CN108747137A - Steel-pipe welding equipment and preparation method thereof - Google Patents
Steel-pipe welding equipment and preparation method thereof Download PDFInfo
- Publication number
- CN108747137A CN108747137A CN201810469504.6A CN201810469504A CN108747137A CN 108747137 A CN108747137 A CN 108747137A CN 201810469504 A CN201810469504 A CN 201810469504A CN 108747137 A CN108747137 A CN 108747137A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- steel
- guide wheel
- pillar
- pipe guide
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23K—SOLDERING OR UNSOLDERING; WELDING; CLADDING OR PLATING BY SOLDERING OR WELDING; CUTTING BY APPLYING HEAT LOCALLY, e.g. FLAME CUTTING; WORKING BY LASER BEAM
- B23K37/00—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups
- B23K37/04—Auxiliary devices or processes, not specially adapted to a procedure covered by only one of the preceding main groups for holding or positioning work
- B23K37/0426—Fixtures for other work
- B23K37/0435—Clamps
- B23K37/0443—Jigs
Abstract
The present invention relates to steel-pipe welding equipment and preparation method thereof, including top plate, it is in transversely arranged pillar that the top plate lower end, which is fixedly connected with four groups, the lower rod end is fixedly connected with bottom plate, one group of pillar side is installed with console, the top plate lower end is fixedly connected with that there are four the clamp systems in lateral equidistant arrangement, the clamp system includes air pump, the air pump lower end is fixedly connected with wheel frame, the wheel frame lower end is rotatably connected to the second steel pipe guide wheel, every group of pillar inner end rotated down is connected with the first steel pipe guide wheel, and first steel pipe guide wheel be located at bottom plate upper end, described first steel pipe guide wheel one end is installed with gear through pillar.Present invention good fixing effect when being welded to steel pipe, steel pipe are not easy to shift in welding, and the invention manufacturing cost is low, and equipment is equipped with welding mechanism, convenient welding, efficient, saving human cost.
Description
Technical field
The present invention relates to steel manufacture field, steel-pipe welding equipment and its preparation side that can carry out efficient welding are referred specifically to
Method.
Background technology
Welded still pipe refer to be welded into again after being deformed into the shapes such as round, rectangular with steel band or steel plate bending, surface has
The steel pipe of seam, the blank that welded still pipe uses is steel plate or strip.
With the progress of rapid development and the welding and inspection technology of quality strip steel rolling production, weldquality constantly carries
The description of height, welded still pipe is increasing, and in more and more fields instead of seamless steel pipe.Welded still pipe is than seamless
Steel pipe is at low cost, production efficiency is high.
Existing equipment needs manually to prepare it, low production efficiency when to steel-pipe welding, in welding, steel
Tube capacity easily shifts.
Invention content
The present invention is exactly directed to the above technical problem, provides a kind of efficient steel-pipe welding equipment and preparation method thereof.
The present invention is mainly achieved through the following technical solutions.
Steel-pipe welding equipment and preparation method thereof, including top plate, the top plate lower end are fixedly connected with four groups in laterally row
The pillar of row, the lower rod end are fixedly connected with bottom plate, and one group of pillar side is installed with console, the top plate
Lower end is fixedly connected there are four the clamp system in lateral equidistant arrangement, and the clamp system includes air pump, the air pump lower end
It is fixedly connected with wheel frame, the wheel frame lower end is rotatably connected to the second steel pipe guide wheel, turns below every group of pillar inner end
It is dynamic to be connected with the first steel pipe guide wheel, and the first steel pipe guide wheel is located at bottom plate upper end, pillar is run through in described first steel pipe guide wheel one end
It is installed with gear, and each two gear is rotatablely connected by hinge, there are two be in pair for installation at the bottom plate upper end center
Claim the welding mechanism of distribution.Each first steel pipe guide wheel is respectively positioned on immediately below the second steel pipe guide wheel.Each hinge is logical
Motor is crossed to be rotatablely connected with gear.Every group of branch column wall has been fixedly connected with two groups of baffles, and baffle is located at clamp system
Side.
Steel-pipe welding equipment and preparation method thereof, step include:Step 1:Two steel pipes are staggered relatively in the first steel pipe
Guide wheel upper end;Step 2:Manipulation console makes air pump drive the second steel pipe guide wheel to bottom offset, the first steel pipe guide wheel and the second steel
Pipe guide wheel is to steel tube clamping;Step 3:Manipulation console makes motor pass through knuckle-joint band moving gear to rotate, make opposite steel pipe displacement
Connect;Step 4:Manipulation welding mechanism welds steel pipe joint;Step 5:Manipulation console makes air pump drive second
Steel pipe guide wheel shifts up, and takes out the steel pipe being welded.
For the present invention in use, two steel pipes are staggered relatively in the first steel pipe guide wheel upper end, manipulation console makes air pump drive
For second steel pipe guide wheel to bottom offset, the first steel pipe guide wheel and the second steel pipe guide wheel to steel tube clamping, manipulation console keeps motor logical
The rotation of knuckle-joint band moving gear is crossed, opposite steel pipe displacement is made to connect, manipulation welding mechanism welds steel pipe joint, manipulates
Console makes air pump that the second steel pipe guide wheel be driven to shift up, and takes out the steel pipe being welded.
Present invention good fixing effect when being welded to steel pipe, steel pipe are not easy to shift in welding, the invention system
Make at low cost, equipment is equipped with welding mechanism, and convenient welding, efficiently saves human cost.
Description of the drawings
In attached drawing, Fig. 1 is main structure chart of the present invention;Fig. 2 is the structure chart of main body clamp system of the present invention.
In figure:1- clamp systems, 2- top plates, 3- pillars, 4- consoles, 5- bottom plates, 6- welding mechanisms, 7- gears, 8- hinges
Chain, 9- motors, the first steel pipes of 10- guide wheel, 11- baffles, 12- air pumps, 13- wheel frames, 14- the second steel pipe guide wheels.
Specific implementation mode
The invention will be further described below in conjunction with the accompanying drawings.
Steel-pipe welding equipment and preparation method thereof, steel-pipe welding equipment and preparation method thereof, including top plate 2,2 lower end of top plate
It is in transversely arranged pillar 3 to be fixedly connected with four groups, and 3 lower end of pillar is fixedly connected with bottom plate 5, and peace is fixed in one group of 3 side of pillar
Equipped with console 4,2 lower end of top plate is fixedly connected there are four the clamp system 1 in lateral equidistant arrangement, and clamp system 1 includes gas
Pump 12,12 lower end of air pump is fixedly connected with wheel frame 13, and 13 lower end of wheel frame is rotatably connected to the second steel pipe guide wheel 14, every group of branch
3 inner end rotated down of column is connected with the first steel pipe guide wheel 10, and the first steel pipe guide wheel 10 is located at 5 upper end of bottom plate, and the first steel pipe is led
It takes turns 10 one end and is installed with gear 7 through pillar 3, and each two gear 7 is rotatablely connected by hinge 8,5 upper end center of bottom plate
There are two the welding mechanisms 6 being symmetric for place's installation.Under each first steel pipe guide wheel 10 is respectively positioned on the second steel pipe guide wheel 14 just
Side.Each hinge 8 is rotatablely connected by motor 9 and gear 7.Every group of 3 inner wall of pillar has been fixedly connected with two groups of baffles 11, and keeps off
Plate 11 is located at 1 side of clamp system.
Steel-pipe welding equipment and preparation method thereof, step include:Step 1:Two steel pipes are staggered relatively in the first steel pipe
10 upper end of guide wheel;Step 2:Manipulation console 4 makes air pump 12 drive the second steel pipe guide wheel 14 to bottom offset, the first steel pipe guide wheel
10 and second steel pipe guide wheel 14 to steel tube clamping;Step 3:Manipulation console 4 makes motor 9 be rotated with moving gear 7 by hinge 8,
Opposite steel pipe displacement is set to connect;Step 4:Manipulation welding mechanism 6 welds steel pipe joint;Step 5:Manipulation control
Platform 4 makes air pump 12 that the second steel pipe guide wheel 14 be driven to shift up, and takes out the steel pipe being welded.
