CN108708265B - A kind of steel camber arch bridge construction method - Google Patents
A kind of steel camber arch bridge construction method Download PDFInfo
- Publication number
- CN108708265B CN108708265B CN201810555228.5A CN201810555228A CN108708265B CN 108708265 B CN108708265 B CN 108708265B CN 201810555228 A CN201810555228 A CN 201810555228A CN 108708265 B CN108708265 B CN 108708265B
- Authority
- CN
- China
- Prior art keywords
- construction
- arch
- steel
- bridge
- installation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D4/00—Arch-type bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of steel camber arch bridge construction methods of technical field of bridge construction, and specific step is as follows for the construction method: S1: foundation pile construction: trestle and platform construction;S2: main arch construction: installation arch springing section pre-buried steel Arch rib positioning steel member;S3: vault support installation: installation closure section steel pipe adjusts welded still pipe after line style;S4: pier column installation: symmetrical to pump lower pipe concrete;S5: floorings bridge floor rack construction: are symmetrically installed to by upstream and downstream from main arch and subarch both ends span centre along bridge;S6: Surfacing Construction: symmetrical construction deck paving appurtenant work, duplication suspender force is simultaneously adjusted to design value, the spray painting coating of steel pipe protection face, after the completion of construction, field test is simultaneously checked and accepted, the present invention is in strict accordance with arrangement and method for construction and construction detailed rules and regulations construction, it can be ensured that stress and deformation in arch erection are controlled, and are guaranteed in arch bridge across the high-precision closure of span centre.
Description
Technical field
The invention discloses a kind of steel camber arch bridge construction methods, specially technical field of bridge construction.
Background technique
Arch bridge is used as a kind of bridge of main supporting member in perpendicular using arch, and arch bridge has across distance
Far, space utilization rate is high, saves the feature of material and shape grace.Arch is the key component in rack construction, cast-in-place coagulation
Need to build arch when native arch bridge to be used to support all or part of arch ring and upper part weight.But existing arch bridge is applied
During work, due to the limitation of its orographic condition of constructing, difficulty of construction is big for arch bridge, long construction period, and the main span of arch bridge encircles knot
Structure zero stress joins the two sections of a bridge, etc, and difficulty is big and closure precision is not high, and there are errors, influence the use of arch bridge.For this purpose, we have proposed one kind
Steel camber arch bridge construction method comes into operation, to solve the above problems.
Summary of the invention
The purpose of the present invention is to provide a kind of steel camber arch bridge construction methods, to solve mentioned above in the background art ask
Topic.
To achieve the above object, the invention provides the following technical scheme: a kind of steel camber arch bridge construction method, the construction method
Specific step is as follows:
S1: foundation pile construction: trestle and platform construction;
Basis and pier stud construction;
5#, 6#, 7# pier capping beam bracket are set up, the construction of 5#, 6#, 7# pier capping beam reaches design to concrete bullet mould and intensity
After value, tensioning bent cap prestressed strand;
S2: main arch construction: installation arch springing section pre-buried steel Arch rib positioning steel member has bound reinforcing bar after-pouring arch springing coagulation
Soil;
Main arch of constructing is basic, sets up bracket, and precompressed, adjustment bracket and template;
The segment main arch 1# and the segment subarch 1# are installed on bracket, and major arch rib 2#~5# section is sequentially installed on bracket
Section and the segment subarch 2#~3#, weld corresponding connector after arch rib line style is adjusted in each segment steel pipe, stull;
S3: vault support installation: installation closure section steel pipe adjusts welded still pipe after line style, and carry out vault concrete
Construction;
The support of erecting and welding vault, and observation mark is carried out on arch rib, observation is carried out in each stage of construction;
S4: pier column installation: it is symmetrical to pump lower pipe concrete, reach design value to down tube concrete layer intensity, bullet mould
It is symmetrical that upper tube inner concrete is perfused and after age concrete phase is greater than four days;
After pipe inner concrete reaches design strength and age concrete phase is greater than four days, transverse girder between arch rib is removed, is installed on arch
Column and intercostal crossbeam;
Pier column and intercostal crossbeam upper bracket are installed, spandrel column and pier column upper beam are installed, master is subsequently mounted
Span of arch middle hanger and span centre suspender crossbeam;
S5: floorings bridge floor rack construction: are symmetrically installed to by upstream and downstream from main arch and subarch both ends along bridge;
Floorings longitudinal wet joint and laterally wet seam are symmetrically poured, with post-stretching suspender force;
S6: Surfacing Construction: symmetrical construction deck paving appurtenant work replicates suspender force and adjusts to design value,
The spray painting coating of steel pipe protection face, after the completion of construction, field test is simultaneously checked and accepted.
