CN108708265A - A kind of steel camber arch bridge construction method - Google Patents
A kind of steel camber arch bridge construction method Download PDFInfo
- Publication number
- CN108708265A CN108708265A CN201810555228.5A CN201810555228A CN108708265A CN 108708265 A CN108708265 A CN 108708265A CN 201810555228 A CN201810555228 A CN 201810555228A CN 108708265 A CN108708265 A CN 108708265A
- Authority
- CN
- China
- Prior art keywords
- construction
- arch
- steel
- bridge
- concrete
- Prior art date
Links
- 238000010276 construction Methods 0.000 title claims abstract description 66
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 53
- 239000010959 steel Substances 0.000 title claims abstract description 53
- 238000009434 installation Methods 0.000 claims abstract description 12
- 280000871617 Vault companies 0.000 claims abstract description 11
- 238000005086 pumping Methods 0.000 claims abstract description 4
- 238000007592 spray painting technique Methods 0.000 claims abstract description 4
- 101710084873 ZBTB8OS Proteins 0.000 claims description 60
- 240000006028 Sambucus nigra Species 0.000 claims description 21
- 230000003601 intercostal Effects 0.000 claims description 6
- 101710042555 EXT2 Proteins 0.000 claims description 3
- 238000005284 basis set Methods 0.000 claims description 3
- 230000000875 corresponding Effects 0.000 claims description 3
- 230000005484 gravity Effects 0.000 claims description 3
- 239000010410 layers Substances 0.000 claims description 3
- 238000000034 methods Methods 0.000 claims description 3
- 230000003014 reinforcing Effects 0.000 claims description 3
- 239000002689 soil Substances 0.000 claims description 3
- 238000003466 welding Methods 0.000 claims description 3
- 239000003224 coccidiostatic agents Substances 0.000 claims description 2
- 238000005303 weighing Methods 0.000 claims 1
- 238000010586 diagrams Methods 0.000 description 6
- 230000015271 coagulation Effects 0.000 description 3
- 238000005345 coagulation Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 2
- 238000006011 modification reactions Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering processes Methods 0.000 description 1
- 239000000463 materials Substances 0.000 description 1
- 238000002360 preparation methods Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D4/00—Arch-type bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Abstract
Description
Technical field
The invention discloses a kind of steel camber arch bridge construction methods, specially technical field of bridge construction.
Background technology
Arch bridge is used as a kind of bridge of main supporting member in perpendicular using arch, and arch bridge has across distance Far, space availability ratio is high, saves the feature of material and shape grace.Arch is the key component in rack construction, cast-in-place coagulation It needs to build arch when native arch bridge to be used for supporting all or part of arch ring and upper part weight.But existing arch bridge is applied During work, due to the limitation of its orographic condition of constructing, the difficulty of construction of arch bridge is big, long construction period, the main span arch knot of arch bridge Structure zero stress joins the two sections of a bridge, etc, and difficulty is big and closure precision is not high, and there are errors, influence the use of arch bridge.For this purpose, we have proposed one kind Steel camber arch bridge construction method comes into operation, to solve the above problems.
Invention content
The purpose of the present invention is to provide a kind of steel camber arch bridge construction methods, to solve mentioned above in the background art ask Topic.
To achieve the above object, the present invention provides the following technical solutions:A kind of steel camber arch bridge construction method, the construction method It is as follows:
S1:Foundation pile construction:Trestle and platform construction;
Basis and pier stud construction;
5#, 6#, 7# pier capping beam holder are set up, the construction of 5#, 6#, 7# pier capping beam waits for that concrete bullet mould and intensity reach design After value, tensioning bent cap prestressed strand;
S2:Main arch is constructed:Arch springing section pre-buried steel Arch rib positioning steel member is installed, reinforcing bar after-pouring arch springing coagulation has been bound Soil;
Construction main arch bracket basis sets up holder, and precompressed, adjustment holder and template;
The segments main arch 1# and the segments subarch 4# are installed on holder, and major arch rib 2#~5# sections are sequentially installed on holder Section and the segments subarch 2#~3#, corresponding connector is welded after arch rib line style is adjusted in each segment steel pipe, stull;
S3:Vault support installation:Closure section steel pipe is installed, adjusts welded still pipe after line style, and carry out arch springing concrete Construction;
Erecting and welding vault supports, and observation mark is carried out on arch rib, and observation is carried out in each stage of construction;
S4:Pier column is installed:The symmetrical lower pipe concrete of pumping waits for that down tube concrete layer intensity, bullet mould reach design value It is symmetrical that upper tube inner concrete is perfused and after age concrete phase is more than four days;
After pipe inner concrete reaches design strength and age concrete phase is more than four days, transverse girder between arch rib is removed, is installed on arch Column and intercostal crossbeam;
Pier column and intercostal crossbeam upper bracket are installed, bridge pier and column upper beam are installed, main arch span centre is subsequently mounted and hangs Bar and span centre suspender crossbeam;
S5:Bridge floor rack construction:From main arch and subarch both ends span centre floorings are symmetrically installed to by upstream and downstream along bridge;
It is symmetrical to pour the contact of bridge panel longitudinal wet and laterally wet contact, with post-stretching suspender force;
S6:Surfacing Construction:Symmetrical construction deck paving appurtenant work replicates suspender force and adjusts to design value, The spray painting application of steel pipe protection face, after the completion of construction, field test is simultaneously checked and accepted.
It preferably,, should be according to design drawing when installing arch springing section pre-buried steel Arch rib positioning steel member in the step S2 Pre- picture mosaic and peg figure are drawn, rod piece number and quantity is checked, spike dowel length areas, lifting center of gravity position is marked on basic rod piece It sets and unit weight and installation direction.
Preferably, in the step S2, holder is contacted with arch rib steel pipe using face, avoids arch rib steel pipe partial from generating excessive Concentrated stress.
Preferably, in the step S3, when vault support is installed, it should ensure that the antidumping in steel girder cantilever erection process is steady Determine coefficient, counterweight balance is carried out with ballast or girder steel dead weight, meets Middle span closing maximum cantilever installation requirements, and spelled on holder When the longeron of the segments steel loading beam 1#, it is necessary to which in the cantilever end of longeron, interim fulcrum is set.
Preferably, in the step S5, during tensioning suspender force, tensioning fulcrum is hung pretensioning span centre sunpender again Bar, sunpender sunpender, span centre both sides and the symmetrical tensioning of bridge floor on the outside of tensioning again on the inside of pretensioning.
Compared with prior art, the beneficial effects of the invention are as follows:The present invention is applied in strict accordance with arrangement and method for construction and construction detailed rules and regulations Work, it can be ensured that stress and deformation in arch erection are controlled, and are ensured in arch bridge across the high-precision closure of span centre.
Description of the drawings
Fig. 1 is foundation pile construction structural schematic diagram of the present invention;
Fig. 2 is main arch constructing structure schematic diagram of the present invention;
Fig. 3 is that vault of the present invention supports mounting structure schematic diagram;
Fig. 4 is pier column mounting structure schematic diagram of the present invention;
Fig. 5 is bridge floor rack construction structural schematic diagram of the present invention;
Fig. 6 is Surfacing Construction structural schematic diagram of the present invention.