For the present invention in use, two steel pipes are staggered relatively in 10 upper end of the first steel pipe guide wheel, manipulation console 4 makes air pump 12
Drive the second steel pipe guide wheel 14 to bottom offset, the first steel pipe guide wheel 10 and the second steel pipe guide wheel 14 to steel tube clamping, manipulation control
Platform 4 makes motor 9 be rotated with moving gear 7 by hinge 8, and opposite steel pipe displacement is made to connect, and manipulation welding mechanism 6 connects to steel pipe
It is welded at place;Manipulation console 4 makes air pump 12 that the second steel pipe guide wheel 14 be driven to shift up, and takes out the steel pipe being welded.
Present invention good fixing effect when being welded to steel pipe, steel pipe are not easy to shift in welding, the invention system
Make at low cost, equipment is equipped with welding mechanism, and convenient welding, efficiently saves human cost.
The above embodiments merely illustrate the technical concept and features of the present invention, and its object is to allow person skilled in the art
Scholar cans understand the content of the present invention and implement it accordingly, and it is not intended to limit the scope of the present invention.It is all according to the present invention
Equivalent change or modification made by Spirit Essence, should be covered by the protection scope of the present invention.
Claims (5)
1. steel-pipe welding equipment and preparation method thereof, including top plate(2), it is characterised in that:The top plate(2)Lower end is fixedly connected
It is in transversely arranged pillar to have four groups(3), the pillar(3)Lower end is fixedly connected with bottom plate(5), one group of pillar(3)Side
End is installed with console(4), the top plate(2)Lower end is fixedly connected with that there are four the clamp systems in lateral equidistant arrangement
(1), the clamp system(1)Including air pump(12), the air pump(12)Lower end is fixedly connected with wheel frame(13), the guide wheel
Frame(13)Lower end is rotatably connected to the second steel pipe guide wheel(14), every group of pillar(3)Inner end rotated down is connected with the first steel
Pipe guide wheel(10), and the first steel pipe guide wheel(10)Positioned at bottom plate(5)Upper end, the first steel pipe guide wheel(10)Pillar is run through in one end
(3)It is installed with gear(7), and each two gear(7)Pass through hinge(8)Rotation connection, the bottom plate(5)At upper end center
There are two the welding mechanisms being symmetric for installation(6).
2. steel-pipe welding equipment and preparation method thereof according to claim 1, it is characterised in that:Each first steel pipe is led
Wheel(10)It is respectively positioned on the second steel pipe guide wheel(14)Underface.
3. steel-pipe welding equipment and preparation method thereof according to claim 1, it is characterised in that:Each hinge(8)It is logical
Cross motor(9)With gear(7)Rotation connection.
4. steel-pipe welding equipment and preparation method thereof according to claim 1, it is characterised in that:Every group of pillar(3)It is interior
Wall has been fixedly connected with two groups of baffles(11), and baffle(11)Positioned at clamp system(1)Side.
5. steel-pipe welding equipment and preparation method thereof, step include:Step 1:Two steel pipes are staggered relatively to lead in the first steel pipe
Wheel(10)Upper end;Step 2:Manipulate console(4)Make air pump(12)Drive the second steel pipe guide wheel(14)To bottom offset, the first steel
Pipe guide wheel(10)With the second steel pipe guide wheel(14)To steel tube clamping;Step 3:Manipulate console(4)Make motor(9)Pass through hinge
(8)Band moving gear(7)Rotation, makes opposite steel pipe displacement connect;Step 4:Manipulate welding mechanism(6)To steel pipe joint into
Row welding;Step 5:Manipulate console(4)Make air pump(12)Drive the second steel pipe guide wheel(14)It shifts up, taking-up is welded
Steel pipe.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810469504.6A CN108747137A (en) | 2018-05-16 | 2018-05-16 | Steel-pipe welding equipment and preparation method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810469504.6A CN108747137A (en) | 2018-05-16 | 2018-05-16 | Steel-pipe welding equipment and preparation method thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN108747137A true CN108747137A (en) | 2018-11-06 |
Family
ID=64008047
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810469504.6A Pending CN108747137A (en) | 2018-05-16 | 2018-05-16 | Steel-pipe welding equipment and preparation method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108747137A (en) |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1848527A (en) * | 1932-03-08 | Pipe clamp | ||
CN201960139U (en) * | 2011-02-24 | 2011-09-07 | 王京生 | Centerless lathe adopting electric spindle and realizing automatic centering of cylindrical rod and pipe material |
CN202464784U (en) * | 2012-02-27 | 2012-10-03 | 库特勒自动化系统(苏州)有限公司 | Roller and transmission device using same |
CN205771390U (en) * | 2016-06-29 | 2016-12-07 | 上虞市海儿铜铝材有限公司 | Copper pipe traction frame |
CN207043653U (en) * | 2017-08-07 | 2018-02-27 | 永康市鹰鹏化工机械有限公司 | One kind automation steel cylinder welding equipment |
CN207190473U (en) * | 2017-09-12 | 2018-04-06 | 海盐创通机械有限公司 | A kind of sheet material double face film covering device |
-
2018
- 2018-05-16 CN CN201810469504.6A patent/CN108747137A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US1848527A (en) * | 1932-03-08 | Pipe clamp | ||
CN201960139U (en) * | 2011-02-24 | 2011-09-07 | 王京生 | Centerless lathe adopting electric spindle and realizing automatic centering of cylindrical rod and pipe material |
CN202464784U (en) * | 2012-02-27 | 2012-10-03 | 库特勒自动化系统(苏州)有限公司 | Roller and transmission device using same |
CN205771390U (en) * | 2016-06-29 | 2016-12-07 | 上虞市海儿铜铝材有限公司 | Copper pipe traction frame |
CN207043653U (en) * | 2017-08-07 | 2018-02-27 | 永康市鹰鹏化工机械有限公司 | One kind automation steel cylinder welding equipment |
CN207190473U (en) * | 2017-09-12 | 2018-04-06 | 海盐创通机械有限公司 | A kind of sheet material double face film covering device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107570907B (en) | Turnover welding device and method for aluminum T-shaped floor of container | |
CN103832797A (en) | Suspension chain conveyor system | |
CN202037395U (en) | Protective nitrogen filling device for evaporator or condenser brazing | |
CN108247273A (en) | A kind of chassis of semi-trailer welding tooling platform | |
CN108747137A (en) | Steel-pipe welding equipment and preparation method thereof | |
CN105798079B (en) | A kind of bending apparatus for correcting | |
CN201625849U (en) | Universal device for welding bogie tube type girder | |
CN210457330U (en) | Device for manufacturing and installing glass fiber reinforced plastic group tank on anti-corrosion basis on site | |
CN102069816A (en) | Motor hanger and urban rail vehicle bogie | |
CN111441628A (en) | Parking equipment's sideslip frame | |
CN207160687U (en) | A kind of novel tower storehouse lifting comb location structure | |
CN108639153A (en) | It is a kind of can presetting angle dexterous type rise chassis of trailer | |
CN210818126U (en) | Gantry type double-station vertical circulation stereo garage combined rack welding workstation | |
CN102806955A (en) | Six-wheeled full-drive fire-fighting robot moving carrier | |
CN113737645A (en) | Bridge steel box girder U rib detection robot | |
CN207670412U (en) | The roof structure of aluminum alloy bodywork | |
CN207824258U (en) | A kind of accurate cold-drawing device of welded still pipe | |
CN205556024U (en) | Composite wall panel car that overturns | |
CN109500538A (en) | EMU chassis overturns tooling | |
CN209453027U (en) | A kind of rail vehicle side beam welding overturning workbench | |
CN115106788B (en) | Double-layer dislocation sleeving device for ultrathin-wall steel strip | |
CN215889401U (en) | Transfer trolley for artificial construction of steel structural member | |
CN209288004U (en) | A kind of external arc plate automatic correction device | |
CN216104946U (en) | Truss vehicle follow-up workbench | |
CN114274074A (en) | Flexible centering table for automobile top covers of multiple automobile types |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181106 |