It preferably,, should be according to design drawing when installing arch springing section pre-buried steel Arch rib positioning steel member in the step S2
Pre- picture mosaic and peg figure are drawn, rod piece number and quantity is checked, peg length areas, lifting center of gravity position is marked on basic rod piece
It sets and unit weight and installation direction.
Preferably, in the step S2, bracket and arch rib steel pipe use face contact, avoid arch rib steel pipe partial from generating excessive
Concentrated stress.
Preferably, in the step S3, when vault support is installed, it should ensure that the antidumping in steel girder cantilever erection process is steady
Determine coefficient, counterweight balance is carried out with ballast or girder steel self weight, meets Middle span closing maximum cantilever installation requirements, and spell on bracket
When the stringer of the segment steel loading beam 1#, it is necessary to which in the cantilever end of stringer, interim fulcrum is set.
Preferably, in the step S5, during tensioning suspender force, tensioning fulcrum is hung pretensioning span centre sunpender again
Bar, sunpender sunpender, span centre two sides and bridge floor bilateral symmetry tensioning on the outside of tensioning again on the inside of pretensioning.
Compared with prior art, the beneficial effects of the present invention are: the present invention is applied in strict accordance with arrangement and method for construction and construction detailed rules and regulations
Work, it can be ensured that stress and deformation in arch erection are controlled, and are guaranteed in arch bridge across the high-precision closure of span centre.
Detailed description of the invention
Fig. 1 is foundation pile construction structural schematic diagram of the present invention;
Fig. 2 is main arch constructing structure schematic diagram of the present invention;
Fig. 3 is that vault of the present invention supports mounting structure schematic diagram;
Fig. 4 is pier column mounting structure schematic diagram of the present invention;
Fig. 5 is bridge floor rack construction structural schematic diagram of the present invention;
Fig. 6 is Surfacing Construction structural schematic diagram of the present invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on
Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other
Embodiment shall fall within the protection scope of the present invention.
The present invention provides a kind of technical solution: a kind of steel camber arch bridge construction method, specific step is as follows for the construction method:
S1: foundation pile construction: trestle and platform construction;
Basis and pier stud construction;
5#, 6#, 7# pier capping beam bracket are set up, the construction of 5#, 6#, 7# pier capping beam reaches design to concrete bullet mould and intensity
After value, tensioning bent cap prestressed strand, (please referring to Fig. 1);
S2: main arch construction: installation arch springing section pre-buried steel Arch rib positioning steel member has bound reinforcing bar after-pouring arch springing coagulation
Soil should draw pre- picture mosaic and peg figure according to design drawing, check bar when installing arch springing section pre-buried steel Arch rib positioning steel member
Part number and quantity, mark peg length areas, lifting center of gravity position and unit weight and installation direction on basic rod piece;
Main arch of constructing is basic, sets up bracket, and precompressed, adjustment bracket and template, bracket are connect with arch rib steel pipe using face
Touching, avoids arch rib steel pipe partial from generating excessive concentrated stress;
The segment main arch 1# and the segment subarch 1# are installed on bracket, and major arch rib 2#~5# section is sequentially installed on bracket
Section and the segment subarch 2#~3#, weld corresponding connector (please referring to Fig. 2) after arch rib line style is adjusted in each segment steel pipe, stull;
S3: vault support installation: installation closure section steel pipe adjusts welded still pipe after line style, and carry out vault concrete
Construction, when vault support installation, should ensure that the anti-coccidia index in steel girder cantilever erection process, with ballast or girder steel from
Counterweight balance is carried out again, meets Middle span closing maximum cantilever installation requirements, and in the stringer of the assembly segment girder steel 1# on bracket,
Interim fulcrum must be set in the cantilever end of stringer;
The support of erecting and welding vault, and observation mark is carried out on arch rib, observation, which is carried out, in each stage of construction (please refers to
Fig. 3);
S4: pier column installation: it is symmetrical to pump lower pipe concrete, reach design value to down tube concrete layer intensity, bullet mould
It is symmetrical that upper tube inner concrete is perfused and after age concrete phase is greater than four days;
After pipe inner concrete reaches design strength and age concrete phase is greater than four days, transverse girder between arch rib is removed, is installed on arch
Column and intercostal crossbeam;
Pier column and intercostal crossbeam upper bracket are installed, spandrel column and pier column upper beam are installed, master is subsequently mounted
Span of arch middle hanger and span centre suspender crossbeam (please referring to Fig. 4);
S5: floorings bridge floor rack construction: are symmetrically installed to by upstream and downstream from main arch and subarch both ends along bridge;
Floorings longitudinal wet joint and laterally wet contact seam are symmetrically poured, with post-stretching suspender force, in tensioning sunpender
During Suo Li, pretensioning span centre sunpender tensioning fulcrum sunpender again, sunpender sunpender on the outside of tensioning again, span centre two on the inside of pretensioning
Side and bridge floor bilateral symmetry tensioning (please referring to Fig. 5);
S6: Surfacing Construction: symmetrical construction deck paving appurtenant work replicates suspender force and adjusts to design value,
The spray painting coating of steel pipe protection face, after the completion of construction, field test is simultaneously checked and accepted and (please refers to Fig. 6).
