CN108755737A - 一种预偏值调整板 - Google Patents
一种预偏值调整板 Download PDFInfo
- Publication number
- CN108755737A CN108755737A CN201810784719.7A CN201810784719A CN108755737A CN 108755737 A CN108755737 A CN 108755737A CN 201810784719 A CN201810784719 A CN 201810784719A CN 108755737 A CN108755737 A CN 108755737A
- Authority
- CN
- China
- Prior art keywords
- disk
- adjustment plate
- plane
- bias adjustment
- plate according
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
Abstract
本发明提供了一种预偏值调整板,包括圆盘,所述圆盘的表面为斜面,所述斜面与水平面的高度差为圆盘直径的千分之一十四,操作方便,仅将调整版平放至基础表面,通过地脚螺栓连接即可。
Description
技术领域
本发明涉及输变电设施领域,尤其涉及一种预偏值调整板。
背景技术
目前,110kV、220kV线路钢管塔越来越普遍,其主要特点是占地面积小,环境破坏程度低,多数用于城边使用。该塔型基础均为单腿,断面较大。
此类塔型的耐张塔基础预偏调整方法基本有两种方法:
①基础面制作成斜面,调整预偏。该方法对基础施工阶段工艺及尺寸要求极高,在满足预偏值的基础上还要保证塔脚板与基础之间的间隙,几乎无法达标。
②杆塔设计预弯,主要就是要求塔材加工时,在某处或某段设计高差,调整预偏。该方法在杆塔组立施工过程中极易出现安装使用错误,而且不易发现。
发明内容
本发明的目的在于针对上述现有技术的不足,提供了一种预偏值调整板,能够将预偏值集中至一处,降低基础施工难度,同时又可以确保杆塔组立。
为实现上述目的,本发明采用了如下技术方案:
本发明提供了一种预偏值调整板,包括圆盘,所述圆盘的表面为斜面,所述斜面与水平面的高度差为圆盘直径的千分之一十四。
进一步,所述圆盘上设有多个等间隔设置的螺孔,多个所述螺孔与所述圆盘的圆心之间的间距均相等。
进一步,所述圆盘的高侧为内角侧。
进一步,所述圆盘的低侧为外角侧。
进一步,所述圆盘的水平面与基础相接触,所述圆盘的斜面通过地脚螺栓与杆塔相固定。
进一步,所述地脚螺栓通过所述螺孔将所述圆盘、基础和杆塔相固定。
本发明的有益效果为:1)操作方便,仅将调整版平放至基础表面,通过地脚螺栓连接即可;
2)加工简单,仅需要一块钢板,按照设计图纸尺寸放样即可;
3)可以避免基础施工时,调整基面高差的难点,按照常规方法将基面做平即可;
4)可以弥补、调整在基础施工时产生的尺寸误差。
附图说明
图1为本发明的一种预偏值调整板的结构示意图之一;
图2为本发明的一种预偏值调整板的结构示意图之二。
具体实施方式
为了使本发明的目的、技术方案及优点更加清楚明白,下面结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅用以解释本发明,并不用于限定本发明。
请参阅图1,一种预偏值调整板,包括圆盘1,所述圆盘1的表面为斜面101,所述斜面101与水平面103的高度差104为圆盘直径的千分之一十四。
即,圆盘1包括水平面103和斜面101,斜面101最高处与水平面的高度差为圆盘直径的千分之一十四;能够将预偏值集中至一处,从而降低基础施工难度,又可确保杆塔组立。
请参阅图2,如:假设该基础端面直径D=2000mm,则:
预偏值=2000×14‰=28mm,即斜面101最高处与水平面103的高度差104为28mm。
预偏值为斜面101最高处与水平面的高度差;
所述圆盘1上设有多个等间隔设置的螺孔102,多个所述螺孔102与所述圆盘1的圆心之间的间距均相等。
所述圆盘1的高侧为内角侧。
所述圆盘1的低侧为外角侧。
由于杆塔需要像导地线的反方向倾斜,通过将杆塔底座制作成斜面,将杆塔从根部开始倾斜。
此外,圆盘1的高侧为内角侧,低侧为外角侧,能够使杆塔向后侧倾倒,从而更好的用力。进一步的使塔杆固定牢固。
所述圆盘1的水平面与基础相接触,所述圆盘1的斜面101通过地脚螺栓与杆塔相固定。
所述地脚螺栓通过所述螺孔102将所述圆盘1、基础和杆塔相固定。
以上所述实施例仅表达了本发明的实施方式,其描述较为具体和详细,但并不能因此而理解为对本发明专利范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本发明构思的前提下,还可以做出若干变形和改进,这些都属于本发明的保护范围。因此,本发明专利的保护范围应以所附权利要求为准。
Claims (6)
1.一种预偏值调整板,其特征在于:包括圆盘(1),所述圆盘(1)的表面为斜面(101),所述斜面(101)与水平面的高度差为圆盘直径的千分之一十四。
2.根据权利要求1所述的一种预偏值调整板,其特征在于:所述圆盘(1)上设有多个等间隔设置的螺孔(102),多个所述螺孔(102)与所述圆盘(1)的圆心之间的间距均相等。
3.根据权利要求1所述的一种预偏值调整板,其特征在于:所述圆盘(1)的高侧为内角侧。
4.根据权利要求1所述的一种预偏值调整板,其特征在于:所述圆盘(1)的低侧为外角侧。
5.根据权利要求1所述的一种预偏值调整板,其特征在于:所述圆盘(1)的水平面与基础相接触,所述圆盘(1)的斜面(101)通过地脚螺栓与杆塔相固定。
6.根据权利要求2所述的一种预偏值调整板,其特征在于:所述地脚螺栓通过所述螺孔(102)将所述圆盘(1)、基础和杆塔相固定。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810784719.7A CN108755737A (zh) | 2018-07-17 | 2018-07-17 | 一种预偏值调整板 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810784719.7A CN108755737A (zh) | 2018-07-17 | 2018-07-17 | 一种预偏值调整板 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108755737A true CN108755737A (zh) | 2018-11-06 |
Family
ID=63970514
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810784719.7A Pending CN108755737A (zh) | 2018-07-17 | 2018-07-17 | 一种预偏值调整板 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108755737A (zh) |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202010016548U1 (de) * | 2010-12-14 | 2011-04-14 | Kötter-Rolf, Ludger | Vorrichtung zur kippsicheren Aufnahme einer Stange |
KR20150020512A (ko) * | 2013-08-12 | 2015-02-26 | 현대건설주식회사 | 구조물의 수평, 수직도 조절 위한 트랜지션 피스 |
CN107654106A (zh) * | 2017-09-12 | 2018-02-02 | 国网辽宁省电力有限公司锦州供电公司 | 输电铁塔塔脚更换方法 |
-
2018
- 2018-07-17 CN CN201810784719.7A patent/CN108755737A/zh active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE202010016548U1 (de) * | 2010-12-14 | 2011-04-14 | Kötter-Rolf, Ludger | Vorrichtung zur kippsicheren Aufnahme einer Stange |
KR20150020512A (ko) * | 2013-08-12 | 2015-02-26 | 현대건설주식회사 | 구조물의 수평, 수직도 조절 위한 트랜지션 피스 |
CN107654106A (zh) * | 2017-09-12 | 2018-02-02 | 国网辽宁省电力有限公司锦州供电公司 | 输电铁塔塔脚更换方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108878327B (zh) | 承载机台及其控制方法 | |
CN108755737A (zh) | 一种预偏值调整板 | |
CN208899514U (zh) | 一种预偏值调整板 | |
CN204858400U (zh) | 倾斜杆塔矫正器 | |
CN209975711U (zh) | 可调节架空建筑基座以及架空建筑物 | |
CN207024535U (zh) | 一种便于调节的电力爬杆装置 | |
CN105375243A (zh) | 横向激励大气压co2激光器主电极调节装置 | |
CN202544382U (zh) | 脚手架连墙件固定装置 | |
CN210858018U (zh) | 一种模板支撑装置 | |
CN207874131U (zh) | 一种专用轴承维修支架 | |
CN215128770U (zh) | 一种心理学用沙盘 | |
CN214476267U (zh) | 一种工程现场管理展示装置 | |
CN211413176U (zh) | 一种邦迪管制管机组中的立辊结构 | |
CN101210458A (zh) | 标高可调式超平地坪模板及其制作方法 | |
CN217382274U (zh) | 一种引导型底座 | |
CN102877655B (zh) | 一种可调拉伸装置及采用该装置实现轻型钢梁安装的方法 | |
CN204531354U (zh) | 一种边坡用脚手架底部支撑组件 | |
CN207499449U (zh) | 一种土木工程用建筑模板连接架 | |
CN103383258B (zh) | 双杆底盘根开定位方法及专用定位仪 | |
CN212897559U (zh) | 一种建筑工程用模板支撑梁装置 | |
CN216896099U (zh) | 一种聚氨酯复合管箱用支撑结构 | |
CN215848726U (zh) | 一种防霉防腐竹胶板 | |
CN214933465U (zh) | 一种新型支撑轮 | |
CN201386349Y (zh) | 混凝土结构预埋钢板安装简易微调整平器 | |
CN103137401A (zh) | 一种扫描抑制电极的装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |