CN108708264A - A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete - Google Patents

A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete Download PDF

Info

Publication number
CN108708264A
CN108708264A CN201810519505.7A CN201810519505A CN108708264A CN 108708264 A CN108708264 A CN 108708264A CN 201810519505 A CN201810519505 A CN 201810519505A CN 108708264 A CN108708264 A CN 108708264A
Authority
CN
China
Prior art keywords
concrete
level
pipe
pumping
arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810519505.7A
Other languages
Chinese (zh)
Inventor
王建军
周邦鸿
韩玉
杜海龙
袁征
翁贻令
何建乔
苏萍
李彩霞
杨占峰
王承亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road and Bridge Engineering Group Co Ltd
Original Assignee
Guangxi Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road and Bridge Engineering Group Co Ltd filed Critical Guangxi Road and Bridge Engineering Group Co Ltd
Priority to CN201810519505.7A priority Critical patent/CN108708264A/en
Publication of CN108708264A publication Critical patent/CN108708264A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D4/00Arch-type bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The present invention provides a kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, belongs to Long-Span Concrete Filled Steel Tubular Arch Bridges technical field of construction.Main arch rib carries out pipe inner concrete pouring construction by the way of being classified endless relay;Wherein, pipe inner concrete perfusion uses jack-block, according to symmetrically with load balance principle, with vault for symmetrical center line, bridge two halves are across symmetrical concrete perfusion;The present invention provides a kind of multi-stage construction methods of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, this construction method constructs to main arch fin steel tube by the way of series classification relay concrete perfusion, securely and reliably, energy saving, greatly reduce plugging risk.

Description

A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete
【Technical field】
The present invention relates to large-span concrete arch bridges construction field, especially a kind of Long-Span Concrete Filled Steel Tubular Arch Bridges The multi-stage construction method of filling concrete.
【Technical background】
The perfusion of pipe inner concrete is one of crucial process of CFST Arch Bridge Construction, and filling concrete is constructed usually By conditionalities such as arch bridge height, concrete quality, equipment performances.Pipe inner concrete pouring construction mostly uses jack-block, closely Vacuum auxiliary pouring method has been invented over year, has in addition to this had no technologic great innovation.With the development of economy and technology, steel The span and height of pipe concrete arch bridge are increasing, and the construction of pipe inner concrete is increasingly difficult to.Currently, CFST Arch Bridge Span has reached 530m, and rise reaches 110m, and single string pipe concrete reaches 1000m3.As this span is big, height is big, single fills Note side measures big steel pipe arch bridge and constructs according to the method for being once filled into top, plugging dangerous.Once there are the feelings such as plugging Condition certainly will seriously affect the quality of concrete in pipe, bring subsequent processing problem.
Therefore, the new side that a kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete is development is studied To.
【Invention content】
In view of posed problems above, the present invention provides a kind of points of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete Grade construction method, this construction method uses stagewise endless relay concrete perfusion, securely and reliably, energy saving, can also be big It is big to reduce plugging risk.
Technical scheme is as follows:
A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, adopts main arch ribbed pipe inner concrete It is irrigated construction with the mode of series classification relay;Wherein, the method for filling of the pipe inner concrete uses jack-block, according to Symmetrically with balance loading principle, with vault for symmetrical center line, bridge two halves are across concrete perfusion simultaneously.It is main in pumping procedure The two halves of arch rib pipe are less than 6m across the progress difference that pours of inner concrete3
Further, 60m is more than for arch rib rise or the CFST Arch Bridge that duration is more than 8h is perfused, using classification Construction method.
Further, every level-one after being classified to the main arch rib is equipped with a stock inlet and a thick liquid discharge mouth;Wherein, The first order stock inlet is set near the arch springing of arch bridge, and afterbody thick liquid discharge mouth is set to vault;(n+1)th grade of stock inlet can be used as N-th grade of thick liquid discharge mouth, n >=1.
Further, the main arch rib unilateral side filling concrete work progress includes the following steps:
S1:Main arch rib rinses:Water is injected into arch rib steel pipe from vault discharge pipe, cleans steel pipe inner wall, and by being opened in The mud hole discharge iron rust of main arch rib tubular arch underfooting edge and other sundries, stop note after flow is limpid and no-sundries exclude Water closes mud hole after the water in main arch ribbed pipe all discharge by electric welding;
S2:First order Concrete Pumping Construction:After carrying out profit pipe operation to concrete pump pipe, by pump machine and level-one inlet pipe Connection, concrete is pumped into main arch ribbed pipe;When concrete pumping to level-one grout outlet position, the discharge of level-one grout outlet is opened Laitance;After laitance is drained, pause level-one pumping;
S3:Second level Concrete Pumping Construction:After level-one concrete laitance drains, starts two level and pump program;To two After grade pump line carries out profit pipe, it is pumped into concrete, after pump line stablizes discharge concrete, two level stock inlet is accessed, into arch rib pipe It is pumped into concrete;The first order continues pump concrete, until pipe inner concrete boundary face is more than two level inlet pipe 3~5m height When, stop level-one pump machine, closes level-one plasma discharge tube valve;Continue pump concrete, concrete pumping to two level pulp in the second level When pipe position, opens two level discharge pipe and laitance is discharged;After laitance is drained, pause two level pumping;
S4:N-th grade of Concrete Pumping Construction:Step S3 is repeated, the pumping construction of the concrete of corresponding stage is completed;
S5:Vault plasma discharge operates:Upward relay pumping concrete step by step repeat the above steps until vault is pumped to, when mixed After solidifying soil is pumped to vault, slow down rate of pumping, continues pump concrete, wait for that laitance drains, and in one continuous time When the good concrete of interior stable discharge character, pause pumping;After standing 5~10min, it is further continued for pumping 5~10min coagulations Soil;Above-mentioned plasma discharge operation is repeated until discharge pipe bubble-free is overflowed, and significant change does not occur and can stop for concrete character Only pump concrete closes final stage inlet pipe valve, completes the pouring construction of unilateral main arch ribbed pipe.
Further, the concrete uses the high performance concrete with self-compaction and shrinkage-compensating function, wherein mixed The expansion degree for coagulating soil reaches 600mm or more, and the presetting period is more than 1.5 times of single-stage construction times.
The present invention has the following advantages that compared with prior art:
1. to main arch fin steel tube, to be pumped method from arch springing to vault, main arch rib is perfused in a manner of endless relay to be classified in the present invention Pipe inner concrete significantly reduces long-span arch bridge the pumping pressure of concrete, greatly reduces and blocks wind in generator tube Danger.
2. it is long and lead to avoid the single construction time using classification endless relay pouring construction for main arch ribbed pipe inner concrete The concrete flowability of cause is lost, and is reduced the sensibility that pouring construction requires working performance of concrete, is substantially reduced mixed Solidifying soil regulation and control difficulty.
In short, the present invention provides a kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, this Kind construction method is irrigated main arch rib using classification endless relay concrete perfusion mode, and safe operation saves energy consumption, greatly It is big to reduce construction cost, effectively reduce plugging risk.
【Specific implementation mode】