Specific implementation mode
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation describes, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
The present invention provides a kind of technical solution:A kind of steel camber arch bridge construction method, the construction method are as follows: S1:Foundation pile construction:Trestle and platform construction;
Basis and pier stud construction;
5#, 6#, 7# pier capping beam holder are set up, the construction of 5#, 6#, 7# pier capping beam waits for that concrete bullet mould and intensity reach design After value, tensioning bent cap prestressed strand, (please referring to Fig.1);
S2:Main arch is constructed:Arch springing section pre-buried steel Arch rib positioning steel member is installed, reinforcing bar after-pouring arch springing coagulation has been bound Soil should draw pre- picture mosaic and peg figure according to design drawing, check bar when installing arch springing section pre-buried steel Arch rib positioning steel member Part is numbered and quantity, and spike dowel length areas, lifting center of gravity position and unit weight and installation direction are marked on basic rod piece;
Construction main arch bracket basis sets up holder, and precompressed, adjustment holder and template, holder use face with arch rib steel pipe Contact, avoids arch rib steel pipe partial from generating excessive concentrated stress;
The segments main arch 1# and the segments subarch 4# are installed on holder, and major arch rib 2#~5# sections are sequentially installed on holder Section and the segments subarch 2#~3#, corresponding connector (please referring to Fig. 2) is welded after arch rib line style is adjusted in each segment steel pipe, stull;
S3:Vault support installation:Closure section steel pipe is installed, adjusts welded still pipe after line style, and carry out arch springing concrete Construction, when vault support installation, should ensure that the anti-coccidia index in steel girder cantilever erection process, with ballast or girder steel from Counterweight balance is carried out again, meets Middle span closing maximum cantilever installation requirements, and in the longeron of the assembly segments girder steel 1# on holder, Must interim fulcrum be set in the cantilever end of longeron;
Erecting and welding vault supports, and observation mark is carried out on arch rib, and carrying out observation in each stage of construction (please refers to Fig. 3);
S4:Pier column is installed:The symmetrical lower pipe concrete of pumping waits for that down tube concrete layer intensity, bullet mould reach design value It is symmetrical that upper tube inner concrete is perfused and after age concrete phase is more than four days;
After pipe inner concrete reaches design strength and age concrete phase is more than four days, transverse girder between arch rib is removed, is installed on arch Column and intercostal crossbeam;
Pier column and intercostal crossbeam upper bracket are installed, bridge pier and column upper beam are installed, main arch span centre is subsequently mounted and hangs Bar and span centre suspender crossbeam (please referring to Fig. 4);
S5:Bridge floor rack construction:From main arch and subarch both ends span centre floorings are symmetrically installed to by upstream and downstream along bridge;
It is symmetrical to pour the contact of bridge panel longitudinal wet and laterally wet contact, with post-stretching suspender force, in tensioning sunpender During Suo Li, pretensioning span centre sunpender tensioning fulcrum sunpender again, sunpender sunpender on the outside of tensioning again, span centre two on the inside of pretensioning Side and the symmetrical tensioning of bridge floor (please referring to Fig. 5);
S6:Surfacing Construction:Symmetrical construction deck paving appurtenant work replicates suspender force and adjusts to design value, The spray painting application of steel pipe protection face, after the completion of construction, field test is simultaneously checked and accepted and (please refers to Fig. 6).
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with Understanding without departing from the principles and spirit of the present invention can carry out these embodiments a variety of variations, modification, replace And modification, the scope of the present invention is defined by the appended.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810555228.5A CN108708265B (en) | 2018-06-01 | 2018-06-01 | A kind of steel camber arch bridge construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810555228.5A CN108708265B (en) | 2018-06-01 | 2018-06-01 | A kind of steel camber arch bridge construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108708265A true CN108708265A (en) | 2018-10-26 |
CN108708265B CN108708265B (en) | 2019-10-25 |
Family