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with
A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding
And modification, the scope of the present invention is defined by the appended.
Claims (5)
1. a kind of steel camber arch bridge construction method, it is characterised in that: specific step is as follows for the construction method:
S1: foundation pile construction: trestle and platform construction;
Basis and pier stud construction;
5#, 6#, 7# pier capping beam bracket are set up, 5#, 6#, 7# pier capping beam are constructed, after concrete bullet mould and intensity reach design value,
Tensioning bent cap prestressed strand;
S2: main arch construction: installation arch springing section pre-buried steel Arch rib positioning steel member has bound reinforcing bar after-pouring arch springing concrete;
Main arch of constructing is basic, sets up bracket, and precompressed, adjustment bracket and template;
The segment main arch 1# and the segment subarch 1# are installed on bracket, and sequentially install on bracket the segment major arch rib 2#~5# and
Corresponding connector is welded after arch rib line style is adjusted in each segment steel pipe, stull in the segment subarch 2#~3#;
S3: vault support installation: installation closure section steel pipe adjusts welded still pipe after line style, and carry out applying for vault concrete
Work;
The support of erecting and welding vault, and observation mark is carried out on arch rib, observation is carried out in each stage of construction;
S4: pier column is installed: it is symmetrical to pump lower pipe concrete, reach design value to down tube concrete layer intensity, bullet mould and mixes
It is symmetrical that upper tube inner concrete is perfused after solidifying soil age phase is greater than four days;
After pipe inner concrete reaches design strength and age concrete phase is greater than four days, transverse girder between arch rib is removed, spandrel column is installed
And intercostal crossbeam;
Pier column and intercostal crossbeam upper bracket are installed, spandrel column and pier column upper beam are installed, be subsequently mounted main arch across
Middle hanger and span centre suspender crossbeam;
S5: floorings bridge floor rack construction: are symmetrically installed to by upstream and downstream from main arch and subarch both ends along bridge;
Floorings longitudinal wet joint and laterally wet seam are symmetrically poured, with post-stretching suspender force;
S6: Surfacing Construction: symmetrical construction deck paving appurtenant work replicates suspender force and adjusts to design value, steel pipe
Protection face spray painting coating, after the completion of construction, field test is simultaneously checked and accepted.
2. a kind of steel camber arch bridge construction method according to claim 1, it is characterised in that: in the step S2, installing
When arch springing section pre-buried steel Arch rib positioning steel member, pre- picture mosaic and peg figure should be drawn according to design drawing, check rod piece number and
Quantity marks peg length areas, lifting center of gravity position and unit weight and installation direction on basic rod piece.
3. a kind of steel camber arch bridge construction method according to claim 1, it is characterised in that: in the step S2, bracket with
Arch rib steel pipe uses face contact, and arch rib steel pipe partial is avoided to generate excessive concentrated stress.
4. a kind of steel camber arch bridge construction method according to claim 1, it is characterised in that: in the step S3, vault branch
When support installation, the anti-coccidia index in steel girder cantilever erection process should ensure that, carried out with ballast or girder steel self weight with galassing
Weighing apparatus, meets Middle span closing maximum cantilever installation requirements, and in the stringer of the assembly segment girder steel 1# on bracket, it is necessary in stringer
Interim fulcrum is arranged in cantilever end.