The following examples can help those skilled in the art that the present invention is more completely understood, but cannot be with any Mode limits the present invention.
Prepare before construction:The every quality detection work for completing tubular arch in CFST Arch Bridge passes through the inspection at scene Arch rib axis and verification absolute altitude are surveyed, grading design is completed;Then each grade of arch rib is carried out opening up stock inlet, thick liquid discharge mouth etc., and Classification welding inlet pipe, discharge pipe, complete the installation of each nozzle valve.
Embodiment 1
A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, adopts main arch ribbed pipe inner concrete It is irrigated construction with the mode of series classification relay;Wherein, the method for filling of the pipe inner concrete uses jack-block, according to Symmetrically with balance loading principle, with vault for symmetrical center line, bridge two halves are across concrete perfusion simultaneously.It is main in pumping procedure The two halves of arch rib pipe are less than 6m across the progress difference that pours of inner concrete3.Wherein, in the multi-stage construction, classification perfusion length root It is determined according to diameter of steel tube, height, concrete performance and the pump power in concrete engineering;The concrete, which uses, to be had certainly The closely knit high performance concrete with shrinkage-compensating function, wherein:Concrete expansion degree should reach 600mm or more, and Slow setting time is answered More than 1.5 times single-stage construction times.
Every level-one after being classified to the main arch rib is equipped with a stock inlet and a thick liquid discharge mouth;Wherein, described first Grade stock inlet is set near the arch springing of arch bridge, and afterbody thick liquid discharge mouth is set to vault;(n+1)th grade of stock inlet can be used as n-th grade of row Starch mouth, n >=1.
Concrete perfusion process includes the following steps in half across the main arch ribbed pipe:
S1:Main arch rib rinses:Water is injected into arch rib steel pipe from vault discharge pipe, cleans steel pipe inner wall, and by being opened in The mud hole discharge iron rust of main arch rib tubular arch underfooting edge and other sundries, stop note after flow is limpid and no-sundries exclude Water closes mud hole after the water in main arch ribbed pipe all discharge by electric welding;
S2:First order Concrete Pumping Construction:After carrying out profit pipe operation to concrete pump pipe, by pump machine and level-one inlet pipe Connection, concrete is pumped into main arch ribbed pipe;When concrete pumping to level-one grout outlet position, the discharge of level-one grout outlet is opened Laitance;After laitance is drained, pause level-one pumping;
S3:Second level Concrete Pumping Construction:After level-one concrete laitance drains, starts two level and pump program;To two After grade pump line carries out profit pipe, it is pumped into concrete, after pump line stablizes discharge concrete, two level stock inlet is accessed, into arch rib pipe It is pumped into concrete;The first order continues pump concrete, until when pipe inner concrete boundary face is more than two level inlet pipe 3m height, Stop level-one pump machine, closes level-one plasma discharge tube valve;Continue pump concrete, concrete pumping to two level grout outlet position in the second level When setting, opens two level discharge pipe and laitance is discharged;After laitance is drained, pause two level pumping;
S4:Vault plasma discharge operates:Upward relay pumping concrete step by step repeat the above steps until vault is pumped to, when mixed After solidifying soil is pumped to vault, slow down rate of pumping, continues pump concrete, wait for that laitance drains, and in one continuous time When the good concrete of interior stable discharge character, pause pumping;After standing 5min, it is further continued for pumping 5min concrete;Repeatedly into Row above-mentioned plasma discharge operation is until discharge pipe bubble-free is overflowed, and significant change does not occur for concrete character can stop pumped concrete Soil closes final stage inlet pipe valve, completes the pouring construction of unilateral main arch ribbed pipe.
Work progress is smooth, and plugging does not occur, and the concrete character of discharge is good.To the concrete filled steel tube that finishes of construction at Type quality carries out pipeline section ultrasound examination, and the average velocity of wave for surveying each section is 4710 ± 108m/s;Illustrate using this The multi-stage construction method of invention can make steel pipe inner concrete homogeneous closely knit.
Embodiment 2
A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, adopts main arch ribbed pipe inner concrete It is irrigated construction with the mode of series classification relay;Wherein, the method for filling of the pipe inner concrete uses jack-block, according to Symmetrically with balance loading principle, with vault for symmetrical center line, bridge two halves are across concrete perfusion simultaneously.It is main in pumping procedure The two halves of arch rib pipe are less than 6m across the progress difference that pours of inner concrete3.Wherein, in the multi-stage construction, classification perfusion length root It is determined according to diameter of steel tube, height, concrete performance and the pump power in concrete engineering;The concrete, which uses, to be had certainly The closely knit high performance concrete with shrinkage-compensating function, wherein:Concrete expansion degree should reach 600mm or more, and Slow setting time is answered More than 1.5 times single-stage construction times.
Every level-one after being classified to the main arch rib is equipped with a stock inlet and a thick liquid discharge mouth;Wherein, described first Grade stock inlet is set near the arch springing of arch bridge, and afterbody thick liquid discharge mouth is set to vault;(n+1)th grade of stock inlet can be used as n-th grade of row Starch mouth, n >=1.
Concrete perfusion process includes the following steps in half across the main arch ribbed pipe:
S1:Main arch rib rinses:Water is injected into arch rib steel pipe from vault discharge pipe, cleans steel pipe inner wall, and by being opened in The mud hole discharge iron rust of main arch rib tubular arch underfooting edge and other sundries, stop note after flow is limpid and no-sundries exclude Water closes mud hole after the water in main arch ribbed pipe all discharge by electric welding;
S2:First order Concrete Pumping Construction:After carrying out profit pipe operation to concrete pump pipe, by pump machine and level-one inlet pipe Connection, concrete is pumped into main arch ribbed pipe;When concrete pumping to level-one grout outlet position, the discharge of level-one grout outlet is opened Laitance;After laitance is drained, pause level-one pumping;
S3:Second level Concrete Pumping Construction:After level-one concrete laitance drains, starts two level and pump program;To two After grade pump line carries out profit pipe, it is pumped into concrete, after pump line stablizes discharge concrete, two level stock inlet is accessed, into arch rib pipe It is pumped into concrete;The first order continues pump concrete, until when pipe inner concrete boundary face is more than two level inlet pipe 5m height, Stop level-one pump machine, closes level-one plasma discharge tube valve;Continue pump concrete, concrete pumping to two level grout outlet position in the second level When setting, opens two level discharge pipe and laitance is discharged;After laitance is drained, pause two level pumping;
S4:Third level Concrete Pumping Construction:Step S3 is repeated, the pumping construction of the concrete of corresponding stage is completed;
S5:Vault plasma discharge operates:Upward relay pumping concrete step by step repeat the above steps until vault is pumped to, when mixed After solidifying soil is pumped to vault, slow down rate of pumping, continues pump concrete, wait for that laitance drains, and in one continuous time When the good concrete of interior stable discharge character, pause pumping;After standing 10min, it is further continued for pumping 10min concrete;Repeatedly Above-mentioned plasma discharge operation is carried out until discharge pipe bubble-free is overflowed, and concrete character significant change does not occur can to stop pumping mixed Solidifying soil, closes final stage inlet pipe valve, completes the pouring construction of unilateral main arch ribbed pipe.
Work progress is smooth, and plugging does not occur, and the concrete character of discharge is good.To the concrete filled steel tube that finishes of construction at Type quality carries out pipeline section ultrasound examination, and the average velocity of wave for surveying each section is 4650 ± 112m/s;Illustrate using this The multi-stage construction method of invention can make steel pipe inner concrete homogeneous closely knit.
Embodiment 3
A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, adopts main arch ribbed pipe inner concrete It is irrigated construction with the mode of series classification relay;Wherein, the method for filling of the pipe inner concrete uses jack-block, according to Symmetrically with balance loading principle, with vault for symmetrical center line, bridge two halves are across concrete perfusion simultaneously.It is main in pumping procedure The two halves of arch rib pipe are less than 6m across the progress difference that pours of inner concrete3.Wherein, in the multi-stage construction, classification perfusion length root It is determined according to diameter of steel tube, height, concrete performance and the pump power in concrete engineering;The concrete, which uses, to be had certainly The closely knit high performance concrete with shrinkage-compensating function, wherein:Concrete expansion degree should reach 600mm or more, and Slow setting time is answered More than 1.5 times single-stage construction times.
Every level-one after being classified to the main arch rib is equipped with a stock inlet and a thick liquid discharge mouth;Wherein, described first Grade stock inlet is set near the arch springing of arch bridge, and afterbody thick liquid discharge mouth is set to vault;(n+1)th grade of stock inlet can be used as n-th grade of row Starch mouth, n >=1.
Concrete perfusion process includes the following steps in half across the main arch ribbed pipe:
S1:Main arch rib rinses:Water is injected into arch rib steel pipe from vault discharge pipe, cleans steel pipe inner wall, and by being opened in The mud hole discharge iron rust of main arch rib tubular arch underfooting edge and other sundries, stop note after flow is limpid and no-sundries exclude Water closes mud hole after the water in main arch ribbed pipe all discharge by electric welding;
S2:First order Concrete Pumping Construction:After carrying out profit pipe operation to concrete pump pipe, by pump machine and level-one inlet pipe Connection, concrete is pumped into main arch ribbed pipe;When concrete pumping to level-one grout outlet position, the discharge of level-one grout outlet is opened Laitance;After laitance is drained, pause level-one pumping;
S3:Second level Concrete Pumping Construction:After level-one concrete laitance drains, starts two level and pump program;To two After grade pump line carries out profit pipe, it is pumped into concrete, after pump line stablizes discharge concrete, two level stock inlet is accessed, into arch rib pipe It is pumped into concrete;The first order continues pump concrete, until when pipe inner concrete boundary face is more than two level inlet pipe 4m height, Stop level-one pump machine, closes level-one plasma discharge tube valve;Continue pump concrete, concrete pumping to two level grout outlet position in the second level When setting, opens two level discharge pipe and laitance is discharged;After laitance is drained, pause two level pumping;
S4:N-th grade of Concrete Pumping Construction:Step S3 is repeated, the pumping construction of the concrete of corresponding stage is completed;
S5:Vault plasma discharge operates:Upward relay pumping concrete step by step repeat the above steps until vault is pumped to, when mixed After solidifying soil is pumped to vault, slow down rate of pumping, continues pump concrete, wait for that laitance drains, and in one continuous time When the good concrete of interior stable discharge character, pause pumping;After standing 8min, it is further continued for pumping 8min concrete;Repeatedly into Row above-mentioned plasma discharge operation is until discharge pipe bubble-free is overflowed, and significant change does not occur for concrete character can stop pumped concrete Soil closes final stage inlet pipe valve, completes the pouring construction of unilateral main arch ribbed pipe.
Work progress is smooth, and plugging does not occur, and the concrete character of discharge is good.To the concrete filled steel tube that finishes of construction at Type quality carries out pipeline section ultrasound examination, and the average velocity of wave for surveying each section is 4680 ± 110m/s;Illustrate using this The multi-stage construction method of invention can make steel pipe inner concrete homogeneous closely knit.
Although above the present invention is described in detail with a general description of the specific embodiments, On the basis of the present invention, it can be made some modifications or improvements, this will be apparent to those skilled in the art.Cause This, these modifications or improvements, belong to the scope of protection of present invention without departing from theon the basis of the spirit of the present invention.

Claims (5)

1. a kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete, which is characterized in that main arch ribbed pipe Inner concrete is irrigated construction by the way of series classification relay;Wherein, the method for filling of the pipe inner concrete uses Jack-block, according to symmetrically with balance loading principle, with vault for symmetrical center line, bridge two halves are across concrete perfusion simultaneously.
2. a kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete according to claim 1, special Sign is, is more than 60m for arch rib rise or the CFST Arch Bridge that duration is more than 8h is perfused, using multi-stage construction method.
3. a kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete according to claim 1, special Sign is that every level-one after being classified to the main arch rib is equipped with a stock inlet and a thick liquid discharge mouth;Wherein, the first order Stock inlet is set near the arch springing of arch bridge, and afterbody thick liquid discharge mouth is set to vault;(n+1)th grade of stock inlet can be used as n-th grade of plasma discharge Mouthful, n >=1.
4. a kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete according to claim 1, special Sign is that the main arch rib unilateral side filling concrete work progress includes the following steps:
S1:Main arch rib rinses:Water is injected into arch rib steel pipe from vault discharge pipe, cleans steel pipe inner wall, and by being opened in main arch The mud hole discharge iron rust of fin steel tube arch springing lower edge and other sundries, stop water filling after flow is limpid and no-sundries exclude, Mud hole is closed by electric welding after the water in main arch ribbed pipe all discharge;
S2:First order Concrete Pumping Construction:After carrying out profit pipe operation to concrete pump pipe, pump machine and level-one inlet pipe are connected It connects, concrete is pumped into main arch ribbed pipe;When concrete pumping to level-one grout outlet position, it is floating to open the discharge of level-one grout outlet Slurry;After laitance is drained, pause level-one pumping;
S3:Second level Concrete Pumping Construction:After level-one concrete laitance drains, starts two level and pump program;To two stage pump After pipe carries out profit pipe, it is pumped into concrete, after pump line stablizes discharge concrete, two level stock inlet is accessed, is pumped into arch rib pipe Concrete;The first order continues pump concrete, until when pipe inner concrete boundary face is more than two level inlet pipe 3~5m height, Stop level-one pump machine, closes level-one plasma discharge tube valve;Continue pump concrete, concrete pumping to two level grout outlet position in the second level When setting, opens two level discharge pipe and laitance is discharged;After laitance is drained, pause two level pumping;
S4:N-th grade of Concrete Pumping Construction:Step S3 is repeated, the pumping construction of the concrete of corresponding stage is completed;
S5:Vault plasma discharge operates:The upward relay pumping concrete step by step that repeats the above steps works as concrete up to being pumped to vault After being pumped to vault, slow down rate of pumping, continue pump concrete, wait for that laitance drains, and is steady within one continuous time Surely when the discharge good concrete of character, pause pumping;After standing 5~10min, it is further continued for pumping 5~10min concrete;Instead Above-mentioned plasma discharge operation is carried out again until discharge pipe bubble-free is overflowed, and significant change does not occur and can stop pumping for concrete character Concrete closes final stage inlet pipe valve, completes the pouring construction of unilateral main arch ribbed pipe.
5. according to a kind of multi-stage construction sides of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete any one of claim 1-4 Method, which is characterized in that the concrete uses the high performance concrete with self-compaction and shrinkage-compensating function, wherein coagulation The expansion degree of soil reaches 600mm or more, and the presetting period is more than 1.5 times of single-stage construction times.
CN201810519505.7A 2018-05-28 2018-05-28 A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete Pending CN108708264A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810519505.7A CN108708264A (en) 2018-05-28 2018-05-28 A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810519505.7A CN108708264A (en) 2018-05-28 2018-05-28 A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete

Publications (1)

Publication Number Publication Date
CN108708264A true CN108708264A (en) 2018-10-26

Family

ID=63870707

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810519505.7A Pending CN108708264A (en) 2018-05-28 2018-05-28 A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete

Country Status (1)

Country Link
CN (1) CN108708264A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577205A (en) * 2018-11-28 2019-04-05 中铁十四局集团第工程发展有限公司 A kind of 180m long-span Steel Arch casting method
CN110725212A (en) * 2019-10-24 2020-01-24 广西路桥工程集团有限公司 Method for determining target pile number and target elevation of steel pipe arch rib installation control point
CN111395174A (en) * 2020-03-23 2020-07-10 广西路桥工程集团有限公司 Method for exhausting air of arch rib in process of pouring concrete-filled steel tube of arch bridge
CN111979926A (en) * 2020-09-16 2020-11-24 中铁二院工程集团有限责任公司 Method for pouring concrete in pipe of long-span concrete-filled steel pipe arch bridge in plateau alpine region
CN113279333A (en) * 2021-05-18 2021-08-20 中电建十一局工程有限公司 Construction method for filling concrete in steel pipe arch bridge
CN113389142A (en) * 2020-03-13 2021-09-14 中交路桥建设有限公司 Continuous pumping jacking and linear control method for single-side arch rib of steel pipe concrete arch

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0567659A1 (en) * 1992-04-21 1993-11-03 Hamco Dinslaken Bausysteme GmbH Bridge-strengthening and method for its manufacture
CN1837482A (en) * 2006-04-12 2006-09-27 四川省交通厅公路规划勘察设计研究院 Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring
CN101446072A (en) * 2008-10-31 2009-06-03 上海市第五建筑有限公司 Construction method for pouring concrete within steel pipe of arch bridge
CN104975570A (en) * 2015-07-14 2015-10-14 中铁九局集团有限公司 Concrete lifting pouring construction method for steel tube arch bridge arch ribs
CN106835998A (en) * 2017-03-29 2017-06-13 贵州桥梁建设集团有限责任公司 Technique is pushed up on being filled under a kind of CFST Arch Bridge pipe inner concrete

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0567659A1 (en) * 1992-04-21 1993-11-03 Hamco Dinslaken Bausysteme GmbH Bridge-strengthening and method for its manufacture
CN1837482A (en) * 2006-04-12 2006-09-27 四川省交通厅公路规划勘察设计研究院 Method and apparatus for pouring concrete into steel pipe of steel pipe concrete arch ring
CN101446072A (en) * 2008-10-31 2009-06-03 上海市第五建筑有限公司 Construction method for pouring concrete within steel pipe of arch bridge
CN104975570A (en) * 2015-07-14 2015-10-14 中铁九局集团有限公司 Concrete lifting pouring construction method for steel tube arch bridge arch ribs
CN106835998A (en) * 2017-03-29 2017-06-13 贵州桥梁建设集团有限责任公司 Technique is pushed up on being filled under a kind of CFST Arch Bridge pipe inner concrete

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109577205A (en) * 2018-11-28 2019-04-05 中铁十四局集团第工程发展有限公司 A kind of 180m long-span Steel Arch casting method
CN110725212A (en) * 2019-10-24 2020-01-24 广西路桥工程集团有限公司 Method for determining target pile number and target elevation of steel pipe arch rib installation control point
CN110725212B (en) * 2019-10-24 2021-03-16 广西路桥工程集团有限公司 Method for determining target pile number and target elevation of steel pipe arch rib installation control point
CN113389142A (en) * 2020-03-13 2021-09-14 中交路桥建设有限公司 Continuous pumping jacking and linear control method for single-side arch rib of steel pipe concrete arch
CN111395174A (en) * 2020-03-23 2020-07-10 广西路桥工程集团有限公司 Method for exhausting air of arch rib in process of pouring concrete-filled steel tube of arch bridge
CN111979926A (en) * 2020-09-16 2020-11-24 中铁二院工程集团有限责任公司 Method for pouring concrete in pipe of long-span concrete-filled steel pipe arch bridge in plateau alpine region
CN113279333A (en) * 2021-05-18 2021-08-20 中电建十一局工程有限公司 Construction method for filling concrete in steel pipe arch bridge

Similar Documents

Publication Publication Date Title
CN108708264A (en) A kind of multi-stage construction method of Long-Span Concrete Filled Steel Tubular Arch Bridges filling concrete
CN206256455U (en) Draining lattice frame beam and draining lattice frame beam bank protection
CN111411628B (en) Medium-heat lining concrete water cooling method based on maximum inner surface temperature difference age
CN105887886A (en) Strong karst development stratum curtain grouting construction method
CN205329748U (en) Sediment removal device is used in hydraulic engineering construction
CN105839604A (en) Rapid diversion tunnel plugging structure and plugging method thereof
CN104343111A (en) Composite foundation for reinforcing thick sand soil layer by using node piles
CN208415269U (en) Foundation pit supporting construction in a kind of mud
CN105350565B (en) A kind of wind electric field blower tower foundation repairing and reinforcing method
CN106835998A (en) Technique is pushed up on being filled under a kind of CFST Arch Bridge pipe inner concrete
CN106087902B (en) For the scupper cyclone shaft energy-dissipating structure and water discharge method of ditch water process
CN205369329U (en) Reinforced structure is repaired on wind -powered electricity generation field fan pylon basis
CN206784327U (en) A kind of stone masonry dam poor quality dam grouting reinforcing structure
CN105019540B (en) Method for quickly perforating hole and installing water inlet pipe in water pool
CN109138116A (en) Concrete expires packet drainage pipeline tubine construction method
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN206529750U (en) A kind of water-conveyance tunnel of utilization reconstruction of diversion tunnel
CN204849713U (en) Simple and easy distribution structure
CN107476245A (en) A kind of process for constructing suitable for cold district sand Di Huhu hilllocks bank protection
CN108316259A (en) Diversion tunnel sets up lock under interim plug joint gate and blocks arrangement and method
CN208685596U (en) A kind of prefabricated pouring mortar pile
CN207919510U (en) Diversion tunnel blocks arrangement using lock under permanent plug first section joint gate
CN103114601B (en) The rapid hardening high pressure jet grouting of strong absorbent formation cuts infiltration method and device thereof
CN110565710A (en) foundation ring loosening and reinforcing treatment scheme
CN105887778A (en) Controllable drainage system of free face near high-pressure tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20181026

RJ01 Rejection of invention patent application after publication