CN108756222A - 平台支撑体系两段式施工方法 - Google Patents
平台支撑体系两段式施工方法 Download PDFInfo
- Publication number
- CN108756222A CN108756222A CN201810848098.4A CN201810848098A CN108756222A CN 108756222 A CN108756222 A CN 108756222A CN 201810848098 A CN201810848098 A CN 201810848098A CN 108756222 A CN108756222 A CN 108756222A
- Authority
- CN
- China
- Prior art keywords
- shaped steel
- construction method
- beam bottom
- steel pipe
- platform system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/36—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
- E04G11/48—Supporting structures for shutterings or frames for floors or roofs
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明涉及一种平台支撑体系两段式施工方法,第一段施工:将架体搭高度搭设至最大梁底处,形成平台;第二段施工:在平台之上放置板底/梁底支撑工具,将架体搭设至梁底、板底,完成全部的平台支撑体系两段式施工。本发明特别适用于层高较高,梁尺寸差异较大的大空间的标准层及地下室等其他结构,尤其在使用盘扣式支撑体系时有较大优点。
Description
技术领域
本发明涉及一种支撑体系施工方法,具体的说是平台支撑体系两段式施工方法。
背景技术
在建筑施工满堂脚手架搭设时,传统的施工方法是将立杆一次性搭设至梁底、板底,由于梁底、板底立杆间距不一 ,满堂脚手架需要按照不同的净高、间距进行搭设,从而导致整体搭设的速度较慢。
发明内容
本发明旨在克服现有技术的缺陷,提供一种平台支撑体系两段式施工方法,避免不同梁构件对架体造成影响,快速搭设满堂脚手架,并能够在满足安全计算的条件下,最大限度的拉大平台以下的立杆间距。
为了解决上述技术问题,本发明是这样实现的:
一种平台支撑体系两段式施工方法,其特征在于它包括如下步骤:
步骤一:第一段施工;
将钢管支架统一搭设至最大梁底部,形成平台;
在钢管支架架顶平台处搭设若干双榀型钢装置,双榀型钢装置在作为主梁的同时也作为二段施工所用的板底或梁底支撑工具的基础;
步骤二:第二段施工;
在双榀型钢装置上间隔放置若干板底或梁底的支撑工具;
在若干板底或梁底支撑工具之间用横杆连接形成稳定体系。
所述的平台支撑体系两段式施工方法,其特征在于:所述钢管支架的各钢管之间还加设水平管。
所述的平台支撑体系两段式施工方法,其特征在于:所述双榀型钢装置包括两个型钢,两个型钢相对放置且中间留有间距,两个型钢的间距处设有套筒,套筒穿设螺栓且该螺栓两端分别连接两个型钢腹板。
所述的平台支撑体系两段式施工方法,其特征在于:所述板底或梁底支撑工具包括支撑钢管,该支撑钢管上部设有顶托用于托住主梁,所述支撑钢管底部设于上述双榀型钢装置的两个型钢之间的间距内。
本发明的有益效果是:两段式施工方法可以统一平台以下立杆间距及搭设净高,从而提高脚手架搭设的效率。通过本施工方法可以有效避免不同梁构件对架体造成影响,使得平台以下的立杆间距得到统一,实现快速、有效的满堂脚手架搭设,同时能最大限度的在满足安全计算的情况下增大满堂脚手架立杆的纵横间距,实现安全与经济的统一。
附图说明
下面结合附图和实施方式对本发明作进一步的详细说明:
图1为本发明的结构示意图。
具体实施方式
如图1所示:一种平台支撑体系两段式施工方法,它包括如下步骤:
步骤一:第一段施工;
将钢管支架1统一搭设至最大梁底部,形成平台;
在钢管支架架顶平台处搭设若干双榀型钢装置2,双榀型钢装置在作为主梁的同时也作为二段施工所用的板底或梁底支撑工具的基础;
步骤二:第二段施工;
在双榀型钢装置上间隔放置若干板底或梁底的支撑工具3;在若干板底或梁底支撑工具之间用横杆4连接形成稳定体系。
板底或梁底的支撑工具上放置主梁6,主梁上部通过木方7支撑楼板8。
进一步的,所述钢管支架的各钢管之间还加设水平管5。
进一步的,所述双榀型钢装置包括两个型钢,两个型钢相对放置且中间留有间距,两个型钢的间距处设有套筒,套筒穿设螺栓且该螺栓两端分别连接两个型钢腹板。
进一步的,所述板底或梁底支撑工具包括支撑钢管,该支撑钢管上部设有顶托9用于托住主梁,所述支撑钢管底部设于上述双榀型钢装置的两个型钢之间的间距内。
Claims (4)
1.平台支撑体系两段式施工方法,其特征在于它包括如下步骤:
步骤一:第一段施工;
将钢管支架统一搭设至最大梁底部,形成平台;
在钢管支架架顶平台处搭设若干双榀型钢装置,双榀型钢装置在作为主梁的同时也作为二段施工所用的板底或梁底支撑工具的基础;
步骤二:第二段施工;
在双榀型钢装置上间隔放置若干板底或梁底的支撑工具;
在若干板底或梁底支撑工具之间用横杆连接形成稳定体系。
2.根据权利要求1所述的平台支撑体系两段式施工方法,其特征在于:所述钢管支架的各钢管之间还加设水平管。
3.根据权利要求2所述的平台支撑体系两段式施工方法,其特征在于:所述双榀型钢装置包括两个型钢,两个型钢相对放置且中间留有间距,两个型钢的间距处设有套筒,套筒穿设螺栓且该螺栓两端分别连接两个型钢腹板。
4.根据权利要求3所述的平台支撑体系两段式施工方法,其特征在于:所述板底或梁底支撑工具包括支撑钢管,该支撑钢管上部设有顶托用于托住主梁,所述支撑钢管底部设于上述双榀型钢装置的两个型钢之间的间距内。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810848098.4A CN108756222A (zh) | 2018-07-27 | 2018-07-27 | 平台支撑体系两段式施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810848098.4A CN108756222A (zh) | 2018-07-27 | 2018-07-27 | 平台支撑体系两段式施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108756222A true CN108756222A (zh) | 2018-11-06 |
Family
ID=63971639
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810848098.4A Pending CN108756222A (zh) | 2018-07-27 | 2018-07-27 | 平台支撑体系两段式施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108756222A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111206768A (zh) * | 2020-01-16 | 2020-05-29 | 天津鼎维固模架工程股份有限公司 | 一种轻型梁板结构平台及其施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202416854U (zh) * | 2012-01-29 | 2012-09-05 | 青岛两仪环保工程有限公司 | 桌模混凝土模板装置 |
CN203201140U (zh) * | 2013-01-24 | 2013-09-18 | 东南大学 | 一种梁板支撑 |
CN104328909A (zh) * | 2014-10-11 | 2015-02-04 | 罗海军 | 带肋梁楼板模板支设方法 |
CN104563494A (zh) * | 2015-01-13 | 2015-04-29 | 中航天建设工程有限公司 | 一种用于承插盘扣式钢管支撑架的转换支撑体系及施工工法 |
CN206625552U (zh) * | 2017-01-19 | 2017-11-10 | 中国建筑第八工程局有限公司 | 盘扣架上的转换梁装置 |
CN207469744U (zh) * | 2017-11-22 | 2018-06-08 | 江苏速捷模架科技有限公司 | 平台支撑施工装置 |
-
2018
- 2018-07-27 CN CN201810848098.4A patent/CN108756222A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202416854U (zh) * | 2012-01-29 | 2012-09-05 | 青岛两仪环保工程有限公司 | 桌模混凝土模板装置 |
CN203201140U (zh) * | 2013-01-24 | 2013-09-18 | 东南大学 | 一种梁板支撑 |
CN104328909A (zh) * | 2014-10-11 | 2015-02-04 | 罗海军 | 带肋梁楼板模板支设方法 |
CN104563494A (zh) * | 2015-01-13 | 2015-04-29 | 中航天建设工程有限公司 | 一种用于承插盘扣式钢管支撑架的转换支撑体系及施工工法 |
CN206625552U (zh) * | 2017-01-19 | 2017-11-10 | 中国建筑第八工程局有限公司 | 盘扣架上的转换梁装置 |
CN207469744U (zh) * | 2017-11-22 | 2018-06-08 | 江苏速捷模架科技有限公司 | 平台支撑施工装置 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111206768A (zh) * | 2020-01-16 | 2020-05-29 | 天津鼎维固模架工程股份有限公司 | 一种轻型梁板结构平台及其施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106522997B (zh) | 一种隧道及地下工程中拱架的施工台车及施工方法 | |
CN111038940A (zh) | 一种轨道式用于吊装运输的牵引系统 | |
CN206352391U (zh) | 承插型键槽式快拆支撑体系 | |
CN106854941B (zh) | 一种大截面看台斜梁及斜柱的施工方法 | |
CN108756222A (zh) | 平台支撑体系两段式施工方法 | |
CN212866793U (zh) | 一种装配式施工电梯停层平台 | |
CN105625732B (zh) | 超高悬挑钢结构桁架无支撑施工方法 | |
CN207499196U (zh) | 一种装配式建筑外墙干挂节点及预制外墙 | |
CN102787717B (zh) | 自承式组合钢模板施工方法 | |
CN215289748U (zh) | 一种t梁横向连接板缝施工装置 | |
CN205990773U (zh) | 一种施工用卸料平台 | |
CN214090865U (zh) | 一种建筑装饰工程用脚手架 | |
CN205116776U (zh) | 支架通道结构 | |
CN211711873U (zh) | 一种轨道式用于吊装运输的牵引系统 | |
CN203257080U (zh) | 一种建筑施工可调式悬挑支撑装置 | |
CN204778385U (zh) | 一种单轨葫芦的轨道固定结构 | |
CN207003838U (zh) | 一种建筑施工用钢筋支撑架 | |
CN209620622U (zh) | 一种提升平台 | |
CN203430006U (zh) | 一种用于建筑外墙施工的快速拆装悬挑支架 | |
CN206693491U (zh) | 一种带钢筋定位骨架结构的空心保温砌块 | |
CN206846097U (zh) | 一种门刚与框架分装式管道支架结构 | |
CN208604911U (zh) | 一种新型悬吊梁支架 | |
CN202144681U (zh) | 一种橹式钢井架 | |
CN201620419U (zh) | 钢支撑结构 | |
CN203160686U (zh) | 一种新型复合支模架体 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181106 |
|
RJ01 | Rejection of invention patent application after publication |