CN108729346A - A kind of ring orientation prestress pipeline configuration and production method - Google Patents

A kind of ring orientation prestress pipeline configuration and production method Download PDF

Info

Publication number
CN108729346A
CN108729346A CN201810706850.1A CN201810706850A CN108729346A CN 108729346 A CN108729346 A CN 108729346A CN 201810706850 A CN201810706850 A CN 201810706850A CN 108729346 A CN108729346 A CN 108729346A
Authority
CN
China
Prior art keywords
jurisdiction
precast concrete
concrete
section
arc section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810706850.1A
Other languages
Chinese (zh)
Other versions
CN108729346B (en
Inventor
王磊
汪国栋
马亚飞
张建仁
卢国林
黄艺辉
任亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201810706850.1A priority Critical patent/CN108729346B/en
Publication of CN108729346A publication Critical patent/CN108729346A/en
Application granted granted Critical
Publication of CN108729346B publication Critical patent/CN108729346B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • B28B21/56Methods or machines specially adapted for the production of tubular articles incorporating reinforcements or inserts
    • B28B21/60Methods or machines specially adapted for the production of tubular articles incorporating reinforcements or inserts prestressed reinforcements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B21/00Methods or machines specially adapted for the production of tubular articles
    • B28B21/70Methods or machines specially adapted for the production of tubular articles by building-up from preformed elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/04Pipes or fittings specially adapted to sewers
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Abstract

The invention discloses a kind of ring orientation prestress pipeline configuration and production methods, ring orientation prestress pipeline configuration includes two pieces or more of the precast concrete arc section of jurisdiction mutually spliced, adjacent two pieces of precast concrete arcs section of jurisdiction is connected by expansive concrete, it is provided on the lateral surface of precast concrete arc section of jurisdiction along circumferentially extending reserved groove, the both ends of the precast concrete curved pipe piece circumferential direction are respectively arranged with tenon and blind mortise;The ring orientation prestress pipeline configuration further includes having the annular steel wire being arranged in the reserved groove and and the thrustor for adjusting spacing between two neighboring precast concrete arc section of jurisdiction.Ring orientation prestress pipeline configuration provided by the invention can bear larger pressure, change traditional anchorage problem, fundamentally curved prestressing force is avoided to lose.Production method provided by the invention can realize precast assembly, construction is simple, safe and reliable, extend the application field of ring orientation prestress pipeline configuration.

Description

A kind of ring orientation prestress pipeline configuration and production method
Technical field
The present invention relates to pipe technology field more particularly to a kind of ring orientation prestress pipeline configuration and production method, this hairs Bright prestress pipe can be applied to the engineering construction fields such as municipal pipeline, open caisson, hollow pier.
Background technology
With China's Development of China's Urbanization, municipal project is developed rapidly, what the pipeline configuration in municipal works used It is more and more, such as feedwater piping, open caisson, cofferdam etc..Pipeline configuration passes through spiral shell in assembly between circumferential two neighboring section of jurisdiction It tethers and connects, the gap between adjacent section of jurisdiction is difficult to obtain effectively closed.With water erosion, stratum differential settlement, traffic The influence of load etc., phenomena such as causing section of jurisdiction gap weakness generation infiltration, destroy.The existing applying method to ring orientation prestress Complexity, and anchor is needed, easily lead to anchorage zone loss of prestress.
In existing research, have technical research of the part about pipeline configuration, but for practicability, convenience and peace It is unsatisfactory from the aspect of full property.Such as application No. is a kind of ring orientation prestress of CN201510523909 to reinforce pipeline configuration And production method, pipeline configuration part devise arch bottom, adjacent fast, sealing block and the block that binds, the above reserved groove binds Block reserving hole channel, arch bottom, adjacent fast, sealing block and the block that binds are together in series to form cylindrical structure by steel strand wires, steel strand wires Through the block outstanding that binds, the steel strand wires lockset by protruding from the block that binds, which is fixed, realizes prestress application.This method is prefabricated multiple It is miscellaneous, construction is cumbersome, and it is big to intert steel strand wires difficulty for large span pipeline configuration, causes prestress application effect poor, prestressing force Tensioning precision is low, and prestressing force is easy loss.
For another example application No. is a kind of prestressing force section of jurisdiction of CN201620461935, two inner and outer pipes loops are devised, each Section of jurisdiction ring is connected and composed by several piece head and the tail of being in charge of, and is uniformly distributed on section of jurisdiction along annulus to steel strand wires duct, any to be in charge of piece Each section of jurisdiction ring is connected carry out tensioning by steel strand wires, obtains ring orientation prestress by least one anchorage slot.It is suchlike The ring orientation prestress loss that traditional anchorage style applies is larger, how to improve anchorage style, it is municipal pipe to avoid loss of prestress One of current important research content of road structure.
Invention content
In order to solve existing prestress pipe structure in tension steel strand(Steel wire)When the excessive problem of loss of prestress, this A kind of ring orientation prestress pipeline configuration of invention offer and production method.Specific technical solution is as follows.
A kind of ring orientation prestress pipeline configuration comprising two pieces or more of the precast concrete arc section of jurisdiction mutually spliced, It is characterized in that:Adjacent two pieces of precast concrete arcs section of jurisdiction is connected by expansive concrete, the precast concrete Be provided on the lateral surface of arc section of jurisdiction along circumferentially extending reserved groove, the precast concrete curved pipe piece it is circumferential two End is respectively arranged with tenon and blind mortise, and two neighboring precast concrete arc section of jurisdiction is spliced by tenon and blind mortise;It is described Ring orientation prestress pipeline configuration further includes having the annular steel wire being arranged in the reserved groove and two neighboring pre- for adjusting The thrustor of spacing between concrete arc-shaped section of jurisdiction processed.
Further, the both ends of the surface of the precast concrete curved pipe piece circumferential direction carry out cutting, kerve or wharf's pavement quality;This Sample is conducive to improve the bonding strength of expansive concrete and precast concrete arc section of jurisdiction.
Further, the length of the tenon is less than the depth of the blind mortise so that and two arc sections of jurisdiction intact can contact, Enhance the structural stability of pipeline under the conditions of ensureing that design is prestressed.
Further, the thrustor includes swing handle, turnbarrel, ball bearing and pushing ram, the rotation One end of handle is located at the inside of precast concrete arc section of jurisdiction, and the other end is located in precast concrete arc section of jurisdiction and has Have a handle bevel gear, the turnbarrel has sleeve bevel gear engage with the handle bevel gear, the turnbarrel and The inner ring of the ball bearing is fixedly connected, and the outer ring of the ball bearing, which is fixed, is embedded in precast concrete arc section of jurisdiction It is interior, the pushing ram is provided in the turnbarrel, the turnbarrel and pushing ram are threadedly coupled, and the pushing ram can be made It moves along a straight line and is stretched out from the bottom of the blind mortise and be connected to the tenon.
Further, the annular steel wire is by welding formation ring-type or forming ring-type by anchorage.
Further, the bottom of the reserved groove is provided with the steel plate for accepting the annular steel wire.Steel plate uses Sheet metal bears pressure of the annular steel wire to precast concrete arc section of jurisdiction, improves annular steel wire and precast concrete curved pipe The stress concentration situation of piece junction.
Further, the diameter of the reserved groove of the precast concrete arc section of jurisdiction is more than the annular steel wire Diameter.
Further, the ratio of mud of the expansive concrete ranging from 0.5-1.0.
Further, the expansive concrete is filled in adjacent two blocks of precast concretes by way of high-pressure slip-casting In connection gap between arc section of jurisdiction.Preferably, the grouting pressure of the high-pressure slip-casting is 0.4~0.6MPa.
Further, the concrete grade of the expansive concrete is not less than the concrete etc. of precast concrete arc section of jurisdiction Grade.
Further, it is additionally provided with protective layer coagulation on the outside of precast concrete arc section of jurisdiction and expansive concrete Soil, thickness are not less than 20mm.Annular steel wire can be sealed in the inside of pipeline by cover concrete, and pipeline is avoided to use It is corroded in the process, is conducive to the endurance quality for improving pipeline.
Based on same inventive concept, the invention further relates to a kind of production methods of ring orientation prestress pipeline configuration, main to wrap Include following steps:
A, prefabricated two pieces or more of precast concrete arc section of jurisdiction, edge is provided on the lateral surface of precast concrete arc section of jurisdiction Circumferentially extending reserved groove, steel plate is placed in the bottom of the reserved groove;The precast concrete curved pipe piece is circumferential Both ends be respectively arranged with tenon and blind mortise, the bottom of precast concrete arc section of jurisdiction (1) blind mortise is provided with for adjusting The thrustor (2) of spacing between two neighboring precast concrete arc section of jurisdiction (1);
B, steel wire is circularized into circlewise steel wire according to design diameter is prefabricated;
C, two pieces or more of precast concrete arc section of jurisdiction is spliced into annular shape, annular steel wire is set in whole concretes In the reserved groove of native arc section of jurisdiction, there is gap between adjacent two pieces of precast concrete arcs section of jurisdiction;
D, gap former is installed in the circumferential end of precast concrete arc section of jurisdiction, the gap former is clamped adjacent two simultaneously The surfaces externally and internally of block precast concrete arc section of jurisdiction;
E, the spacing between two neighboring precast concrete arc section of jurisdiction (1) is adjusted by thrustor (2) so that annular steel wire (3) reach scheduled prestressing force;
F, the gap mesohigh between adjacent two pieces of precast concrete arcs section of jurisdiction injects expansive concrete slurries;
G, pipeline is conserved, the prestress application of complete twin conduit, removes gap former after expansive concrete expansion.
Further, it is also had steps of after above-mentioned steps G:In precast concrete arc section of jurisdiction and expansion coagulation Cover concrete is poured into a mould in the outside of soil, and the thickness of cover concrete is not less than 20mm, is conserved after pouring.
Beneficial effects of the present invention are:
1), the present invention ring orientation prestress technology, may be implemented pipeline configuration precast assembly construction, using expansive concrete come Adjacent two pieces of precast concrete arcs section of jurisdiction is connected, expansive concrete and precast concrete arc section of jurisdiction integrate, and improve The water permeability resistance energy of pipeline.The expansion that high-pressure slip-casting uses(Seif-citing rate)Concrete, have impervious strong, early stage it is fast it is hard, after The features such as phase intensity height, energy of resistance to sulfate.
2), high tensile steel wire be close in the reserved groove for being looped around precast concrete arc section of jurisdiction, using auxiliary pusher and Joint gap increases between itself dilatancy of expansive concrete makes adjacent two pieces of precast concrete arcs section of jurisdiction, forces prefabricated Concrete arc-shaped section of jurisdiction is displaced outwardly, so that cricoid high tensile steel wire provides ring orientation prestress for pipeline, the method changes Traditional anchorage technology, fundamentally avoids the loss of curved prestressing force.
3), the present invention ring orientation prestress pipeline configuration, complicated steel wire stretching tool need not be used, due to two pieces with On the diameter of a circle that surrounds of precast concrete arc section of jurisdiction be less than the diameter of annular steel wire, annular steel wire can very easily It is placed in the reserved groove of precast concrete arc section of jurisdiction, precast concrete arc is displaced outwardly again after placing annular steel wire Section of jurisdiction avoids to generate the gap for injecting expansive concrete and wears steel wire in the prior art(Steel strand wires)Cumbersome mistake Journey simplifies construction, reduces cost, saves human and material resources.It is main to be the reduction of curved prestressing force loss.
Description of the drawings
Fig. 1 is the schematic diagram of a specific embodiment of ring orientation prestress pipeline configuration of the present invention;
Fig. 2 is that ring orientation prestress pipeline configuration takes out 1/2 cross section pipe schematic diagram;
Fig. 3 is ring orientation prestress pipeline configuration cross-sectional view;
Fig. 4 is the position view of precast concrete arc section of jurisdiction;
Fig. 5 is the distributing position schematic diagram of annular steel wire;
Fig. 6 is auxiliary pusher front view;
Fig. 7 is auxiliary pusher southwest isometric views;
Fig. 8 is auxiliary pusher southeast isometric views.
In figure:1, precast concrete arc section of jurisdiction, 2, thrustor, 3, annular steel wire, 4, cover concrete, 5, expansion Concrete, 6, reserved groove, 7, gap former, 21, swing handle, 22, screw sheel built in gear, 23, steel ball idler wheel, 24, Screw propulsion rod.
Specific implementation mode
Present invention is further described in detail below in conjunction with the accompanying drawings.
Embodiment 1
Referring to Fig. 1-8, ring orientation prestress pipeline configuration, cross-sectional structure is as shown in figures 1 and 3, including three pieces of mutually splicings Precast concrete arc section of jurisdiction 1, the circumferential both ends in every piece of precast concrete arc section of jurisdiction 1 are respectively arranged with tenon and blind mortise, Two neighboring precast concrete arc section of jurisdiction 1 is spliced by tenon and blind mortise, adjacent two pieces of precast concrete arcs section of jurisdiction 1 Between be expansive concrete 5, precast concrete arc section of jurisdiction 1 and expansive concrete 5 constitute a circular ring pipe together, described swollen Swollen concrete 2 is formed by high-pressure slip-casting;The bottom of blind mortise is provided with for adjusting adjacent two pieces of precast concrete arcs section of jurisdiction 1 Between spacing thrustor 2, the spacing of adjacent two pieces of precast concrete arcs section of jurisdiction 1 can be adjusted by thrustor 2 to be made It obtains annular steel wire 3 and forms scheduled ring orientation prestress;It is provided with reserved groove 6 on the lateral surface of precast concrete arc section of jurisdiction 1, The annular steel wire 3 for fettering three pieces of precast concrete arc sections of jurisdiction 1, the reserved groove 6 are provided in the reserved groove 6 It can preferably be arranged multiple, so that more annular steel wires 3 are arranged on precast concrete arc section of jurisdiction 1, expansive concrete 5 is swollen During swollen, there are increased trend, abducent precast concrete arc in the gap between contiguous prefabricated concrete arc-shaped section of jurisdiction 1 Shape section of jurisdiction 1 forms pulling force to annular steel wire 3, to generate ring orientation prestress to pipeline.It should be noted that, although the present embodiment The middle technical solution using three pieces of precast concrete arc sections of jurisdiction 1, but the present invention can also use two pieces, four pieces or four pieces It combines to form ring orientation prestress pipeline configuration above precast concrete arc section of jurisdiction 1.
Thrustor 2 includes swing handle 21, turnbarrel 22, ball bearing 23 and pushing ram 24, the swing handle 21 one end is located at the inside of precast concrete arc section of jurisdiction 1, and the other end is located in precast concrete arc section of jurisdiction 1 and has There are handle bevel gear, the turnbarrel 22 that there is the sleeve bevel gear engaged with the handle bevel gear, the turnbarrel 22 are fixedly connected with the inner ring of the ball bearing 23, and the outer ring of the ball bearing 23, which is fixed, is embedded in the precast concrete In arc section of jurisdiction 1, the pushing ram 24 is provided in the turnbarrel 22, the turnbarrel 22 and 24 screw thread of pushing ram connect It connects, the pushing ram 24 can be for linear motion and stretching is connected to the tenon from the bottom of the blind mortise.Wherein, this field skill Art personnel are understandable that:The rotation of axial guide groove or gib block limitation pushing ram 24, guide groove can be set on pushing ram 24 Or gib block thinks that the linear motion of pushing ram 24 is realized in cooperation with precast concrete arc section of jurisdiction 1;Turn when rotating swing handle 21 Dynamic handle 21 drives turnbarrel 22 to rotate, and the turnbarrel 22 of rotation drives pushing ram 24 to move along a straight line, and pushing ram 24 abuts In tenon, the adjusting of 1 spacing of adjacent two pieces of precast concrete arcs section of jurisdiction is realized.
Match ratio, expanding material and the volume of expansive concrete, must all determine through overtesting.It, should be according to structure before experiment Necessary expansion rate, speed of expansion, concrete strength and the cement and aggregate used, using constraint identical with pipeline configuration Condition and curing condition are tested, to obtain required swelling agent type and volume, to reach the prestressing force size of design.
The ratio of mud of the expansive concrete ranging from 0.5 ~ 1.0.
The concrete grade of the expansive concrete 5 is not less than the concrete grade of precast concrete arc section of jurisdiction 1.
The high-pressure slip-casting is added to the self-stressing concretes slurries of waterproof material by special high-pressure slip casting, is filled by high pressure Note equipment by the expansive concrete slurries high pressure for being added to waterproof material be injected into adjacent two pieces of precast concrete arcs section of jurisdiction 1 it Between gap in, gap is filled up, meet water after(Water filling)With cross-linking reaction, great amount of carbon dioxide gas is discharged, is generated secondary Elastomer is pressed into and is full of with secondary osmotic pressure and had the gap by osmotic pressure, high pressure thrust, reaches leak-stopping purpose.The grouting pressure is 0.4~0.6MPa.
The circumferential both ends of the surface in precast concrete arc section of jurisdiction 1 carry out cutting, kerve or wharf's pavement quality;Be conducive in this way Improve the bonding strength of expansive concrete 5 and precast concrete arc section of jurisdiction 1.
Preferably, the length of the tenon is less than the depth of the blind mortise so that two arc sections of jurisdiction intact can contact.This Sample can make the structural stability for enhancing pipeline under the conditions of ensureing that design is prestressed.
Preferably, the annular steel wire 3 is by welding formation ring-type or forming ring-type by anchorage.Using anchorage shape Circlewise when steel wire, anchorage can be placed in the gap between adjacent two pieces of precast concrete arcs section of jurisdiction 1, then be inflated coagulation Soil cladding.
Preferably, the bottom for reserving groove 6 is provided with the steel plate for accepting the annular steel wire 3.Steel plate uses thin steel Plate bears pressure of the annular steel wire to precast concrete arc section of jurisdiction, improves annular steel wire and connects with precast concrete arc section of jurisdiction Connect the stress concentration situation at place.The diameter of reserved groove 6 is more than the diameter of annular steel wire 3.
Embodiment 2
On the basis of embodiment 1, ring orientation prestress pipeline configuration of the invention is in precast concrete arc section of jurisdiction and swollen Cover concrete 4 is additionally provided on the outside of swollen concrete, thickness is not less than 20mm.Cover concrete can be by cyclic annular steel Silk is sealed in the inside of pipeline, and pipeline is avoided to be corroded in use, is conducive to the endurance quality for improving pipeline.
The present invention also provides a kind of production method of ring orientation prestress pipeline configuration, specific implementation step is as follows:
1, first, in accordance with conventional casting method and design drawing, precast concrete arc section of jurisdiction 1, precast concrete curved pipe are made Groove 6 is reserved in the outside setting of piece 1, and the diameter for reserving groove 6 is slightly larger than the diameter of annular steel wire 3.
2, after 1 form removal of precast concrete arc section of jurisdiction, section of jurisdiction segmental arc surface residual particle or protrusion are cleared up, prefabricated The circumferential both ends end face of concrete arc-shaped section of jurisdiction 1 carries out kerve, cutting or plucking(Increase section of jurisdiction segmental arc 1 and expansive concrete 2 Between frictional force).
3, annular steel wire 3 is looped around in the reserved groove 6 on precast concrete arc section of jurisdiction 1, and fitted closely therewith.
4, the gap former 7 at the circumferential both ends in precast concrete arc section of jurisdiction 1 is installed, gap former 7 is clamped adjacent simultaneously The surfaces externally and internally of two pieces of precast concrete arc sections of jurisdiction 1.
5, the spacing between two neighboring precast concrete arc section of jurisdiction 1 is adjusted by thrustor 2 so that annular steel wire 3 reach scheduled prestressing force;
6, after pushing tow reaches predetermined pre-tensioning force, the gap mesohigh injection between adjacent two pieces of precast concrete arcs section of jurisdiction is swollen Swollen concrete, match ratio, expanding material and volume by adjusting expansive concrete make actually applied prestressing force be slightly larger than Design prestressing force;
7, the cover concrete 4 for carrying out annular steel wire 3 pours, and cover concrete 4 is located at 1 He of precast concrete arc section of jurisdiction The outside of expansive concrete 2 and annular in shape, wherein the thickness of cover concrete is not less than 20mm, pour complete after maintenance it is circumferential The making of prestress pipe structure.
Ring orientation prestress pipeline configuration provided by the invention can bear very big pressure, change traditional anchorage problem, from Fundamentally curved prestressing force is avoided to lose.The seif-citing rate that its high-pressure slip-casting used uses(Expansion)Concrete has impermeability By force, the features such as early stage is fast hard, later strength is high, the energy of resistance to sulfate.Production method provided by the invention can realize precast assembly, apply Work is simple, safe and reliable, extends the application field of ring orientation prestress pipeline configuration.
The embodiment of the present invention is described with above attached drawing, in the absence of conflict, the reality in the present invention The feature applied in example and embodiment can be combined with each other.The invention is not limited in above-mentioned specific implementation mode, above-mentioned tool Body embodiment is only schematical, rather than limitation, those skilled in the art under the inspiration of the present invention, Without breaking away from the scope protected by the purposes and claims of the present invention, many forms can be also made, these belong to this Within the protection domain of invention.

Claims (10)

1. a kind of ring orientation prestress pipeline configuration comprising two pieces or more of the precast concrete arc section of jurisdiction (1) mutually spliced, It is characterized in that:Adjacent two pieces of precast concrete arcs section of jurisdiction (1) is connected by expansive concrete (5), described prefabricated It is provided on the lateral surface of concrete arc-shaped section of jurisdiction (1) along circumferentially extending reserved groove (6), the precast concrete arc The both ends of section of jurisdiction (1) circumferential direction are respectively arranged with tenon and blind mortise, and two neighboring precast concrete arc section of jurisdiction (1) is by convex Tenon and blind mortise splicing;The ring orientation prestress pipeline configuration further includes having the annular steel wire being arranged in the reserved groove (6) (3) and the thrustor (2) for adjusting spacing between two neighboring precast concrete arc section of jurisdiction (1).
2. a kind of ring orientation prestress pipeline configuration according to claim 1, which is characterized in that the precast concrete arc The both ends of the surface of section of jurisdiction (1) circumferential direction carry out cutting, kerve or wharf's pavement quality;The length of the tenon is less than the depth of the blind mortise.
3. a kind of ring orientation prestress pipeline configuration according to claim 1, which is characterized in that the thrustor(2)Packet Include swing handle(21), turnbarrel(22), ball bearing(23)And pushing ram(24), the swing handle(21)One end position Inside in precast concrete arc section of jurisdiction (1), the other end are located in precast concrete arc section of jurisdiction (1) and have handle Bevel gear, the turnbarrel(22)With the sleeve bevel gear engaged with the handle bevel gear, the turnbarrel(22) With the ball bearing(23)Inner ring be fixedly connected, the ball bearing(23)Outer ring fix be embedded in the concrete In native arc section of jurisdiction (1), the turnbarrel(22)Inside it is provided with the pushing ram(24), the turnbarrel(22)And propulsion Bar(24)It is threadedly coupled, the pushing ram(24)Can it is for linear motion and from the bottom of the blind mortise stretch out be connected to it is described convex Tenon.
4. a kind of ring orientation prestress pipeline configuration according to claim 1, which is characterized in that the reserved groove (6) Bottom is provided with for accepting the annular steel wire(3)Steel plate.
5. a kind of ring orientation prestress pipeline configuration according to claim 1, which is characterized in that the expansive concrete (5) The ratio of mud ranging from 0.5-1.0.
6. a kind of ring orientation prestress pipeline configuration according to claim 1, which is characterized in that the expansive concrete (5) It is filled in by way of high-pressure slip-casting in the gap between adjacent two pieces of precast concrete arcs section of jurisdiction;Preferably, institute The grouting pressure for stating high-pressure slip-casting is 0.4~0.6MPa.
7. a kind of ring orientation prestress pipeline configuration according to claim 1, which is characterized in that the expansive concrete (5) Concrete grade be not less than precast concrete arc section of jurisdiction (1) concrete grade.
8. a kind of ring orientation prestress pipeline configuration according to claim 1, which is characterized in that the precast concrete arc Cover concrete (4) is additionally provided on the outside of section of jurisdiction (1) and expansive concrete (5), thickness is not less than 20mm.
9. a kind of production method of ring orientation prestress pipeline configuration, which is characterized in that include the following steps:
A, prefabricated two pieces or more of precast concrete arc section of jurisdiction (1), sets on the lateral surface of precast concrete arc section of jurisdiction (1) It is equipped with along circumferentially extending reserved groove (6), steel plate, the precast concrete is placed in the bottom of the reserved groove (6) The both ends of arc section of jurisdiction (1) circumferential direction are respectively arranged with tenon and blind mortise, the bottom of precast concrete arc section of jurisdiction (1) blind mortise Portion is provided with the thrustor (2) for adjusting spacing between two neighboring precast concrete arc section of jurisdiction (1);
B, steel wire is circularized into circlewise steel wire (3) according to design diameter is prefabricated;
C, two pieces or more of precast concrete arc section of jurisdiction (1) is spliced into annular shape, annular steel wire (3) is set in whole pre- In the reserved groove (6) of concrete arc-shaped section of jurisdiction (1) processed, there is gap between adjacent two pieces of precast concrete arcs section of jurisdiction (1);
D, in the circumferential end installation gap former (7) of precast concrete arc section of jurisdiction (1), the gap former (7) is simultaneously The surfaces externally and internally of adjacent two pieces of precast concrete arcs section of jurisdiction (1) is clamped;
E, the spacing between two neighboring precast concrete arc section of jurisdiction (1) is adjusted by thrustor (2) so that annular steel wire (3) reach scheduled prestressing force;
F, the gap mesohigh between adjacent two pieces of precast concrete arcs section of jurisdiction (1) injects expansive concrete slurries;
G, pipeline is conserved, the prestress application of complete twin conduit, removes gap former (7) after expansive concrete expansion.
10. a kind of production method of ring orientation prestress pipeline configuration according to claim 9, which is characterized in that above-mentioned It is also had steps of after step G:In precast concrete arc section of jurisdiction (1) and the cast protection of the outside of expansive concrete (5) The thickness of layer concrete (4), cover concrete (4) is not less than 20mm, is conserved after pouring.
CN201810706850.1A 2018-07-02 2018-07-02 Circumferential prestress pipeline structure and manufacturing method thereof Active CN108729346B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810706850.1A CN108729346B (en) 2018-07-02 2018-07-02 Circumferential prestress pipeline structure and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810706850.1A CN108729346B (en) 2018-07-02 2018-07-02 Circumferential prestress pipeline structure and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN108729346A true CN108729346A (en) 2018-11-02
CN108729346B CN108729346B (en) 2023-05-26

Family

ID=63925575

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810706850.1A Active CN108729346B (en) 2018-07-02 2018-07-02 Circumferential prestress pipeline structure and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN108729346B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112647971A (en) * 2020-12-24 2021-04-13 陕西国防工业职业技术学院 BIM subway section of jurisdiction convenient to concatenation
CN113073995A (en) * 2021-03-30 2021-07-06 深圳大学 Self-resetting prestressed pipe piece structure and assembling method thereof
CN117249312A (en) * 2023-08-23 2023-12-19 保定市水泥制管有限公司 Permeation-proof concrete pipeline and production process thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2670602Y (en) * 2003-12-26 2005-01-12 上海同岩土木工程科技有限公司 Shield tunnel prestressing pipe
CN102536265A (en) * 2012-02-03 2012-07-04 葛洲坝集团第五工程有限公司 Shield tunneling prestress lining construction method and used prestressed pipe pieces
CN104612706A (en) * 2015-01-27 2015-05-13 济南轨道交通集团有限公司 Prestressed modulus type duct piece for whole-ring reinforcing in tunnel and construction method
CN204492834U (en) * 2015-01-27 2015-07-22 济南轨道交通集团有限公司 The prestress die numerical expression section of jurisdiction that in a kind of tunnel, semi-ring is reinforced
WO2017081990A1 (en) * 2015-11-11 2017-05-18 鹿島建設株式会社 Precast structure, and construction method for underground structures
CN208395643U (en) * 2018-07-02 2019-01-18 长沙理工大学 A kind of ring orientation prestress pipeline configuration

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2670602Y (en) * 2003-12-26 2005-01-12 上海同岩土木工程科技有限公司 Shield tunnel prestressing pipe
CN102536265A (en) * 2012-02-03 2012-07-04 葛洲坝集团第五工程有限公司 Shield tunneling prestress lining construction method and used prestressed pipe pieces
CN104612706A (en) * 2015-01-27 2015-05-13 济南轨道交通集团有限公司 Prestressed modulus type duct piece for whole-ring reinforcing in tunnel and construction method
CN204492834U (en) * 2015-01-27 2015-07-22 济南轨道交通集团有限公司 The prestress die numerical expression section of jurisdiction that in a kind of tunnel, semi-ring is reinforced
WO2017081990A1 (en) * 2015-11-11 2017-05-18 鹿島建設株式会社 Precast structure, and construction method for underground structures
CN208395643U (en) * 2018-07-02 2019-01-18 长沙理工大学 A kind of ring orientation prestress pipeline configuration

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112647971A (en) * 2020-12-24 2021-04-13 陕西国防工业职业技术学院 BIM subway section of jurisdiction convenient to concatenation
CN113073995A (en) * 2021-03-30 2021-07-06 深圳大学 Self-resetting prestressed pipe piece structure and assembling method thereof
CN113073995B (en) * 2021-03-30 2021-12-07 深圳大学 Self-resetting prestressed pipe piece structure and assembling method thereof
CN117249312A (en) * 2023-08-23 2023-12-19 保定市水泥制管有限公司 Permeation-proof concrete pipeline and production process thereof

Also Published As

Publication number Publication date
CN108729346B (en) 2023-05-26

Similar Documents

Publication Publication Date Title
CN104775428B (en) Compound-type pre-stvessed anchor cable structure and construction method thereof
CN104790394B (en) Prefabricated anchor head pressure anchor wire structure and construction method thereof
CN108729346A (en) A kind of ring orientation prestress pipeline configuration and production method
CN204703160U (en) Two anchoring section prestressed anchor Cable Structure
CN109184737A (en) The tunnel prestressing force constraint of pressure energy-absorbing can be allowed to fill liner supporting system and technique
CN105201514B (en) A kind of water-bearing stratum shaft wall structure and construction method
CN204703159U (en) Prefabricated anchor head pressure anchor wire structure
WO2016058275A1 (en) Underground steel-concrete structure pipeline with spiral composite reinforcement ring on inner wall thereof and manufacturing method thereof
CN103410161A (en) Slant grouting control steel anchor pipe frame and construction method thereof
CN103669346A (en) Sleeve valve pipe and application to landslide control
CN105350531B (en) The pile tube anchor pole composite foundation and construction technology of tension compression bidirectional load can be born
CN106592585A (en) Extension body compaction pile capable of eliminating pile foundation negative friction and construction method
CN206467561U (en) Prefabricated assembled twin columns vase bridge pier
CN101487258B (en) Bearing rope anchor of cable crane and its construction method
CN101982643A (en) Tunnel prestressed concrete lining structure and construction procedure thereof
CN108104121A (en) For improving the structure and method of pressure anchor wire cement grout body compression strength
CN105862990A (en) Prefabricated assembly well wall structure and construction method thereof
CN108677943A (en) Repeatedly control slip casting pre-stressed steel anchor pipe anchor cable composite structure and its construction method
CN205576929U (en) Along with boring with high -pressure slip casting system of tubular pile stake side segmentation
CN208395643U (en) A kind of ring orientation prestress pipeline configuration
CN108824230B (en) Method for reinforcing underwater bridge pier by FRP pipe
CN108867639A (en) The replaceable anchor pole of overall length inflatable gib
CN109113749A (en) Four line large section railway tunnel construction method of weak surrounding rock
CN110593894B (en) Novel shield tunnel concrete pipe piece miniature reinforcing pile
CN208309580U (en) A kind of uplift pile by post-tensioning method being used in combination with pile body grouting behind shaft or drift lining

Legal Events

Date Code Title Description