ID=63870148
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810555228.5A CN108708265B (en) | 2018-06-01 | 2018-06-01 | A kind of steel camber arch bridge construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108708265B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700103A (en) * | 2019-10-16 | 2020-01-17 | 中铁工程服务有限公司 | Construction method of continuous composite beam |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101289836A (en) * | 2007-12-05 | 2008-10-22 | 中铁大桥局股份有限公司 | Auxiliary erection method of horizontal cable of steel truss arched bridge |
CN201151866Y (en) * | 2008-01-29 | 2008-11-19 | 袁悦 | Arch beam type overbridge |
CN102367650A (en) * | 2011-08-05 | 2012-03-07 | 中铁一局集团厦门建设工程有限公司 | Construction method of steel pipe arch bridge |
KR20130000641A (en) * | 2011-06-23 | 2013-01-03 | 주식회사 교량과 고속철도 | A half-trough arch bridge with connection girder for additional longitudinal forces control of continuous welded rail and construction method |
CN204282187U (en) * | 2014-11-26 | 2015-04-22 | 广东省公路勘察规划设计院股份有限公司 | A kind of novel Butterfly Arch Bridge |
-
2018
- 2018-06-01 CN CN201810555228.5A patent/CN108708265B/en active IP Right Grant
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101289836A (en) * | 2007-12-05 | 2008-10-22 | 中铁大桥局股份有限公司 | Auxiliary erection method of horizontal cable of steel truss arched bridge |
CN201151866Y (en) * | 2008-01-29 | 2008-11-19 | 袁悦 | Arch beam type overbridge |
KR20130000641A (en) * | 2011-06-23 | 2013-01-03 | 주식회사 교량과 고속철도 | A half-trough arch bridge with connection girder for additional longitudinal forces control of continuous welded rail and construction method |
CN102367650A (en) * | 2011-08-05 | 2012-03-07 | 中铁一局集团厦门建设工程有限公司 | Construction method of steel pipe arch bridge |
CN204282187U (en) * | 2014-11-26 | 2015-04-22 | 广东省公路勘察规划设计院股份有限公司 | A kind of novel Butterfly Arch Bridge |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110700103A (en) * | 2019-10-16 | 2020-01-17 | 中铁工程服务有限公司 | Construction method of continuous composite beam |
Also Published As
Publication number | Publication date |
---|---|
CN108708265B (en) | 2019-10-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101200916B (en) | Construction method of prestressed suspension type building structure | |
CN101126279B (en) | Silo slipform construction technique | |
CN105568866B (en) | Across the large-span steel box beam push construction method of existing road | |
CN104975566B (en) | Apply the steel pipe support in cable-stayed bridge arch tower is constructed | |
CN101845849B (en) | Large-span steel gallery erected between new building and old building and construction method thereof | |
CN103741601B (en) | Tower, beam and cable synchronous bridge forming technology | |
CN101487232A (en) | Steel box girder assembling construction method | |
CN101503911B (en) | High-altitude integral jacking and longitudinal slope regulation construction process and system for multi-span simply supported bridge | |
CN103437279B (en) | Overhead cast-in-place box compression struts and construction technology thereof | |
Han et al. | Flexural behaviour of concrete filled steel tubular (CFST) chord to hollow tubular brace truss: experiments | |
CN102418315B (en) | Construction method for concrete-filled steel tube arched bridge with large low-buckle tower erection bridge width | |
CN205329560U (en) | Large -span continuous beam bridge strides existing station rotation construction with system of turning | |
CN102493362B (en) | Construction method for midspan closure segment of longspan continuous rigid frame bridge | |
CN101768916A (en) | Lower flange improved corrugated steel web plate composite box girder and construction method thereof | |
CN102505636B (en) | Construction method of No.0 block of continuous rigid frame bridge of double-thin-wall pier | |
CN108004928B (en) | A kind of asymmetric rigid frame-continuous girder construction technology | |
CN103643800B (en) | The erection & lift system of buckling-restrained bracing member and construction method thereof | |
KR101259138B1 (en) | Rahmen bridge with structure for joining beams and walls | |
CN102587286A (en) | Simply supported-continuous construction method for bridge superstructure | |
CN103711201A (en) | Large-span prestressed concrete beam board frame structural system | |
CN108457188B (en) | A kind of walking incremental launching construction by multipoint jacking construction | |
CN107905114B (en) | A kind of construction method of large span Successive interference cancellation | |
CN105952474A (en) | Rapid construction method for primary support of confined concrete of large-section tunnel | |
CN108660903A (en) | CFST Arch Bridge and construction method | |
CN103510541B (en) | In a kind of mast-up hole, the device of steel pipe column is installed in lifting |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |