工法 | |
CN107165316A (zh) | 一种便于安装、成型的装配式钢结构外挂墙板节点及其施工工艺 | |
CN110046363B (zh) | 一种混凝土结构内管道组精确预埋的施工方法 | |
CN1059726C (zh) | 一种楼板与管道间隙防渗漏施工方法及设备 | |
CN102587654A (zh) | Pvc排水直埋管件施工工法 | |
CN211118029U (zh) | 适用于已有池壁后埋套管的结构 | |
KR100509208B1 (ko) | 고무화 아스팔트 및 폴리우레탄레진으로된 몰탈과스테인레스 배수로를 사용한 건축물 지하바닥 및 배수로시공방법 | |
CN102213006A (zh) | Upvc套筒直埋法 | |
AU2012101957A4 (en) | Piping | |
CN112982623A (zh) | 高层建筑排水管道装配式施工方法 | |
CN105350784B (zh) | 利用引管定位技术一次成型预埋套管安装方法 | |
CA2026420C (en) | Plumbing sleeve | |
Puller | The Waterproofness of Structural Diaphragm Walls. | |
JP2008274620A (ja) | さや管 | |
EP0434725A1 (en) | A method and device for laying waste pipes in hollow flooring blocks | |
CN215630818U (zh) | 一种ptw墙板与基础的连接节点结构 | |
CN219933207U (zh) | 一种混凝土浇筑预埋式套管 | |
CN214146797U (zh) | 一种基于直接预埋法的水管防渗铺设系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Construction method of PVC waterproof embedded casing for main riser against wall in kitchen and bathroom Effective date of registration: 20220726 Granted publication date: 20210423 Pledgee: China Construction Bank Corporation Nantong Haimen sub branch Pledgor: CHINA UNION CENTURY CONSTRUCTION GROUP CO.,LTD. Registration number: Y2022320010418 |