5. a kind of steel camber arch bridge construction method according to claim 1, it is characterised in that: in the step S5, in tensioning
During suspender force, pretensioning span centre sunpender tensioning fulcrum sunpender again, sunpender sunpender on the outside of tensioning again on the inside of pretensioning, across
Middle two sides and bridge floor bilateral symmetry tensioning.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810555228.5A CN108708265B (en) | 2018-06-01 | 2018-06-01 | A kind of steel camber arch bridge construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810555228.5A CN108708265B (en) | 2018-06-01 | 2018-06-01 | A kind of steel camber arch bridge construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108708265A CN108708265A (en) | 2018-10-26 |
CN108708265B true CN108708265B (en) | 2019-10-25 |
Family
ID=63870148
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810555228.5A Active CN108708265B (en) | 2018-06-01 | 2018-06-01 | A kind of steel camber arch bridge construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108708265B (en) |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700103B (en) * | 2019-10-16 | 2022-04-08 | 中铁工程服务有限公司 | Construction method of continuous composite beam |
CN112878171A (en) * | 2021-01-05 | 2021-06-01 | 中交路桥建设有限公司 | Large-span steel structure arch bridge and construction method |
CN112853994A (en) * | 2021-01-18 | 2021-05-28 | 中铁二十局集团第一工程有限公司 | Steel pipe support of arched bridge and construction method thereof |
CN112921827A (en) * | 2021-04-25 | 2021-06-08 | 中国电建市政建设集团有限公司 | Construction method for hoisting large-span steel bridge box girder and hoisting and installing special-shaped component |
CN113202033A (en) * | 2021-04-29 | 2021-08-03 | 中交路桥建设有限公司 | Arch beam cross installation construction method of half-through tied steel box arch bridge |
CN113944095A (en) * | 2021-11-05 | 2022-01-18 | 上海市政工程设计研究总院(集团)有限公司 | Through tied arch bridge and construction method thereof |
CN114408763B (en) * | 2022-03-29 | 2022-08-02 | 河南省豫威起重机有限公司 | Cable crane for hydraulic engineering construction |
CN117470427B (en) * | 2023-12-25 | 2024-02-23 | 贵州路桥集团有限公司 | Horizontal stress measurement method for main arch ring during one-way erection of arch bridge deck |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101289836A (en) * | 2007-12-05 | 2008-10-22 | 中铁大桥局股份有限公司 | Auxiliary erection method of horizontal cable of steel truss arched bridge |
CN201151866Y (en) * | 2008-01-29 | 2008-11-19 | 袁悦 | Arch beam type overbridge |
KR20130000641A (en) * | 2011-06-23 | 2013-01-03 | 주식회사 교량과 고속철도 | A half-trough arch bridge with connection girder for additional longitudinal forces control of continuous welded rail and construction method |
CN102367650A (en) * | 2011-08-05 | 2012-03-07 | 中铁一局集团厦门建设工程有限公司 | Construction method of steel pipe arch bridge |
CN204282187U (en) * | 2014-11-26 | 2015-04-22 | 广东省公路勘察规划设计院股份有限公司 | A kind of novel Butterfly Arch Bridge |
-
2018
- 2018-06-01 CN CN201810555228.5A patent/CN108708265B/en active Active
Also Published As
Publication number | Publication date |
---|---|
CN108708265A (en) | 2018-10-26 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108708265B (en) | A kind of steel camber arch bridge construction method | |
CN110331668B (en) | Construction method of bidirectional inclined V-shaped bridge tower of cable-stayed bridge without back cables | |
CN105648926B (en) | Large-Span Continuous girder span building up station rotation swivel construction method | |
CN102733316B (en) | Integral synchronous rotary jacking construction method for small radius horizontal curved bridge | |
CN102322142B (en) | Construction method for 45-DEG-inclined long-overhanging reinforced concrete structure project | |
CN102808383B (en) | Curved bridge counter-slope jacking construction process | |
CN103850363B (en) | Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall | |
CN105672134A (en) | Through concrete-filled steel tube tied-arch bridge erection construction method | |
CN106192717B (en) | Bridge steel and concrete mixing section and its installation method | |
CN104264592A (en) | Construction method of continuous beam | |
CN111749145A (en) | Incremental launching construction method | |
CN103774560B (en) | The curved bridge construction engineering method of suspension type cast-in-situ template | |
CN105714692A (en) | Cast-in-cantilever beam concrete filled steel tube temporary concretion system | |
CN106400686A (en) | Embedded part suspension bracket and construction method thereof | |
CN112554077A (en) | Steel pipe concrete assembled truss composite beam construction system and construction method | |
CN205242278U (en) | A triangle string basket method is hanged and is watered device for deck bridge construction | |
CN109968522A (en) | The mounting device and installation method of prefabricated case beam bottom web reinforcement skeleton | |
CN111395186B (en) | Method for erecting temporary pier of large-span steel-concrete composite beam cable-stayed bridge | |
CN110983987B (en) | Construction method of steel-concrete combined beam | |
CN206034265U (en) | Steel reinforced concrete of bridge combines section | |
JP4057724B2 (en) | Support structure of bridge girder in extrusion method | |
CN203729211U (en) | Suspension type curved bridge panel cast-in-situ formwork | |
CN114717968A (en) | Construction method for main tower of cable-stayed bridge | |
CN115506272A (en) | Installation and construction method for regular octagonal steel ladle concrete cable tower | |
CN205604085U (en) | Unsettled support of built -in fitting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |