CN108797881A - A kind of construction method of heat preservation ceiling structure - Google Patents
A kind of construction method of heat preservation ceiling structure Download PDFInfo
- Publication number
- CN108797881A CN108797881A CN201810611722.9A CN201810611722A CN108797881A CN 108797881 A CN108797881 A CN 108797881A CN 201810611722 A CN201810611722 A CN 201810611722A CN 108797881 A CN108797881 A CN 108797881A
- Authority
- CN
- China
- Prior art keywords
- layer
- heat preservation
- wall
- block
- waterproof
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/001—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by provisions for heat or sound insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/62—Insulation or other protection; Elements or use of specified material therefor
- E04B1/66—Sealings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/06—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
- E04B9/12—Connections between non-parallel members of the supporting construction
- E04B9/16—Connections between non-parallel members of the supporting construction the members lying in different planes
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/18—Means for suspending the supporting construction
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/18—Means for suspending the supporting construction
- E04B9/20—Means for suspending the supporting construction adjustable
Abstract
The invention discloses a kind of construction methods of heat preservation ceiling structure, include the following steps:S1, it pours to build up In-situ cast concrete board and place built-in connection in In-situ cast concrete board on top plate and tiles on heat preservation sunpender and steel wire is installed, the lower end for keeping the temperature sunpender is equipped with adjustable suspender member by heat preservation hanger erection on built-in connection;It simultaneously connect by S2, installation upper layer c-type keel with adjustable suspender member, installs lower layer's c-type keel and directly connect it by levels keel connecting member with upper layer C keel;FC plates are fixed on lower layer's c-type keel by S3, block-by-block, and then block-by-block fills thermal insulation material between steel wire and FC plates;S4, wall-insulation layer is installed on wall.Thermal insulation material is painted on FC plates by the present invention, one-pass molding, need not cut, Pingdu is guaranteed, beautiful appearance, have the characteristics that safety easy for construction, low cost, adiabatic vapor-proof performance are good, heat preservation sunpender, which plays partition cold bridge, prevents what thermal energy from transmitting to scatter and disappear.
Description
Technical field
The present invention relates to a kind of construction methods of heat preservation ceiling structure.
Background technology
Traditional freezer roof heat insulation is directly repeatedly sprayed in structure roof using existing polyurathamc, after molding it is concave-convex not
It is flat, then insulating layer is trimmed with cutter, electric saw, final flatness also is difficult to reach design requirement, and wastes material, people
Work destroys polyurethane foamed thermal-insulating surface hydrophobicity film.
Invention content
In order to solve the above technical problem, the present invention provides a kind of construction methods of heat preservation ceiling structure.
In order to achieve the above object, technical scheme is as follows:
The present invention provides a kind of construction method of heat preservation ceiling structure, includes the following steps:
S1, it is poured on top plate and builds up In-situ cast concrete board and place built-in connection in In-situ cast concrete board, hanger erection will be kept the temperature
In on built-in connection, the tiling installation steel wire on heat preservation sunpender, the lower end for keeping the temperature sunpender is equipped with adjustable suspender member;
S2, installation upper layer c-type keel simultaneously it connect with adjustable suspender member, installation lower layer's c-type keel and by its with it is upper
Layer C keel are directly connected by levels keel connecting member;
FC plates are fixed on lower layer's c-type keel by S3, block-by-block, and then block-by-block fills thermal insulating material between steel wire and FC plates
Material;
S4, wall-insulation layer is installed on wall.
As a preferred option, In-situ cast concrete board includes the concrete Roofing slab from top to bottom set gradually, upper waterproof in step S1
Layer, thermal insulation board, lower waterproof layer, powder flat bed and waterproof vapor barrier layer.
As a preferred option, the thickness of concrete Roofing slab is 4cm, and the thickness of upper layer waterproof concrete is 4-6cm, the thickness of thermal insulation board
Degree is 8-10.5cm, and the thickness of lower layer's waterproof roll is 0.2-0.4cm, and the thickness of powder flat bed is 1.5-2cm.
As a preferred option, lower waterproof layer includes modified asphalt waterproof coiled material and the uncured waterproof layer of rubber asphalt.
As a preferred option, the wall-insulation layer in step S4 includes the wall-insulation being set in turn on exterior wall surface
Plate and protection wall, the top of wall-insulation plate and the junction of In-situ cast concrete board are coated with grease seal layer.
The invention has the advantages that:Compared to the prior art, thermal insulation material is painted on FC plates the present invention,
One-pass molding, need not cut, Pingdu is guaranteed, beautiful appearance, have safety easy for construction, low cost, thermal insulation every vapour
The good feature of energy.Meanwhile by keeping the temperature sunpender, playing partition cold bridge prevents scattering and disappearing for thermal energy transmission.
Specific implementation mode
The following detailed description of the preferred embodiment of the present invention.
In order to reach the purpose of the present invention, a kind of heat preservation ceiling structure is provided in the one of which embodiment of the present invention
Construction method, include the following steps:
S1, it is poured on top plate and builds up In-situ cast concrete board and place built-in connection in In-situ cast concrete board, hanger erection will be kept the temperature
In on built-in connection, the tiling installation steel wire on heat preservation sunpender, the lower end for keeping the temperature sunpender is equipped with adjustable suspender member;
S2, installation upper layer c-type keel simultaneously it connect with adjustable suspender member, installation lower layer's c-type keel and by its with it is upper
Layer C keel are directly connected by levels keel connecting member;
FC plates are fixed on lower layer's c-type keel by S3, block-by-block, and then block-by-block fills thermal insulating material between steel wire and FC plates
Material;
S4, wall-insulation layer is installed on wall.
In order to further optimize the implementation result of the present invention, in another embodiment of the invention, aforementioned interior
On the basis of appearance, In-situ cast concrete board includes the concrete Roofing slab, upper waterproof layer, heat preservation from top to bottom set gradually in above-mentioned step S1
Plate, lower waterproof layer, powder flat bed and waterproof vapor barrier layer.
In order to further optimize the implementation result of the present invention, in another embodiment of the invention, aforementioned interior
On the basis of appearance, the thickness of above-mentioned concrete Roofing slab is 4cm, and the thickness of upper layer waterproof concrete is 4-6cm, and present embodiment is optional
4cm,5cm,6cm;The thickness of thermal insulation board is 8-10.5cm, present embodiment optional 8cm, 9cm, 10.5cm;Lower layer's waterproof roll
Thickness be 0.2-0.4cm, present embodiment optional 0.2cm, 0.3cm, 0.4cm;The thickness of powder flat bed is this implementation of 1.5-2cm
Mode optional 1.5cm, 1.8cm, 2cm;.
In order to further optimize the implementation result of the present invention, in another embodiment of the invention, aforementioned interior
On the basis of appearance, above-mentioned lower waterproof layer includes modified asphalt waterproof coiled material and the uncured waterproof layer of rubber asphalt.
In order to further optimize the implementation result of the present invention, in another embodiment of the invention, aforementioned interior
On the basis of appearance, the wall-insulation layer in above-mentioned step S4 includes the wall-insulation plate being set in turn on exterior wall surface and guarantor
Revetment, the top of wall-insulation plate and the junction of In-situ cast concrete board are coated with grease seal layer.
Compared to the prior art, thermal insulation material is painted on FC plates the present invention, and one-pass molding need not cut, put down
Degree is guaranteed, beautiful appearance, has the characteristics that safety easy for construction, low cost, thermal insulation vapor-proof performance are good.Meanwhile passing through guarantor
Warm sunpender, playing partition cold bridge prevents scattering and disappearing for thermal energy transmission.
What has been described above is only a preferred embodiment of the present invention, it is noted that for those of ordinary skill in the art
For, without departing from the concept of the premise of the invention, various modifications and improvements can be made, these belong to the present invention
Protection domain.
Claims (5)
1. a kind of construction method of heat preservation ceiling structure, which is characterized in that include the following steps:
S1, poured on top plate and build up In-situ cast concrete board and place built-in connection in In-situ cast concrete board, will heat preservation hanger erection in pre-
It buries on connector, the tiling installation steel wire on heat preservation sunpender, the lower end for keeping the temperature sunpender is equipped with adjustable suspender member;
It simultaneously connect by S2, installation upper layer c-type keel with adjustable suspender member, and installation lower layer's c-type keel are simultaneously imperial by itself and upper layer C
Bone is directly connected by levels keel connecting member;
FC plates are fixed on lower layer's c-type keel by S3, block-by-block, and then block-by-block fills thermal insulation material between steel wire and FC plates;
S4, wall-insulation layer is installed on wall.
2. the construction method of heat preservation ceiling structure according to claim 1, which is characterized in that In-situ cast concrete board packet in step S1
Include the concrete Roofing slab from top to bottom set gradually, upper waterproof layer, thermal insulation board, lower waterproof layer, powder flat bed and waterproof vapor barrier layer.
3. the construction method of heat preservation ceiling structure according to claim 2, which is characterized in that the thickness of concrete Roofing slab is
The thickness of 4cm, upper layer waterproof concrete are 4-6cm, and the thickness of thermal insulation board is 8-10.5cm, and the thickness of lower layer's waterproof roll is 0.2-
The thickness of 0.4cm, powder flat bed are 1.5-2cm.
4. the construction method of heat preservation ceiling structure according to claim 3, which is characterized in that lower waterproof layer includes modified drips
Green waterproof roll and the uncured waterproof layer of rubber asphalt.
5. the construction method of heat preservation ceiling structure according to claim 1, which is characterized in that the wall-insulation in step S4
Layer includes the wall-insulation plate being set in turn on exterior wall surface and protection wall, the top of wall-insulation plate and the company of In-situ cast concrete board
The place of connecing is coated with grease seal layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810611722.9A CN108797881A (en) | 2018-06-13 | 2018-06-13 | A kind of construction method of heat preservation ceiling structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810611722.9A CN108797881A (en) | 2018-06-13 | 2018-06-13 | A kind of construction method of heat preservation ceiling structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108797881A true CN108797881A (en) | 2018-11-13 |
Family
ID=64085800
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810611722.9A Pending CN108797881A (en) | 2018-06-13 | 2018-06-13 | A kind of construction method of heat preservation ceiling structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108797881A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112982799A (en) * | 2021-03-02 | 2021-06-18 | 中锦泰(北京)建筑工程有限公司 | Energy-saving building interior decoration structure |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2542352A1 (en) * | 1983-03-10 | 1984-09-14 | Pozzi Michel | Device for installing false ceilings or partitions |
CN101525920A (en) * | 2009-04-03 | 2009-09-09 | 广州拜尔冷链聚氨酯科技有限公司 | Ceiling structure of cold storage and construction method thereof |
CN103883080A (en) * | 2014-03-07 | 2014-06-25 | 沈阳金铠建筑科技股份有限公司 | Integrated roof water prevention and heat preservation structure and construction method thereof |
CN203905254U (en) * | 2014-04-16 | 2014-10-29 | 苏州金螳螂建筑装饰股份有限公司 | Prefabricated installation structure for special-shaped sculpture modelling hung ceiling |
CN106121296A (en) * | 2016-06-29 | 2016-11-16 | 展宏(福建)板业发展有限公司 | A kind of construction method of low-temperature cold store |
-
2018
- 2018-06-13 CN CN201810611722.9A patent/CN108797881A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
FR2542352A1 (en) * | 1983-03-10 | 1984-09-14 | Pozzi Michel | Device for installing false ceilings or partitions |
CN101525920A (en) * | 2009-04-03 | 2009-09-09 | 广州拜尔冷链聚氨酯科技有限公司 | Ceiling structure of cold storage and construction method thereof |
CN103883080A (en) * | 2014-03-07 | 2014-06-25 | 沈阳金铠建筑科技股份有限公司 | Integrated roof water prevention and heat preservation structure and construction method thereof |
CN203905254U (en) * | 2014-04-16 | 2014-10-29 | 苏州金螳螂建筑装饰股份有限公司 | Prefabricated installation structure for special-shaped sculpture modelling hung ceiling |
CN106121296A (en) * | 2016-06-29 | 2016-11-16 | 展宏(福建)板业发展有限公司 | A kind of construction method of low-temperature cold store |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112982799A (en) * | 2021-03-02 | 2021-06-18 | 中锦泰(北京)建筑工程有限公司 | Energy-saving building interior decoration structure |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102116078A (en) | Heat insulation and water prevention integration building roof and construction method thereof | |
CN206693562U (en) | Build composite pad and building heat preservation sound-insulating structure | |
CN106760245A (en) | A kind of anastrophe energy-saving roofing system and its construction method | |
CN107965097B (en) | A kind of roof insulation system and its construction using foam glass board | |
CN105386570A (en) | Breathing thermal insulation roof structure and construction method | |
CN102409816A (en) | Double-layer waterproof heat-preserving fireproof metal roof | |
CN108797881A (en) | A kind of construction method of heat preservation ceiling structure | |
CN203213532U (en) | Low-temperature radiant floor heating construction structure | |
WO2019237760A1 (en) | Energy-saving building system using porous silicate material for thermal insulation | |
CN109297081B (en) | Wall floor heating module and integrated wall floor heating system | |
CN110331822A (en) | A kind of roof heat insulation protection integration product and its construction method | |
CN106223499A (en) | A kind of manufacture method of composite building thermal insulation template | |
JP2001227119A (en) | Roof top construction method for wooden house | |
CN203795636U (en) | Polyurethane foam waterproof heat preservation system for building floor heating | |
CN204326583U (en) | A kind of container type house | |
CN105839864A (en) | Quickly-built sloping roof based on cold-bent thin wall type steel structure | |
RU2728045C1 (en) | Method of overhaul of flat roofing by covering with panels | |
CN103628634B (en) | The energy-conservation dry-method structure of pitched roof heat preservation ventilating and construction method thereof | |
CN205777148U (en) | A kind of based on cold formed steel structure build pitched roof soon | |
CN112064785A (en) | Waterproof node structure of rear window frame of precast concrete outer wall and mounting method of waterproof node structure | |
CN105863180A (en) | Novel roof fireproof isolating belt and construction method thereof | |
CN102140922A (en) | Novel tunnel anti-freezing and heat-insulating layer | |
CN215563906U (en) | High-rise passive house residential building roof heat-insulating waterproof structure in cold region | |
CN108978910A (en) | A kind of water-proof heat-insulating slab | |
CN109159504A (en) | A kind of building roof waterproof layer |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB02 | Change of applicant information | ||
CB02 | Change of applicant information |
Address after: 215000 No. 16 Jinda Road, Weiting Town, Suzhou Industrial Park, Suzhou City, Jiangsu Province Applicant after: Suzhou Erjian Construction Group Co., Ltd. Address before: 215000 No. 16 Jinda Road, Weiting Town, Suzhou Industrial Park, Suzhou City, Jiangsu Province Applicant before: Suzhou Zhongzheng Construction Engineering Co., Ltd. |
|
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181113 |